B LANTAI 1
I STRUKTUR BAWAH Rp 613,011,435.01
II PEKERJAAN BETON Rp 559,055,986.05
III ARSITEKTUR Rp 860,795,993.23
IV MEP Rp 462,338,499.99
C LANTAI 2
I STRUKTUR Rp 465,293,345.13
II ARSITEKTUR Rp 842,199,472.88
III MEP Rp 285,292,000.00
D LANTAI ATAP
I ARSITEKTUR Rp 86,869,235.81
PT. Sentral Pembangu
E PEKERJAAN LANSEKAP Rp 747,817,961.66
TOTAL Rp 5,287,804,702.66
PEMBULATAN Rp 5,816,585,000.00
Terbilang : Lima miliar delapan ratus enam belas juta lima ratus delapan puluh lima ribu rupiah
TIME SCHEDULE "S" CURVE
Pengadaan Bangunan Gedung Kantor PT. Sucofindo (Persero) Cabang Medan
Tahun Anggaran 2017
I PEKERJAAN PERSIAPAN Rp 351,780,772.90 6.653% 1.11% 1.11% 1.11% 1.11% 1.11% 1.11%
II PEKERJAAN LAIN-LAIN Rp 13,350,000.00 0.252% 0.13% 0.13%
A STRUKTUR BAWAH
I PEKERJAAN GALIAN DAN URUGAN Rp 177,700,648.76 3.361% 1.12% 1.12% 1.12%
II PEKERJAAN PONDASI DAN BETON Rp 435,310,786.25 8.232% 2.74% 2.74% 2.74%
B PEKERJAAN LANTAI 1
I PEKERJAAN BETON Rp -
Rp 559,055,986.05 10.573% 2.64% 2.64% 2.64% 2.64%
C PEKERJAAN LANTAI 2
I PEKERJAAN BETON Rp 465,293,345.13 8.799% 2.20% 2.20% 2.20% 2.20%
A STRUKTUR BAWAH
I PEKERJAAN GALIAN DAN URUGAN Rp 177,700,648.76
II PEKERJAAN PONDASI DAN BETON Rp 435,310,786.25
B PEKERJAAN LANTAI 1
I PEKERJAAN BETON Rp 559,055,986.05
C PEKERJAAN LANTAI 2
I PEKERJAAN BETON Rp 465,293,345.13
A LANTAI 1 Rp 860,795,993.23
I PEKERJAAN DINDING dan SEKAT Rp 208,329,252.03
II PEKERJAAN BETON NON STRUKTURAL Rp 27,193,280.03
III PEKERJAAN PLERSTERAN dan ACIAN Rp 78,311,637.63
IV PEKERJAAN PINTU DAN JENDELA Rp 105,917,999.25
V PEKERJAAN PENUTUP LANTAI dan DINDING Rp 196,670,456.62
VI PEKERJAAN ATAP ENTRANCE Rp 37,209,600.00
VII PEKERJAAN PLAFOND Rp 53,404,689.50
VIII PEKERJAAN DEKORATIF dan ACESORIS Rp 107,625,974.79
IX PEKERJAAN PENGECATAN Rp 46,133,103.39
B LANTAI 2 Rp 842,199,472.88
I PEKERJAAN DINDING dan SEKAT Rp 230,005,537.55
II PEKERJAAN BETON NON STRUKTURAL Rp 60,081,029.95
III PEKERJAAN PLERSTERAN dan ACIAN Rp 38,739,073.93
IV PEKERJAAN PINTU DAN JENDELA Rp 43,751,646.17
V PEKERJAAN PENUTUP LANTAI dan DINDING Rp 151,800,273.79
VI PEKERJAAN ATAP Rp 33,573,231.90
VII PEKERJAAN PLAFOND Rp 67,688,072.00
VIII PEKERJAAN DEKORATIF dan ACESORIS Rp 112,763,386.45
IX PEKERJAAN PENGECATAN Rp 103,797,221.14
LANTAI 2 Rp 285,292,000.00
A PLUMBING ( PEMIPAAN ) Rp 34,926,000.00
I PEKERJAAN PEMIPAAN AIR BERSIH Rp 5,339,500.00
II PEKERJAAN PIPA AIR BEKAS DAN KOTOR
a Instalasi pipa air kotor dan bekas PVC class AW 10 kg/cm Rp 9,866,500.00
b Instalasi pipa buangan air hujan PVC class AW 10 kg/cm Rp 12,930,000.00
c Pipa buangan tinja PVC class AW 10 kg/cm Rp 6,790,000.00
B PEKERJAAN LISTRIK Rp 71,989,800.00
I PANEL DISTRIBUSI Rp 12,850,000.00
II PEKERJAAN PENERANGAN DAN STOPKONTAK
a Armature penerangan Rp 23,429,800.00
b Instalasi Kabel Rp 35,710,000.00
C VENTILASI DAN TATA UDARA Rp 105,590,000.00
D PEKERJAAN ELEKTRONIKA Rp 72,786,200.00
I SISTEM FIRE ALARM
b Armature Rp 3,610,000.00
c Instalasi fire alarm Rp 5,630,000.00
II SISTEM CCTV
a Peralatan Utama CCTV Rp 1,340,000.00
b Armature dan Instalasi CCTV Rp 1,790,000.00
III SISTEM KABEL TELEPON Rp 3,530,000.00
IV SISTEM KABEL DATA Rp 15,700,000.00
V SISTEM TATA SUARA
a Armature dan Instalasi Tata Suara Rp 10,255,000.00
VI SISTEM MATV Rp 6,002,000.00
VII SISTEM PENANGKAL PETIR Rp 24,929,200.00
1 2 3 4 5 6 7=4x6
PEKERJAAN PENDAHULUAN
I PEKERJAAN PERSIAPAN
1 Pembersihan lokasi pekerjaan Taksir 1.00 Ls 4,400,000.00 4,400,000.00
2 Mobilisasi/Demobilisasi Taksir 1.00 Ls 1,400,000.00 1,400,000.00
3 Perizinan Dihitung L 1.00 Ls 201,000,000.00 201,000,000.00
4 Penambahan Daya Harga Satuan 80,000.00 Va 969.00 77,520,000.00
5 Pembuatan Pagar Sementara Tinggi 2 Meter A.2.2.1.2 33.40 M' 422,992.75 14,127,957.85
6 Pembuatan Gudang dan Direksi Keet Taksir 15.00 M2 500,000.00 7,500,000.00
7 Pengukuran/Bowplank A.2.2.1.4 105.00 M' 84,335.00 8,855,175.00
8 Bongkar Bangunan Lama Taksir 1.00 Ls 12,000,000.00 12,000,000.00
9 Dinding Pembatas Semantara Bangunan Lama Taksir 100.98 M2 120,000.00
10 Bongkar dan Pasang Kembali Kanopi Parkiran
a. Pembongkran Taksir 1.00 Unt 500,000.00 500,000.00
b. Galian Pondasi A.2.3.1.1 13.52 M3 74,050.00 1,001,156.00
c. Pengurugkan Bekas Galian Pondasi A.2.3.1.9 11.30 M3 53,100.00 599,897.25
d. Pasir Urug A.2.3.1.11 0.42 M3 153,220.00 64,735.45
e. Lantai Kerja A.4.1.1.2 10.40 M3 748,141.60 7,780,672.64
f. Pondasi Tapak
- Beton A.4.1.1.5 1.80 M3 802,866.60 1,445,159.88
- Besi A.4.1.1.17. 199.47 Kg 11,751.30 2,344,014.18
- Bekisting A.4.1.1.20 6.00 M2 73,994.00 443,964.00
g. Pedastel
- Beton A.4.1.1.5 1.62 M3 802,866.60 1,303,152.85
- Besi A.4.1.1.17. 184.30 Kg 11,751.30 2,165,712.55
- Bekisting A.4.1.1.22 18.55 M2 138,027.00 2,560,400.85
h. Sloof 20x30 Cm
- Beton A.4.1.1.5 1.20 M3 802,866.60 963,439.92
- Besi A.4.1.1.17. 147.45 Kg 11,751.30 1,732,706.47
- Bekisting A.4.1.1.21 12.00 M2 79,385.67 952,628.00
i. Plat Baja Uk. 400x400x1.8 mm Taksir 5.00 Bh 124,000.00 620,000.00
j. Angkur Taksir 20.00 Bh 25,000.00 500,000.00
Jumlah I Rp 351,780,772.90
II PEKERJAAN LAIN-LAIN
1 Pembuatan Foto Dokumentasi Taksir 1.00 Ls 500,000.00 500,000.00
2 Administrasi dan Pembuatan Laporan Taksir 1.00 Ls 3,000,000.00 3,000,000.00
3 Pembuatan Ass Buildrawing Taksir 1.00 Ls 4,000,000.00 4,000,000.00
4 Pemasangan Papan Proyek Taksir 1.00 Ls 250,000.00 250,000.00
5 P3K dan Keamanan Taksir 1.00 Ls 800,000.00 800,000.00
6 Kelengkapan K3 Dihitung A 10.00 Set 480,000.00 4,800,000.00
Jumlah II Rp 13,350,000.00
TOTAL I + II Rp 365,130,772.90
337,153,132.85
6.38%
Rencana Anggaran Biaya
Pekerjaan Struktur
Pengadaan Bangunan Gedung Kantor PT. Sucofindo (Persero) Cabang Medan
Tahun Anggaran 2017
1 2 3 4 5 6 7=4x6
PEKERJAAN STRUKTUR
A STRUKTUR BAWAH
I PEKERJAAN GALIAN DAN URUGAN
1 Galian Tanah A.2.3.1.1 62.97 M3 74,050.00 4,662,767.07
2 Urugan Pasir dibawah Pondasi A.2.3.1.11 2.44 M3 153,220.00 373,971.72
3 Mengurug kembali Tanah Galian A.2.3.1.9 25.37 M3 53,100.00 1,347,163.99
