2023

Minggu Ke 21 ( Dua Puluh Satu )


23-Nov-2023
Periode 24-Nov-2023

·PROGRES FISIK : 47.38 %


REKAPAN MINGGUAN
Pemilik Pekerjaan

Tanggal : 23 November 2023


Tahun Anggaran 2023

KEMAJUAN S/D MINGGU

PRESENTASE
KONTRAK KEMAJUAN MINGGU INI KEMAJUAN S/D MINGGU INI
NO URAIAN LALU
JUMLAH HARGA BOBOT HARGA BOBOT HARGA BOBOT HARGA BOBOT
% Rp) % Rp) % Rp) %

%
1 2 3 4 5 6 7 8 9 10
1 PEKERJAAN PERSIAPAN 177,370,619.65 2.40 - 171,508,119.65 2.32 - - - - 171,508,119.65 2.32 96.69
2 PEKERJAAN TANAH DAN URUGAN 259,784,264.82 3.52 - 255,166,779.12 3.52 - - - - 255,166,779.12 3.52 100.00
3 PEKERJAAN PASANGAN DAN PLESTERAN 1,904,274,975.66 25.78 - 1,023,561,536.87 13.86 - - - - 1,023,561,536.87 13.86 53.75
4 PEKERJAAN BETON BERTULANG 1,465,793,535.12 19.85 - 744,783,478.26 15.36 - 192,112,190.33 2.98 - 936,895,668.60 18.34 92.41
5 PEKERJAAN KUSEN, PINTU , JENDELA DAN PENGGANTUNG 525,389,070.18 7.11 - - - - - - - - - -
6 PEKERJAAN ATAP DAN PLAFOND 895,263,217.52 12.12 - - - - 95,703,490.74 1.30 - 95,703,490.74 1.30 10.69
7 PEKERJAAN LANTAI 234,377,217.10 3.17 - - - - - - - - - -
8 PEKERJAAN 2 UNIT SEPTICTANK DAN SANITAIR 120,609,078.07 1.63 - - - - - - - - - -
9 INSTALASI LISTRIK 139,583,954.20 1.89 - - - - - - - - - -
10 PEKERJAAN PENANGKAL PETIR 16,200,000.00 0.22 - - - - - - - - - -
11 PEKERJAAN JALAN MASUK 670,225,726.14 9.08 - 70,980,667.40 0.97 - 43,789,374.18 0.60 - 114,770,041.58 1.58 17.39
12 PEKERJAAN PAGAR 725,438,319.63 9.82 - 421,338,422.32 5.71 - 41,657,310.70 0.56 - 462,995,733.02 6.27 63.82
13 PEKERJAAN PELATARAN 31,784,206.47 0.43 - 9,756,842.00 0.13 - - - - 9,756,842.00 0.13 30.70
15 PEKERJAAN FINISHING 139,325,375.13 1.89 - - - - - - - - - -
16 PEKERJAAN LAIN-LAIN 79,940,380.16 1.08 - 5,000,000.00 0.07 - - - - 5,000,000.00 0.07 6.25
JUMLAH HARGA 7,385,359,939.88 100.00 2,702,095,845.62 41.94 373,262,365.96 5.45 3,075,358,211.58 47.38 471.71

a REALISASI SAMPAI DENGAN MINGGU LALU 41.94

b REALISASI FISIK SAMPAI DENGAN MINGGU INI 47.38

c RENCANA SAMPAI DENGAN MINGGU INI MENURUT TIME SCHEDULE 96.85

d DEVIASI FISIK TERHADAP TIME SCHEDULE - 49.47


PRESENTASE (%)
PROGRES PEKERJAAN MINGGUAN
KONTRAK
SAMPAI DENGAN
MINGGU LALU MINGGU INI
MINGGU INI
No. URAIAN PEKERJAAN
HARGA SATUAN JUMLAH HARGA BOBOT VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
SAT VOL VOL ADD
( Rp ) ( Rp ) (%) (%) (%) (%)

