TABEL 1
DATA LHR RUAS JALAN DPU BINA MARGA
Tahun LHR (SMP/Hari)
1999 17706
2000 17864
2001 19234
2002 20219
2003 29363
2004 27253
Metode Regresi
Tahun LHR (SMP) Y) X Y=(y-y') X=(x-x') XY X2
1999 17706 0 -4233.83333 -2.5 10584.583 0
2000 17864 1 -4075.83333 -1.5 6113.75 1
2001 19234 2 -2705.83333 -0.5 1352.9167 4
2002 20219 3 -1720.83333 0.5 -860.41667 9
2003 29363 4 7423.16667 1.5 11134.75 16
2004 27253 5 5313.16667 2.5 13282.917 25
∑ 131639 15 41608.5 55
𝒙 ̅ 𝜮_𝒙/𝜫
15
2.5 2.5
6
(𝒚 ) ̅_(𝜮_𝒚
/𝒏) 131639 21939.83
21939.8333
6
𝑏=(∑128▒𝒙_𝒚 ̇ )/(∑128▒𝒙^𝟐 )
41608.5 756.5182
756.518182
55
𝒚^′=𝒂+𝒃𝒙
a = Y - bx 21939.833 756.518182 0
NILAI 21939.833
ⅈ=𝒃/𝒂 𝒙𝟏𝟎𝟎%
% Pertumbuhan
0.0345 3.448 %
Luasan KOMPOSISI (%) L.Avrg GFA AREA (%)
A 40 60 2,400
B 25 150 3,750
C 20 180 3,600
D 10 200 2,000
E 5 300 1,500
100 13,250
Komp.KendKOMPOSISI
MV 30
LH 30
BUS 20
TRUK 2 10
TRUK 3 10
Y 21939.83
756.518
MENENTUKAN LAJUR
Maka digunakan Lebar jembatan C=Co x FCw x FCsp x FCsf
(2X1900) x 1,00 x 1,00 x 0,95 hasil
LEBAR lajur Maka Untuk Lebar jembatan adalah :
L = Lebar lajur + Lebar trotoar + drainase
9 meter
3.5
AS JALAN
x FCsp x FCsf
x FCsp x FCsf
0.95 1805
KAN LAJUR
x FCsp x FCsf
3610
analisa aspek hidrologi (untuk tinggi muka air)
diambil beberapa tahun kebelakang
1995-2005
DATA CURAH HUJAN BULANAN (mm)
TAHUN 1995 1996 1997 1998 1999 2000
JAN 338
FEB 344
MART 434
APR 138
MEI 204
JUNI 245
JULI 48
AGS 0
SEPT 16
OKT 196
NOV 258
DES 351
JUMLAH 2572
average 214.33 136.83 161.58 186.25 133.17 102.42
max 214.33
LB (M2)
78000 1.5
2.5
4.75
77991.25 M2
LB 78000