4 Timbunan Tanah dan Pemadatan A.2.3.1.11.a 643.81 M3 153,220.00 98,644,422.84
5 Urugan Pasir Bawah Lantai A.2.3.1.11 25.65 M3 153,220.00 3,930,056.69
6 Whiremas M-6 A.4.1.1.19 1,351.65 Kg 10,247.95 13,851,630.20
7 Rabat Beton Bawah Lantai A.4.1.1.5 51.30 M3 802,866.60 41,186,676.02
8 Lantai kerja Beton A.4.1.1.4 21.17 M3 647,308.00 13,703,960.24
Jumlah I Rp 177,700,648.76
II PEKERJAAN PONDASI DAN BETON
1 Pile Cap (PC1)
- Beton A.4.1.1.18. 19.95 M3 866,226.40 17,281,493.87
- Besi A.4.1.1.17.b 1,494.37 Kg 12,381.30 18,502,209.31
- Bekisting A.4.1.1.20 29.49 M2 73,994.00 2,181,816.68
2 Pile Cap (PC2)
- Beton A.4.1.1.18. 5.06 M3 866,226.40 4,385,271.15
- Besi A.4.1.1.17.b 1,230.13 Kg 12,381.30 15,230,557.77
- Bekisting A.4.1.1.20 31.50 M2 73,994.00 2,330,811.00
3 Pile Cap (PC3)
- Beton A.4.1.1.18. 1.72 M3 866,226.40 1,490,992.19
- Besi A.4.1.1.17.b 548.15 Kg 12,381.30 6,786,831.93
- Bekisting A.4.1.1.20 15.30 M2 73,994.00 1,132,108.20
4 Pekerjaan Tiang Pancang
- Mobilisasi Alat & Tiang Pancang Taksir 1.00 Ls 22,500,000.00 22,500,000.00
- Tiang Pancang Square 20 x 20 Cm K-250 Taksir 630.00 M' 228,000.00 143,640,000.00
- Upah Pemancangan Taksir 630.00 M' 105,000.00 66,150,000.00
- Penyambungan Tiang Pancang Taksir 105.00 Titik 60,000.00 6,300,000.00
- Memecah Kepala Tiang Pancang Taksir 105.00 Titik 50,000.00 5,250,000.00
5 Sloof 25x45 (bentang 4m)
- Beton A.4.1.1.18. 27.46 M3 866,226.40 23,783,761.71
- Besi A.4.1.1.17.b 3,575.03 Kg 12,381.30 44,263,462.24
- Bekisting A.4.1.1.21 86.45 M2 79,385.67 6,862,732.11
6 Sloof 20x35
- Beton A.4.1.1.18. 7.50 M3 866,226.40 6,497,131.11
- Besi A.4.1.1.17.b 1,006.41 Kg 12,381.30 12,460,612.42
- Bekisting A.4.1.1.21 75.01 M2 79,385.67 5,954,321.93
7 Join Pile Ccap, Sloof, Kolom Lt 1
- Besi A.4.1.1.17.b 1,803.26 Kg 12,381.30 22,326,672.63
Jumlah I Rp 435,310,786.25
SUB. TOTAL - A Rp 613,011,435.01
NO JENIS PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 6 7=4x6
B PEKERJAAN LANTAI 1
I PEKERJAAN BETON
1 Pekerjaan Kolom 35x35 cm
- Beton A.4.1.1.18. 18.13 M3 866,226.40 15,704,684.63
- Besi A.4.1.1.17.b 6,016.84 Kg 12,381.30 74,496,336.72
- Bekisting A.4.1.1.22 207.20 M2 138,027.00 28,599,194.40
2 Pekerjaan Kolom 25x30 cm
- Beton A.4.1.1.18. 4.55 M3 866,226.40 3,936,998.99
- Besi A.4.1.1.17.b 959.30 Kg 12,381.30 11,877,428.76
- Bekisting A.4.1.1.22 66.66 M2 138,027.00 9,200,879.82
3 Pekerjaan Tangga Putar
- Beton A.4.1.1.18. 3.32 M3 866,226.40 2,875,958.27
- Besi A.4.1.1.17.b 668.39 Kg 12,381.30 8,275,547.42
- Bekisting Dihitung J 19.80 M2 271,925.00 5,385,338.66
4 Pekerjaan Tangga Belakang
- Beton A.4.1.1.18. 2.78 M3 866,226.40 2,403,880.91
- Besi A.4.1.1.17.b 368.80 Kg 12,381.30 4,566,238.92
- Bekisting Dihitung J 18.09 M2 271,925.00 4,919,123.25
5 Pekerjaan Balok B1 (30/50)
- Beton A.4.1.1.18. 13.70 M3 866,226.40 11,869,727.11
- Besi A.4.1.1.17.b 2,386.39 Kg 12,381.30 29,546,587.85
- Bekisting A.4.1.1.23 127.41 M2 216,490.50 27,583,487.59
6 Pekerjaan Balok B2 (25/45)
- Beton A.4.1.1.18. 5.16 M3 866,226.40 4,468,981.10
- Besi A.4.1.1.17.b 791.69 Kg 12,381.30 9,802,127.54
- Bekisting A.4.1.1.23 56.91 M2 216,490.50 12,319,792.41
7 Pekerjaan Balok B3 (20/40)
- Beton A.4.1.1.18. 2.50 M3 866,226.40 2,168,337.92
- Besi A.4.1.1.17.b 355.58 Kg 12,381.30 4,402,533.76
- Bekisting A.4.1.1.23 33.97 M2 216,490.50 7,354,615.27
8 Pekerjaan Balok (25/50)
- Beton A.4.1.1.18. 10.40 M3 866,226.40 9,010,920.13
- Besi A.4.1.1.17.b 1,570.54 Kg 12,381.30 19,445,337.37
- Bekisting A.4.1.1.23 110.60 M2 216,490.50 23,942,766.85
9 Pekerjaan Pelat Lantai t = 12 cm
- Beton A.4.1.1.18. 64.27 M3 866,226.40 55,668,448.45
- Wiremash A.4.1.1.19 3,851.07 Kg 10,247.95 39,465,523.62
- Floordeck Profil W-960mm, T-0.7 btm Dihitung J 426.09 M2 271,925.00 115,863,353.97
10 Join LT 1
- Beton A.4.1.1.18. 2.94 M3 866,226.40 2,546,705.62
- Besi A.4.1.1.17.b 729.83 Kg 12,381.30 9,036,275.13
- Bekisting A.4.1.1.22 16.80 M2 138,027.00 2,318,853.60
Jumlah I Rp 559,055,986.05
SUB. TOTAL - B Rp 559,055,986.05
C PEKERJAAN LANTAI 2
I PEKERJAAN BETON
1 Pekerjaan Kolom 35x35 cm
- Beton A.4.1.1.18. 16.32 M3 866,226.40 14,134,216.17
- Besi A.4.1.1.19 2,960.57 Kg 10,247.95 30,339,781.49
- Bekisting A.4.1.1.22 186.48 M2 138,027.00 25,739,274.96
2 Pekerjaan Kolom 25x30 cm
- Beton A.4.1.1.18. 3.33 M3 866,226.40 2,884,533.91
- Besi A.4.1.1.19 718.53 Kg 10,247.95 7,363,476.04
- Bekisting A.4.1.1.22 48.84 M2 138,027.00 6,741,238.68
3 Pekerjaan Balok B2 (25/45)
- Beton A.4.1.1.18. 11.51 M3 866,226.40 9,970,469.43
- Besi A.4.1.1.17.b 1,753.11 Kg 12,381.30 21,705,773.91
NO JENIS PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 6 7=4x6
- Bekisting A.4.1.1.23 126.96 M2 216,490.50 27,485,932.64
NO JENIS PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 6 7=4x6
4 Pekerjaan Balok (25/50)
- Beton A.4.1.1.18. 12.11 M3 866,226.40 10,492,167.27
- Besi A.4.1.1.17.b 1,820.70 Kg 12,381.30 22,542,584.34
- Bekisting A.4.1.1.23 128.78 M2 216,490.50 27,878,564.14
5 Pekerjaan Balok 15/45 cm
- Beton A.4.1.1.18. 6.08 M3 866,226.40 5,266,067.48
- Besi A.4.1.1.17.b 828.62 Kg 12,381.30 10,259,435.23
- Bekisting A.4.1.1.23 64.64 M2 216,490.50 13,994,422.20
6 ###
Pekerjaan Tangga Belakang
- Beton A.4.1.1.18. 2.78 M3 866,226.40 2,403,880.91
- Besi A.4.1.1.17.b 368.80 Kg 12,381.30 4,566,238.92
- Bekisting Dihitung J 18.09 M2 271,925.00 4,919,123.25
7 Pekerjaan Pelat Lantai t = 10 cm
- Beton A.4.1.1.18. 49.59 M3 866,226.40 42,955,855.33
- Wiremash A.4.1.1.19 4,056.38 Kg 10,247.95 41,569,577.40
- Floordeck Profil W-960mm, T-0.7 btm Dihitung J 443.85 M2 271,925.00 120,694,591.06
8 Join Lantai 2
- Beton A.4.1.1.18. 2.65 M3 866,226.40 2,292,035.05
- Besi A.4.1.1.19 683.76 Kg 10,247.95 7,007,137.08
- Bekisting A.4.1.1.22 15.12 M2 138,027.00 2,086,968.24
Jumlah I Rp 465,293,345.13
SUB. TOTAL - C Rp 465,293,345.13
1 2 3 4 5 6 7=4x6
PEKERJAAN ARSITEKTUR
A LANTAI 1
I PEKERJAAN DINDING dan SEKAT