1 2 3 4 5 6 7 8 10 11 13 14 16 17

A PEKERJAAN BANGUNAN PUSKESMAS

I PEKERJAAN PERSIAPAN

1 Pengukuran dan Pemasangan Bouwplank M1 91.80 91.80 143,165.54 13,142,596.19 0.178 91.80 0.178 - 91.80 0.178 100.0

2 Papan Nama Proyek BH 1.00 1.00 576,372.72 576,372.72 0.008 1.00 0.008 - 1.00 0.008 100.0

3 Pembuatan Direksi Keet Los Kerja dan Gudang M2 30.00 30.00 2,617,215.61 78,516,468.37 1.063 30.00 1.063 - 30.00 1.063 100.0

4 Pembongkaran dan Pengangkuta Hasil Bongkaran 1 Gedung Eksisting Ls 1.00 1.00 7,500,000.00 7,500,000.00 0.102 1.00 0.102 - 1.00 0.102 100.0

5 Pemagaran Daerah Kerja M1 99.80 99.80 106,063.95 10,585,182.37 0.143 99.80 0.143 - 99.80 0.143 100.0

6 Manajemen Mutu / Pengujian Material Ls 1.00 1.00 5,000,000.00 5,000,000.00 0.068 1.00 0.068 - 1.00 0.068 100.0

7 Keselamatan dan Kesehatan Kerja (K3) Ls 1.00 1.00 45,300,000.00 45,300,000.00 0.613 1.00 0.613 - 1.00 0.613 100.0

8 Administrasi ,Dokumentasi & Pelaporan Ls 1.00 1.00 7,500,000.00 7,500,000.00 0.102 0.65 0.066 - 0.65 0.066 65.0

9 Mobilisasi dan Demobilisasi Ls 1.00 1.00 9,250,000.00 9,250,000.00 0.125 0.65 0.081 - 0.65 0.081 65.0

JUMLAH PEKERJAAN PERSIAPAN 177,370,619.65 2.40 2.32 - 2.32

II PEKERJAAN TANAH DAN URUGAN - -

1 Pek. Galian Perataan Tanah (Stripping) dan Pembersihan Lahan M3 115.20 115.20 82,775.00 9,535,680.00 0.129 115.20 0.129 - 115.20 0.129 100.0

2 Pek. Galian Tanah untuk Pondasi Footplate M3 99.00 99.00 82,775.00 8,194,725.00 0.111 99.00 0.111 - 99.00 0.111 100.0

3 Pek. Galian Tanah untuk Pondasi Menerus dan Selasar M3 209.08 141.00 82,775.00 11,671,192.23 0.158 141.00 0.158 - 141.00 0.158 100.0

4 Pek. Urugan Pasir Dibawah Pondasi Menerus M3 17.88 17.88 1,785,818.40 31,938,290.61 0.432 17.88 0.432 - 17.88 0.432 100.0
5 Pek. Urugan Pasir Dibawah Lantai dan Selasar M3 28.08 28.08 1,785,818.40 50,145,736.05 0.679 28.08 0.679 - 28.08 0.679 100.0

6 Pek. Urugan Sirtu Peninggi Pail Lantai dan Selasar M3 80.59 80.59 1,783,068.40 143,689,012.84 1.946 80.59 1.946 - 80.59 1.946 100.0

Pek. Urugan Tanah Peninggi Lantai M3 76.19 60,500.00 4,609,628.10 0.062 76.19 0.062 - 76.19 0.062 100.0

JUMLAH PEKERJAAN TANAH DAN URUGAN 259,784,264.82 3.52 3.52 - 3.52

III PEKERJAAN PASANGAN DAN PLESTERAN - -

1 Pek. Pasangan Aanstamping / Batu Kosong M3 75.83 49.47 2,383,698.56 117,910,962.11 1.597 49.47 1.597 - 49.47 1.597 100.0

