60
60
87
220
NILAI : Rp 137,750,000
LOKASI : KAB. GAYO LUES
SUMBER DANA : DAU
T.A : 2022
KONSULTAN PERENCANA :
REKAPITULASI RAB
T.A : 2023
JUMLAH Rp 124,100,018.69
PPN 11% Rp 13,651,002.06
JUMLAH TOTAL Rp 137,751,020.74
DIBULATKAN Rp 137,750,000.00
TERBILANG : Seratus Tiga Puluh Tujuh Juta Tujuh Ratus Lima Puluh Ribu Rupiah
Mengetahui/Menyetujui
PENGGUNA ANGGARAN ( PA)
DINAS PENDIDIKAN DAYAH
KAB. GAYO LUES
1 M³ Membuat beton mutu f'c = 14,5 Mpa (K-175), Slump (120 ± 20) mm
A.4.1.1.5 Rp 1,336,284.00
A. BAHAN : Semen PC (1 Kg) 326.000 Kg Rp 1,950.00 Rp 635,700.00
Pasir Beton 760.000 Kg Rp 170.00 Rp 129,200.00
Kerikil 1,029.000 Kg Rp 170.00 Rp 174,930.00
Air 215.000 Ltr Rp 160.00 Rp 34,400.00
JUMLAH A Rp 974,230.00
B. UPAH : PEKERJA 1.650 OH Rp 86,000.00 Rp 141,900.00
TUKANG 0.275 OH Rp 118,000.00 Rp 32,450.00
KEPALA TUKANG 0.028 OH Rp 129,000.00 Rp 3,612.00
MANDOR 0.083 OH Rp 118,000.00 Rp 9,794.00
JUMLAH B Rp 187,756.00
Jumlah (A+B) Rp 1,161,986.00
Overhead Rp 174,297.90
Total Rp 1,336,283.90
1 M² Pengecetan tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
A.4.7.1.10 Rp 25,724.00
A. BAHAN : Plamur Dinding / Plafond 0.100 Kg Rp 32,000.00 Rp 3,200.00
Cat Dasar 0.100 Kg Rp 24,000.00 Rp 2,400.00
Cat Tembok KW. Standart 0.260 Kg Rp 24,800.00 Rp 6,448.00
JUMLAH A Rp 12,048.00
B. UPAH : PEKERJA 0.020 OH Rp 86,000.00 Rp 1,720.00
TUKANG 0.063 OH Rp 118,000.00 Rp 7,434.00
KEPALA TUKANG 0.006 OH Rp 129,000.00 Rp 812.70
MANDOR 0.003 OH Rp 118,000.00 Rp 354.00
JUMLAH B Rp 10,320.70
Jumlah (A+B) Rp 22,368.70
Overhead Rp 3,355.31
Total Rp 25,724.01
*) Overhead = 15.0%
KONSULTAN PERENCANA
CV. KARYA VISIONER CONSULTANT
ALFIKAR HASWARTALMI, ST
DIREKTUR
DAFTAR ANALISA HARGA SATUAN PEKERJAAN SUPLEMEN
SUPLEMEN. 01 1 m³ Sloof 18 x 25 cm
Uraian Analisa Pekerjaan Satuan Indeks Harga Satuan Jumlah Harga
Beton K-175 A.4.1.1.5 M³ 1.000 Rp 1,336,284.00 Rp 1,336,284.00
Pembesian (Polos) A.4.1.1.17 Kg 129.529 Rp 23,280.00 Rp 3,015,436.96
Bekisting 3x Pakai A.4.1.1.21 M² 11.111 Rp 114,717.00 Rp 1,274,633.33
Lain - Lain Lain - Lain Ls 1.000 Rp 20,000.00 Rp 20,000.00
Jumlah Rp 5,646,354.29
Harga Satuan Pekerjaan Rp 5,646,354.00
SUPLEMEN. 02 1 m³ Kolom 20 x 20 cm
Uraian Satuan Indeks Harga Satuan Jumlah Harga
Beton K-175 A.4.1.1.5 M³ 1.000 Rp 1,336,284.00 Rp 1,336,284.00
Pembesian (Polos) A.4.1.1.17 Kg 142.379 Rp 23,280.00 Rp 3,314,584.83
Bekisting 3x Pakai A.4.1.1.22 M² 20.000 Rp 266,565.00 Rp 5,331,300.00
Lain - Lain Lain - Lain Ls 1.000 Rp 20,000.00 Rp 20,000.00
Jumlah Rp 10,002,168.83
Harga Satuan Pekerjaan Rp 10,002,169.00
SUPLEMEN. 03 1 m³ Kolom 20 x 30 cm
Uraian Satuan Indeks Harga Satuan Jumlah Harga
Beton K-175 A.4.1.1.5 M³ 1.000 Rp 1,336,284.00 Rp 1,336,284.00
Pembesian (Polos) A.4.1.1.17 Kg 103.761 Rp 23,280.00 Rp 2,415,555.79