1 Pass. 1 Bata Camp. 1 pc : 4 ps (Penahan Tanah) A.4.4.1.9a 40.05 M2 206,956.81 8,287,585.26
2 Pass. 1/2 Bata Camp. 1 pc : 2 ps A.4.4.1.7 65.07 M2 109,059.25 7,096,485.07
3 Pass. 1/2 Bata Camp. 1 pc : 4 ps A.4.4.1.9 564.35 M2 100,870.65 56,926,351.33
Jumlah I Rp 208,329,252.03
II PEKERJAAN BETON NON STRUKTURAL
1 Sloof 15x20 Cm
- Beton A.4.1.1.5 2.68 M3 802,866.60 2,153,288.22
- Besi A.4.1.1.17. 772.46 Kg 11,751.30 9,077,399.08
- Bekisting A.4.1.1.21 35.76 M2 79,385.67 2,838,831.44
2 Kolom Praktis A.4.1.1.35 139.20 M' 78,845.40 10,975,279.68
3 Plat Beton Meja Pantry
- Beton A.4.1.1.5 0.18 M3 802,866.60 140,501.66
- Besi A.4.1.1.17. 15.42 Kg 11,751.30 181,200.85
- Bekisting A.4.1.1.24 1.75 M2 239,040.50 418,320.88
4 Balok Lateh A.4.1.1.36 14.50 M' 97,135.05 1,408,458.23
Jumlah II Rp 27,193,280.03
III PEKERJAAN PLERSTERAN dan ACIAN
1 Plesteran 1: 2 A.4.4.2.2 133.03 M2 63,853.25 8,494,558.07
2 Plesteran 1: 4 A.4.4.2.4 1,124.65 M2 59,659.94 67,096,556.02
3 Plesteran Ciprat (Kemprot) A.4.4.2.23 55.95 M2 48,624.19 2,720,523.54
1 2 3 4 5 6 7=4x6
4 Pekerjaan Pintu P3
- Rangka Kayu, Penutup Poluwood Finsh. HPL Dihitung I 1.60 M2 682,206.04 1,091,529.66
- Engsel Penggantung A.4.6.2.5 3.00 Set 30,996.00 92,988.00
- Kunci Tanam A.4.6.2.2 1.00 Set 125,760.00 125,760.00
- Door Stoper A.4.6.2.13 1.00 Set 38,960.00 38,960.00
5 Pekerjaan Pintu P3A (pintu geser)
- Rangka Kayu, Penutup Poluwood Finsh. HPL Dihitung I 1.60 M2 682,206.04 1,091,529.66
- Rel Penggantung Hagra Satuan 1.00 Set 235,000.00 235,000.00
- Kunci Tanam A.4.6.2.2 1.00 Set 125,760.00 125,760.00
6 Pekerjaan Pintu P4
- Rangka Kayu, Penutup Poluwood Finsh. HPL Dihitung I 3.36 M2 682,206.04 2,292,212.28
- Engsel Penggantung Hagra Satuan 6.00 Set 235,000.00 1,410,000.00
- Kunci Tanam A.4.6.2.2 2.00 Set 125,760.00 251,520.00
- Door Stoper A.4.6.2.13 2.00 Set 38,960.00 77,920.00
7 Pekerjaan Pintu P6 (shaff) Aluminium Warna Putih Dihitung C 0.72 M2 681,057.40 490,361.33
- Kusen dan Daun Pintu Aluminium
8 Pekerjaan Jendela J1 Aluminium Warna Putih
- Type J1 Kusen Aluminium Harga Satuan 38.4 M' 178,600.00 6,858,240.00
- Daun Jendela Almunium dan Kaca + Acsesoris Taksir 5.07 M2 450,000.00 2,281,500.00
Komplit (terpasang)
- Kaca bening t-5 mm A.4.6.2.17 3.51 M2 152,739.60 536,116.00
9 Pekerjaan Jendela J2 Aluminium Warna Putih
- Type J2 kusen Aluminium Harga Satuan 9.30 M' 178,600.00 1,660,980.00
- Daun Jendela Almunium dan Kaca + Acsesoris Taksir 1.43 M2 450,000.00 643,500.00
Komplit (terpasang)
10 Pekerjaan Jendela J3 Aluminium Warna Putih
- Type J3 kusen Aluminium Harga Satuan 109.60 M' 178,600.00 19,574,560.00
- Daun Jendela Almunium dan Kaca + Acsesoris Taksir 17.00 M2 450,000.00 7,650,000.00
Komplit (terpasang)
- Kaca bening t-5 mm A.4.6.2.17 17.00 M2 152,739.60 2,596,573.20
11 Pekerjaan Jendela J4 Aluminium Warna Putih
- Type J3 kusen Aluminium Harga Satuan 60.00 M' 178,600.00 10,716,000.00
- Daun Jendela Almunium dan Kaca + Acsesoris Taksir 9.35 M2 450,000.00 4,205,250.00
Komplit (terpasang)
- Kaca bening t-5 mm A.4.6.2.17 7.80 M2 152,739.60 1,191,368.88
12 Pekerjaan Jendela J5 Aluminium Warna Putih
- Type J5 kusen Aluminium Harga Satuan 14.60 M' 178,600.00 2,607,560.00
- Daun Jendela Almunium dan Kaca + Acsesoris Taksir 1.96 M2 450,000.00 882,000.00
Komplit (terpasang)
- Kaca bening t-5 mm A.4.6.2.17 2.90 M2 152,739.60 442,562.99
13 Pekerjaan Jendela J6 Aluminium Warna Putih
- Type J6 kusen Aluminium Harga Satuan 4.50 M' 178,600.00 803,700.00
- Daun Jendela Almunium dan Kaca + Acsesoris Taksir 0.55 M2 450,000.00 247,500.00
Komplit (terpasang)
Jumlah IV Rp 105,917,999.25
V PEKERJAAN PENUTUP LANTAI dan DINDING
1 Pasangan Lantai Geranite 60x60 cm A.4.4.3.9.a 499.78 M2 268,722.76 134,300,917.38
2 Pasangan Lantai Keramik KM 40 x40 cm (selasar) A.4.4.3.35b 45.04 M2 218,607.25 9,846,070.54
3 Pasangan Lantai Keramik KM 30 x30 cm A.4.4.3.35 21.25 M2 213,982.00 4,546,582.55
4 Pasangan Dinding Keramik 30 x 60 cm A.4.4.3.54.a 89.53 M2 265,656.24 23,784,203.17
5 Pasangan Dinding Granite Hitam 60 x 60 cm Ent TAKSIR 14 22.79 M2 384,947.91 8,772,962.79
5 Plint Geranit 10x60 Cm A.4.4.3.41a 107.95 M2 57,273.08 6,182,629.42
6 Plint Keramik 10x40 Cm A.4.4.3.41b 90.10 M2 32,915.52 2,965,688.08
6 Antislip Tangga (10x60 Cm) Granite A.4.4.3.41a 109.50 M' 57,273.08 6,271,402.70
Jumlah V Rp 196,670,456.62
NO JENIS PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 6 7=4x6
VI PEKERJAAN ATAP ENTRANCE
1 Pemasangan Rangka Kuda-Kuda Pipa Besi Taksir 17.94 M2 640,000.00 11,481,600.00
2 Penutup Atap Kaca Temperet Tebal 12 mm Taksir 17.94 M2 1,200,000.00 21,528,000.00
3 Text & Logo Sucofindo (Akrilik) Taksir 1.00 Ls 4,200,000.00 4,200,000.00
Jumlah VI Rp 37,209,600.00
VII PEKERJAAN PLAFOND
1 Pemasangan Rangka Furing Plafond Supl. PPL 6.1 469.10 M2 71,150.00 33,376,465.00
2 Pemasangan Plafond Gypsum tebal 9 mm A.4.5.1.7 469.10 M2 42,695.00 20,028,224.50
Jumlah IX Rp 46,133,103.39
SUB. TOTAL - A Rp 860,795,993.23
B LANTAI 2
I PEKERJAAN DINDING dan SEKAT
1 Pass. 1/2 Bata Camp. 1 pc : 2 ps A.4.4.1.7 32.10 M2 109,059.25 3,500,801.76
2 Pass. 1/2 Bata Camp. 1 pc : 4 ps A.4.4.1.9 300.12 M2 100,870.65 30,273,299.48
Dinding Kaca T-8 mm Rangka Aluminium
3 Warna Putih TAKSIR 15 151.42 M2 738,970.00 111,894,837.40
1 2 3 4 5 6 7=4x6
II PEKERJAAN BETON NON STRUKTURAL
1 Kolom Praktis A.4.1.1.35 58.80 M' 78,845.40 4,636,109.52
2 Balok Lateh A.4.1.1.36 59.00 M' 97,135.05 5,730,967.95
3 Kisi - Kisi (Secondary skin)
- Beton A.4.1.1.5 15.70 M3 802,866.60 12,608,217.09
- Besi A.4.1.1.17. 1,369.31 Kg 11,751.30 16,091,124.64
- Bekisting A.4.1.1.22 152.25 M2 138,027.00 21,014,610.75
Jumlah II Rp 60,081,029.95
III PEKERJAAN PLERSTERAN dan ACIAN
1 Plesteran 1: 2 A.4.4.2.2 45.87 M2 63,853.25 2,928,789.15
2 Plesteran 1: 4 A.4.4.2.4 600.24 M2 59,659.94 35,810,284.79
Jumlah IV Rp 43,751,646.17
V PEKERJAAN PENUTUP LANTAI dan DINDING
1 Pasangan Lantai Geranite 60x60 cm A.4.4.3.9.a 444.39 M2 268,722.76 119,417,707.32