2 Pek. Pasangan Batu Pondasi Menerus Mortar Tipe N (5,2 Mpa) M3 223.71 199.88 3,096,872.03 618,994,209.63 8.381 199.88 8.381 - 199.88 8.381 100.0

3 Pek. Pasangan Batu Pondasi Selasar dan Saluran Mortar Tipe N (5,2 Mpa) M3 46.56 46.56 3,096,872.03 144,186,180.93 1.952 - - - - - -

4 Pek. Plester Saluran Selasar 1 Pc : 4 PP Tebal 15 Cm M2 136.08 136.08 109,926.54 14,958,803.49 0.203 - - - - - -

5 Pek. Acian Saluran Selasar M2 136.08 136.08 47,279.26 6,433,761.15 0.087 - - - - - -

6 Pek. Pasangan Tangga Mortar Tipe N (5,2 Mpa) M3 27.65 27.65 3,096,872.03 85,628,511.63 1.159 - - - - - -

7 Pek. Pasangan Bata Ringan (10 x 20 x 60 cm) Dinding dengan Mortar Siap Pakai
M2 1,028.83 881.26 325,280.13 286,655,714.57 3.881 881.26 3.881 - 881.26 3.881 100.0

8 Pek. Pemasangan 1 m2 Dinding Terawang dengan Mortar Tipe N,fc’ 5,2 Mpa M2 9.79 9.79 908,592.31 8,896,118.18 0.120 - - - - - -

9 Pek. Plester Dinding dengan Semen Instan (MU 301) Tebal 8 mm M2 2,057.66 1,762.52 136,244.88 240,133,782.85 3.251 - - - - - -

10 Pek. Acian Dinding dengan Semen Instan (MU 270) Tebal 2 mm M2 2,057.66 1,762.52 67,601.15 119,148,111.49 1.613 - - - - - -

11 Pek. Pasangan Aluminium Composit Panel ( ACP ) Tebal 4 mm Setara M2 238.44 238.44 1,095,994.04 261,328,819.63 3.538 - - - - - -

JUMLAH PEKERJAAN PASANGAN DAN PLESTERAN 1,904,274,975.66 25.78 13.86 - 13.86

IV PEKERJAAN BETON BERTULANG - -

1 Pek. Rabat Lantai Beton Mutu f’c = 7,4 Mpa (K100) M3 16.51 16.51 3,127,991.67 51,643,142.43 0.699 2.53 0.107 - 2.53 0.107 15.3

2 Pek. Rabat Beton Lantai Kerja Footplate Beton Mutu f’c = 7,4 Mpa (K100) M3 6.60 6.60 3,127,991.67 20,644,745.01 0.280 6.60 0.280 - 6.60 0.280 100.0

3 Pek. Footplate 100/100 Cm Beton Mutu f’c = 21,7 Mpa (K250) M3 19.80 19.80 8,280,590.43 163,955,690.51 2.220 19.80 2.220 - 19.80 2.220 100.0

4 Pek. Kolom Pedestal 25/25 Cm Beton Mutu f’c = 21,7 Mpa (K250) M3 5.84 3.69 13,570,974.57 50,110,823.60 0.679 3.69 0.679 - 3.69 0.679 100.0

5 Pek. Kolom Struktur 25/25 Cm Beton Mutu f’c = 21,7 Mpa (K250) M3 16.21 15.88 13,570,974.57 215,524,039.90 2.918 15.88 2.918 - 15.88 2.918 100.0

6 Pek. Kolom Praktis 11/15 Cm Beton Mutu f’c = 21,7 Mpa (K250) M3 10.46 10.46 16,053,275.53 167,917,262.03 2.274 9.94 2.161 - 9.94 2.161 95.0

