TIME SCHEDULE

KEGIATAN : PEMBANGUNAN DINDING PENAHAN TANAH


PEKERJAAN : DINDING PENAHAN TANAH
URAIAN PEKERJAAN : PEMASANGAN DINDING PENAHAN TANAH
LOKASI : .........................
T. ANGGARAN : 2022

WAKTU PELAKSANAAN 90 (SEMBILAN PULUH) HARI KALENDER


BOBOT BULAN KE I BULAN KE II BULAN KE III PREST
NO URAIAN PEKERJAAN KET
(%) MINGGU KE ASI
1 2 3 4 5 6 7 8 9 10 11 12

A PEKERJAAN PEPSIAPAN 3.390 1.695 1.695 100


B PEKERJAAN DINDING PENAHAN TANAH
1 PEKERJAAN GALIAN TANAH 8.851 4.426 4.426
2 PEKERJAAN PASIR URUG 0.378 0.189 0.189
3 PEKERJAAN PASANGAN BATU KALI 18.156 4.539 4.539 4.539 4.539
4 PEKERJAAN PASANGAN BATU KALI PLENSENGAN 61.277 10.213 10.213 10.213 10.213 10.213 10.213
5 PEKERJAAN PLESTERAN 1:2 2.828 1.414 1.414
6 PEKERJAAN SIAR 1:2 5.119 2.560 2.560

JUMLAH 100.000
Jumlah / Bobot Rencana per Minggu 6.310 21.062 14.752 14.752 14.752 14.186 14.186
Kumulatif Bobot Rencana per Minggu 0.000 6.310 27.371 42.123 56.875 71.627 85.814 100.000
Realisasi Bobot
Bobot Cepat ( + )
Bobot Lambat ( - )

Waktu Pelaksanaan 42 (hari) Kalender ........., Juli 2022


Dibuat Oleh
...............
................................................................

.............................
.........................
RENCANA ANGGARAN BIAYA

KEGIATAN : PEMBANGUNAN DINDING PENAHAN TANAH


PEKERJAAN : DINDING PENAHAN TANAH
URAIAN PEKERJAAN
: PEMASANGAN DINDING PENAHAN TANAH
LOKASI : .........................
T. ANGGARAN : 2022

HARGA JUMLAH PPN TOTAL


NO. URAIAN PEKERJAAN VOLUME STN SATUAN HARGA 11% HARGA
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
11%

A PEKERJAAN PEPSIAPAN 1,259,139.93 1,397,645.33


1. Pengukuran dan pemasangan Bowplank 7.00 m' 72,486.33 507,404.33 55,814.48 563,218.81
2 Pembersihan lahan 7.00 m2 19,360.00 135,520.00 14,907.20 150,427.20
3 Pekerjaan Pipa diameter 2 inchi 9.00 m' 68,468.40 616,215.60 67,783.72 683,999.32
JUMLAH PEKERJAAN PEPSIAPAN 1,259,139.93 1,397,645.33

B PEKERJAAN DINDING PENAHAN TANAH 35,879,094.80 39,825,795.23


1 PEKERJAAN GALIAN TANAH
1 Galian Tanah pondasi 1 4.62 m3 87,450.00 404,019.00 44,442.09 448,461.09
2 Galian Tanah pondasi 2 12.60 m3 87,450.00 1,101,870.00 121,205.70 1,223,075.70
3 Galian Tanah pondasi 3 4.62 m3 87,450.00 404,019.00 44,442.09 448,461.09
4 Galian Tanah pondasi 3 15.75 m3 87,450.00 1,377,337.50 151,507.13 1,528,844.63

JUMLAH PEKERJAAN GALIAN TANAH 3,287,245.50 3,648,842.51

2 PEKERJAAN PASIR URUG


1 Pasir Urug 1 0.42 m3 166,980.00 70,131.60 7,714.48 77,846.08
2 Pasir Urug 2 0.42 m3 166,980.00 70,131.60 7,714.48 77,846.08

