SUB JUMLAH
NO URAIAN PEK ERJAAN
(Rp)
TERBILANG : # Sebelas Milyar Delapan Ratus Tujuh Puluh Satu Juta Enam Ratus Sebelas Ribu Rupiah
#
Tasikmalaya, . . . . . . . . . . 2023
Dibuat Oleh :
CV. ARSILAND CONSULTANT
SUB JUMLAH
NO URAIAN PEK ERJAAN
(Rp)
I PEKERJAAN PERSIAPAN
1 Pek. pembersihan lahan A.2.2.1.9 680,00 m2 17,800,00 12,104,000,00
3 Pas. Direksi keet A.2.2.1.5 10,00 m2 662,600,00 6,626,000,00
4 Penyedian air kerja + listrik kerja U&B 1,00 ls 300,000,00 300,000,00
JUMLAH I 19,030,000,00
II PEKERJAAN PELAKSANAAN
A.I PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian tanah A.2.3.1.1 62,50 m3 85,300,00 5,331,250,00
2 Pek. Urugan kembali A.2.3.1.9 62,50 m3 61,500,00 3,843,750,00
3 Pek. Urugan pasir bawah pondasi A.2.3.1.11 10,24 m3 241,100,00 2,468,864,00
4 Pek. Pengurugan 1m3 sirtu padat A.2.3.1.14 50,00 m3 375,700,00 18,785,000,00
5 Pek. Aanstamping A.3.2.1.9 15,00 m3 566,900,00 8,503,500,00
6 Pek. Pondasi batu kali, 1 pc : 5 ps A.3.2.1.3 62,50 m3 928,800,00 58,050,000,00
JUMLAH A.I 96,982,364,00
A.II PEKERJAAN BETON
1 Pek. Beton Sloof S1 15/20
- Beton K175 A.4.1.1.5 12,60 m3 1,123,100,00 14,151,060,00
- Besi beton A.4.1.1.17 1,053,35 kg 20,200,00 21,277,664,32
- Bekisting A.4.1.1.21 84,00 m2 118,000,00 9,912,000,00
2 Pek. Kolom K1 20/30
- Beton K175 A.4.1.1.5 11,97 m3 1,123,100,00 13,443,507,00
- Besi beton A.4.1.1.17 1,636,50 kg 20,200,00 33,057,381,46
- Bekisting A.4.1.1.22 199,50 m2 109,000,00 21,745,500,00
5 Pek. Beton Balok 15/25 Elv. +3.00
- Beton K175 A.4.1.1.5 1,41 m3 1,123,100,00 1,579,359,38
- Besi beton A.4.1.1.17 235,74 kg 20,200,00 4,762,003,55
- Bekisting A.4.1.1.36 24,38 m2 134,900,00 3,288,187,50
8 Pek. Lantai rabat beton/ beton tumbuk 1:3:5
- Beton A.4.1.1.4 49,00 m3 858,100,00 42,046,900,00
- Bekisting A.4.1.1.24 20,00 m2 384,500,00 7,690,000,00
JUMLAH A.II 172,953,563,21
A.III PEKERJAAN DINDING
1 Pek. Pasangan Dinding A.4.4.1.10 598,50 m2 152,200,00 91,091,700,00
2 Pek. Plesteran Dinding A.4.4.2.5 1,197,00 m2 68,900,00 82,473,300,00
3 Pek. acian A.4.4.2.27 1,197,00 m2 41,900,00 50,154,300,00
JUMLAH A.III 223,719,300,00
A.IV PEKERJAAN KUSEN PINTU DAN JENDELA
1 Pek. kusen tipe P1 Dihit. F-02 18,00 unit 5,576,900,00 100,384,200,00
2 Pek. kusen tipe P2 Dihit. F-04 6,00 unit 1,803,000,00 10,818,000,00
3 Pek. kusen tipe PB1 A.4.2.1.4 14,85 m2 1,106,400,00 16,430,040,00
4 Pek. kusen tipe PB2 A.4.2.1.4 35,00 m2 1,106,400,00 38,724,000,00
5 Pek. kusen tipe J1 Dihit. F-08 15,00 unit 2,176,100,00 32,641,500,00
JUMLAH A.IV 198,997,740,00
A.V PEKERJAAN PENUTUP ATAP
1 Pek. Rangka atap baja ringan Dihit. K-43 680,00 m2 175,000,00 119,000,000,00
2 Pek. Penutup atap baja ringan A.4.5.2.31 680,00 m2 137,500,00 93,500,000,00
3 Pek. Bubungan/ nok genteng Dihit. F-13A 180,00 m' 55,000,00 9,900,000,00
JUMLAH A.V 222,400,000,00
A.VI PEKERJAAN PLAFON
1 Pek. Rangka hollow galvanis A.4.2.1.20 450,00 m2 96,500,00 43,425,000,00
2 Pek. Plafon Gypsum board A.4.5.1.7 450,00 m2 53,900,00 24,255,000,00
KODE HARGA SAT. JML. HARGA
NO URAIAN PEKERJAAN VOLUME
ANALISA Rp. Rp.
1 2 3 4 5 6
4 Pek. Profil Plafon A.4.5.1.11 210,00 m' 30,400,00 6,384,000,00
JUMLAH A.VI 74,064,000,00
A.VII PEKERJAAN LANTAI
1 Pek. Urugan pasir bawah lantai A.2.3.1.11 450,00 m3 241,100,00 108,495,000,00
2 Pek. Lantai Kramik 40x40 A.4.4.3.69 450,00 m2 219,400,00 98,730,000,00
3 Pek. Lantai kramik 40x40 Antislip A.4.4.3.70 230,00 m2 221,600,00 50,968,000,00
JUMLAH A.VII 258,193,000,00
A.VIII PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding A.4.7.1.10 1,197,00 m2 30,800,00 36,867,600,00
2 Pek. Pengecatan Plafon Dihit. N-01 450,00 m2 26,000,00 11,700,000,00
JUMLAH A.VIII 48,567,600,00
A.IX PEKERJAAN ELEKTRIKAL
- Instalasi
1 Pas. Instalasi lampu P-01 80,00 ttk 197,000,00 15,760,000,00
2 Pas. Instalasi stopkontak P-03 25,00 ttk 178,200,00 4,455,000,00
- Aksesoris
3 Pas. Down Light U&B 80,00 bh 94,000,00 7,520,000,00
4 Pas. Lampu SL U&B 25,00 bh 42,900,00 1,072,500,00
5 Pas. Stop Kontak P-12 15,00 bh 96,150,00 1,442,250,00
7 Pas. Saklar tunggal P-15 15,00 bh 98,200,00 1,473,000,00
JUMLAH A.IX 31,722,750,00
A.X PEKERJAAN HURUP AKRILIK
1 Pek. Pas Hurup Uk 12cm Dihitung 30,00 bh 7,000,00 210,000,00
2 Pek. pas Hurup Uk 25cm Dihitung 40,00 bh 14,000,00 560,000,00
4 Pek. Pas Logo Dihitung 2,00 bh 950,000,00 1,900,000,00
2,670,000,00
A.XI PEKERJAAN PERAPIHAN
1 Pembersihan sisa pekerjaan - 1,00 ls 1,500,000,00 1,500,000,00
REKAPITULASI RENCANA ANGGARAN BIAYA
RINCIAN RENCANA ANGGARAN BIAYA
KEGIATAN : PERENCANAAN PEMBANGUNAN LAPANGAN MINI SOCCER
PEKERJAAN :
PERENCANAAN PEMBANGUNAN LAPANGAN MINI SOCCER
:
LOKASI : DESA SERANG KECAMATAN SALAWU KAB. TASIKMALAYA
SUMBER DANA : APBD KOTA TASIKMALAYA, T.A. 2022
I PEKERJAAN PERSIAPAN
1 Pek. pembersihan lahan A.2.2.1.9 2,128.00 m2 18,400.00 39,155,200.00
2 Papan Nama Proyek ( 80 x 120 cm) U&B 1.00 bh 300,000.00 300,000.00
3 Pas. Direksi keet A.2.2.1.5 9.00 m2 659,400.00 5,934,600.00
4 Penyedian air kerja + listrik kerja U&B 1.00 ls 3,000,000.00 3,000,000.00
5 Biaya Sistem Manajemen Kesehatan Keselamatan 1.00 ls 6,668,000.00 6,668,000.00
konstruksi (SMK3)
JUMLAH I 55,057,800.00
II PEKERJAAN PELAKSANAAN
A LAPANGAN MINI SOCCER
A.I PEKERJAAN TANAH DAN PONDASI
1 Pek. Pengukuran & Bouwplank A.2.2.1.4 188.00 m' 83,900.00 15,773,200.00
2 Pek. Galian biasa untuk timbunan A.2.3.1.1 13,814.50 m3 124,700.00 1,722,668,150.00
3 Pek. Urugan pasir bawah pondasi A.2.3.1.11 7.52 m3 241,200.00 1,813,824.00
4 Pek. Lantai kerja pondasi setempat A.4.1.1.4 1.44 m3 906,100.00 1,304,784.00
5 Pek. Sloof
- Beton K225 A.4.1.1.7 7.92 m3 1,142,800.00 9,050,976.00
- Besi beton A.4.1.1.17 829.52 kg 20,200.00 16,756,402.98
- Bekisting A.4.1.1.20 19.20 m2 221,600.00 4,254,720.00
6 Pek. Urugan Sirtu Perataan Elevasi Lantai A.2.3.1.14 532.00 m3 376,000.00 200,032,000.00
JUMLAH A.I 1,971,654,056.98
A.II PEKERJAAN LAPANGAN
1 Pek. Pemasangan Box Culvert 200x200 U&B 35.00 bh 13,238,763.74 463,356,730.73
2 Pek. Drainase Saluran Batu 1 SP : 4 PP A.3.2.1.2 71.44 m3 949,800.00 67,853,712.00
3 Pek. Urugan Sirtu Padat A.2.3.1.14 212.80 m3 1,142,800.00 243,187,840.00
4 Pek. Pelapisan Ijuk Resapan A.2.3.1.13 2,128.00 m2 30,700.00 65,329,600.00
5 Pek. Instalasi Pipa PVC 2" A.5.1.1.29 888.00 m1 54,600.00 48,484,800.00
6 Pek. Beton Sloof S2 15/20 -
7 - Beton K225 A.4.1.1.7 3.21 m3 1,142,800.00 3,668,388.00
8 - Besi beton A.4.1.1.17 544.18 kg 20,200.00 10,992,436.00
9 - Bekisting A.4.1.1.21 21.39 m2 235,900.00 5,045,901.00
6 Pek. Instalasi Rumput Sintetis U&B 2,128.00 m2 150,000.00 319,200,000.00
7 Pek. Urugan Sirtu Padat A.4.1.1.7 11.04 m3 1,142,800.00 12,616,512.00
8 Pek. Pemasangan Pipa Galvanis 3" A.5.1.1.31 313.00 m1 123,900.00 38,780,700.00
9 Pek. Pemasangan Kawat Harmonika Galvanis U&B 940.00 m2 37,500.00 35,250,000.00
10 Pek. Tiang Gawang U&B 2.00 bh 7,200,000.00 14,400,000.00
JUMLAH A.II 796,956,177.00
A.III PEKERJAAN DINDING
1 Pek. Pasangan Dinding A.4.4.1.10 188.00 m2 165,400.00 31,095,200.00
2 Pek. Plesteran Dinding A.4.4.2.5 376.00 m2 68,300.00 25,680,800.00
3 Pek. Acian A.4.4.2.27 376.00 m2 42,600.00 16,017,600.00
JUMLAH A.III 72,793,600.00
JUMLAH A 2,896,461,633.98
B RUANG GANTI DAN TRIBUN
B.I PEKERJAAN TANAH DAN PONDASI
1 Pek. Pengukuran & Bouwplank A.2.2.1.4 58.00 m2 83,900.00 4,866,200.00
2 Pek Galian Tanah Biasa A.2.3.1.1 32.48 m3 85,600.00 2,780,288.00
3 Pek. Pondasi Batu Campuran 1 SP : 4 PP A.3.2.1.2 31.90 m3 949,800.00 30,298,620.00
4 Pek. Sloof
- Beton K225 A.4.1.1.7 1.74 m3 1,142,800.00 1,988,472.00
- Besi beton A.4.1.1.17 255.83 kg 20,200.00 5,167,709.71
- Bekisting A.4.1.1.20 9.60 m2 221,600.00 2,127,360.00
JUMLAH B.I 47,228,649.71
KODE HARGA SAT. JML. HARGA
NO URAIAN PEKERJAAN VOLUME
ANALISA Rp. Rp.