7 Pek. Sloof 25/35 Cm Beton Mutu f’c = 21,7 Mpa (K250) M3 30.65 0.00 8,481,443.50 - - -

Pek. Sloof 25/35 Cm Beton Mutu f’c = 21,7 Mpa (K250) M3 29.60 7,603,465.07 225,072,070.35 3.048 29.60 3.047 - 29.60 3.047 100.0

8 Pek. Sloof 15/20 Cm Beton Mutu f’c = 21,7 Mpa (K250) M3 2.45 2.45 10,852,291.57 26,588,114.34 0.360 2.45 0.360 - 2.45 0.360 100.0

9 Pek. Balok 25/35 Cm Beton Mutu f’c = 21,7 Mpa (K250) M3 32.10 32.10 9,851,907.20 316,246,221.01 4.282 10.20 1.361 2.601 29.70 3.962 92.5
19.5
10 Pek. Ring Balk 10/20 Cm Beton Mutu f’c = 21,7 Mpa (K250) M3 3.17 1.64 10,408,696.79 17,080,671.43 0.231 - - - - - -

11 Pek. Talang Beton f’c = 21,7 Mpa (K250) M3 19.00 0.00 11,726,386.29 - - -

Pek. Lantai Talang Beton f’c = 21,7 Mpa (K250) M3 7.97 8,447,683.60 67,351,691.79 0.912 7.97 0.912 - 7.97 0.912 100.0

Pek. Lisplang Luar Beton f’c = 21,7 Mpa (K250) M3 8.77 8,161,250.65 71,574,821.11 0.969 8.77 0.969 - 8.77 0.969 100.0

Pek. Lisplang Dalam Beton f’c = 21,7 Mpa (K250) M3 5.44 6,927,472.70 37,657,741.58 0.510 1.38 0.129 4.06 0.381 5.44 0.510 100.0

12 Pek. Meja Beton Mutu f’c = 21,7 Mpa (K250) M3 0.70 0.70 11,726,386.29 8,208,470.40 0.111 - - - - - -

13 Pek. Beton Penutup Saluran Selasar Tebal 12 Cm f’c = 21,7 Mpa (K250) M3 0.42 0.42 11,726,386.29 4,925,082.24 0.067 - - - - - -

Pek. Balok Latai 10/15 cm Beton Mutu f'c = 21,7 Mpa (K250) 2.06 10,344,919.30 21,292,947.40 0.288 1.55 0.217 - 1.55 0.217 75.2

