PROGRES MINGGUAN
MINGGU KE :
IV (Empat)
PERIODE :
27 October 2022 - 03 November 2022
Konsultan Pengawas
CV. GRAFIKA REKA CIPTA
Engineering Consultant
LAPORAN KEMAJUAN PEKERJAAN
Minggu Ke Empat
Periode, 27 October 2022 - 03 November 2022
III PEK. PAS. BATU, DINDING DAN PLESTERAN Rp 193,442,148 26.08 1.33 7.77 9.11
1. Pasangan batu kosong (Aanstamping) M3 Rp 574,532 20.38 Rp 11,706,673 1.58 0.32 1.55 1.26 80.00 1.58 81.55
2. Pasangan pondasi batu kali 1 SP : 5 PP M3 Rp 1,012,535 37.25 Rp 37,716,787 5.08 1.02 2.73 4.07 80.00 5.08 82.73
3. Rollag Bata 1:4, Tangga Entrance, Ramp M3 Rp 1,115,627 0.79 Rp 878,891 0.12 - - - - - -
4. Pasangan dinding bata 1/2 batu 1 SP : 5 PP M² Rp 152,763 312.90 Rp 47,799,191 6.44 - - 2.15 33.33 2.15 33.33
5. Pasangan dinding bata 1/2 batu 1 SP : 3 PP M² Rp 160,604 31.99 Rp 5,137,326 0.69 - - 0.30 42.86 0.30 42.86
6. CV. GRAFIKA REKA CIPTA M² Rp 77,097 611.87 Rp 47,173,745 6.36 - - - - - -
7. Plesteran trasram kamar mandi 1 SP : 3 PP M² Rp 81,370 63.98 Rp 5,205,643 0.70 - - - - - -
8. Acian dinding M² Rp 46,562 572.85 Rp 26,673,421 3.60 - - - - - -
9. Cor rabat beton 1 : 3 : 5; ramp, lantai bangunan M3 Rp 1,355,096 7.42 Rp 10,051,495 1.36 - - - - - -
10. Pasangan bata 1/2 batu 1 SP : 5 PP; meja beton M² Rp 152,763 2.28 Rp 348,300 0.05 - - - - - -
11. Plesteran meja beton 1 SP : 5 PP M² Rp 77,097 4.41 Rp 339,998 0.05 - - - - - -
12. Acian meja beton M² Rp 46,562 8.82 Rp 410,679 0.06 - - - - - -
VIII PEKERJAAN PLAFON DAN KERAMIK 14.69 - - - - - 3.67 3.67 - - 3.67 3.67 -