PROYEK PEMBANGUNAN PABRIK PT COHEN FURNITURE INDONESIA JEPARA

Pekerjaan :
Lokasi :

REKAPITULASI

I. PEK. PERSIAPAN 20,460,600


II. PEKERJAAN SIPIL PONDASI GEDUNG PABRIK 35X21 m 185,907,676.71
III. PEKERJAAN KONTRUKSI BAJA DAN BETON (KOMPOSIT) 1,343,168,908.20
IV. PEKERJAAN ATAP 127,248,000.00
V. PEKERJAAN SIPIL 139,460,400.46
VI. PEKERJAAN KONSEN PINTU DAN JENDELA
VII. PEKERJAAN CAT
VIII. PEKERJAAN MEKANIKAL/ELEKTRIKAL

Terbilang Sub Total 1,816,245,585.37


Dua Milyar Dua puluh lima juta rupiah PPN 10% 208,868,242.32
Jumlah Total 2,025,113,827.69
Dibulatkan 2,025,000,000.00
BILLS OF APPROXIMATE QUANTITY
PABRIK PT COHEN FURNITURE INDONESIA
JEPARA JAWA TENGAH
Unit Price Total Price
No. Item Pekerjaan Unit Qty (Rp.) ( Rp) Remark

A PEKERJAAN PERSIAPAN
1 Pembersihan lahan m2 735.00 5,000 3,675,000
2 Pengukuran dan Bouwplank m1 262.00 48,800 12,785,600
3 Peralatan,Air ,listrik kerja ls 1.00 1,500,000 1,500,000
4 Peralatan keselamatan kerja ls 1.00 2,500,000 2,500,000
Sub Jumlah Pekerjaan Persiapan Rp. 20,460,600
B PEKERJAAN SIPIL PONDASI GEDUNG PABRIK 35X21 m
1 Galian Pondasi telapak 150*150*150 m3 81.00 51,100 4,139,100
2 Galian Sloof m3 174.00 51,100 8,891,400
3 Galian pondasi batu kali + saluran m3 57.60 51,100 2,943,360
4 Urugan kembali lobang pondasi m3 88.64 25,550 2,264,624
5 Urugan Pasir padat tebal 10 cm m3 137.70 119,100 16,400,070
6 Sloof beton bertulang 25 * 40 m3 30.00 4,198,196 125,945,894
7 Pondasi batu kali m3 35.28 557,600 19,672,128
8 Pasangan bata merah 1/2 bata tinggi 35 cm m2 39.00 92,400 3,603,600
9 Plester,aci m2 39.00 52,500 2,047,500
sub jumlah pek. Sipil Pondasi pendukung utama Rp. 185,907,677
C. PEKERJAAN KONTRUKSI BAJA DAN BETON (KOMPOSIT)
1 1 Berat baja Kolom dan Balok kg 81,904.70 14,750 1,208,094,325
2 Base plate 370x195x12 mm kg 50.00 18,700 935,000
3 Angkur dia.19 mm bh 150.00 38,000 5,700,000
4 Shear Conector dia. 7/8 bh 6,348.00 13,500 85,698,000
5 Shear Conector dia. 3/4 bh 1,625.00 15,000 24,375,000
6 Plat simpul 630x150x12mm kg 356.08 18,200 6,480,583
7 Pengaku L 50.50.5 kg 450.00 18,200 8,190,000
8 Baud span dia.3/4" bh 480.00 7,700 3,696,000 1,343,168,908
sub jumlah pek. Konstruksi 1,343,168,908
Unit Price Total Price
No. Item Pekerjaan Unit Qty (Rp.) ( Rp) Remark
Pindahan hal 1. Rp. 1,549,537,185
D PEKERJAAN ATAP
1 Atap Allumunium 0.4 mm m2 1,132.00 78,000 88,296,000
2 Nok Allumunium 0.4 mm m1 51.00 118,000 6,018,000
3 Baud roofing bh 6,528.00 1,250 8,160,000
4 Talang datar Zincalum 0.4 mm m1 102.00 115,000 11,730,000
5 Lisplank plat 1.2 mm m1 64.00 84,000 5,376,000
6 Talang PVC 4" m1 144.00 36,000 5,184,000
7 Corong talang bh 18.00 40,000 720,000
9 Knee 4" bh 72.00 24,500 1,764,000
sub jumlah pekerjaan atap 127,248,000
E PEKERJAAN SIPIL
a 1 Kolom pengaku dinding 15 * 25 m3 6.75 4,198,196 28,337,826
2 Balok pengaku 15*25 m3 5.40 4,198,196 22,670,261
3 Ring balok 15 * 20 m3 6.48 4,198,196 27,204,313
4 Pasang dinding conblock 19*19*38 m2 960.00 63,800 61,248,000
sub jumlah pek. Sipil Rp. 139,460,400
Sub Jumlah Rp. 1,816,245,585
PPN & PPH 11,5 % 208,868,242
Total Rp. 2,025,113,828
Grand total dibulatkan Rp. 2,025,000,000
2,755,102
per m2