2 Pasangan Lantai Keramik KM 40 x40 cm (selasar) A.4.4.3.35b 27.00 M2 218,607.25 5,902,395.75
3 Pasangan Lantai Keramik KM 30 x30 cm A.4.4.3.35 18.33 M2 213,982.00 3,922,825.02
4 Pasangan Dinding Keramik 30 x 60 cm A.4.4.3.35 74.12 M2 213,982.00 15,860,345.84
5 Plint Geranit 10x60 Cm (Rata Plesteran) A.4.4.3.41a 77.60 M' 57,273.08 4,444,391.32
6 Plint Keramik 10/40 A.4.4.3.41b 22.50 M' 32,915.52 740,599.13
NO JENIS PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 6 7=4x6
5 Antislip Tangga (10x60 Cm) Granite A.4.4.3.41a 26.40 M' 57,273.08 1,512,009.42
Jumlah V Rp 151,800,273.79
NO JENIS PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 6 7=4x6
VI PEKERJAAN ATAP
1 Rangka Kuda-Kuda Baja Ringan C-75.75 Harga Satuan 145.28 M2 115,000.00 16,707,200.00
2 Penutup Atap Metal Spandek T-0.35 mm A.4.5.2.40 145.28 M2 75,830.00 11,016,582.40
3 Rabung Atap Metal Spandek 0.35 Mm A.4.5.2.41 22.70 M' 48,085.00 1,091,529.50
4 List Plank Kayu A.4.6.1.21 45.40 M' 104,800.00 4,757,920.00
Jumlah VI Rp 33,573,231.90
VII PEKERJAAN PLAFOND
1 Pemasangan Rangka Furing Plafond Supl. PPL 6.1 575.50 M2 71,150.00 40,946,825.00
2 Pemasangan Plafond Gypsum tebal 9 mm A.4.5.1.7 537.00 M2 42,695.00 22,927,215.00
3 Pemasangan Plafond Calsiboard tebal 6 mm A.4.5.1.7.a 48.00 M2 79,459.00 3,814,032.00
Jumlah IX Rp 103,797,221.14
SUB. TOTAL - B Rp 842,199,472.88
C LANTAI ATAP
I PEKERJAAN DINDING DAN PLASTERAN
1 Pasangan Batu-Bata 1/2 Camp. 1 : 4 A.4.4.1.9 204.44 M2 109,059.25 22,296,481.02
2 Pasangan Roster A. 4.4.1.23 1.65 M2 638,154.10 1,052,954.27
3 Pasangan Galssblock A.4.4.1.23a 0.83 M2 718,620.65 592,862.04
4 Plasteran 1 : 4 Tebal 1,5 cm A.4.4.2.4 408.89 M2 59,659.94 24,394,205.35
5 Pintu Besi Tangga Harag Satuan 2.52 M2 800,000.00 2,016,000.00
Jumlah I Rp 50,352,502.67
NO JENIS PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 6 7=4x6
II PEKERJAAN BETON NON STRUKTURAL
1 Kolom Praktis A.4.1.1.35 51.60 M' 78,845.40 4,068,422.64
2 Rink Balok A.4.1.1.36 169.90 M' 97,135.05 16,503,245.00
Jumlah II Rp 20,571,667.64
III PEKERJAAN LANTAI
1 Pasangan Lantai Keramik 40x40 cm A.4.4.3.35b 2.40 M2 218,607.25 524,657.40
2 Waterproofing Dak Beton Dihitung D 14.56 M2 101,480.00 1,477,548.80
Jumlah IV Rp 2,002,206.20
IV PEKERJAAN PENGECATAN
1 Cat Tembok Eksterior (watershil) A.4.7.1.10a 408.89 M2 34,099.50 13,942,859.31
Jumlah V Rp 13,942,859.31
SUB. TOTAL - C Rp 86,869,235.81
1 2 3 4 5 6 7=4x6
LANTAI 1
A PLUMBING ( PEMIPAAN )
a Instalasi pipa air kotor dan bekas PVC class AW 10 kg/cm 14,401,800.00
Lantai 1
1 Dia. 4" ( 100 mm ) Dihitung 63.00 M' 125,000.00 7,875,000.00
2 Dia. 3" ( 80 mm ) Dihitung 29.00 M' 87,500.00 2,537,500.00
3 Dia. 2" ( 50 mm ) Dihitung 3.00 M' 47,100.00 141,300.00
4 Dia. 1 1/4" ( 32 mm ) Dihitung 6.00 M' 33,000.00 198,000.00
5 Fitting dan acessories Dihitung 1.00 Ls 2,100,000.00 2,100,000.00
6 Material bantu Dihitung 1.00 Ls 1,050,000.00 1,050,000.00
7 Test commisioning Dihitung 1.00 Ls 500,000.00 500,000.00
C Septick Tank Instalasi pipa buangan tinja PVC class AW 10 kg/cm 24,450,199.99
Lantai 1
1 Dia. 4" ( 100 mm ) Dihitung 36.00 M' 125,000.00 4,500,000.00
2 Material bantu Dihitung 1.00 Ls 220,000.00 220,000.00
3 Test commisioning Dihitung 1.00 Ls 445,000.00 445,000.00
4 Septick Tank
Galian Tanah A.2.3.1.1 24.98 M3 74,050.00 1,849,398.75
Pasir Urug A.2.3.1.11 0.68 M3 153,220.00 103,423.50
Rabat Beton A.4.1.1.2 1.62 M3 748,141.60 1,211,989.39
Kolom 15x15 cm A.4.1.1.35 36.00 M' 78,845.40 2,838,434.40
Plat Lantai Supl. 01 1.24 M3 3,760,000.00 4,653,000.00
Pasangan Bata A.4.4.1.7 45.05 M2 109,059.25 4,912,573.69
Plesteran A.4.4.2.2 52.47 M2 63,853.25 3,350,380.26
Pipa Besi Hawa Taksir 3.00 Unit 122,000.00 366,000.00
B PEKERJAAN LISTRIK
Lantai 1
1 Main Distribution panel ( MDP ) c/w interlock manual + ATS / AMF sistem automatis Dihitung 1.00 Unit 24,500,000.00 24,500,000.00
2 Panel sub distribution ( SDP ) lantai 1 Dihitung 1.00 Unit 6,800,000.00 6,800,000.00
3 Panel sub distribution ( SDP ) AC lantai 1 Dihitung 1.00 Unit 6,550,000.00 6,550,000.00
4 Panel sub distribution ( SDP ) pompa Dihitung 1.00 Unit 2,700,000.00 2,700,000.00
Lantai 1
a Armature penerangan 21,422,000.00
1 Downlight dia.4" + bola lampu LED 9 Wat Dihitung 11.00 Bh 149,000.00 1,639,000.00
2 Downlight dia.4" + bola lampu LED 7 Wat Dihitung 12.00 Bh 112,000.00 1,344,000.00
3 TLD RM LED ( 3 x 8 Wat ) Dihitung 18.00 Bh 500,000.00 9,000,000.00
4 TLD RM LED ( 2 x 8 Wat ) Dihitung 10.00 Bh 350,000.00 3,500,000.00
5 Baret 22 wat Dihitung 9.00 Bh 356,000.00 3,204,000.00
6 Stop kontak Dihitung 57.00 Bh 33,000.00 1,881,000.00
7 Saklar tunggal Dihitung 7.00 Bh 37,000.00 259,000.00
8 Saklar Ganda Dihitung 14.00 Bh 42,500.00 595,000.00
LANTAI 1
Unit AC :
AC Split Wall Mounted
1 - Ac kapasitas 18000 btu/h ( 2 PK ) Dihitung 7.00 Unit 6,800,000.00 47,600,000.00
2 - Ac kapasitas 12000 btu/h ( 1 1/2 PK ) Dihitung 2.00 Unit 5,000,000.00 10,000,000.00
3 - Ac kapasitas 7000 btu/h ( 3/4 PK ) Dihitung 6.00 Unit 4,000,000.00 24,000,000.00
4 - Ac kapasitas 5000 btu/h ( 1/2 PK ) Dihitung 2.00 Unit 3,850,000.00 7,700,000.00
5 Pipa Refrigrant + Kable Control ac 1/2 S/D 1 PK Dihitung 79.00 M' 80,500.00 6,359,500.00
6 Pipa Refrigrant + Kable control ac 1 1/2 PK Dihitung 21.00 M' 105,000.00 2,205,000.00
7 Pipa Refrigrant + Kable control ac 2 PK Dihitung 51.00 M' 125,000.00 6,375,000.00
Pipa drain
8 Pipa Drain pipa dia. 3/4 " + isolation ac 1/2 S/D 2 PK Dihitung 121.00 M' 23,000.00 2,783,000.00
9 Axial Fan Type Dihitung 2.00 Unit 1,870,000.00 3,740,000.00
- Kap. 285 Cfm / 18 wat/ 220 V/ 50 hz
10 - Pipa PVC class D 5 kg/cm3 Dihitung 9.00 M' 85,000.00 765,000.00
11 - Flexible Round Duct Dia. 4" Dihitung 6.00 M' 45,000.00 270,000.00
12 - Griell Ex haus fan uk. 40 x 25 cm Dihitung 3.00 Bh 225,000.00 675,000.00
13 Ex haust Fan ceiling Type Dihitung 2.00 Unit 750,000.00 1,500,000.00
- Kap. 285 Cfm / 18 wat/ 220 V/ 50 hz
14 - Pipa PVC class D 5 kg/cm3 Dihitung 1.00 M' 85,000.00 85,000.00
