Diagram Batang dan Kurva S

Pekerjaan : RUMAH TEMPAT TINGGAL DANDHI ALDIANSYAH


Lokasi : BRANGSONG
Tahun : 2020/2021

Bulan
No Jenis Pekerjaan Harga (Rp) Bobot (%)
Awal Proyek Jan Feb Mar Apr Mei Jun Jul Agustus Sep Okt Nov Des

I PEKERJAAN PERSIAPAN Rp 42,188,844.26 13.691 1.369


II PEKERJAAN TANAH Rp 1,383,800.98 0.449 0.225 0.225 0.225
III PEKERJAAN PONDASI Rp 11,049,725.50 3.586 1.195 1.195 1.195 1.195
IV PEKERJAAN DINDING Rp 19,048,884.73 6.182 0.883 0.883 0.883 0.883 0.883 0.883 0.883 0.883
V PEKERJAAN PLESTERAN DINDING Rp 8,367,995.23 2.716 0.339 0.339 0.339 0.339 0.339 0.339 0.339 0.339 0.339
VI PEKERJAAN KAYU Rp 108,056,777.50 35.066 5.844 5.844 5.844 5.844 5.844 5.844 5.844
VII PEKERJAAN BETON Rp 38,397,507.97 12.461 2.077 2.077 2.077 2.077 2.077 2.077 2.077
VIII PEKERJAAN PENUTUP ATAP Rp 21,128,039.20 6.856 1.714 1.714 1.714 1.714 1.714
IX PEKERJAAN PLAFON Rp 8,543,718.83 2.773 0.462 0.462 0.462 0.462 0.462 0.462 0.462
X PEKERJAAN PENUTUP LANTAI DAN DINDING Rp 17,826,360.17 5.785 1.157 1.157 1.157 1.157 1.157 1.157
XI PEKERJAAN KUNCI DAN KACA Rp 3,507,563.00 1.138 0.379 0.379 0.379 0.379
XII PEKERJAAN PENGECATAN Rp 17,811,632.99 5.780 1.445 1.445 1.445 1.445 1.445
XIII PEKERJAAN INSTALASI LISTRIK Rp 2,970,000.00 0.964 0.482 0.482 0.482
XIV PEKERJAAN SANITASI Rp 7,870,599.50 2.554 0.851 0.851 0.851 0.851
TOTAL Rp 308,151,449.85 100.000
Jumlah Bobot 2.642 2.642 4.495 3.299 3.299 9.144 9.606 9.880 11.002 11.853 12.335 6.112
Progress Bulanan 2.642 5.285 9.779 13.079 16.378 25.522 35.127 45.007 56.009 67.862 80.198 86.309
1 2 3 4 5 6 7 8 9 10 11 12