1 2 3 4 5 6
B.II PEKERJAAN BETON
1 Pek. Kolom
- Beton K225 A.2.2.1.4 3.68 m3 1,142,800.00 4,205,504.00
- Besi beton Dihit. F-04 895.63 kg 20,200.00 18,091,748.69
- Bekisting A.4.2.1.4 36.80 m2 221,600.00 8,154,880.00
2 Pek. Balok
- Beton K225 A.2.2.1.4 2.16 m3 1,142,800.00 2,468,448.00
- Besi beton Dihit. F-04 344.37 kg 20,200.00 6,956,371.41
- Bekisting A.4.2.1.4 10.80 m2 221,600.00 2,393,280.00
3 Pek. Ringbalk
- Beton K225 A.2.2.1.4 1.08 m3 1,142,800.00 1,234,224.00
- Besi beton Dihit. F-04 222.58 kg 20,200.00 4,496,138.50
- Bekisting A.4.2.1.4 9.90 m2 221,600.00 2,193,840.00
JUMLAH B.II 50,194,434.60
B.III PEKERJAAN LANTAI
1 Pek. Urugan pasir bawah lantai A.2.3.1.11 3.45 m3 241,200.00 832,140.00
2 Pek. Lantai Granit 60x60 Polished (Garuda Madrid) A.4.4.3.69 69.00 m2 229,700.00 15,849,300.00
3 Pek. Lantai keramik 25x25 Antislip Asia Tile Platinum Dihit. I-04 4.50 m2 236,400.00 1,063,800.00
JUMLAH B.III 17,745,240.00
B.IV PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding Mowilex/Jotun A.4.7.1.10 222.14 m2 28,800.00 6,397,632.00
2 Pek. Pengecatan Plafon Dihit. N-01 69.00 m2 25,000.00 1,725,000.00
JUMLAH B.IV 8,122,632.00
B.V PEKERJAAN ELEKTRIKAL, MEKANIKAL
- Instalasi
1 Pas. Instalasi Listrik Baru U&B 1.00 ls 3,000,000.00 3,000,000.00
2 Pas. Instalasi lampu P-01 4.00 ttk 197,000.00 788,000.00
3 Pas. Instalasi stopkontak P-03 2.00 ttk 178,200.00 356,400.00
4 Penangkal Petir + grounding P-11 1.00 ttk 1,173,000.00 1,173,000.00
5 Pas. Lampu RMI 2x18 Watt U&B 4.00 bh 269,000.00 1,076,000.00
6 Pas. Stop Kontak P-12 4.00 bh 96,150.00 384,600.00
7 Pas. Saklar ganda P-16 2.00 bh 101,670.00 203,340.00
8 Box Schreeng In-bouw C4 U&B 1.00 bh 52,500.00 52,500.00
9 Pas. Instalasi PJU P-04 4.00 bh 4,450,490.00 17,801,960.00
JUMLAH B.V 24,835,800.00
B.VI PEKERJAAN SANITASI
1 Pek. Sanitair
- Pas. Closet jongkok Sistem Jet A.5.1.1.3A 2.00 bh 4,145,400.00 8,290,800.00
- Pas. Wastafel A.5.1.1.5A 2.00 bh 2,165,400.00 4,330,800.00
- Pas. Kran dinding A.5.1.1.19 2.00 bh 81,600.00 163,200.00
- Pas. Floor Drain A.5.1.1.14 2.00 bh 70,300.00 140,600.00
2 Instalasi Pemipaan Air Bersih
- Pipa PVC dia. 3/4" Setara Maspion A.5.1.1.26 25.00 m' 30,700.00 767,500.00
- Pipa PVC dia. 1/2" Setara Maspion A.5.1.1.25 10.00 m' 23,400.00 234,000.00
- Instalasi pipa + material bantu (support, lem, socket dll) - 1.00 ls 108,300.00 108,300.00
3 Instalasi Pemipaan Air Kotor
- Pipa PVC-D dia. 1 1/2" Setara Maspion A.5.1.1.28 10.00 m' 55,400.00 554,000.00
- Pipa PVC dia. 3" Setara Maspion A.5.1.1.31 12.00 m' 123,900.00 1,486,800.00
- Pipa PVC dia. 4" Setara Maspion A.5.1.1.32 10.00 m' 208,200.00 2,082,000.00
- Pipa air hujan PVC dia. 4" Setara Maspion A.5.1.1.32 15.00 m' 208,200.00 3,123,000.00
- Instalasi pipa + material bantu (support, lem, socket dll) - 1.00 ls 731,600.00 731,600.00
5 Septictank Dihit. O-04 1.00 unit 11,233,500.00 11,233,500.00
JUMLAH B.VI 33,246,100.00
JUMLAH B 181,372,856.31
SUB REKAPITULASI PEKERJAAN GEDUNG AREA CAMPING
RINCIAN RENCANA ANGGARAN BIAYA
SUB JUMLAH
NO URAIAN PEK ERJAAN
(Rp)
I PEKERJAAN PERSIAPAN
1 Pek. pembersihan lahan A.2.2.1.9 612,00 m2 17,800,00 10,893,600,00
3 Pas. Direksi keet A.2.2.1.5 9,00 m2 662,600,00 5,963,400,00
4 Penyedian air kerja + listrik kerja U&B 1,00 ls 300,000,00 300,000,00
JUMLAH I 17,157,000,00
II PEKERJAAN PELAKSANAAN
A.I PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian tanah A.2.3.1.1 56,25 m3 85,300,00 4,798,125,00
2 Pek. Urugan kembali A.2.3.1.9 56,25 m3 61,500,00 3,459,375,00
3 Pek. Urugan pasir bawah pondasi A.2.3.1.11 9,22 m3 241,100,00 2,221,977,60
4 Pek. Pengurugan 1m3 sirtu padat A.2.3.1.14 45,00 m3 375,700,00 16,906,500,00
5 Pek. Aanstamping A.3.2.1.9 13,50 m3 566,900,00 7,653,150,00
6 Pek. Pondasi batu kali, 1 pc : 5 ps A.3.2.1.3 56,25 m3 928,800,00 52,245,000,00
JUMLAH A.I 87,284,127,60
A.II PEKERJAAN BETON
1 Pek. Beton Sloof S1 15/20
- Beton K175 A.4.1.1.5 11,34 m3 1,123,100,00 12,735,954,00
- Besi beton A.4.1.1.17 948,01 kg 20,200,00 19,149,897,89
- Bekisting A.4.1.1.21 75,60 m2 118,000,00 8,920,800,00
2 Pek. Kolom K1 20/30
- Beton K175 A.4.1.1.5 10,77 m3 1,123,100,00 12,099,156,30
- Besi beton A.4.1.1.17 1,472,85 kg 20,200,00 29,751,643,32
- Bekisting A.4.1.1.22 179,55 m2 109,000,00 19,570,950,00
5 Pek. Beton Balok 15/25 Elv. +3.00
- Beton K175 A.4.1.1.5 1,27 m3 1,123,100,00 1,421,423,44
- Besi beton A.4.1.1.17 212,17 kg 20,200,00 4,285,803,20
- Bekisting A.4.1.1.36 21,94 m2 134,900,00 2,959,368,75
8 Pek. Lantai rabat beton/ beton tumbuk 1:3:5
- Beton A.4.1.1.4 44,10 m3 858,100,00 37,842,210,00
- Bekisting A.4.1.1.24 18,00 m2 384,500,00 6,921,000,00
JUMLAH A.II 155,658,206,89
A.III PEKERJAAN DINDING
1 Pek. Pasangan Dinding A.4.4.1.10 538,65 m2 152,200,00 81,982,530,00
2 Pek. Plesteran Dinding A.4.4.2.5 1,077,30 m2 68,900,00 74,225,970,00
3 Pek. acian A.4.4.2.27 1,077,30 m2 41,900,00 45,138,870,00
JUMLAH A.III 201,347,370,00
A.IV PEKERJAAN KUSEN PINTU DAN JENDELA
1 Pek. kusen tipe P1 Dihit. F-02 18,00 unit 5,576,900,00 100,384,200,00
2 Pek. kusen tipe P2 Dihit. F-04 6,00 unit 1,803,000,00 10,818,000,00
3 Pek. kusen tipe PB1 A.4.2.1.4 14,85 m2 1,106,400,00 16,430,040,00
4 Pek. kusen tipe PB2 A.4.2.1.4 35,00 m2 1,106,400,00 38,724,000,00
5 Pek. kusen tipe J1 Dihit. F-08 15,00 unit 2,176,100,00 32,641,500,00
JUMLAH A.IV 198,997,740,00
A.V PEKERJAAN PENUTUP ATAP
1 Pek. Rangka atap baja ringan Dihit. K-43 612,00 m2 175,000,00 107,100,000,00
2 Pek. Penutup atap baja ringan A.4.5.2.31 612,00 m2 137,500,00 84,150,000,00
3 Pek. Bubungan/ nok genteng Dihit. F-13A 162,00 m' 55,000,00 8,910,000,00
JUMLAH A.V 200,160,000,00
A.VI PEKERJAAN PLAFON
1 Pek. Rangka hollow galvanis A.4.2.1.20 405,00 m2 96,500,00 39,082,500,00
2 Pek. Plafon Gypsum board A.4.5.1.7 405,00 m2 53,900,00 21,829,500,00
KODE HARGA SAT. JML. HARGA
NO URAIAN PEKERJAAN VOLUME
ANALISA Rp. Rp.
