LAPORAN TUGAS

METODE PERBAIKAN DAN PERKUATAN STRUKTUR BAJA

Dosen Pengampu :
Afif Navir Refani, ST. MT.

Disusun Oleh :
Kelas A-2015
Basdian Kurniadi 10111510000048

DEPARTEMEN TEKNIK INFRASTRUKTUR SIPIL


FAKULTAS VOKASI
INSTITUT TEKNOLOGI SEPULUH NOPEMBER
SURABAYA
2018
DAFTAR ISI

DAFTAR ISI........................................................................................................... i
DAFTAR GAMBAR .............................................................................................. i
DAFTAR TABEL .................................................................................................. i
BAB 1 RENCANA ANGGARAN BIAYA .................................................... 1
1.1. Rencana Anggaran Biaya ......................................................................... 1
BAB 2 DETAIL PERKUATAN STRUKTUR ............................................. 2
2.1. Perkuatan Kolom ...................................................................................... 2
2.2. Perkuatan Balok ....................................................................................... 2
LAMPIRAN ........................................................................................................... 3

DAFTAR GAMBAR

Gambar 2.1 Perkuatan kolom baja terbungkus beton ............................................. 2


Gambar 2.2 Perkuatan balok dengan modifikasi profil .......................................... 2

DAFTAR TABEL

Tabel 1.1 Rencana Anggaran Biaya Perkuatan Struktur......................................... 1

i
BAB 1
RENCANA ANGGARAN BIAYA

1.1. Rencana Anggaran Biaya


Berikut merupakan rencana anggaran biaya mengenai pekerjaan
pelaksanaan perkuatan bangunan :

Tabel 1.1 Rencana Anggaran Biaya Perkuatan Struktur

Harga Satuan
No Uraian Volume Satuan Jumlah
(Rp)

A1 Pekerjaan Persiapan
1 Administrasi dan Dokumentasi 1 L³ Rp5,000,000 Rp5,000,000
2 Bouwplank / pagar pengaman lokasi 25 m' (titik) Rp111,393 Rp2,784,825
3 Gudang material 6 m² Rp352,350 Rp2,114,100
4 Listrik kerja dan air kerja 1 L³ Rp3,000,000 Rp3,000,000
5 Mobilisasi dan demobilisasi 1 L³ Rp5,000,000 Rp5,000,000
Total A1 : Rp17,898,925

A2 Struktur Rangka Baja Perkuatan Balok


1 Balok T (½WF) 100x150x13x8 1301 kg Rp15,000 Rp19,515,000
2 Pelat Baja 282x15 4250 kg Rp15,000 Rp63,750,000
3 Pekerjaan Pengelasan Dengan Las Listrik 500 cm Rp3,568 Rp1,784,000
4 Scaffolding Lebar 1,9 meter/set 15 buah/set Rp535,000 Rp8,025,000
5 Finishing (pengecatan besi) 50 m² Rp45,688 Rp2,284,400
Total A2 : Rp95,358,400

A3 Struktur Kolom Komposit


1 Beton K-300 untuk Concrete Jacketing
Kolom (Jayamix) 14.08 m³ Rp905,000 Rp12,742,400

2 Shear Connector D 19 792 buah Rp12,000 Rp9,504,000


3 Tulangan Longitudinal D16 833.36 kg Rp9,800 Rp8,166,928
4 Tulangan Sengkang Ø10 501 kg Rp9,000 Rp4,509,000
5 Bekisting Kolom 20 m² Rp407,630 Rp8,152,600
6 Finishing 20 m² Rp525,000 Rp10,500,000
Total A3 : Rp53,574,928
PPN 10% Rp16,683,225
Jumlah Total : Rp183,515,478

1
BAB 2
DETAIL PERKUATAN STRUKTUR

2.1. Perkuatan Kolom


Perkuatan kolom dilakukan dengan membungkus baja profil dengan beton
atau biasa disebut concrete encasement sehingga menjadi elemen komposit. Berikut
adalah data spesifikasi beton yang akan digunakan sebagai perkuatan:
1. Dimensi kolom = 400/400 mm
2. Mutu beton, f’c = 25 MPa
3. Mutu baja tulangan longitudinal, fy = 400 MPa
4. Mutu baja tulangan sengkang, fy = 240 MPa
5. Tebal selimut = 40 mm
6. Tulangan longitudinal = 12 D 16
7. Tulangan sengkang = D10-150

Gambar 2.1 Perkuatan kolom baja terbungkus beton


Detail dan gambar perencanaan terlampir
2.2. Perkuatan Balok
Perkuatan balok dilakukan dengan memodifikasi profil dengan memasang
plat baja pada sayap kiri dan kanan profil, juga dengan menambahkan setengah
profil WF di bawah penampang.
1. Plat baja : 282 mm x 15 mm
2. ½ WF : 150 x 150 x 12 x 15

Gambar 2.2 Perkuatan balok dengan modifikasi profil


Detail dan gambar perencanaan terlampir

2
LAMPIRAN