Anda di halaman 1dari 2

BUAT JADWAL PELAKSANAAN PEKERJAAN / TIME SCHEDULE

NAMA :

NIM :

BIAYA BOBOT MINGGU


NO URAIAN PEKERJAAN
RUPIAH % 1 2 3 4 5 6 7 8 9

I PEK. PONDASI Rp 17,518,000.00 17.05 5.68 5.68 5.68

II PEK. BETON & DINDING Rp 26,497,660.00 25.79 6.45 6.45 6.45 6.45

III PEK. KAP & ATAP Rp 10,537,000.00 10.25 5.13 5.13

IV PEK. PLAFOND Rp 6,633,592.00 6.46 3.23 3.23

V PEK. PLESTERAN Rp 6,686,713.00 6.51 2.17 2.17 2.17

VI PEK. LANTAI Rp 8,775,500.00 8.54 4.27

VII PEK. PINTU & JENDELA Rp 7,369,850.00 7.17 3.59 3.59

VIII PEK. CAT & KAPURAN Rp 4,750,500.00 4.62 2.31 2.31

IX PEK. FINISHING DALAM Rp 7,951,790.00 7.74

X PEK. FINISHING LUAR Rp 6,029,528.00 5.87 2.93

JUMLAH NILAI PEKERJAAN Rp 102,750,133.00 100.00


KEMAJUAN MINGGU 5.68 5.68 5.68 6.45 10.03 12.20 16.06 12.84 10.43
RENCANA
KOMULATIF KEMAJUAN 0 5.683 11.37 17.05 23.50 33.53 45.73 61.79 74.62 85.06
PRESTASI
10 11 12 %

100 %

90 %

80 %

70 %

60 %

4.27 50 %

40 %

30 %

3.87 3.87 20 %

2.93 10 %

7.20 3.87 3.87


92.26 96.13 100.00