1 2 3 4 5 6
4 Pek. Profil Plafon A.4.5.1.11 189,00 m' 30,400,00 5,745,600,00
JUMLAH A.VI 66,657,600,00
A.VII PEKERJAAN LANTAI
1 Pek. Urugan pasir bawah lantai A.2.3.1.11 405,00 m3 241,100,00 97,645,500,00
2 Pek. Lantai Kramik 40x40 A.4.4.3.69 405,00 m2 219,400,00 88,857,000,00
3 Pek. Lantai kramik 40x40 Antislip A.4.4.3.70 207,00 m2 221,600,00 45,871,200,00
JUMLAH A.VII 232,373,700,00
A.VIII PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding A.4.7.1.10 1,077,30 m2 30,800,00 33,180,840,00
2 Pek. Pengecatan Plafon Dihit. N-01 405,00 m2 26,000,00 10,530,000,00
JUMLAH A.VIII 43,710,840,00
A.IX PEKERJAAN ELEKTRIKAL
- Instalasi
1 Pas. Instalasi lampu P-01 72,00 ttk 197,000,00 14,184,000,00
2 Pas. Instalasi stopkontak P-03 22,50 ttk 178,200,00 4,009,500,00
- Aksesoris
3 Pas. Down Light U&B 72,00 bh 94,000,00 6,768,000,00
4 Pas. Lampu SL U&B 22,50 bh 42,900,00 965,250,00
5 Pas. Stop Kontak P-12 13,50 bh 96,150,00 1,298,025,00
7 Pas. Saklar tunggal P-15 13,50 bh 98,200,00 1,325,700,00
JUMLAH A.IX 28,550,475,00
A.X PEKERJAAN HURUP AKRILIK
1 Pek. Pas Hurup Uk 12cm Dihitung 25,00 bh 7,000,00 175,000,00
2 Pek. pas Hurup Uk 25cm Dihitung 35,00 bh 14,000,00 490,000,00
4 Pek. Pas Logo Dihitung 1,00 bh 950,000,00 950,000,00
1,615,000,00
A.XI PEKERJAAN PERAPIHAN
1 Pembersihan sisa pekerjaan - 1,00 ls 1,500,000,00 1,500,000,00
SUB REKAPITULASI PEKERJAAN GEDUNG LUMBUNG PANEN
RINCIAN RENCANA ANGGARAN BIAYA
SUB JUMLAH
NO URAIAN PEK ERJAAN
(Rp)
I PEKERJAAN PERSIAPAN
1 Pek. pembersihan lahan A.2.2.1.9 136,00 m2 17,800,00 2,420,800,00
3 Pas. Direksi keet A.2.2.1.5 2,00 m2 662,600,00 1,325,200,00
4 Penyedian air kerja + listrik kerja U&B 1,00 ls 300,000,00 300,000,00
JUMLAH I 4,046,000,00
II PEKERJAAN PELAKSANAAN
A.I PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian tanah A.2.3.1.1 12,50 m3 85,300,00 1,066,250,00
2 Pek. Urugan kembali A.2.3.1.9 12,50 m3 61,500,00 768,750,00
3 Pek. Urugan pasir bawah pondasi A.2.3.1.11 2,05 m3 241,100,00 493,772,80
4 Pek. Pengurugan 1m3 sirtu padat A.2.3.1.14 10,00 m3 375,700,00 3,757,000,00
5 Pek. Aanstamping A.3.2.1.9 3,00 m3 566,900,00 1,700,700,00
6 Pek. Pondasi batu kali, 1 pc : 5 ps A.3.2.1.3 12,50 m3 928,800,00 11,610,000,00
JUMLAH A.I 19,396,472,80
A.II PEKERJAAN BETON
1 Pek. Beton Sloof S1 15/20
- Beton K175 A.4.1.1.5 2,52 m3 1,123,100,00 2,830,212,00
- Besi beton A.4.1.1.17 210,67 kg 20,200,00 4,255,532,86
- Bekisting A.4.1.1.21 16,80 m2 118,000,00 1,982,400,00
2 Pek. Kolom K1 20/30
- Beton K175 A.4.1.1.5 2,39 m3 1,123,100,00 2,688,701,40
- Besi beton A.4.1.1.17 327,30 kg 20,200,00 6,611,476,29
- Bekisting A.4.1.1.22 39,90 m2 109,000,00 4,349,100,00
5 Pek. Beton Balok 15/25 Elv. +3.00
- Beton K175 A.4.1.1.5 0,28 m3 1,123,100,00 315,871,88
- Besi beton A.4.1.1.17 47,15 kg 20,200,00 952,400,71
- Bekisting A.4.1.1.36 4,88 m2 134,900,00 657,637,50
8 Pek. Lantai rabat beton/ beton tumbuk 1:3:5
- Beton A.4.1.1.4 9,80 m3 858,100,00 8,409,380,00
- Bekisting A.4.1.1.24 4,00 m2 384,500,00 1,538,000,00
JUMLAH A.II 34,590,712,64
A.III PEKERJAAN DINDING
1 Pek. Pasangan Dinding A.4.4.1.10 119,70 m2 152,200,00 18,218,340,00
2 Pek. Plesteran Dinding A.4.4.2.5 239,40 m2 68,900,00 16,494,660,00
3 Pek. acian A.4.4.2.27 239,40 m2 41,900,00 10,030,860,00
JUMLAH A.III 44,743,860,00
A.IV PEKERJAAN KUSEN PINTU DAN JENDELA
1 Pek. kusen tipe P1 Dihit. F-02 1,00 unit 5,576,900,00 5,576,900,00
2 Pek. kusen BV2 Dihit. F-13 10,00 unit 2,451,300,00 24,513,000,00
JUMLAH A.IV 30,089,900,00
A.V PEKERJAAN PENUTUP ATAP
1 Pek. Rangka atap baja ringan Dihit. K-43 136,00 m2 175,000,00 23,800,000,00
2 Pek. Penutup atap baja ringan A.4.5.2.31 136,00 m2 137,500,00 18,700,000,00
3 Pek. Bubungan/ nok genteng Dihit. F-13A 36,00 m' 55,000,00 1,980,000,00
JUMLAH A.V 44,480,000,00
A.VI PEKERJAAN PLAFON
1 Pek. Rangka hollow galvanis A.4.2.1.20 90,00 m2 96,500,00 8,685,000,00
2 Pek. Plafon Gypsum board A.4.5.1.7 90,00 m2 53,900,00 4,851,000,00
4 Pek. Profil Plafon A.4.5.1.11 42,00 m' 30,400,00 1,276,800,00
JUMLAH A.VI 14,812,800,00
A.VII PEKERJAAN LANTAI
KODE HARGA SAT. JML. HARGA
NO URAIAN PEKERJAAN VOLUME
ANALISA Rp. Rp.
1 2 3 4 5 6
1 Pek. Urugan pasir bawah lantai A.2.3.1.11 90,00 m3 241,100,00 21,699,000,00
2 Pek. Lantai Kramik 40x40 A.4.4.3.69 90,00 m2 219,400,00 19,746,000,00
3 Pek. Lantai kramik 40x40 Antislip A.4.4.3.70 46,00 m2 221,600,00 10,193,600,00
JUMLAH A.VII 51,638,600,00
A.VIII PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding A.4.7.1.10 239,40 m2 30,800,00 7,373,520,00
2 Pek. Pengecatan Plafon Dihit. N-01 90,00 m2 26,000,00 2,340,000,00
JUMLAH A.VIII 9,713,520,00
A.IX PEKERJAAN ELEKTRIKAL
- Instalasi
1 Pas. Instalasi lampu P-01 16,00 ttk 197,000,00 3,152,000,00
2 Pas. Instalasi stopkontak P-03 5,00 ttk 178,200,00 891,000,00
- Aksesoris
3 Pas. Down Light U&B 16,00 bh 94,000,00 1,504,000,00
4 Pas. Lampu SL U&B 5,00 bh 42,900,00 214,500,00
5 Pas. Stop Kontak P-12 3,00 bh 96,150,00 288,450,00
7 Pas. Saklar tunggal P-15 3,00 bh 98,200,00 294,600,00
JUMLAH A.IX 6,344,550,00
A.X PEKERJAAN HURUP AKRILIK
1 Pek. Pas Hurup Uk 12cm Dihitung 25,00 bh 7,000,00 175,000,00
2 Pek. pas Hurup Uk 25cm Dihitung 35,00 bh 14,000,00 490,000,00
4 Pek. Pas Logo Dihitung 1,00 bh 950,000,00 950,000,00
1,615,000,00
A.XI PEKERJAAN PERAPIHAN
1 Pembersihan sisa pekerjaan - 1,00 ls 1,500,000,00 1,500,000,00
SUB REKAPITULASI PEKERJAAN GEDUNG GUDANG ALAT
RINCIAN RENCANA ANGGARAN BIAYA
SUB JUMLAH
NO URAIAN PEK ERJAAN
(Rp)
I PEKERJAAN PERSIAPAN
1 Pek. pembersihan lahan A.2.2.1.9 136,00 m2 17,800,00 2,420,800,00
3 Pas. Direksi keet A.2.2.1.5 2,00 m2 662,600,00 1,325,200,00
4 Penyedian air kerja + listrik kerja U&B 1,00 ls 300,000,00 300,000,00
JUMLAH I 4,046,000,00
II PEKERJAAN PELAKSANAAN
A.I PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian tanah A.2.3.1.1 12,50 m3 85,300,00 1,066,250,00
2 Pek. Urugan kembali A.2.3.1.9 12,50 m3 61,500,00 768,750,00
3 Pek. Urugan pasir bawah pondasi A.2.3.1.11 2,05 m3 241,100,00 493,772,80
4 Pek. Pengurugan 1m3 sirtu padat A.2.3.1.14 10,00 m3 375,700,00 3,757,000,00
5 Pek. Aanstamping A.3.2.1.9 3,00 m3 566,900,00 1,700,700,00
6 Pek. Pondasi batu kali, 1 pc : 5 ps A.3.2.1.3 12,50 m3 928,800,00 11,610,000,00
JUMLAH A.I 19,396,472,80
A.II PEKERJAAN BETON
1 Pek. Beton Sloof S1 15/20
- Beton K175 A.4.1.1.5 2,52 m3 1,123,100,00 2,830,212,00
- Besi beton A.4.1.1.17 210,67 kg 20,200,00 4,255,532,86
- Bekisting A.4.1.1.21 16,80 m2 118,000,00 1,982,400,00
2 Pek. Kolom K1 20/30
- Beton K175 A.4.1.1.5 2,39 m3 1,123,100,00 2,688,701,40
- Besi beton A.4.1.1.17 327,30 kg 20,200,00 6,611,476,29
- Bekisting A.4.1.1.22 39,90 m2 109,000,00 4,349,100,00
5 Pek. Beton Balok 15/25 Elv. +3.00
- Beton K175 A.4.1.1.5 0,28 m3 1,123,100,00 315,871,88
- Besi beton A.4.1.1.17 47,15 kg 20,200,00 952,400,71
- Bekisting A.4.1.1.36 4,88 m2 134,900,00 657,637,50
8 Pek. Lantai rabat beton/ beton tumbuk 1:3:5
- Beton A.4.1.1.4 9,80 m3 858,100,00 8,409,380,00
- Bekisting A.4.1.1.24 4,00 m2 384,500,00 1,538,000,00
JUMLAH A.II 34,590,712,64
A.III PEKERJAAN DINDING
1 Pek. Pasangan Dinding A.4.4.1.10 119,70 m2 152,200,00 18,218,340,00
2 Pek. Plesteran Dinding A.4.4.2.5 239,40 m2 68,900,00 16,494,660,00
3 Pek. acian A.4.4.2.27 239,40 m2 41,900,00 10,030,860,00
JUMLAH A.III 44,743,860,00
A.IV PEKERJAAN KUSEN PINTU DAN JENDELA
1 Pek. kusen tipe P1 Dihit. F-02 1,00 unit 5,576,900,00 5,576,900,00
2 Pek. kusen BV2 Dihit. F-13 10,00 unit 2,451,300,00 24,513,000,00
JUMLAH A.IV 30,089,900,00
A.V PEKERJAAN PENUTUP ATAP
1 Pek. Rangka atap baja ringan Dihit. K-43 136,00 m2 175,000,00 23,800,000,00
2 Pek. Penutup atap baja ringan A.4.5.2.31 136,00 m2 137,500,00 18,700,000,00
3 Pek. Bubungan/ nok genteng Dihit. F-13A 36,00 m' 55,000,00 1,980,000,00
JUMLAH A.V 44,480,000,00
A.VI PEKERJAAN PLAFON
1 Pek. Rangka hollow galvanis A.4.2.1.20 90,00 m2 96,500,00 8,685,000,00
2 Pek. Plafon Gypsum board A.4.5.1.7 90,00 m2 53,900,00 4,851,000,00
4 Pek. Profil Plafon A.4.5.1.11 42,00 m' 30,400,00 1,276,800,00
JUMLAH A.VI 14,812,800,00
A.VII PEKERJAAN LANTAI
KODE HARGA SAT. JML. HARGA
NO URAIAN PEKERJAAN VOLUME
ANALISA Rp. Rp.