15 - Flexible Round Duct Dia. 4" Dihitung 1.00 M' 45,000.00 45,000.00
16 - Griell Ex haus fan uk. 40 x 25 cm Dihitung 1.00 Bh 225,000.00 225,000.00
17 Material bantu Dihitung 1.00 Ls 2,100,000.00 2,100,000.00
18 Suport dan hanger Dihitung 1.00 Ls 1,100,000.00 1,100,000.00
19 Test Commisioning Dihitung 1.00 Ls 1,000,000.00 1,000,000.00
D PEKERJAAN ELEKTRONIKA
Lantai 1
a Peralatan Utama Fire Alarm 8,700,000.00
1 MCFA Cap. 6 Zone Convensional Dihitung 1.00 Unit 3,550,000.00 3,550,000.00
2 MTBFA Dihitung 1.00 Unit 1,850,000.00 1,850,000.00
3 Pengabelan kabel grounding dari bak kontrol ke unit Main Hub NYA 10 mm Dihitung 1.00 Ls 1,700,000.00 1,700,000.00
4 Kabel dari TB FA ke MCFA kabel FRC 4 x 1,5 mm dalam pipa counduit Dihitung 1.00 Ls 1,600,000.00 1,600,000.00
II SISTEM CCTV
LANTAI 1
a PERALATAN UTAMA 18,050,000.00
1 Digital Video recorder (DVR ) hard disk 2 Terra 8 channel Dihitung 1.00 Unit 3,700,000.00 3,700,000.00
2 Monitor LED 40 inchi Dihitung 1.00 Unit 4,850,000.00 4,850,000.00
3 komputer server c/w keyboard Dihitung 1.00 Unit 5,500,000.00 5,500,000.00
4 back up batery 2 Kva ( UPS ) Dihitung 1.00 Unit 4,000,000.00 4,000,000.00
LANTAI 1
Armature
1 - camera dome infra red Dihitung 4.00 Unit 670,000.00 2,680,000.00
Instalasi
1 Kabel power NYM 3 x 1,5 mm + pipa counduit Dihitung 4.00 Titik 220,000.00 880,000.00
2 kabel coaxial + pipa counduit Dihitung 4.00 Titik 300,000.00 1,200,000.00
3 material bantu Dihitung 1.00 Ls 550,000.00 550,000.00
4 Test commisioning Dihitung 1.00 Ls 750,000.00 750,000.00
a INSTALASI
1 Instalasi kabel telephone ITC 2x2x0,6 mm + dalam pipa couduit PVC Dihitung 7.00 Titik 175,000.00 1,225,000.00
2 Outlet telepon Dihitung 7.00 Bh 55,000.00 385,000.00
3 TB telepon Dihitung 1.00 Bh 950,000.00 950,000.00
4 Material bantu Dihitung 1.00 Ls 450,000.00 450,000.00
5 Test commisioning Dihitung 1.00 Ls 350,000.00 350,000.00
LANTAI 1
a PERALATAN UTAMA 22,300,000.00
1 - Amplifier Kap. 240 Wat Dihitung 1.00 Unit 4,500,000.00 4,500,000.00
2 - Mixer Pre Amplifier Kap. 240 Wat Dihitung 1.00 Unit 3,200,000.00 3,200,000.00
3 - Paging Microphone Dihitung 1.00 Bh 1,400,000.00 1,400,000.00
4 - Rak kabinet untuk penempatan peralatan Tata Suara Dihitung 1.00 Unit 8,900,000.00 8,900,000.00
5 - MDFTS ( 20 pair ) Dihitung 1.00 Unit 2,300,000.00 2,300,000.00
6 - Pengkabelan instalasi utama Dihitung 1.00 Ls 1,200,000.00 1,200,000.00
7 - Test commisioning Dihitung 1.00 Ls 800,000.00 800,000.00
VI SISTEM MATV
1 Instalasi MATV Kabel coaxial RG 6 Vol Dihitung 36.00 M' 195,000.00 7,020,000.00
2 Outlet TV Dihitung 1.00 Bh 75,000.00 75,000.00
3 Acessories Dihitung 1.00 Ls 150,000.00 150,000.00
4 Stopkontak TV Dihitung 1.00 Ttk 195,000.00 195,000.00
TOTAL 32,707,500.00
LANTAI 2
A PLUMBING ( PEMIPAAN )
a Instalasi pipa air kotor dan bekas PVC class AW 10 kg/cm 9,866,500.00
Lantai 2
1 Dia. 4" ( 100 mm ) Dihitung 31.00 M' 125,000.00 3,875,000.00
2 Dia. 3" ( 80 mm ) Dihitung 28.00 M' 87,500.00 2,450,000.00
3 Dia. 2" ( 50 mm ) Dihitung 15.00 M' 47,100.00 706,500.00
4 Dia. 1 1/4" ( 32 mm ) Dihitung 5.00 M' 33,000.00 165,000.00
5 Fitting dan acessories Dihitung 1.00 Ls 1,450,000.00 1,450,000.00
6 Material bantu Dihitung 1.00 Ls 720,000.00 720,000.00
7 Test commisioning Dihitung 1.00 Ls 500,000.00 500,000.00
B PEKERJAAN LISTRIK
Lantai 2
1 Panel sub distribution ( SDP ) lantai Dihitung 1.00 Unit 6,800,000.00 6,800,000.00
2 Panel sub distribution ( SDP ) AC lantai 2 Dihitung 1.00 Unit 6,050,000.00 6,050,000.00
Lantai 2
a Armature penerangan 23,429,800.00
1 Downlight dia.4" + bola lampu LED 9 Wat Dihitung 29.00 Bh 149,000.00 4,321,000.00
2 Downlight dia.4" + bola lampu LED 7 Wat Dihitung 7.00 Bh 112,000.00 784,000.00
3 Lampu spotlight LED 20 Wat Dihitung 2.00 Bh 325,000.00 650,000.00
4 TLD RM LED ( 3 x 8 Wat ) Dihitung 23.00 Bh 500,000.00 11,500,000.00
5 TLD RM LED ( 2 x 8 Wat ) Dihitung 6.00 Bh 350,000.00 2,100,000.00
6 Baret 22 wat Dihitung 2.00 Bh 356,000.00 712,000.00
7 Stop kontak Dihitung 54.00 Bh 33,000.00 1,782,000.00
8 Stop kontak lantai stainless steel Dihitung 3.00 Bh 275,000.00 825,000.00
9 Saklar tunggal Dihitung 6.00 Bh 33,000.00 198,000.00
10 Saklar Ganda Dihitung 12.00 Bh 42,500.00 510,000.00
11 Saklar triple Dihitung 1.00 Bh 47,800.00 47,800.00
LANTAI 2
Unit AC Split wall mounted:
1 - Ac kapasitas 18000 btu/h ( 2 PK ) Dihitung 9.00 Unit 6,800,000.00 61,200,000.00
2 - Ac kapasitas 9000 btu/h ( 1 PK ) Dihitung 1.00 Unit 4,542,500.00 4,542,500.00
3 - Ac kapasitas 7000 btu/h ( 3/4 PK ) Dihitung 4.00 Unit 4,000,000.00 16,000,000.00
4 Pipa Refrigrant + Kable Control + ac 1/2 S/D 1 PK Dihitung 51.00 M' 80,500.00 4,105,500.00
5 Pipa Refrigrant + Kable Control +isolation ac 2 PK Dihitung 69.00 M' 125,000.00 8,625,000.00
6 Pipa Drain dia. 3/4 mm + isolation Dihitung 94.00 M' 23,000.00 2,162,000.00
7 Exhaust Fan Ceiling Mount Type Dihitung 1.00 Unit 750,000.00 750,000.00
- Kap. 285 Cfm / 18 wat/ 220 V/ 50 hz
8 - Pipa PVC class D 5 kg/cm3 Dihitung 1.00 M' 85,000.00 85,000.00
9 - Flexible Round Duct Dia. 4" Dihitung 1.00 M' 45,000.00 45,000.00
10 - Griell Ex haus fan uk. 40 x 25 cm Dihitung 1.00 Bh 225,000.00 225,000.00
11 Axial Fan Type Dihitung 2.00 Unit 1,870,000.00 3,740,000.00
- Kap. 285 Cfm / 18 wat/ 220 V/ 50 hz
12 - Pipa PVC class D 5 kg/cm3 Dihitung 4.00 M' 85,000.00 340,000.00
13 - Flexible Round Duct Dia. 4" Dihitung 3.00 M' 45,000.00 135,000.00
14 - Griell Ex haus fan uk. 40 x 25 cm Dihitung 1.00 Bh 225,000.00 225,000.00
15 Material bantu Dihitung 1.00 Ls 1,250,000.00 1,250,000.00
16 Suport dan hanger Dihitung 1.00 Ls 960,000.00 960,000.00
17 Test Commisioning Dihitung 1.00 Ls 1,200,000.00 1,200,000.00
D PEKERJAAN ELEKTRONIKA
Lantai 2
Armature dan instalasi fire alarm 3,610,000.00
a Armature
1 Smoke Detector Dihitung 18.00 Bh 115,000.00 2,070,000.00
2 Alarm Bell Dihitung 2.00 Bh 340,000.00 680,000.00
3 Lampu Indikator Dihitung 2.00 Bh 110,000.00 220,000.00
