TIME SCHEDULE

RUMAH 2 LANTAI

URAIAN PEKERJAAN JUMLAH HARGA BOBOT BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4
NO. (%) MINGGU KE- MINGGU KE- MINGGU KE- MINGGU KE-
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 PEKRJAAN Rp 135,122.90 0.026 0.026
PERSIAPAN
2 PEKERJAAN Rp 63,938,742.12 12.136 4.045 4.045 4.045
TANAH & PONDASI
3 PEKRJAAN Rp 81,944,382.95 15.553 3.888 3.888 3.888 3.888
KONSTRUKSI BETON
4 PEKRJAAN Rp 141,711,996.97 26.897 6.724 6.724 6.724 6.724
PASANGAN DINDING
5 PEKRJAAN Rp 106,779,273.22 20.267 4.053 4.053 4.053 4.053 4.053
PINTU & JENDELA
6 PEKRJAAN Rp 74,063,052.67 14.057 2.811 2.811 2.811 2.811 2.811
ATAP
7 PEKRJAAN Rp 622,320.00 0.118 0.024 0.024 0.024 0.024 0.024
INSTALASI LISTRIK
8 PEKRJAAN Rp 18,701,873.85 3.550 1.775 1.775
LANTAI & DINDING
9 PEKRJAAN Rp 8,692,644.55 1.650 0.330 0.330 0.330 0.330 0.330
SANITASI AIR
10 PEKRJAAN Rp 30,275,487.29 5.746 1.437 1.437 1.437 1.437
FINISHING
TOTAL Rp 526,864,896.52 100.000
RENCANA PROGRES MINGGUAN 4.071 4.045 4.045 3.888 3.888 10.613 14.666 10.801 13.613 7.218 7.218 3.165 6.353 3.541 1.437 1.437
KOMUKATIF PROGRES MINGGUAN 4.071 8.116 12.161 16.050 19.938 30.551 45.217 56.018 69.631 76.849 84.068 87.233 93.585 97.127 98.563 100.000