1 2 3 4 5 6
1 Pek. Urugan pasir bawah lantai A.2.3.1.11 90,00 m3 241,100,00 21,699,000,00
2 Pek. Lantai Kramik 40x40 A.4.4.3.69 90,00 m2 219,400,00 19,746,000,00
3 Pek. Lantai kramik 40x40 Antislip A.4.4.3.70 46,00 m2 221,600,00 10,193,600,00
JUMLAH A.VII 51,638,600,00
A.VIII PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding A.4.7.1.10 239,40 m2 30,800,00 7,373,520,00
2 Pek. Pengecatan Plafon Dihit. N-01 90,00 m2 26,000,00 2,340,000,00
JUMLAH A.VIII 9,713,520,00
A.IX PEKERJAAN ELEKTRIKAL
- Instalasi
1 Pas. Instalasi lampu P-01 16,00 ttk 197,000,00 3,152,000,00
2 Pas. Instalasi stopkontak P-03 5,00 ttk 178,200,00 891,000,00
- Aksesoris
3 Pas. Down Light U&B 16,00 bh 94,000,00 1,504,000,00
4 Pas. Lampu SL U&B 5,00 bh 42,900,00 214,500,00
5 Pas. Stop Kontak P-12 3,00 bh 96,150,00 288,450,00
7 Pas. Saklar tunggal P-15 3,00 bh 98,200,00 294,600,00
JUMLAH A.IX 6,344,550,00
A.X PEKERJAAN HURUP AKRILIK
1 Pek. Pas Hurup Uk 12cm Dihitung 25,00 bh 7,000,00 175,000,00
2 Pek. pas Hurup Uk 25cm Dihitung 35,00 bh 14,000,00 490,000,00
4 Pek. Pas Logo Dihitung 1,00 bh 950,000,00 950,000,00
1,615,000,00
A.XI PEKERJAAN PERAPIHAN
1 Pembersihan sisa pekerjaan - 1,00 ls 1,500,000,00 1,500,000,00
SUB REKAPITULASI PEKERJAAN GEDUNG PEMBIBITAN
RINCIAN RENCANA ANGGARAN BIAYA
SUB JUMLAH
NO URAIAN PEK ERJAAN
(Rp)
I PEKERJAAN PERSIAPAN
1 Pek. pembersihan lahan A.2.2.1.9 136,00 m2 17,800,00 2,420,800,00
3 Pas. Direksi keet A.2.2.1.5 2,00 m2 662,600,00 1,325,200,00
4 Penyedian air kerja + listrik kerja U&B 1,00 ls 300,000,00 300,000,00
JUMLAH I 4,046,000,00
II PEKERJAAN PELAKSANAAN
A.I PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian tanah A.2.3.1.1 12,50 m3 85,300,00 1,066,250,00
2 Pek. Urugan kembali A.2.3.1.9 12,50 m3 61,500,00 768,750,00
3 Pek. Urugan pasir bawah pondasi A.2.3.1.11 2,05 m3 241,100,00 493,772,80
4 Pek. Pengurugan 1m3 sirtu padat A.2.3.1.14 10,00 m3 375,700,00 3,757,000,00
5 Pek. Aanstamping A.3.2.1.9 3,00 m3 566,900,00 1,700,700,00
6 Pek. Pondasi batu kali, 1 pc : 5 ps A.3.2.1.3 12,50 m3 928,800,00 11,610,000,00
JUMLAH A.I 19,396,472,80
A.II PEKERJAAN BETON
1 Pek. Beton Sloof S1 15/20
- Beton K175 A.4.1.1.5 2,52 m3 1,123,100,00 2,830,212,00
- Besi beton A.4.1.1.17 210,67 kg 20,200,00 4,255,532,86
- Bekisting A.4.1.1.21 16,80 m2 118,000,00 1,982,400,00
2 Pek. Kolom K1 20/30
- Beton K175 A.4.1.1.5 2,39 m3 1,123,100,00 2,688,701,40
- Besi beton A.4.1.1.17 327,30 kg 20,200,00 6,611,476,29
- Bekisting A.4.1.1.22 39,90 m2 109,000,00 4,349,100,00
5 Pek. Beton Balok 15/25 Elv. +3.00
- Beton K175 A.4.1.1.5 0,28 m3 1,123,100,00 315,871,88
- Besi beton A.4.1.1.17 47,15 kg 20,200,00 952,400,71
- Bekisting A.4.1.1.36 4,88 m2 134,900,00 657,637,50
8 Pek. Lantai rabat beton/ beton tumbuk 1:3:5
- Beton A.4.1.1.4 9,80 m3 858,100,00 8,409,380,00
- Bekisting A.4.1.1.24 4,00 m2 384,500,00 1,538,000,00
JUMLAH A.II 34,590,712,64
A.III PEKERJAAN DINDING
1 Pek. Pasangan Dinding A.4.4.1.10 119,70 m2 152,200,00 18,218,340,00
2 Pek. Plesteran Dinding A.4.4.2.5 239,40 m2 68,900,00 16,494,660,00
3 Pek. acian A.4.4.2.27 239,40 m2 41,900,00 10,030,860,00
JUMLAH A.III 44,743,860,00
A.IV PEKERJAAN KUSEN PINTU DAN JENDELA
1 Pek. kusen tipe P1 Dihit. F-02 1,00 unit 5,576,900,00 5,576,900,00
2 Pek. kusen BV2 Dihit. F-13 10,00 unit 2,451,300,00 24,513,000,00
JUMLAH A.IV 30,089,900,00
A.V PEKERJAAN PENUTUP ATAP
1 Pek. Rangka atap baja ringan Dihit. K-43 136,00 m2 175,000,00 23,800,000,00
2 Pek. Penutup atap baja ringan A.4.5.2.31 136,00 m2 137,500,00 18,700,000,00
3 Pek. Bubungan/ nok genteng Dihit. F-13A 36,00 m' 55,000,00 1,980,000,00
JUMLAH A.V 44,480,000,00
A.VI PEKERJAAN PLAFON
1 Pek. Rangka hollow galvanis A.4.2.1.20 90,00 m2 96,500,00 8,685,000,00
2 Pek. Plafon Gypsum board A.4.5.1.7 90,00 m2 53,900,00 4,851,000,00
4 Pek. Profil Plafon A.4.5.1.11 42,00 m' 30,400,00 1,276,800,00
JUMLAH A.VI 14,812,800,00
A.VII PEKERJAAN LANTAI
KODE HARGA SAT. JML. HARGA
NO URAIAN PEKERJAAN VOLUME
ANALISA Rp. Rp.