4 Manual Push Buton Dihitung 2.00 Bh 320,000.00 640,000.00
II SISTEM CCTV
LANTAI 2
a Armature
1 - camera dome infra red Dihitung 2.00 Unit 670,000.00 1,340,000.00
INSTALASI
1 Instalasi kabel telephone ITC 2x2x0,6 mm + dalam pipa couduit PVC Dihitung 6.00 Titik 175,000.00 1,050,000.00
2 Outlet telepon Dihitung 6.00 Bh 55,000.00 330,000.00
3 TB telephone Dihitung 1.00 Bh 950,000.00 950,000.00
4 Material bantu Dihitung 1.00 Ls 400,000.00 400,000.00
5 Test commisioning Dihitung 1.00 Ls 800,000.00 800,000.00
Lantai 2
ARMATURE & INSTALASI
1 Instalasi internet / data system kabel UTP Cat.6 + PVC Conduit Dihitung 41.00 Titik 210,000.00 8,610,000.00
2 Outlet data conector cat 6 Dihitung 41.00 Bh 75,000.00 3,075,000.00
3 Switch 16 Port 10/100 Mbps Dihitung 3.00 Bh 785,000.00 2,355,000.00
4 Material Bantu Dihitung 1.00 Ls 860,000.00 860,000.00
5 Testing & Commissioning Dihitung 1.00 Ls 800,000.00 800,000.00
VI SISTEM MATV
1 Instalasi MATV Kabel coaxial RG 6 Vol Dihitung 24.00 M' 198,000.00 4,752,000.00
2 Spiter 4 way Dihitung 1.00 Bh 385,000.00 385,000.00
3 Antena TV Dihitung 1.00 Bh 175,000.00 175,000.00
4 Outlet TV Dihitung 2.00 Bh 75,000.00 150,000.00
5 Acessories Dihitung 1.00 Ls 150,000.00 150,000.00
6 Stopkontak TV Dihitung 2.00 Ttk 195,000.00 390,000.00
Penangkal petir light Thomas Radius 125 mtr Dihitung 1.00 Unit 8,700,000.00 8,700,000.00
Pengadaan pipa galvavis Diameter 2 inci dan 1,5" Dudukan antena Petir Dihitung 10.00 M' 350,000.00 3,500,000.00
Pengadaan pondasi Tiang penangkal petir Dihitung 1.00 Bh 890,000.00 890,000.00
Pengadaan Sling baja 3 mm Dihitung 60.00 M' 7,500.00 450,000.00
Pengadaan kabel Penghantar Nyy 1 x 50 mm Dihitung 41.00 M' 95,600.00 3,919,600.00
Pengadaan kabel Bc 50 mm untuk Arde / Grounding Dihitung 36.00 M' 95,600.00 3,441,600.00
Pengadaan Box panel Kontrol Arde anti Petir komplit Busbar Arde Dihitung 1.00 Unit 750,000.00 750,000.00
Pengadaan kabel Nyy 3 x 1,5mm untuk lampu indikator tower Dihitung 50.00 M' 18,600.00 930,000.00
Skun Kabel Bimetal dan sarung 50 mm , 25 mm Dihitung 4.00 Bh 12,000.00 48,000.00
Pengadaan Lampu tower komplit kap , Foto cell Celcon dan breaket Dihitung 1.00 Unit 1,650,000.00 1,650,000.00
Test Merger grounding 5 Ohm Dihitung 1.00 Ls 650,000.00 650,000.00
1 2 3 4 5 6 7=4x6
PEKERJAAN LANSEKAP
I PEKERJAAN PENINGGIAN HALAMAN
1 Dinding Penahan Tanah
- Galian Tanah A.2.3.1.1 10.51 M3 74,050.00 778,413.60
- Pasir Urug A.2.3.1.11 0.88 M3 153,220.00 134,220.72
- Pondasi Tapak Beton Betulang Uk. 90x90x25Cm
Beton A.4.1.1.5 2.84 M3 802,866.60 2,276,126.81
Besi A.4.1.1.17. 208.90 Kg 11,751.30 2,454,822.13
Bekisting A.4.1.1.20 6.30 M2 73,994.00 466,162.20
- Sloof 25x25 Cm
Beton A.4.1.1.5 2.23 M3 802,866.60 1,786,378.19
Besi A.4.1.1.17. 171.27 Kg 11,751.30 2,012,634.07
Bekisting A.4.1.1.21 8.90 M2 79,385.67 706,532.43
- Kolom 25x25 Cm
Beton A.4.1.1.5 1.44 M3 802,866.60 1,159,138.65
Besi A.4.1.1.17. 134.71 Kg 11,751.30 1,582,970.62
Bekisting A.4.1.1.22 11.55 M2 138,027.00 1,594,211.85
- Balok 25x25 Cm
Beton A.4.1.1.5 1.17 M3 802,866.60 938,350.34
Besi A.4.1.1.17. 101.50 Kg 11,751.30 1,192,736.47
Bekisting A.4.1.1.23 4.68 M2 216,490.50 1,012,093.09
- Pasangan 1 Bata A.4.4.1.9a 17.80 M2 206,956.81 3,683,831.13
2 Ramp
- Whiremash M-6 A.4.1.1.19 296.06 Kg 10,247.95 3,033,978.80
- Rabat Beton Dipola Garis A.4.1.1.5 4.80 M3 802,866.60 3,853,759.68
3 Penimbunan Halaman Dengan Tanah Timbun A.2.3.1.11.a 740.00 M3 153,220.00 113,382,800.00
4 Pemadatan Tanah Timbun A.2.3.1.10 740.00 M3 53,100.00 39,294,000.00
5 Pasir Urug A.2.3.1.11 48.30 M3 153,220.00 7,400,526.00
6 Pasangan Grassblock Dihitung H 690.00 M2 241,152.00 166,394,880.00
7 Rolag Bata Kuncian Grass Block A.4.4.2.2 48.00 M2 63,853.25 3,064,956.21
8 Plesteran A.4.4.2.4 72.00 M2 59,659.94 4,295,515.97
Jumlah I Rp 362,499,038.95
II PEKERJAAN PAGAR
1 Pagar Depan
- Galian Tanah A.2.3.1.1 0.58 M3 74,050.00 42,652.80
- Pasir urug A.2.3.1.11 0.07 M3 153,220.00 11,031.84
- Rabat Beton A.4.1.1.5 0.07 M3 802,866.60 57,806.40
- Pondasi Tapak Beton Betulang Uk. 50x50x20 Cm
Beton A.4.1.1.5 0.29 M3 802,866.60 231,225.58
Besi A.4.1.1.17. 19.74 Kg 11,751.30 231,937.09
Bekisting A.4.1.1.20 0.48 M2 73,994.00 35,517.12
- Sloof 15x20 Cm
Beton A.4.1.1.5 0.33 M3 802,866.60 264,945.98
Besi A.4.1.1.17. 35.28 Kg 11,751.30 414,587.54
Bekisting A.4.1.1.21 2.20 M2 79,385.67 174,648.47
- Kolom 15x15 cm A.4.1.1.35 18.20 M' 78,845.40 1,434,986.28
- Ring Blaok A.4.1.1.36 27.50 M' 97,135.05 2,671,213.88
- Beton Dudukan Text A.4.1.1.5 0.60 M3 802,866.60 481,719.96
- Pas. Bata 1/2 Camp 1:2 A.4.4.2.2 55.00 M2 63,853.25 3,511,928.99
- Plesteran Camp. 1:4 A.4.4.2.4 55.00 M2 59,659.94 3,281,296.92
- Pekerjaan Relifan Taksir 63.00 M' 62,000.00 3,906,000.00
NO JENIS PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 6 7=4x6
- Pintu Sorong Pagar (Hollow + Plat Baja Taksir 24.00 M2 700,000.00 16,800,000.00
1.6 MM) Finsh Cat Besi
- Text Steanless Steel "SUCOFINDO - MEDAN" Taksir 1.00 Unit 7,000,000.00 7,000,000.00
- Cat Tembok Eksterior (watershil) A.4.7.1.10a 110.00 M2 34,099.50 3,750,945.00
2 Pagar Samping
- Kolom 15x15 cm A.4.1.1.35 30.00 M' 78,845.40 2,365,362.00
- Ring Blaok A.4.1.1.36 96.00 M' 97,135.05 9,324,964.80
- Pas. Bata 1/2 Camp 1:2 A.4.4.2.2 96.00 M2 63,853.25 6,129,912.42
- Plesteran Camp. 1:4 A.4.4.2.4 192.00 M2 59,659.94 11,454,709.25
- Pekerjaan Relifan Taksir 96.00 M' 62,000.00 5,952,000.00
- Cat Tembok A.4.7.1.10 384.00 M2 18,679.50 7,172,928.00
Jumlah II Rp 86,702,320.31
III PEKERJAAN DEKORATIF LANSEKAP
1 Pekerjaan Tiang Bendera
- Galian Tanah A.2.3.1.1 0.43 M3 74,050.00 31,989.60
- Pasir urug A.2.3.1.11 0.03 M3 153,220.00 3,861.14
- Rabat Beton A.4.1.1.5 0.03 M3 802,866.60 20,232.24
- Pondasi Tiang Bendera
Beton A.4.1.1.5 0.25 M3 802,866.60 200,716.65
Besi A.4.1.1.17. 17.76 Kg 11,751.30 208,743.38
Bekisting A.4.1.1.20 1.00 M2 73,994.00 73,994.00
- Pas. Bata 1/2 Camp 1:2 A.4.4.2.2 2.40 M2 63,853.25 153,247.81