JUMLAH PEKERJAAN PASIR URUG 140,263.20 155,692.15


3 PEKERJAAN PASANGAN BATU KALI
1 Pasangan Batu Kali 1 4.20 m3 802,725.00 3,371,445.00 370,858.95 3,742,303.95
2 Pasangan Batu Kali 2 4.20 m3 802,725.00 3,371,445.00 370,858.95 3,742,303.95

JUMLAH PEKERJAAN PASANGAN BATU KALI 6,742,890.00 7,484,607.90


4 PEKERJAAN PASANGAN BATU KALI PLENSENGAN
1 Pasangan Batu Kali Plensengan1 12.60 m3 802,725.00 10,114,335.00 1,112,576.85 11,226,911.85
2 Pasangan Batu Kali Plensengan2 15.75 m3 802,725.00 12,642,918.75 1,390,721.06 14,033,639.81

JUMLAH PEKERJAAN PASANGAN BATU KALI PLENSENGAN22,757,253.75 25,260,551.66


5 PEKERJAAN PLESTERAN 1:2
1 Plesteran Memanjang Bagian atas 1 4.20 m2 79,319.24 333,140.81 36,645.49 369,786.30
2 Plesteran Memanjang bagia atas 2 2.80 m2 79,319.24 222,093.87 24,430.33 246,524.20
3 Plesteran Memanjang Bagian Tumpuan 2.80 m2 79,319.24 222,093.87 24,430.33 246,524.20
4 Plesteran Memanjang Bagian samping 1 2.00 m2 79,319.24 158,638.48 17,450.23 176,088.71
5 Plesteran Memanjang Bagian samping 2 1.44 m2 79,319.24 114,219.71 12,564.17 126,783.87

JUMLAH PEKERJAAN PLESTERAN 1:2 1,050,186.74 1,165,707.28


6 PEKERJAAN SIAR 1:2
1 Siar 1:2 DPT 2 23.83 m2 35,087.58 835,996.68 91,959.63 927,956.32
2 Siar 1:2 DPT 3 30.36 m2 35,087.58 1,065,258.93 117,178.48 1,182,437.41

JUMLAH PEKERJAAN SIAR 1:2 1,901,255.61 2,110,393.73


REKAPITULASI RENCANA ANGGARAN BIAYA

KEGIATAN : PEMBANGUNAN DINDING PENAHAN TANAH


PEKERJAAN : DINDING PENAHAN TANAH
URAIAN PEKERJAAN : PEMASANGAN DINDING PENAHAN TANAH
LOKASI : .........................
T. ANGGARAN : 2022

SUB JUMLAH BIAYA JUMLAH BIAYA


NO. URAIAN PEKERJAAN
( Rp. ) ( Rp. )

A PEKERJAAN PEPSIAPAN 1,397,645.33


B PEKERJAAN DINDING PENAHAN TANAH 39,825,795.23
1 PEKERJAAN GALIAN TANAH 3,648,842.51
2 PEKERJAAN PASIR URUG 155,692.15
3 PEKERJAAN PASANGAN BATU KALI 7,484,607.90
4 PEKERJAAN PASANGAN BATU KALI PLENSENGAN 25,260,551.66
5 PEKERJAAN PLESTERAN 1:2 1,165,707.28
6 PEKERJAAN SIAR 1:2 2,110,393.73

41,223,440.55

JUMLAH 41,223,440.55
TOTAL JUMLAH 41,223,440.55
DIBULATKAN 41,220,000.00

Terbilang : Empat Puluh Satu Juta Dua Ratus Dua Puluh Ribu Rupiah

........., Juli 2022


Diperiksa Oleh Dibuat Oleh
Tim Teknis ...............
..................................... ................................................................

....................... .............................
....................... .........................

Diketahui Oleh
....................................
..................................

....................................
..................................................