1 2 3 4 5 6
1 Pek. Urugan pasir bawah lantai A.2.3.1.11 90,00 m3 241,100,00 21,699,000,00
2 Pek. Lantai Kramik 40x40 A.4.4.3.69 90,00 m2 219,400,00 19,746,000,00
3 Pek. Lantai kramik 40x40 Antislip A.4.4.3.70 46,00 m2 221,600,00 10,193,600,00
JUMLAH A.VII 51,638,600,00
A.VIII PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding A.4.7.1.10 239,40 m2 30,800,00 7,373,520,00
2 Pek. Pengecatan Plafon Dihit. N-01 90,00 m2 26,000,00 2,340,000,00
JUMLAH A.VIII 9,713,520,00
A.IX PEKERJAAN ELEKTRIKAL
- Instalasi
1 Pas. Instalasi lampu P-01 16,00 ttk 197,000,00 3,152,000,00
2 Pas. Instalasi stopkontak P-03 5,00 ttk 178,200,00 891,000,00
- Aksesoris
3 Pas. Down Light U&B 16,00 bh 94,000,00 1,504,000,00
4 Pas. Lampu SL U&B 5,00 bh 42,900,00 214,500,00
5 Pas. Stop Kontak P-12 3,00 bh 96,150,00 288,450,00
7 Pas. Saklar tunggal P-15 3,00 bh 98,200,00 294,600,00
JUMLAH A.IX 6,344,550,00
A.X PEKERJAAN HURUP AKRILIK
1 Pek. Pas Hurup Uk 12cm Dihitung 25,00 bh 7,000,00 175,000,00
2 Pek. pas Hurup Uk 25cm Dihitung 35,00 bh 14,000,00 490,000,00
4 Pek. Pas Logo Dihitung 1,00 bh 950,000,00 950,000,00
1,615,000,00
A.XI PEKERJAAN PERAPIHAN
1 Pembersihan sisa pekerjaan - 1,00 ls 1,500,000,00 1,500,000,00
SUB REKAPITULASI PEKERJAAN GEDUNG FOOD COURT
RINCIAN RENCANA ANGGARAN BIAYA
SUB JUMLAH
NO URAIAN PEK ERJAAN
(Rp)
I PEKERJAAN PERSIAPAN
1 Pek. pembersihan lahan A.2.2.1.9 136,00 m2 17,800,00 2,420,800,00
3 Pas. Direksi keet A.2.2.1.5 2,00 m2 662,600,00 1,325,200,00
4 Penyedian air kerja + listrik kerja U&B 1,00 ls 300,000,00 300,000,00
JUMLAH I 4,046,000,00
II PEKERJAAN PELAKSANAAN
A.I PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian tanah A.2.3.1.1 12,50 m3 85,300,00 1,066,250,00
2 Pek. Urugan kembali A.2.3.1.9 12,50 m3 61,500,00 768,750,00
3 Pek. Urugan pasir bawah pondasi A.2.3.1.11 2,05 m3 241,100,00 493,772,80
4 Pek. Pengurugan 1m3 sirtu padat A.2.3.1.14 10,00 m3 375,700,00 3,757,000,00
5 Pek. Aanstamping A.3.2.1.9 3,00 m3 566,900,00 1,700,700,00
6 Pek. Pondasi batu kali, 1 pc : 5 ps A.3.2.1.3 12,50 m3 928,800,00 11,610,000,00
JUMLAH A.I 19,396,472,80
A.II PEKERJAAN BETON
1 Pek. Beton Sloof S1 15/20
- Beton K175 A.4.1.1.5 2,52 m3 1,123,100,00 2,830,212,00
- Besi beton A.4.1.1.17 210,67 kg 20,200,00 4,255,532,86
- Bekisting A.4.1.1.21 16,80 m2 118,000,00 1,982,400,00
2 Pek. Kolom K1 20/30
- Beton K175 A.4.1.1.5 2,39 m3 1,123,100,00 2,688,701,40
- Besi beton A.4.1.1.17 327,30 kg 20,200,00 6,611,476,29
- Bekisting A.4.1.1.22 39,90 m2 109,000,00 4,349,100,00
5 Pek. Beton Balok 15/25 Elv. +3.00
- Beton K175 A.4.1.1.5 0,28 m3 1,123,100,00 315,871,88
- Besi beton A.4.1.1.17 47,15 kg 20,200,00 952,400,71
- Bekisting A.4.1.1.36 4,88 m2 134,900,00 657,637,50
8 Pek. Lantai rabat beton/ beton tumbuk 1:3:5
- Beton A.4.1.1.4 9,80 m3 858,100,00 8,409,380,00
- Bekisting A.4.1.1.24 4,00 m2 384,500,00 1,538,000,00
JUMLAH A.II 34,590,712,64
A.III PEKERJAAN DINDING
1 Pek. Pasangan Dinding A.4.4.1.10 68,40 m2 152,200,00 10,410,480,00
2 Pek. Plesteran Dinding A.4.4.2.5 136,80 m2 68,900,00 9,425,520,00
3 Pek. acian A.4.4.2.27 136,80 m2 41,900,00 5,731,920,00
JUMLAH A.III 25,567,920,00
A.IV PEKERJAAN KUSEN PINTU DAN JENDELA
1 Pek. kusen tipe P1 Dihit. F-02 1,00 unit 5,576,900,00 5,576,900,00
2 Pek. kusen BV2 Dihit. F-13 6,00 unit 2,451,300,00 14,707,800,00
JUMLAH A.IV 20,284,700,00
A.V PEKERJAAN PENUTUP ATAP
1 Pek. Rangka atap baja ringan Dihit. K-43 136,00 m2 175,000,00 23,800,000,00
2 Pek. Penutup atap baja ringan A.4.5.2.31 136,00 m2 137,500,00 18,700,000,00
3 Pek. Bubungan/ nok genteng Dihit. F-13A 36,00 m' 55,000,00 1,980,000,00
JUMLAH A.V 44,480,000,00
A.VI PEKERJAAN PLAFON
1 Pek. Rangka hollow galvanis A.4.2.1.20 90,00 m2 96,500,00 8,685,000,00
2 Pek. Plafon Gypsum board A.4.5.1.7 90,00 m2 53,900,00 4,851,000,00
4 Pek. Profil Plafon A.4.5.1.11 42,00 m' 30,400,00 1,276,800,00
JUMLAH A.VI 14,812,800,00
A.VII PEKERJAAN LANTAI
KODE HARGA SAT. JML. HARGA
NO URAIAN PEKERJAAN VOLUME
ANALISA Rp. Rp.
1 2 3 4 5 6
1 Pek. Urugan pasir bawah lantai A.2.3.1.11 90,00 m3 241,100,00 21,699,000,00
2 Pek. Lantai Kramik 40x40 A.4.4.3.69 90,00 m2 219,400,00 19,746,000,00
3 Pek. Lantai kramik 40x40 Antislip A.4.4.3.70 46,00 m2 221,600,00 10,193,600,00
JUMLAH A.VII 51,638,600,00
A.VIII PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding A.4.7.1.10 136,80 m2 30,800,00 4,213,440,00
2 Pek. Pengecatan Plafon Dihit. N-01 90,00 m2 26,000,00 2,340,000,00
JUMLAH A.VIII 6,553,440,00
A.IX PEKERJAAN ELEKTRIKAL
- Instalasi
1 Pas. Instalasi lampu P-01 16,00 ttk 197,000,00 3,152,000,00
2 Pas. Instalasi stopkontak P-03 5,00 ttk 178,200,00 891,000,00
- Aksesoris
3 Pas. Down Light U&B 16,00 bh 94,000,00 1,504,000,00
4 Pas. Lampu SL U&B 5,00 bh 42,900,00 214,500,00
5 Pas. Stop Kontak P-12 3,00 bh 96,150,00 288,450,00
7 Pas. Saklar tunggal P-15 3,00 bh 98,200,00 294,600,00
JUMLAH A.IX 6,344,550,00
A.X PEKERJAAN HURUP AKRILIK
1 Pek. Pas Hurup Uk 12cm Dihitung 25,00 bh 7,000,00 175,000,00
2 Pek. pas Hurup Uk 25cm Dihitung 35,00 bh 14,000,00 490,000,00
4 Pek. Pas Logo Dihitung 1,00 bh 950,000,00 950,000,00
1,615,000,00
A.XI PEKERJAAN PERAPIHAN
1 Pembersihan sisa pekerjaan - 1,00 ls 1,500,000,00 1,500,000,00
SUB REKAPITULASI PEKERJAAN KIOS JUAL BELI BUAH
RINCIAN RENCANA ANGGARAN BIAYA
SUB JUMLAH
NO URAIAN PEK ERJAAN
(Rp)
I PEKERJAAN PERSIAPAN
1 Pek. pembersihan lahan A.2.2.1.9 136,00 m2 17,800,00 2,420,800,00
3 Pas. Direksi keet A.2.2.1.5 2,00 m2 662,600,00 1,325,200,00
4 Penyedian air kerja + listrik kerja U&B 1,00 ls 300,000,00 300,000,00
JUMLAH I 4,046,000,00
II PEKERJAAN PELAKSANAAN
A.I PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian tanah A.2.3.1.1 12,50 m3 85,300,00 1,066,250,00
2 Pek. Urugan kembali A.2.3.1.9 12,50 m3 61,500,00 768,750,00
3 Pek. Urugan pasir bawah pondasi A.2.3.1.11 2,05 m3 241,100,00 493,772,80
4 Pek. Pengurugan 1m3 sirtu padat A.2.3.1.14 10,00 m3 375,700,00 3,757,000,00
5 Pek. Aanstamping A.3.2.1.9 3,00 m3 566,900,00 1,700,700,00
6 Pek. Pondasi batu kali, 1 pc : 5 ps A.3.2.1.3 12,50 m3 928,800,00 11,610,000,00
JUMLAH A.I 19,396,472,80
A.II PEKERJAAN BETON
1 Pek. Beton Sloof S1 15/20
- Beton K175 A.4.1.1.5 2,52 m3 1,123,100,00 2,830,212,00
- Besi beton A.4.1.1.17 210,67 kg 20,200,00 4,255,532,86
- Bekisting A.4.1.1.21 16,80 m2 118,000,00 1,982,400,00
2 Pek. Kolom K1 20/30
- Beton K175 A.4.1.1.5 2,39 m3 1,123,100,00 2,688,701,40
- Besi beton A.4.1.1.17 327,30 kg 20,200,00 6,611,476,29
- Bekisting A.4.1.1.22 39,90 m2 109,000,00 4,349,100,00
5 Pek. Beton Balok 15/25 Elv. +3.00
- Beton K175 A.4.1.1.5 0,28 m3 1,123,100,00 315,871,88
- Besi beton A.4.1.1.17 47,15 kg 20,200,00 952,400,71
- Bekisting A.4.1.1.36 4,88 m2 134,900,00 657,637,50
8 Pek. Lantai rabat beton/ beton tumbuk 1:3:5
- Beton A.4.1.1.4 9,80 m3 858,100,00 8,409,380,00
- Bekisting A.4.1.1.24 4,00 m2 384,500,00 1,538,000,00
JUMLAH A.II 34,590,712,64
A.III PEKERJAAN DINDING
1 Pek. Pasangan Dinding A.4.4.1.10 68,40 m2 152,200,00 10,410,480,00
2 Pek. Plesteran Dinding A.4.4.2.5 136,80 m2 68,900,00 9,425,520,00
3 Pek. acian A.4.4.2.27 136,80 m2 41,900,00 5,731,920,00
JUMLAH A.III 25,567,920,00
A.IV PEKERJAAN KUSEN PINTU DAN JENDELA
1 Pek. kusen tipe P1 Dihit. F-02 1,00 unit 5,576,900,00 5,576,900,00
2 Pek. kusen BV2 Dihit. F-13 6,00 unit 2,451,300,00 14,707,800,00
JUMLAH A.IV 20,284,700,00
A.V PEKERJAAN PENUTUP ATAP
1 Pek. Rangka atap baja ringan Dihit. K-43 136,00 m2 175,000,00 23,800,000,00
2 Pek. Penutup atap baja ringan A.4.5.2.31 136,00 m2 137,500,00 18,700,000,00
3 Pek. Bubungan/ nok genteng Dihit. F-13A 36,00 m' 55,000,00 1,980,000,00
JUMLAH A.V 44,480,000,00
A.VI PEKERJAAN PLAFON
1 Pek. Rangka hollow galvanis A.4.2.1.20 90,00 m2 96,500,00 8,685,000,00
2 Pek. Plafon Gypsum board A.4.5.1.7 90,00 m2 53,900,00 4,851,000,00
4 Pek. Profil Plafon A.4.5.1.11 42,00 m' 30,400,00 1,276,800,00
JUMLAH A.VI 14,812,800,00
A.VII PEKERJAAN LANTAI
KODE HARGA SAT. JML. HARGA
NO URAIAN PEKERJAAN VOLUME
ANALISA Rp. Rp.