- Plesteran Camp. 1:4 A.4.4.2.4 2.40 M2 59,659.94 143,183.87
- Pekerjaan Relifan Taksir 6.00 M' 62,000.00 372,000.00
- Cat Tembok Eksterior (watershil) A.4.7.1.10a 2.40 M2 34,099.50 81,838.80
2 Rumput Gajah Mini Taksir 462.50 M2 33,000.00 15,262,500.00
3 Vegetasi (Pohon Peneduh) T- 7 M Taksir 22.00 Btg 700,000.00 15,400,000.00
4 Perdu Taksir 1.00 Ls 250,000.00 250,000.00
1 2 3 4 5 6 7=4x6
4 Pekerjaan Atap
- Rangka Atap Baja Ringan Harga Satuan 177.55 M2 115,000.00 20,418,250.00
- Atap Metal Spandeg Tebal 0.35 mm A.4.5.2.40 177.55 M2 75,830.00 13,463,616.50
- Rabung Atap Metal Tebal 0.35 mm A.4.5.2.41 32.00 M' 48,085.00 1,538,720.00
- Listplang Kayu A.4.6.1.21 49.80 M' 104,800.00
6 Pekerjaan Lantai dan Dinding
- Pengurukan Peninggian Lantai A.2.3.1.11.a 154.00 M3 153,220.00 23,596,263.05
- Pasir Urug Bawah Lantai A.2.3.1.11 7.70 M3 153,220.00 1,179,813.15
- Plat Wiremash M-6 A.4.1.1.19 142.11 Kg 10,247.95 1,456,309.82
- Rabat Beton t- 10 Cm A.4.1.1.5 15.40 M3 802,866.60 12,364,346.36
9 Pekerjaan Plumbing Dihitung
- Intalasi Air Bersih Dihitung 18.00 M' 29,500.00 531,000.00
- Intalasi Air Kotor Dia 4 inc Dihitung 6.00 M' 87,500.00 525,000.00
- Floor Drain Dihitung 2.00 Bh 89,010.00 178,020.00
- Krain 3/4 Dihitung 6.00 Bh 68,585.00 411,510.00
- Closet Jongkok A.5.1.1.2 2.00 Unit 543,228.60
Jumlah IV Rp 144,300,062.26
V PEKERJAAN POS JAGA
1 Pekerjaan Beton
- Balok 15x25 Cm
Beton A.4.1.1.5 1.02 M3 802,866.60 821,934.68
Besi A.4.1.1.17. 108.06 Kg 11,751.30 1,269,894.21
Bekisting A.4.1.1.23 6.14 M2 216,490.50 1,329,792.90
- Dak Beton
Beton A.4.1.1.5 3.49 M3 802,866.60 2,804,413.03
Besi A.4.1.1.17. 232.68 Kg 11,751.30 2,734,277.32
Bekisting A.4.1.1.24 17.47 M2 239,040.50 4,174,842.33
- Kolom Praktis A.4.1.1.35 36.00 M' 78,845.40 2,838,434.40
- Relifan Taksir 35.20 M' 70,000.00 2,464,000.00
2 Pekerjaan Dinding dan Plesteran
- Pas. Bata 1/2 Camp 1:4 A.4.4.1.9 17.61 M3 100,870.65 1,776,332.15
- Pas. RosterCamp 1:4 A. 4.4.1.23 0.48 M2 638,154.10 306,313.97
- Pas. Glass Block Camp 1:4 A.4.4.1.23a 0.24 M2 718,620.65 172,468.96
- Plesteran Camp. 1:4 A.4.1.1.5 35.22 M2 59,659.94 2,101,223.23
3 Pekerjaan Pintu Aluminium KM Taksir 2.00 Unit 1,000,000.00 2,000,000.00
4 Pekerjaan Lantai dan Dinding
- Rabat Beton t- 10 Cm A.4.1.1.5 1.39 M3 802,866.60 1,112,773.11
- Lantai Keramik 40x40 cm A.4.4.3.35b 10.92 M2 218,607.25 2,387,191.17
- Lantai Keramik 30x30 cm A.4.4.3.35 4.62 M2 213,982.00 988,596.84
- Dinding Keramik KM Uk. 60x30 cm A.4.4.3.54.a 9.60 M2 265,656.24 2,550,299.90
5 Pekerjaan Dekoratif dan Finishing
- Cat Tembok Interior A.4.7.1.10 74.94 M2 18,679.50 1,399,841.73
- Cat Tembok Eksterior (watershil) A.4.7.1.10a 60.61 M2 34,099.50 2,066,685.45
- Water Proofing Dihitung D 34.93 M2 101,480.00 3,544,696.40
6 Pekerjaan Elektrikal
- Instalasi lampu penerangan kabel Dihitung 4.00 Ttk 190,000.00 760,000.00
NYM 3 x 2,5 mm dalam pipa counduit
- Instalasi stopkontak kabel NYM 3 x 2,5 Dihitung 2.00 Ttk 200,000.00 400,000.00
mm dalam pipa counduit
- Downlight dia.4" + bola lampu LED 9 Wat Dihitung 2.00 Bh 149,000.00 298,000.00
- Downlight dia.4" + bola lampu LED 3 Wat Dihitung 2.00 Bh 112,000.00 224,000.00
- Stop Kontak Dihitung 2.00 Bh 33,000.00 66,000.00
- Seklar Tunggal Dihitung 2.00 Bh 33,000.00 66,000.00
- Seklar Seri Dihitung 2.00 Bh 42,500.00 85,000.00
7 Pekerjaan Plumbing
- Intalasi Air Bersih Dihitung 24.00 M' 29,500.00 708,000.00
- Intalasi Air Kotor Dihitung 6.00 M' 125,000.00 750,000.00
NO JENIS PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 6 7=4x6
- Intalasi Tinja Dihitung 24.00 M' 125,000.00 3,000,000.00
- Floor Drain Dihitung 1.00 Bh 89,010.00 89,010.00
- Kloset A.5.1.1.2 1.00 Bh 543,228.60 543,228.60
- Krain 3/4 Dihitung 2.00 Bh 68,585.00 137,170.00
Jumlah V Rp 45,970,420.37
VI PEKERJAAN DRAINASE
1 Pekerjaan Tanah
- Galian A.2.3.1.1 23.63 M3 74,050.00 1,749,431.25
- Urugkan Pasir A.2.3.1.11 2.63 M3 153,220.00 402,202.50
2 Rabat Beton A.4.1.1.5 3.94 M3 802,866.60 3,161,287.24
3 Pass.1/2 Bata camp. 1:2 A.4.4.2.2 94.50 M2 63,853.25 6,034,132.54
4 Plesteran camp. 1:4 A.4.4.2.4 94.50 M2 59,659.94 5,637,864.71
5 Riol Beton Dia 30 Cm Harga Satun 15.00 M' 93,000.00 1,395,000.00
6 Grill Besi Taksir 15.75 M2 300,000.00 4,725,000.00
Jumlah VI Rp 23,104,918.24
VII SELASAR PENGHUBUNG BANGUNAN
1 Pekerjaan Tanah
- Galian A.2.3.1.1 3.43 M3 74,050.00 253,991.50
- Urugkan Pasir A.2.3.1.11 2.64 M3 153,220.00 404,500.80
2 Rabat Beton A.4.1.1.5 5.28 M3 802,866.60
3 Pondasi Tapak 60x60x20 cm
- Beton A.4.1.1.5 0.72 M3 802,866.60 578,063.95
- Besi A.4.1.1.17. 49.34 Kg 11,751.30 579,842.72
- Bekisting A.4.1.1.20 2.40 M2 73,994.00 177,585.60
4 Sloof 15x20 cm
- Beton A.4.1.1.5 1.20 M3 802,866.60 963,439.92
- Besi A.4.1.1.17. 128.88 Kg 11,751.30 1,514,549.18
- Bekisting A.4.1.1.21 4.00 M2 79,385.67 317,542.67
5 Kolom 20x20 cm
- Beton A.4.1.1.5 0.94 M3 802,866.60 754,694.60
- Besi A.4.1.1.17. 7.77 Kg 11,751.30 91,296.24
- Bekisting A.4.1.1.22 9.40 M2 138,027.00 1,297,453.80
6 Tiang Pipa Besi T-1.6 mm Ø 4 inc Taksir 23.00 M' 225,000.00 5,175,000.00
7 Pass.1/2 Bata camp. 1:2 A.4.4.2.2 18.40 M2 100,870.65 1,856,019.96
8 Plesteran camp. 1:4 A.4.4.2.4 18.40 M2 59,659.94 1,097,742.97
9 Pekerjaan Atap
- Rangka Atap Hollow Harga Satuan 52.80 M2 425,000.00 22,440,000.00
- Penutup Atap Metal Spandek .35 mm A.4.5.2.40 52.80 M2 75,830.00 4,003,824.00
- Talang Pipa PVC 4 Inac Dihitung 33.00 M' 125,000.00 4,125,000.00
10 Pekerjaan Paving Block Dihitung K 52.80 M2 96,937.00 5,118,273.60
11 Pengecatan Tembok A.4.7.1.10a 34.90 M2 34,099.50 1,190,072.55
12 Pekerjaan Elektrikal
- Instalasi lampu penerangan kabel NYM 3 x 2,5 Dihitung 4.00 Ttk 190,000.00 760,000.00
mm dalam pipa counduit
- Bola lampu LED 9 Wat + Fiting Dihitung 4.00 Bh 85,000.00 340,000.00
PERHITUNGAN VOLUME
KE RAB
NO URAIAN PEKERJAAN P L T JLH UNIT LUAS KONST VOL
VOL SAT
KE RAB
NO URAIAN PEKERJAAN P L T JLH UNIT LUAS KONST VOL
VOL SAT
Arah x
