Anda di halaman 1dari 1

JADWAL PELAKSANAAN

PROGRAM : Pembinaan Sekolah Menengah Pertama


KEGIATAN : Pembangunan/ Rehabilitasi Bangunan SMP
PEKERJAAN : Rehabilitasi Ruang Kelas Beserta Perabotnya
LOKASI : Sogan, Wates, Kulon Progo, Yogyakarta
TAHUN ANGGARAN : 2019

JUMLAH HARGA BULAN 1 BULAN 2 BULAN 3 BULAN 4


NO. URAIAN PEKERJAAN BOBOT (%)
( Rp. ) 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

A REHAB RUANG KELAS 9B


I PEKERJAAN PERSIAPAN 4,469,049.83 1.490 1.490
II PEKERJAAN BETON 5,493,945.45 1.831 0.916 0.916
III PEKERJAAN KAYU KOSEN PINTU DAN JENDELA 2,769,795.00 0.923 0.308 0.308 0.308
IV PEKERJAAN RANGKA DAN PENUTUP ATAP 56,917,564.80 18.973 4.743 4.743 4.743 4.743
V PEKERJAAN PLAFOND GYPSUM 9,781,860.00 3.261 1.630 1.630
VI PEKERJAAN LANTAI KERAMIK 3,097,523.00 1.033 0.516 0.516
VII PEKERJAAN PENGGANTUNG, PENGUNCI DAN KACA 777,803.00 0.259 0.259
VIII PEKERJAAN PENGECATAN 5,083,877.34 1.695 1.695
IX PEKERJAAN LISTRIK 1,660,000.00 0.553 0.553
X PEKERJAAN LAIN LAIN 19,750,000.00 6.583 1.646 1.646 1.646 1.646

B REHAB RUANG KELAS 9C


I PEKERJAAN BETON 5,493,945.45 1.831 0.916 0.916
II PEKERJAAN KAYU KOSEN PINTU DAN JENDELA 2,769,795.00 0.923 0.308 0.308 0.308
III PEKERJAAN RANGKA DAN PENUTUP ATAP 56,917,564.80 18.973 4.743 4.743 4.743 4.743
IV PEKERJAAN PLAFOND GYPSUM 9,781,860.00 3.261 1.630 1.630
V PEKERJAAN LANTAI KERAMIK 3,097,523.00 1.033 0.516 0.516
VI PEKERJAAN PENGGANTUNG, PENGUNCI DAN KACA 777,803.00 0.259 0.259
VII PEKERJAAN PENGECATAN 5,083,877.34 1.695 1.695
VIII PEKERJAAN LISTRIK 1,660,000.00 0.553 0.553
IX PEKERJAAN LAIN LAIN 4,000,000.00 1.333 0.333 0.333 0.333 0.333

B REHAB RUANG KELAS 9D


I PEKERJAAN BETON 5,493,945.45 1.831 0.916 0.916
II PEKERJAAN KAYU KOSEN PINTU DAN JENDELA 2,769,795.00 0.923 0.308 0.308 0.308
III PEKERJAAN RANGKA DAN PENUTUP ATAP 56,917,564.80 18.973 4.743 4.743 4.743 4.743
IV PEKERJAAN PLAFOND GYPSUM 9,781,860.00 3.261 1.630 1.630
V PEKERJAAN LANTAI KERAMIK 14,132,207.39 4.711 2.355 2.355
VI PEKERJAAN PENGGANTUNG, PENGUNCI DAN KACA 777,803.00 0.259 0.259
VII PEKERJAAN PENGECATAN 5,083,877.34 1.695 1.695
VIII PEKERJAAN LISTRIK 1,660,000.00 0.553 0.553
IX PEKERJAAN LAIN LAIN 4,000,000.00 1.333 0.333 0.333 0.333 0.333

JUMLAH 300,000,840.00
100.000
DIBULATKAN 300,000,000.00
RENCANA. 4.237 2.747 14.229 14.229 19.120 19.120 1.660 0.000 4.166 4.311 0.923 0.923 4.007 4.007 4.007 2.313
KUMULATIF 4.237 6.984 21.213 35.442 54.563 73.683 75.343 75.343 79.509 83.820 84.743 85.666 89.674 93.681 97.688 100.000

Kulon Progo, 14 Februari 2019


MENGETAHUI MENGETAHUI Dibuat Oleh :
FASILITATOR KEPALA SEKOLAH P2S
SMP N 3 WATES

RACHMAT SULITYAWAN, ST. Drs. AGUS SUTIK DWIARTANTA Drs. SUTIYONO


NIP : 19680907 199802 1 002 NIP : 19600910 198303 1 008