1 2 3 4 5 6
1 Pek. Urugan pasir bawah lantai A.2.3.1.11 90,00 m3 241,100,00 21,699,000,00
2 Pek. Lantai Kramik 40x40 A.4.4.3.69 90,00 m2 219,400,00 19,746,000,00
3 Pek. Lantai kramik 40x40 Antislip A.4.4.3.70 46,00 m2 221,600,00 10,193,600,00
JUMLAH A.VII 51,638,600,00
A.VIII PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding A.4.7.1.10 136,80 m2 30,800,00 4,213,440,00
2 Pek. Pengecatan Plafon Dihit. N-01 90,00 m2 26,000,00 2,340,000,00
JUMLAH A.VIII 6,553,440,00
A.IX PEKERJAAN ELEKTRIKAL
- Instalasi
1 Pas. Instalasi lampu P-01 16,00 ttk 197,000,00 3,152,000,00
2 Pas. Instalasi stopkontak P-03 5,00 ttk 178,200,00 891,000,00
- Aksesoris
3 Pas. Down Light U&B 16,00 bh 94,000,00 1,504,000,00
4 Pas. Lampu SL U&B 5,00 bh 42,900,00 214,500,00
5 Pas. Stop Kontak P-12 3,00 bh 96,150,00 288,450,00
7 Pas. Saklar tunggal P-15 3,00 bh 98,200,00 294,600,00
JUMLAH A.IX 6,344,550,00
A.X PEKERJAAN HURUP AKRILIK
1 Pek. Pas Hurup Uk 12cm Dihitung 25,00 bh 7,000,00 175,000,00
2 Pek. pas Hurup Uk 25cm Dihitung 35,00 bh 14,000,00 490,000,00
4 Pek. Pas Logo Dihitung 1,00 bh 950,000,00 950,000,00
1,615,000,00
A.XI PEKERJAAN PERAPIHAN
1 Pembersihan sisa pekerjaan - 1,00 ls 1,500,000,00 1,500,000,00
SUB REKAPITULASI PEKERJAAN GEDUNG FOOD COURT
RINCIAN RENCANA ANGGARAN BIAYA
SUB JUMLAH
NO URAIAN PEK ERJAAN
(Rp)
I PEKERJAAN PERSIAPAN
1 Pek. pembersihan lahan A.2.2.1.9 20,00 m2 17,800,00 356,000,00
3 Pas. Direksi keet A.2.2.1.5 2,00 m2 662,600,00 1,325,200,00
4 Penyedian air kerja + listrik kerja U&B 1,00 ls 300,000,00 300,000,00
JUMLAH I 1,981,200,00
II PEKERJAAN PELAKSANAAN
A.I PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian tanah A.2.3.1.1 12,25 m3 85,300,00 1,044,925,00
2 Pek. Urugan kembali A.2.3.1.9 12,25 m3 61,500,00 753,375,00
3 Pek. Urugan pasir bawah pondasi A.2.3.1.11 7,00 m3 241,100,00 1,687,700,00
4 Pek. Pengurugan 1m3 sirtu padat A.2.3.1.14 10,00 m3 375,700,00 3,757,000,00
5 Pek. Aanstamping A.3.2.1.9 3,00 m3 566,900,00 1,700,700,00
6 Pek. Pondasi batu kali, 1 pc : 5 ps A.3.2.1.3 6,25 m3 928,800,00 5,805,000,00
JUMLAH A.I 14,748,700,00
A.II PEKERJAAN BETON
1 Pek. Beton Sloof S1 15/20
- Beton K175 A.4.1.1.5 1,32 m3 1,123,100,00 1,482,492,00
- Besi beton A.4.1.1.17 75,43 kg 20,200,00 1,523,623,22
- Bekisting A.4.1.1.21 6,00 m2 118,000,00 708,000,00
2 Pek. Kolom K1 20/30
- Beton K175 A.4.1.1.5 1,03 m3 1,123,100,00 1,152,300,60
- Besi beton A.4.1.1.17 140,27 kg 20,200,00 2,833,489,84
- Bekisting A.4.1.1.22 17,10 m2 109,000,00 1,863,900,00
5 Pek. Beton Balok 15/25 Elv. +3.00
- Beton K175 A.4.1.1.5 0,28 m3 1,123,100,00 315,871,88
- Besi beton A.4.1.1.17 47,15 kg 20,200,00 952,400,71
- Bekisting A.4.1.1.36 4,88 m2 134,900,00 657,637,50
8 Pek. Lantai rabat beton/ beton tumbuk 1:3:5
- Beton A.4.1.1.4 9,80 m3 858,100,00 8,409,380,00
- Bekisting A.4.1.1.24 4,00 m2 384,500,00 1,538,000,00
JUMLAH A.II 21,437,095,74
A.III PEKERJAAN DINDING
1 Pek. Pasangan Dinding A.4.4.1.10 45,60 m2 152,200,00 6,940,320,00
2 Pek. Plesteran Dinding A.4.4.2.5 91,20 m2 68,900,00 6,283,680,00
3 Pek. acian A.4.4.2.27 91,20 m2 41,900,00 3,821,280,00
JUMLAH A.III 17,045,280,00
A.IV PEKERJAAN KUSEN PINTU DAN JENDELA
1 Pek. kusen tipe P1 Dihit. F-02 1,00 unit 5,576,900,00 5,576,900,00
2 Pek. kusen BV2 Dihit. F-13 2,00 unit 2,451,300,00 4,902,600,00
JUMLAH A.IV 10,479,500,00
A.V PEKERJAAN PENUTUP ATAP
1 Pek. Rangka atap baja ringan Dihit. K-43 20,00 m2 175,000,00 3,500,000,00
2 Pek. Penutup atap baja ringan A.4.5.2.31 20,00 m2 137,500,00 2,750,000,00
3 Pek. Bubungan/ nok genteng Dihit. F-13A 12,00 m' 55,000,00 660,000,00
JUMLAH A.V 6,910,000,00
A.VI PEKERJAAN PLAFON
1 Pek. Rangka hollow galvanis A.4.2.1.20 20,00 m2 96,500,00 1,930,000,00
2 Pek. Plafon Gypsum board A.4.5.1.7 20,00 m2 53,900,00 1,078,000,00
4 Pek. Profil Plafon A.4.5.1.11 42,00 m' 30,400,00 1,276,800,00
JUMLAH A.VI 4,284,800,00
A.VII PEKERJAAN LANTAI
KODE HARGA SAT. JML. HARGA
NO URAIAN PEKERJAAN VOLUME
ANALISA Rp. Rp.
1 2 3 4 5 6
1 Pek. Urugan pasir bawah lantai A.2.3.1.11 20,00 m3 241,100,00 4,822,000,00
2 Pek. Lantai Kramik 40x40 A.4.4.3.69 20,00 m2 219,400,00 4,388,000,00
3 Pek. Lantai kramik 40x40 Antislip A.4.4.3.70 10,00 m2 221,600,00 2,216,000,00
JUMLAH A.VII 11,426,000,00
A.VIII PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding A.4.7.1.10 91,20 m2 30,800,00 2,808,960,00
2 Pek. Pengecatan Plafon Dihit. N-01 20,00 m2 26,000,00 520,000,00
JUMLAH A.VIII 3,328,960,00
A.IX PEKERJAAN ELEKTRIKAL
- Instalasi
1 Pas. Instalasi lampu P-01 5,00 ttk 197,000,00 985,000,00
2 Pas. Instalasi stopkontak P-03 5,00 ttk 178,200,00 891,000,00
- Aksesoris
3 Pas. Down Light U&B 5,00 bh 94,000,00 470,000,00
4 Pas. Lampu SL U&B 5,00 bh 42,900,00 214,500,00
5 Pas. Stop Kontak P-12 3,00 bh 96,150,00 288,450,00
7 Pas. Saklar tunggal P-15 3,00 bh 98,200,00 294,600,00
JUMLAH A.IX 3,143,550,00
A.X PEKERJAAN HURUP AKRILIK
1 Pek. Pas Hurup Uk 12cm Dihitung 25,00 bh 7,000,00 175,000,00
2 Pek. pas Hurup Uk 25cm Dihitung 35,00 bh 14,000,00 490,000,00
4 Pek. Pas Logo Dihitung 1,00 bh 950,000,00 950,000,00
1,615,000,00
A.XI PEKERJAAN PERAPIHAN
1 Pembersihan sisa pekerjaan - 1,00 ls 1,500,000,00 1,500,000,00
SUB REKAPITULASI PEKERJAAN MESJID
RINCIAN RENCANA ANGGARAN BIAYA
SUB JUMLAH
NO URAIAN PEK ERJAAN
(Rp)
I PEK. PERSIAPAN
1 Sewa pagar sementara dari seng tinggi 2 m ls 32,92 m' 92,000,00 3,028,640,00
2 Papan nama proyek ls 1,00 bh 350,000,00 350,000,00
3 Pengukuran dan pemasangan Bouwplank A.2.2.1.4 89,00 m' 68,200,00 6,069,800,00
4 Penyedian air kerja + listrik kerja ls 1,00 ls 1,500,000,00 1,500,000,00
5 Biaya Sistem Manajemen Kesehatan Keselamatan ls
1,00 ls 7,922,000,00 7,922,000,00
konstruksi (SMK3)
JUMLAH I 18,870,440,00
II PEKERJAAN PELAKSANAAN
A.I PEKERJAAN TANAH DAN PONDASI
1 Pek. galian tanah A.2.3.1.1 130,16 m3 85,300,00 11,102,648,00
2 Pek. urugan kembali A.2.3.1.9 25,16 m3 61,500,00 1,547,340,00
3 Pek. urugan pasir bawah pondasi A.2.3.1.11 7,65 m3 148,000,00 1,132,200,00
4 Pek. aanstamping A.3.2.1.9 18,25 m3 566,900,00 10,345,925,00
5 Pasang pondasi batu kali, 1 pc : 5 ps A.3.2.1.3 40,16 m3 928,800,00 37,300,608,00
6 Pek. urugan sirtu A.2.3.1.14 30,46 m3 375,700,00 11,443,822,00
JUMLAH A.I 72,872,543,00
A.II PEKERJAAN BETON
1 Pek. beton pondasi sumuran
- Beton K250 A.4.1.1.8 24,11 m3 1,204,600,00 29,045,315,20
- Besi beton A.4.1.1.17 2,999,78 kg 20,200,00 60,595,556,00
2 Pek. beton pile cap / poer plat P1
- Beton K250 A.4.1.1.8 17,28 m3 1,204,600,00 20,815,488,00
- Besi beton A.4.1.1.17 1,638,45 kg 20,200,00 33,096,649,60
- Bekisting A.4.1.1.20 57,60 m2 221,600,00 12,764,160,00
3 Pek. beton poer plat P2
- Beton K250 A.4.1.1.8 0,72 m3 1,204,600,00 867,312,00
- Besi beton A.4.1.1.17 83,02 kg 20,200,00 1,677,084,80