Tul. Atas D13-150 0.56 9.00 20.00 0.000133 7,850.00 104.28
Tul. Bawah D13-100 1.48 12.00 20.00 0.000133 7,850.00 371.30
Arah y
Tul. Atas D13-150 1.24 4.00 20.00 0.000133 7,850.00 103.03
Tul. Bawah D16-100 3.04 6.00 20.00 0.000201 7,850.00 575.02
Arah y
Tul. Atas D13-150 0.56 4.00 17.00 0.0001 7,850.00 39.39
Tul. Bawah D16-100 1.61 5.00 17.00 0.0002 7,850.00 216.28
- Pembesian Ulir
Tul. Utama D16 3.65 8.00 44.00 0.0002 7,850.00 2,027.85
Sengkang Ø8-150/200 1.12 21.29 44.00 0.0001 7,850.00 414.02
- Pembesian Ulir
Tul. Utama D16 4.65 6.00 20.00 0.0002 7,850.00 880.71
Sengkang Ø8-150/200 1.12 27.13 20.00 0.0001 7,850.00 239.75
- Pembesian Ulir
Tul. Utama 4Ø10 2.85 4.00 2.00 0.0001 7,850.00 14.06
Sengkang Ø8-150/200 1.12 16.63 2.00 0.0001 7,850.00 14.69
6 Sloof 20/35
KE RAB
NO URAIAN PEKERJAAN P L T JLH UNIT LUAS KONST VOL
VOL SAT
Beton total 7.39 M3
Bentang 5
- Beton 4.65 0.20 0.35 7.00 2.28
- Pembesian Ulir
Tul. Utama D16 4.65 6.00 9.00 0.0002 7,850.00 396.32
Sengkang Ø8-150/200 0.82 28.00 9.00 0.0001 7,850.00 81.54
Bentang 4
- Beton 3.65 0.20 0.35 20.00 5.11
- Pembesian Ulir
Tul. Utama D16 3.65 6.00 25.00 0.0001 7,850.00 337.55
Sengkang Ø8-150/200 0.82 22.00 25.00 0.0001 7,850.00 177.96
B PEKERJAAN LANTAI 1
I PEKERJAAN BETON
1 Pekerjaan Kolom 35x35 cm
- Beton 0.35 0.35 5.00 40.00 24.50 24.50 M3
- Pembesian Ulir
Penulangan Kolom 5,073.22 Kg
Tul. Utama 12-D16 5.00 12.00 40.00 0.0002 7,850.00 3,788.01
Sengkang Ø10-125/175 1.52 34.29 40.00 0.0001 7,850.00 1,285.22
- Pembesian Ulir
Penulangan Kolom 810.11 Kg
Tul. Utama 8-D13 5.05 8.00 12.00 0.0001 7,850.00 505.14
Sengkang Ø8-150/175 1.86 34.63 12.00 0.0001 7,850.00 304.98
KE RAB
NO URAIAN PEKERJAAN P L T JLH UNIT LUAS KONST VOL
VOL SAT
Balok Tangga
Tulangan Utama D13
Sengkang D10-100/200
Bordes
Tul. Atas D10-200
Tul. Bawah D13-150
Balok Tangga
Tulangan Utama D13 3.16 5.00 1.00 0.0001 7,850.00 16.44
Sengkang D10-100/200 0.90 25.00 1.00 0.0001 7,850.00 8.84
Bordes
Tul. Atas D10-200 3.12 16.00 2.00 0.0001 7,850.00 61.56
Tul. Bawah D13-150 3.16 22.00 2.00 0.0001 7,850.00 144.69
- Pembesian Ulir Kg
Jarak 5 m 4.65
Tul. Utuh D16 4.65 6.00 18.00 0.0002 7,850.00 792.64
Tul. Tumpuan D16 1.48 4.00 18.00 0.0002 7,850.00 168.47
Tul. Lapangan D16 2.65 2.00 18.00 0.0002 7,850.00 150.29
Tul. Bagi Ø10 4.65 2.00 18.00 0.0001 7,850.00 103.21
Sengkang Ø10-125/175 1.52 31.89 18.00 0.0001 7,850.00 537.86
- Bekisting 2x pakai 120.20 1.06 127.41 127.41 M2
KE RAB
NO URAIAN PEKERJAAN P L T JLH UNIT LUAS KONST VOL
VOL SAT
Jarak 4 m 3.69
Tul. Utuh D13 3.69 6.00 6.00 0.000133 7,850.00 138.41
Tul. Tumpuan D13 1.18 4.00 6.00 0.000133 7,850.00 29.57
Tul. Lapangan D13 2.11 2.00 6.00 0.000133 7,850.00 26.32
Sengkang Ø8-125/175 1.30 25.30 6.00 0.000050 7,850.00 77.64
KE RAB
NO URAIAN PEKERJAAN P L T JLH UNIT LUAS KONST VOL
VOL SAT
Pengurangan Void
Void 1 1.526 136 2.00 415.072
Void 2 10.2 20.34667 2.00 415.072
B PEKERJAAN LANTAI 2
I PEKERJAAN BETON
1 Pekerjaan Kolom 35x35 cm
- Beton 0.35 0.35 3.70 36.00 16.32 16.32 M3
- Pembesian Ulir
Penulangan Kolom 2,960.57 Kg
Tul. Utama 12-D16 4.63 8.00 36.00 0.000201 7,850.00 2,104.62
Sengkang Ø10-125/175 1.52 25.37 36.00 0.000079 7,850.00 855.95
- Pembesian Ulir
Penulangan Kolom 718.53 Kg
Tul. Utama 8-D13 4.63 8.00 12.00 0.000133 7,850.00 463.13
Sengkang Ø8-125/175 1.86 29.00 12.00 0.000050 7,850.00 255.41
Balok Tangga
Tulangan Utama D13 3.16 5.00 1.00 0.0001 7,850.00 16.44
Sengkang D8-100/200 0.90 25.00 1.00 0.0001 7,850.00 8.84
Bordes
Tul. Atas D10-200 3.12 16.00 2.00 0.0001 7,850.00 61.56
Tul. Bawah D13-150 3.16 22.00 2.00 0.0001 7,850.00 144.69
KE RAB
NO URAIAN PEKERJAAN P L T JLH UNIT LUAS KONST VOL
VOL SAT
Bekisting Bordes 2.50 1.10 2.75
Jarak 4 m 3.70
Tul. Utuh D13 3.70 6.00 31.00 0.000133 7,850.00 716.10
Tul. Tumpuan D13 1.18 4.00 31.00 0.000133 7,850.00 152.94
Tul. Lapangan D13 2.11 2.00 31.00 0.000133 7,850.00 136.15
Sengkang Ø8-125/175 1.30 25.34 31.00 0.000050 7,850.00 401.66
Jarak 4m 3.65
Tul. Utuh D13 3.65 6.00 12.00 0.000133 7,850.00 273.82
Tul. Tumpuan D13 1.17 4.00 12.00 0.000133 7,850.00 58.64
Tul. Lapangan D13 2.09 2.00 12.00 0.000133 7,850.00 52.14
Tul. Bagi Ø10 3.65 2.00 12.00 0.000079 7,850.00 54.01
Sengkang Ø8-125/175 1.50 26.77 12.00 0.000050 7,850.00 189.60
Jarak 4 m 3.75
Tul. Memanjang4-Ø10 3.75 4.00 14.00 0.000079 7,850.00 129.47
Tul. Bagi Ø8 3.75 4.00 14.00 0.000050 7,850.00 82.86
Sengkang Ø8-150 1.96 25.00 14.00 0.000050 7,850.00 270.68
KE RAB
NO URAIAN PEKERJAAN P L T JLH UNIT LUAS KONST VOL
VOL SAT
pengurangan
Void 1
Arah x Ø10-150 3.75 303.33 1.00 0.000050 7,850.00 448.84
Arah y Ø10-150 22.75 50.00 1.00 0.000050 7,850.00 448.84
Void 2
Arah x Ø10-150 3.75 33.33 1.00 0.000050 7,850.00 49.32
Arah y Ø10-150 2.50 50.00 1.00 0.000050 7,850.00 49.32
- Pembesian Ulir
Total penullangan
Penulangan Sloof 25/45
Tul. Utama D16 menerus 112,5 cm 1.13 8.00 32.00 0.000201 7,850.00 454.56
Sengkang Ø8-150 1.12 7.50 32.00 0.000050 7,850.00 106.06
Tul. Utama D16 menerus 45 cm 0.45 8.00 20.00 0.000201 7,850.00 113.64
Sengkang Ø8-150 1.12 3.00 20.00 0.000050 7,850.00 26.52
Tul. Utama D16 bengkok 0.63 8.00 34.00 0.000201 7,852.00 268.81
Sengkang Ø8-150 1.12 1.00 34.00 0.000079 7,850.00 23.48
- Pembesian Ulir
Penulangan Kolom
Tul. Utama 12-D16 0.50 12.00 48.00 0.0002 7,850.00 454.56
Sengkang Ø10-125/175 1.52 5.00 48.00 0.0001 7,850.00 224.91
Penulangan Balok 30/50
Tul. menerus D16 0.35 8.00 10.00 0.0002 7,850.00 44.19
Tul. Bagi menerusØ10 0.50 2.00 10.00 0.0001 7,850.00 6.17
KE RAB
NO URAIAN PEKERJAAN P L T JLH UNIT LUAS KONST VOL
VOL SAT
- Bekisting total 15.12 M2
- Pembesian Ulir
Penulangan Kolom
Tul. Utama 12-D16 0.45 12.00 48.00 0.0002 7,850.00 409.10
Sengkang Ø10-125/175 1.52 5.00 48.00 0.0001 7,850.00 224.91
Penulangan Balok 30/50
Tul. menerus D16 0.35 8.00 10.00 0.0002 7,850.00 44.19
Tul. Bagi menerusØ10 0.45 2.00 10.00 0.0001 7,850.00 5.55
Medan, 2016
Diperiksa oleh : Dibuat Oleh :
PEJABAT PEMBUAT KOMITMEN PT. ARANGSIBU RAYA CONSULTANT