NO. URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN PAJAK JUMLAH HARGA
Rp. 10% Rp.
1 2 3 4 5 6 7
A PEKERJAAN PERSIAPAN
1 Papan Nama Kegiatan Ls 1.00 50,000.00 5,000.00 55,000.00
2 Pas. Bouplank / Profil Ls 1.00 491,500.00 49,150.00 540,650.00
3 Biaya SMK3 Konstruksi Ls 1.00 3,007,000.00 300,700.00 3,307,700.00
Jumlah A 3,903,350.00
B PEKERJAAN PELAKSANAAN
1 Pek. Galian Tanah Pondasi M3 47.92 67,375.00 322,861.00 3,551,471.00
2 Pek. Urugan Tanah Kembali M3 14.38 22,758.33 32,726.48 359,991.26
3 Pek. Buangan Tanah M3 26.83 29,524.00 79,212.89 871,341.81
4 Pek. Pasangan Batu Kali 1 : 4 M3 188.11 817,225.00 15,372,543.66 169,097,980.28
5 Pek. Siaran M2 145.31 57,227.50 831,548.48 9,147,033.29
6 Pek. Plesteran M2 59.12 59,783.00 353,437.10 3,887,808.06
7 Pek. Acian M2 59.12 34,388.75 203,306.29 2,236,369.19
8 Pek. Pengecatan M2 10.46 15,206.40 15,905.89 174,964.84
Jumlah B 189,326,959.73
REKAPITULASI
BILL OF QUANTITY
NO PEKERJAAN JUMLAH
Jumlah A + B 193,230,309.73
Total Jumlah 193,230,309.73
DIBULATKAN 193,230,000.00
Terbilang :
Seratus Sembilan Puluh Empat Juta Delapan Ratus Delapan Puluh Ribu Rupiah
Garut 2019
Penawar
CV/PT/FIRMA
Nama Jelas
Jabatan
PERHITUNGAN BIAYA SMK3 KONSTRUKSI
1 Penyiapan RK3K :
b Pembuatan Kartu Identitas Pekerja (KIP) Org 5 5,000.00 25,000.00
5 Personil K3
a Petugas K3 OB 1 1,000,000.00 1,000,000.00
6 Fasilitas/Sarana Kesehatan :
a Peralatan P3K (Kotak P3K) Ls 1 75,000.00 75,000.00
7 Rambu-Rambu :
a Rambu Peringatan Bh 2 75,000.00 150,000.00
b Rambu Informasi Bh 1 75,000.00 75,000.00