- Bekisting A.4.1.1.20 2,88 m2 221,600,00 638,208,00
4 Pek. beton sloof 15/20
- Beton K250 A.4.1.1.8 4,14 m3 1,204,600,00 4,991,862,40
- Besi beton A.4.1.1.17 721,81 kg 20,200,00 14,580,521,60
- Bekisting A.4.1.1.21 28,20 m2 236,000,00 6,655,200,00
5 Pek. beton kolom praktis 12/12 ( KP )
- Beton K175 A.4.1.1.5 0,92 m3 1,123,100,00 1,033,252,00
- Besi beton A.4.1.1.17 243,33 kg 20,200,00 4,915,225,60
- Bekisting A.4.1.1.22 0,30 m2 105,700,00 32,132,80
6 Pek. beton kolom 30/30 ( K1 )
- Beton K250 A.4.1.1.8 9,72 m3 1,204,600,00 11,708,712,00
- Besi beton A.4.1.1.17 1,971,33 kg 20,200,00 39,820,825,60
- Bekisting A.4.1.1.22 64,80 m2 327,000,00 21,189,600,00
7 Pek. beton kolom 15/30 ( K2 )
- Beton K250 A.4.1.1.8 0,58 m3 1,204,600,00 693,849,60
- Besi beton A.4.1.1.17 113,83 kg 20,200,00 2,299,406,40
- Bekisting A.4.1.1.22 5,78 m2 327,000,00 1,888,752,00
8 Pek. beton balok lintel 12/15 ( BL )
- Beton K175 A.4.1.1.5 1,62 m3 1,123,100,00 1,823,914,40
- Besi beton A.4.1.1.17 330,77 kg 20,200,00 6,681,513,60
- Bekisting A.4.1.1.23 16,26 m2 134,900,00 2,194,013,60
9 Pek. beton balok 20/40 ( B1 )
- Beton K250 ( Ready Mix ) A.4.1.1.8.a 3,79 m3 1,204,600,00 4,567,843,20
- Besi beton A.4.1.1.17 1,421,44 kg 20,200,00 28,713,088,00
- Bekisting A.4.1.1.23 51,56 m2 336,300,00 17,339,628,00
10 Pek. beton balok 20/30 ( B2 )
- Beton K250 ( Ready Mix ) A.4.1.1.8.a 1,56 m3 1,152,200,00 1,797,432,00
- Besi beton A.4.1.1.17 486,97 kg 19,300,00 9,398,482,40
- Bekisting A.4.1.1.23 24,24 m2 321,700,00 7,798,008,00
11 Pek. beton balok 15/25 ( B3 )
- Beton K250 ( Ready Mix ) A.4.1.1.8.a 0,19 m3 1,152,200,00 221,222,40
- Besi beton A.4.1.1.17 75,67 kg 19,300,00 1,460,469,60
- Bekisting A.4.1.1.23 4,11 m2 321,700,00 1,322,830,40
12 Pek. beton balok 15/20 ( B4 )
- Beton K250 ( Ready Mix ) A.4.1.1.8.a 1,67 m3 1,152,200,00 1,926,478,40
- Besi beton A.4.1.1.17 245,54 kg 19,300,00 4,738,999,20
- Bekisting A.4.1.1.23 25,70 m2 321,700,00 8,266,403,20
13 Pek. beton listplank 7/40
- Beton K250 ( Ready Mix ) A.4.1.1.8.a 1,42 m3 1,152,200,00 1,631,515,20
- Besi beton A.4.1.1.17 253,54 kg 19,300,00 4,893,399,20
- Bekisting A.4.1.1.23 22,46 m2 321,700,00 7,226,668,80
14 Pek. Plat lantai beton tebal 12 cm
- Beton K250 ( Ready Mix ) A.4.1.1.8.a 13,81 m3 1,152,200,00 15,909,577,60
- Besi beton A.4.1.1.17 1,417,02 kg 19,300,00 27,348,408,80
- Bekisting A.4.1.1.24 94,82 m2 384,500,00 36,459,828,00
JUMLAH A.II 461,028,837,60
A.III PEKERJAAN DINDING
1 Pek. dinding bata merah A.4.4.1.10 413,60 m2 139,200,00 57,573,120,00
2 Pek. plesteran dinding A.4.4.2.5 903,77 m2 64,000,00 57,841,280,00
3 Pek. acian A.4.4.2.27 987,47 m2 39,900,00 39,400,053,00
4 Pek. dinding partisi double GRC + rangka baja ringan A.4.4.2.30 24,41 m2 269,400,00 6,576,054,00
5 Pek. dinding batu alam A.4.4.3.58 4,19 m2 345,000,00 1,445,550,00
6 Pek. dinding keramik KM/WC, 25x40 cm corak/warna Dihit. I-05 31,20 m2 289,000,00 9,016,800,00
7 Pek. dinding meja beton granit 60x60 cm A.4.4.3.72 7,36 m2 482,500,00 3,551,200,00
8 Pek. Glass block U&B 8,00 bh 27,000,00 216,000,00
9 Pek. roster beton U&B 4,00 bh 7,900,00 31,600,00
JUMLAH A.III 175,651,657,00
A.IV PEKERJAAN KUSEN PINTU & JENDELA,KUNCI DAN KACA
1 Pek. kusen 4" & daun pintu alumunium warna ( P1 ) Dihit. F-03 4,00 unit 5,080,350,00 20,321,400,00
2 Pek. kusen 4" & daun pintu alumunium warna ( P2 ) Dihit. F-04 4,00 unit 3,007,100,00 12,028,400,00
3 Pek. kusen 4" & daun pintu alumunium warna ( P3 ) Dihit. F-05 2,00 unit 1,727,800,00 3,455,600,00
4 Pek. kusen 4" & daun pintu alumunium warna ( P4 ) Dihit. F-06 1,00 unit 1,604,400,00 1,604,400,00
5 Pek. kusen 4" & daun jendela alumunium warna ( J2 ) Dihit. F-11 1,00 unit 2,258,400,00 2,258,400,00
6 Pek. kusen 4" & daun jendela alumunium warna ( J3 ) Dihit. F-12 1,00 unit 1,205,200,00 1,205,200,00
7 Pek. kusen bouvenlight alumunium warna ( BV1 ) Dihit. F-13 4,00 unit 693,000,00 2,772,000,00
8 Pek. kusen bouvenlight alumunium warnal ( BV2 ) Dihit. F-14 2,00 unit 360,500,00 721,000,00
9 Pas. sticker sandblast kaca pintu & kaca jendela U&B 57,87 m2 150,000,00 8,680,500,00
JUMLAH A.IV 53,046,900,00
A.V PEKERJAAN RANGKA DAN PENUTUP ATAP
1 Pek. kuda-kuda baja ringan U&B 225,00 m2 165,000,00 37,125,000,00
2 Pek. penutup atap bitumen A.4.5.2.31 225,00 m2 188,800,00 42,480,000,00
3 Pek. bubungan/ nok bitumen A.4.5.2.36 28,81 m' 177,800,00 5,122,418,00
4 Pek. Talang miring galvallum - 4,04 m' 97,500,00 393,900,00
5 Pas. kalsiplank A.4.6.1.30 48,70 m' 64,700,00 3,150,890,00
JUMLAH A.V 88,272,208,00
A.VI PEKERJAAN PLAFOND
Pek. rangka langit-langit besi hollow 1x40.40.1,3 mm,
1 A.4.2.1.20 305,06 m2 92,300,00 28,157,038,00
modul 60x60 cm
2 Pek. plafond gypsum A.4.5.1.7 319,09 m2 51,500,00 16,433,135,00
3 Pek. listprofil gypsum A.4.5.1.11 246,85 m' 29,100,00 7,183,335,00
JUMLAH A.VI 51,773,508,00
A.VII PEKERJAAN LANTAI
1 Pek. urugan pasir bawah lantai A.2.3.1.11 12,97 m3 151,400,00 1,963,658,00
2 Pek. lantai granit 60x60 warna A.4.4.3.69 250,84 m2 376,100,00 94,340,924,00
3 Pek. lantai granit 60x60 warna anti slip A.4.4.3.70 20,45 m2 399,100,00 8,161,595,00
4 Pek. lantai keramik 40x40 corak/warna ( antislip ) Dihit. I-03 8,64 m2 208,000,00 1,797,120,00
5 Pondasi pinggir rabat beton (pas.bata) A.4.4.1.10 48,10 m2 139,200,00 6,695,520,00
6 Pek. rabat beton A.4.1.1.4 2,88 m3 809,600,00 2,331,648,00
7 Pek. Railing tangga dan ramp stainless steel - 12,52 m2 650,000,00 8,138,000,00
JUMLAH A.VII 123,428,465,00
A.VIII PEKERJAAN PENGECATAN
1 Pek. pengecatan dinding A.4.7.1.10 867,09 m2 27,600,00 23,931,684,00
2 Pek. pengecatan plafond Dihit. N-01 319,09 m2 24,000,00 7,658,160,00
3 Pek. pengecatan listplank A.4.7.1.4 9,74 m2 46,900,00 456,806,00
JUMLAH A.VIII 32,046,650,00
A.IX PEKERJAAN ELECTRIKAL
- Instalasi
1 Pas. Instalasi lampu P-01 37,00 ttk 188,400,00 6,970,800,00
2 Pas. Instalasi stopkontak P-03 15,00 ttk 170,500,00 2,557,500,00
- Aksesoris
1 Pas. Down Light 18 W EX PHILIPS U&B 13,00 bh 94,000,00 1,222,000,00
2 Pas. Lampu SL 18 W EX PHILIPS U&B 12,00 bh 36,000,00 432,000,00
3 Pas. Lampu TL 2x18 W TKI ex Philips ( RMI ) U&B 11,00 bh 269,000,00 2,959,000,00
4 Pas. Lampu Baret U&B 1,00 bh 325,000,00 325,000,00
5 Stop Kontak U&B 15,00 bh 29,210,00 438,150,00
6 Saklar ganda U&B 13,00 bh 19,250,00 250,250,00
7 Saklar tunggal U&B 7,00 bh 15,950,00 111,650,00
- Pek. Penyambungan Listrik PLN
1 Biaya Pemasangan Listrik 3500 watt 1,00 lot 7,000,000,00 7,000,000,00
2 Box Schreeng In-bouw C4 U&B 1,00 bh 52,500,00 52,500,00
Pentanahan (Grounding) Netral Sistem & Pentanahan
3 U&B 1,00 ls 658,400,00 658,400,00
Body
4 Ohm Saklar u/PLN & Diesel U&B 1,00 bh 203,000,00 203,000,00
5 Cable NYY 4 x 10 mm U&B 4,00 m' 37,500,00 150,000,00
JUMLAH A.IX 23,330,250,00
A.X PEKERJAAN SANITARY