Bekisting 3x Pakai A.4.1.1.22 M² 16.667 Rp 266,565.00 Rp 4,442,750.00
Lain - Lain Lain - Lain Ls 1.000 Rp 20,000.00 Rp 20,000.00
Jumlah Rp 8,214,589.79
Harga Satuan Pekerjaan Rp 8,214,590.00
SUPLEMEN. 04 1 m³ Kolom 30 x 60 cm
Uraian Satuan Indeks Harga Satuan Jumlah Harga
Beton K-175 A.4.1.1.5 M³ 1.000 Rp 1,336,284.00 Rp 1,336,284.00
Pembesian (Polos) A.4.1.1.17 Kg 95.426 Rp 23,280.00 Rp 2,221,524.57
Bekisting 3x Pakai A.4.1.1.22 M² 10.000 Rp 266,565.00 Rp 2,665,650.00
Lain - Lain Lain - Lain Ls 1.000 Rp 20,000.00 Rp 20,000.00
Jumlah Rp 6,243,458.57
Harga Satuan Pekerjaan Rp 6,243,459.00
SUPLEMEN. 05 1 m³ Balok 20 x 25 cm
Uraian Satuan Indeks Harga Satuan Jumlah Harga
Beton K-175 A.4.1.1.5 M³ 1.000 Rp 1,336,284.00 Rp 1,336,284.00
Pembesian (Polos) A.4.1.1.17 Kg 118.849 Rp 23,280.00 Rp 2,766,798.02
Bekisting 3x Pakai A.4.1.1.23 M² 10.000 Rp 272,993.00 Rp 2,729,930.00
Lain - Lain Lain - Lain Ls 1.000 Rp 20,000.00 Rp 20,000.00
Jumlah Rp 6,853,012.02
Harga Satuan Pekerjaan Rp 6,853,012.00
A. UPAH PEKERJA
HARGA SATUAN
No. URAIAN UPAH SATUAN KETERANGAN
Rp
1 KEPALA TUKANG 129,000.00 OH
2 TUKANG 118,000.00 OH
3 MANDOR 118,000.00 OH
4 PEKERJA 86,000.00 OH
B. HARGA BAHAN
HARGA SATUAN
No. URAIAN BAHAN SATUAN KETERANGAN
Rp
I BAHAN PASANGAN
1 Bata Merah 840.00 buah Wil. I
2 Batako 5,760.00 buah Wil. I
3 Batu Kali / Belah 249,600.00 m³ Wil. I
4 Batu Koral dan Kerikil 239,200.00 m³ Wil. I
5 Kerikil 170.00 Kg Wil. I
6 Batu Pecah Ukuran Bervariasi/splite 478,400.00 m³ Wil. I
7 Beton Roster / Terawang 16,800.00 buah Wil. I
8 Beton Roster Motif 55,200.00 buah Wil. I
9 Beton Ready Mix K-200 2,080,000.00 m³ Wil. I
10 Beton Ready Mix K-225 2,184,000.00 m³ Wil. I
11 Beton Ready Mix K-250 2,392,000.00 m³ Wil. I
12 Beton Ready Mix K-300 2,704,000.00 m³ Wil. I
13 Beton Ready Mix K-350 2,912,000.00 m³ Wil. I
14 Beton Ready Mix K-400 3,120,000.00 m³ Wil. I
15 Pasir Beton / Pasir Pasang 239,200.00 m³ Wil. I
16 Pasir Beton 170.00 Kg Wil. I
17 Pasir Urug 186,300.00 m³ Wil. I
23 Tanah Urug 144,000.00 m³ Wil. I
24 Air 160.00 Ltr Wil. I
Wil. I
II SEMEN Wil. I
1 Semen Instan - Zak Wil. I
2 Semen PC (40 Kg) 78,000.00 Zak Wil. I
3 Semen PC (50 Kg) 98,000.00 Zak Wil. I
4 Semen PC (1 Kg) 1,950.00 Kg Wil. I
5 Semen Pengisi Warna (Import) 32,800.00 Kg Wil. I
6 Semen Pengisi 6,000.00 Kg Wil. I
7 Semen Putih 12,800.00 Kg Wil. I
8 Semen Warna 15,360.00 Kg Wil. I
Wil. I
III KAYU Wil. I
1 Kayu Dolken 12,420.00 Btg Wil. I
2 Kayu Bekisting 3,946,800.00 m³ Wil. I
3 Kayu Sembarang 3,946,800.00 m³ Wil. I
4 Kayu Papan Sembarang 3,946,800.00 m³ Wil. I
5 Kayu Kelas III 4,680,000.00 m³ Wil. I
6 Kayu Papan Kelas III 4,659,200.00 m³ Wil. I
7 Kayu Kelas II 5,589,000.00 m³ Wil. I
8 Kayu Papan Kelas II 5,023,200.00 m³ Wil. I
9 Kayu Kelas I 6,458,400.00 m³ Wil. I
10 Kayu Papan Kelas I 6,458,400.00 m³ Wil. I
Wil. I
