JADWAL PELAKSANAAN PEKERJAAN

TIME SCHEDULE
PEKERJAAN : RUMAH TYPE 36
LOKASI : Kp.kepupu RT.001 / RW.008 Kel.Pasir putih Kec.Sawangan Kota Depok Jawa barat
ANGGARAN BIAYA : Rp. 140,863,551.70
WAKTU PELAKSANAAN : 90 hari kalender

MINGGU KE
BOBOT SEPTEMBER 2023 OKTOBER 2023 NOVEMBER 2023
NO URAIAN PEKERJAAN NILAI PEKERJAAN PEKERJAA KETERANGAN
N (%) 12-18 19-25 26-2 3-9 10-16 17-23 24-30 31-6 7-13 14-20 21-27 28-4
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN Rp 1,630,640.00 1.158 1.158
II PEKERJAAN TANAH DAN URUGAN Rp 1,433,601.32 1.018 1.018
III PEKERJAAN PASANGAN PONDASI Rp 7,214,507.68 5.122 1.707 1.707 1.707
IV PEKERJAAN PASANGAN DINDING DAN PLESTERAN Rp 21,598,807.66 15.333 3.833 3.833 3.833 3.833
V PEKERJAAN BETON Rp 33,640,467.70 23.882 4.776 4.776 4.776 4.776 4.776
VI PEKERJAAN KUSEN PINTU DAN JENDELA Rp 11,844,483.57 8.408 4.204 4.204
VII PEKERJAAN ATAP DAN LANGIT LANGIT Rp 23,836,002.28 16.921 5.640 5.640 5.640
VIII PEKERJAAN KERAMIK LANTAI DAN DINDING Rp 7,711,757.75 5.475 5.475
IX PEKERJAAN KUNCI DAN KACA Rp 2,156,959.93 1.531 1.531
X PEKERJAAN SANITASI Rp 1,784,510.50 1.267 1.267
XI PEKERJAAN PENGECATAN Rp 6,101,406.86 4.331 4.331
XII PEKERJAAN LISTRIK Rp 2,805,000.00 1.991 1.991
XIII PEKERJAAN INSTALASI AIR Rp 16,478,606.46 11.698 5.849 5.849
XIV PEKERJAAN LAIN - LAIN Rp 2,626,800.00 1.865 1.865
JUMLAH TOTAL Rp 140,863,551.70 100.0
JUMLAH 1.158 2.725 1.707 6.484 8.610 8.610 8.610 24.303 15.694 11.115 4.789 6.196
PROGRESS RENCANA
KUMULATIF 1.158 3.883 5.590 12.073 20.683 29.292 37.902 62.206 77.899 89.014 93.804 100.000