TIME SCHEDULE PELAKSANAAN

BOBOT MING
NO URAIAN PEKERJAAN BIAYA RUPIAH
% 1 2 3 4 5

I PEK. PERSIAPAN Rp 7,500,800.00 2.237 1.119 1.119

II PEK. GALIAN PONDASI Rp 15,750,600.00 4.698 2.349 2.349

III PE. PASANGAN PONDASI BATU KALI Rp 35,250,750.00 10.514 3.505 3.505 3.505

IV PEK. SLOOF & KOLOM Rp 45,004,800.00 13.424 4.475 4.475

V PEK. DINDING & KOSEN Rp 25,950,000.00 7.740 2.580

VI PEK. RINGBALK Rp 15,450,700.00 4.608

VII PEK. KAP & ATAP Rp 75,008,000.00 22.373

VII PEK. PLAFOND Rp 12,765,100.00 3.807

VIII PEK. PLESTERAN Rp 7,686,713.00 2.293

IX PEK. LANTAI Rp 11,251,200.00 3.356

X PEK. PINTU & JENDELA Rp 16,369,850.00 4.883


XI PEK. PENGECATAN Rp 8,250,000.00 2.461

XII PEK. FINISHING DALAM Rp 30,003,200.00 8.949

XIII PEK. FINISHING LUAR Rp 20,500,000.00 6.115

XIV PEK. TAMAN Rp 8,525,000.00 2.543

JUMLAH NILAI PEKERJAAN Rp 335,266,713.00 100.000


JUMLAH (RENCANA) 1.119 3.468 5.854 7.979 10.559
RENCANA
JUMLAH KOMULATIF (RENCANA) 1.119 4.586 10.440 18.419 28.979
AAN

MINGGU PRESENTASI
6 7 8 9 10 11 12 %
100

90

80
4.475

2.580 2.580 70

2.304 2.304
60
7.458 7.458 7.458

1.904 1.904 50

0.764 0.764 0.764


40
1.119 1.119 1.119

2.441 2.441 30
0.820 0.820 0.820
20
2.983 2.983 2.983

2.038 2.038 2.038 10

1.271 1.271
0

10.260 8.090 11.346 14.283 16.321 7.411 3.310


39.239 47.328 58.675 72.958 89.279 96.690 100.000