Dosen Pengampu :
Afif Navir Refani, ST. MT.
Disusun Oleh :
Kelas A-2015
Basdian Kurniadi 10111510000048
DAFTAR ISI........................................................................................................... i
DAFTAR GAMBAR .............................................................................................. i
DAFTAR TABEL .................................................................................................. i
BAB 1 RENCANA ANGGARAN BIAYA .................................................... 1
1.1. Rencana Anggaran Biaya ......................................................................... 1
BAB 2 DETAIL PERKUATAN STRUKTUR ............................................. 2
2.1. Perkuatan Kolom ...................................................................................... 2
2.2. Perkuatan Balok ....................................................................................... 2
LAMPIRAN ........................................................................................................... 3
DAFTAR GAMBAR
DAFTAR TABEL
i
BAB 1
RENCANA ANGGARAN BIAYA
Harga Satuan
No Uraian Volume Satuan Jumlah
(Rp)
A1 Pekerjaan Persiapan
1 Administrasi dan Dokumentasi 1 L³ Rp5,000,000 Rp5,000,000
2 Bouwplank / pagar pengaman lokasi 25 m' (titik) Rp111,393 Rp2,784,825
3 Gudang material 6 m² Rp352,350 Rp2,114,100
4 Listrik kerja dan air kerja 1 L³ Rp3,000,000 Rp3,000,000
5 Mobilisasi dan demobilisasi 1 L³ Rp5,000,000 Rp5,000,000
Total A1 : Rp17,898,925