1 Pas. Mesin pompa air - 1,00 bh 3,500,000,00 3,500,000,00
2 Pas. Jet washer A.5.1.1.19.B 4,00 bh 154,400,00 617,600,00
3 Pas. Washtafel Lengkap A.5.1.1.5 4,00 bh 1,290,300,00 5,161,200,00
4 Instalasi Pemipaan Air Bersih
- Pipa PVC dia. 3/4" A.5.1.1.26 90,24 m' 29,100,00 2,625,984,00
- Kran dinding 1/2" A.5.1.1.19 4,00 bh 76,300,00 305,200,00
- Kran Angsa A.5.1.1.19.A 2,00 bh 147,100,00 294,200,00
- Instalasi pipa + material bantu (support, lem, socket dll) - 90,24 ls 4,400,00 397,056,00
- Instalasi pipa + material bantu (support, lem, socket dll) - 198,36 ls 6,400,00 1,269,504,00
6 Pek. hand railing stainless steel KM/WC 40 cm U&B 4,00 bh 145,000,00 580,000,00
7 Septictank Dihit. O-02 1,00 unit 5,923,900,00 5,923,900,00
8 Resapan Dihit. O-03 1,00 unit 281,000,00 281,000,00
JUMLAH A.X 42,933,470,00
C.II PEK. MENARA AIR
1 Galian Tanah Pondasi Plat A.2.3.1.1 2,56 m3 81,600,00 208,896,00
2 Urugan Tanah Kembali A.2.3.1.9 1,79 m3 58,800,00 105,252,00
3 Lantai Kerja beton tumbuk t= 5cm A.4.1.1.4 0,13 m3 809,600,00 105,248,00
4 Pondasi Plat 80 x 80 x 20 cm
- Beton K250 A.4.1.1.8 0,51 m3 1,152,200,00 587,622,00
- Besi beton A.4.1.1.17 78,60 kg 19,300,00 1,516,980,00
- Bekisting A.4.1.1.20 2,56 m3 212,000,00 542,720,00
5 Pasangan Kolom Beton 20/20
- Beton K250 A.4.1.1.8 0,14 m3 1,047,100,00 146,594,00
- Besi beton A.4.1.1.17 39,71 kg 14,400,00 571,824,00
- Bekisting A.4.1.1.22 2,88 m3 284,700,00 819,936,00
6 Pasangan Sloof Beton 15/20
- Beton K250 A.4.1.1.8 0,19 m3 1,152,200,00 218,918,00
- Besi beton A.4.1.1.17 35,33 kg 19,300,00 681,869,00
- Bekisting A.4.1.1.21 1,02 m3 225,700,00 230,214,00
7 Besi siku 60 x 60 x 65 mm A.4.2.1.1 100,54 kg 31,200,00 3,136,848,00
8 Besi siku 50 x 50 x 5 mm A.4.2.1.1 169,20 kg 31,200,00 5,279,040,00
9 Base Plat t= 6 mm A.4.2.1.1 7,54 kg 31,200,00 235,248,00
10 Angkur Besi dia. 16mm U&B 16,00 bh 19,000,00 304,000,00
11 Pasang Tangga Pemeliharaan Besi Pipa GIP Ø 1" A.5.1.1.21 6,50 m' 93,900,00 610,350,00
12 Pasang Tangga Pemeliharaan Besi Pipa GIP Ø 1,5" A.5.1.1.22 14,00 m' 121,300,00 1,698,200,00
13 Beton Tumbuk Lantai Bawah Torn t= 5 cm A.4.1.1.4 0,20 m3 809,600,00 161,920,00
14 Cat Besi Rangka Menara + Tangga Pemeliharaan A.4.7.1.16. 15,44 m2 33,800,00 521,872,00
JUMLAH C.II 17,683,551,00
SUB REKAPITULASI PEKERJAAN GAZEBO
RINCIAN RENCANA ANGGARAN BIAYA
SUB JUMLAH
NO URAIAN PEK ERJAAN
(Rp)
I PEKERJAAN PERSIAPAN
1 Pek. pembersihan lahan A.2.2.1.9 49,00 m2 17,800,00 872,200,00
3 Pas. Direksi keet A.2.2.1.5 2,00 m2 662,600,00 1,325,200,00
4 Penyedian air kerja + listrik kerja U&B 1,00 ls 300,000,00 300,000,00
JUMLAH I 2,497,400,00
II PEKERJAAN PELAKSANAAN
A.I PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian tanah A.2.3.1.1 5,00 m3 85,300,00 426,500,00
2 Pek. Urugan kembali A.2.3.1.9 5,00 m3 61,500,00 307,500,00
3 Pek. Urugan pasir bawah pondasi A.2.3.1.11 2,05 m3 241,100,00 493,772,80
4 Pek. Pengurugan 1m3 sirtu padat A.2.3.1.14 10,00 m3 375,700,00 3,757,000,00
5 Pek. Aanstamping A.3.2.1.9 3,00 m3 566,900,00 1,700,700,00
6 Pek. Pondasi batu kali, 1 pc : 5 ps A.3.2.1.3 5,00 m3 928,800,00 4,644,000,00
JUMLAH A.I 11,329,472,80
A.II PEKERJAAN BETON
1 Pek. Beton Sloof S1 15/20
- Beton K175 A.4.1.1.5 1,20 m3 1,123,100,00 1,347,720,00
- Besi beton A.4.1.1.17 100,47 kg 20,200,00 2,029,532,41
- Bekisting A.4.1.1.21 8,00 m2 118,000,00 944,000,00
2 Pek. Kolom K1 20/30
- Beton K175 A.4.1.1.5 0,68 m3 1,123,100,00 768,200,40
- Besi beton A.4.1.1.17 93,51 kg 20,200,00 1,888,993,23
- Bekisting A.4.1.1.22 11,40 m2 109,000,00 1,242,600,00
5 Pek. Beton Balok 15/25 Elv. +3.00
- Beton K175 A.4.1.1.5 0,28 m3 1,123,100,00 315,871,88
- Besi beton A.4.1.1.17 47,15 kg 20,200,00 952,400,71
- Bekisting A.4.1.1.36 4,88 m2 134,900,00 657,637,50
8 Pek. Lantai rabat beton/ beton tumbuk 1:3:5
- Beton A.4.1.1.4 9,80 m3 858,100,00 8,409,380,00
- Bekisting A.4.1.1.24 4,00 m2 384,500,00 1,538,000,00
JUMLAH A.II 20,094,336,12
A.III PEKERJAAN DINDING
1 Pek. Pasangan Dinding A.4.4.1.10 14,25 m2 152,200,00 2,168,850,00
2 Pek. Plesteran Dinding A.4.4.2.5 28,50 m2 68,900,00 1,963,650,00
3 Pek. acian A.4.4.2.27 28,50 m2 41,900,00 1,194,150,00
JUMLAH A.III 5,326,650,00
A.IV PEKERJAAN PENUTUP ATAP
1 Pek. Rangka atap baja ringan Dihit. K-43 49,00 m2 175,000,00 8,575,000,00
2 Pek. Penutup atap baja ringan A.4.5.2.31 49,00 m2 137,500,00 6,737,500,00
3 Pek. Bubungan/ nok genteng Dihit. F-13A 25,00 m' 55,000,00 1,375,000,00
JUMLAH A.IV 16,687,500,00
A.V PEKERJAAN PLAFON
1 Pek. Rangka hollow galvanis A.4.2.1.20 25,00 m2 96,500,00 2,412,500,00
2 Pek. Plafon Gypsum board A.4.5.1.7 25,00 m2 53,900,00 1,347,500,00
4 Pek. Profil Plafon A.4.5.1.11 20,00 m' 30,400,00 608,000,00
JUMLAH A.V 4,368,000,00
A.VI PEKERJAAN LANTAI
1 Pek. Urugan pasir bawah lantai A.2.3.1.11 12,00 m3 241,100,00 2,893,200,00
2 Pek. Lantai Kramik 40x40 A.4.4.3.69 25,00 m2 219,400,00 5,485,000,00
3 Pek. Lantai kramik 40x40 Antislip A.4.4.3.70 7,20 m2 221,600,00 1,595,520,00
JUMLAH A.VI 9,973,720,00
KODE HARGA SAT. JML. HARGA
NO URAIAN PEKERJAAN VOLUME
ANALISA Rp. Rp.
1 2 3 4 5 6
A.VII PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding A.4.7.1.10 28,50 m2 30,800,00 877,800,00
2 Pek. Pengecatan Plafon Dihit. N-01 25,00 m2 26,000,00 650,000,00
JUMLAH A.VII 1,527,800,00
A.VIII PEKERJAAN ELEKTRIKAL
- Instalasi
1 Pas. Instalasi lampu P-01 1,00 ttk 197,000,00 197,000,00
2 Pas. Instalasi stopkontak P-03 1,00 ttk 178,200,00 178,200,00
- Aksesoris
3 Pas. Down Light U&B 2,00 bh 94,000,00 188,000,00
4 Pas. Lampu SL U&B 2,00 bh 42,900,00 85,800,00
5 Pas. Stop Kontak P-12 1,00 bh 96,150,00 96,150,00
7 Pas. Saklar tunggal P-15 1,00 bh 98,200,00 98,200,00
JUMLAH A.VIII 843,350,00
A.IX PEKERJAAN HURUP AKRILIK
1 Pek. Pas Hurup Uk 12cm Dihitung 25,00 bh 7,000,00 175,000,00
2 Pek. pas Hurup Uk 25cm Dihitung 35,00 bh 14,000,00 490,000,00
4 Pek. Pas Logo Dihitung 1,00 bh 950,000,00 950,000,00
1,615,000,00
A.X PEKERJAAN PERAPIHAN
1 Pembersihan sisa pekerjaan - 1,00 ls 1,500,000,00 1,500,000,00
SUB REKAPITULASI PEKERJAAN GEDUNG RESORT AREA
RINCIAN RENCANA ANGGARAN BIAYA
SUB JUMLAH
NO URAIAN PEK ERJAAN
(Rp)
I PEKERJAAN PERSIAPAN
3 Biaya Sistem Manajemen Kesehatan Keselamatan konstruksi 1,00 ls 1,818,000,00 1,818,000,00
(SMK3)
JUMLAH I 1,818,000,00
II PEKERJAAN PELAKSANAAN
1 Pek. Lapisan - perekat Aspal cair/Emulsi : 6.1 (2a) 4,243,81 m3 29,860,86 126,723,814,93
2 Pek. Laston lapis Aus ( Ac-Wc ) : 6.3(5a) 283,27 Ton 1,654,235,30 468,602,374,81
3 Pembersihan sisa pekerjaan - 1,00 ls 5,000,000,00 5,000,000,00
4 Pekerjaan Paving Blok 4,365,00 m2 144,500,00 630,742,500,00
5 Pek. DPT A.3.2.1.2 554,63 m3 968,700,00 537,265,237,50
6 Pek. Galian Pondasi DPT A.2.3.1.9 256,36 m3 61,500,00 15,766,140,00
JUMLAH II 1,784,100,067,24