V ATAP DAN PENUTUP ATAP Wil. I
1 Listplank Motif Kerawang Gayo 108,800.00 M' Wil. I
2 Rabung 6 kaki x 12" 19,520.00 Lbr Wil. I
3 Rabung 7 kaki x 12" 22,800.00 Lbr Wil. I
4 Rabung Genteng Metal 56,320.00 Lbr Wil. I
5 Rabung Seng Metal Warna Uk. 0,25 KW Eksport 21,680.00 Lbr Wil. I
6 Rabung Seng Metal Warna Uk. 0,30 30,400.00 Lbr Wil. I
7 Rangka Kuda - Kuda Baja Berat 200,000.00 m² Wil. I
8 Rangka Kuda - Kuda Uk. 0,75 108,800.00 m² Wil. I
9 Rangka Kuda - Kuda Uk. 1,00 132,000.00 m² Wil. I
10 Seng 6 Kaki 9 Parit 48,000.00 lbr Wil. I
11 Seng 7 Kaki 9 Parit 54,400.00 lbr Wil. I
12 Seng 8 Kaki 9 Parit 60,800.00 lbr Wil. I
13 Seng 6 Kaki 11 Parit 58,400.00 lbr Wil. I
14 Seng 7 Kaki 11 Parit 67,200.00 lbr Wil. I
15 Seng 8 Kaki 11 Parit 76,000.00 lbr Wil. I
16 Seng Datar BJLS 0,2 mm 60,800.00 lbr Wil. I
17 Seng Galvanized 0,25 mm 60,000.00 lbr Wil. I
18 Seng Metal (Genteng Metal) Warna Uk. 0,25 KW Standart 44,800.00 lbr Wil. I
19 Seng Metal (Genteng Metal) Warna Uk. 0,25 KW Eksport 48,800.00 lbr Wil. I
20 Seng Metal (Genteng Metal) Warna Uk. 0,30 KW Standart 55,200.00 lbr Wil. I
21 Seng Metal (Genteng Metal) Warna Uk. 0,30 KW Eksport 60,000.00 lbr Wil. I
21 Seng Spandek 0.30 mm 55,200.00 m² Wil. I
VI PLAFOND
1 Asbes 3 mm, 100 x 100 Cm 21,200.00 Lbr Wil. I
2 Gypsum Board 9 mm flat 104,000.00 Lbr Wil. I
3 Gypsum Board 9 mm flat KW Eksport 108,800.00 Lbr Wil. I
3 HPL Polos 205,600.00 Lbr Wil. I
4 HPL Motif 332,600.00 Lbr Wil. I
5 HPL Polos Timbal Balik Terpasang 1,409,600.00 m² Wil. I
6 HPL Motif Timbal Balik Terpasang 1,788,800.00 m² Wil. I
7 List Gypsum Kecil 21,600.00 buah Wil. I
8 List Gypsum Besar 27,200.00 buah Wil. I
9 List tepi kayu meranti profil uk. 3 x 300 cm 27,200.00 M' Wil. I
10 Plafond PVC + Pasang 347,200.00 m² Wil. I
11 Plywood Warna 97,600.00 Lbr Wil. I
12 Profil Motif Tengah Uk. Kecil 27,200.00 buah Wil. I
13 Profil Motif Tengah Uk. Sedang 29,600.00 buah Wil. I
14 Profil Motif Tengah Uk. Besar 32,800.00 buah Wil. I
15 Triplek 3 mm 56,000.00 Lbr Wil. I
16 Triplek 4 mm 68,000.00 Lbr Wil. I
17 Triplek 8 mm 135,200.00 Lbr Wil. I
18 Triplek 12 mm 184,000.00 Lbr Wil. I
19 Plywood hitam 8 mm 223,200.00 Lbr Wil. I
XI SANITARY
1 Bak Mandi Fiber Glass - Standart 189,600.00 buah Wil. I
2 Closet Jongkok - Standart 162,400.00 buah Wil. I
3 Closet Duduk Komplit 1,626,400.00 Unit Wil. I
4 Floor Drain Plastik 11,200.00 buah Wil. I
5 Floor Drain Stainlessteel 103,200.00 buah Wil. I
6 Kran air - Standart 11,200.00 buah Wil. I
7 Kran Stainlessteel 48,800.00 buah Wil. I
8 Tempat Sabun 68,800.00 buah Wil. I
9 Urinoir - Komplit 920,000.00 Unit Wil. I
10 Washtafel - Komplit 695,200.00 Unit Wil. I
11 Shower Box 18,400,000.00 Unit Wil. I
12 Sealtape 5,600.00 buah Wil. I
KONSULTAN PERENCANA
CV. KARYA VISIONER CONSULTANT
ALFIKAR HASWARTALMI, ST
DIREKTUR