JUMLAH PEKERJAAN BETON BERTULANG 1,465,793,535.12 19.85 15.36 2.98 18.34

V PEKERJAAN KUSEN, PINTU , JENDELA DAN PENGGANTUNG - -

1 Pek. Kusen Aluminium M' 973.85 973.85 198,891.00 193,689,997.18 2.623 - - - - - -

2 Pek. Daun Bouvenlight Pintu Utama + Kaca 5 mm Panasap M2 0.83 0.83 1,619,167.61 1,343,909.11 0.018 - - - - - -

3 Pek. Daun Pintu Aluminium + Kaca 8 mm Panasap M2 81.18 81.18 1,205,262.60 97,843,218.07 1.325 - - - - - -

4 Pek. Daun Jendela Aluminium + Kaca 5 mm Panasap M2 64.88 71.45 1,072,715.60 76,647,031.61 1.038 - - - - - -

5 Pek. Daun Bouvenlight Aluminium + Kaca 5 mm Panasap M2 14.60 32.09 1,072,715.60 34,428,592.72 0.466 - - - - - -

6 Pas. Pintu Aluminium KM/WC Unit 3.00 3.00 1,553,554.58 4,660,663.73 0.063 - - - - - -

7 Pas. Pintu Aluminium KM/WC Untuk Difabel Unit 1.00 1.00 1,553,554.58 1,553,554.58 0.021 - - - - - -

8 Pek. Kaca Mati Panasap 5 mm M2 108.81 89.92 342,067.61 30,758,103.72 0.416 - - - - - -

9 Pas. Kunci Pintu + Jendela + BouvenlightAluminium Bh 168.00 62.00 274,129.52 16,996,030.52 0.230 - - - - - -

10 Pas. Pull Handel Pintu PSG 47.00 47.00 250,974.52 11,795,802.65 0.160 - - - - - -

11 Pas. Hengsel Jendela + Bouvenlight Bh 194.00 194.00 37,437.02 7,262,782.75 0.098 - - - - - -

12 Pas. Engsel Sliding Jendela + Bouvenlight Bh 84.00 54.00 392,927.37 21,218,078.11 0.287 - - - - - -

13 Pas. Engsel Pintu Bh 141.00 141.00 58,084.02 8,189,847.45 0.111 - - - - - -

14 Pas. Door Closer Bh 47.00 47.00 261,479.52 12,289,537.65 0.166 - - - - - -

15 Pas. Hak Angin Pintu + Jendela + Bouvenlight Bh 105.00 0.00 46,072.02 - - -

16 Pas. Grendel Pintu + Jendela + Bouvenlight Bh 8.00 115.00 58,364.52 6,711,920.32 0.091 - - - - - -

JUMLAH PEKERJAAN KUSEN, PINTU , JENDELA DAN PENGGANTUNG 525,389,070.18 7.11 - - -

VI PEKERJAAN ATAP DAN PLAFOND - -


1 Pek. Kuda-kuda + Reng Baja Ringan M2 630.92 630.92 446,045.35 281,418,933.54 3.810 - - 214.56 1.296 214.56 1.296 34.0

2 Pek. Atap Bitumen gelombang Monolayer 3 mm Onduline M2 630.92 630.92 215,617.76 136,037,555.29 1.842 - - - - - -

3 Pek. Bubungan Atap + Jurai Ounduline M 107.36 107.36 375,402.58 40,303,220.56 0.546 - - - - - -

4 Pek. Plafond Gypsum Rangka Hollow 40.40 mm Modul 60 x 60 M2 567.41 567.41 771,053.57 437,503,508.14 5.924 - - - - - -

JUMLAH PEKERJAAN ATAP DAN PLAFOND 895,263,217.52 12.12 - 1.30 1.30

VII PEKERJAAN LANTAI - -

1 Pek. Pas. Granit Tile 60 x 60 Anti Slip Teras, Selasar dan Tangga M2 101.65 101.65 373,884.49 38,005,358.03 0.515 - - - - - -

2 Pek. Pas. Granit Tile 60 x 60 Polos M2 427.27 419.96 373,884.49 157,015,631.52 2.126 - - - - - -

3 Pek. Pas. Keramik 20 x 40 Meja Beton dan Bak M2 11.09 11.09 280,496.11 3,110,701.82 0.042 - - - - - -

4 Pek. Pas. Keramik 20 x 40 Dinding M2 74.30 74.30 280,496.11 20,840,860.68 0.282 - - - - - -

5 Pek. Pas. Keramik 10 x 60 Plint M2 47.99 50.39 162,172.77 8,171,237.35 0.111 - - - - - -

6 Pek. Pas. Keramik 20 x 20 KM/WC M2 65.20 16.54 437,223.63 7,233,427.70 0.098 - - - - - -

JUMLAH PEKERJAAN LANTAI 234,377,217.10 3.17 - - -

VIII PEKERJAAN 2 UNIT SEPTICTANK DAN SANITAIR - -

1 Pek. Galian Tanah Septictank & Bak Kontrol M3 31.5 31.50 82,775.00 2,607,412.50 0.035 - - - - - -

2 Pas. Bata Ringan Septictank dan Bak Kontrol dengan Mortar Siap Pakai M2 58.5 58.50 325,280.13 19,028,887.46 0.258 - - - - - -

3 Pek. Plester Dinding dengan Semen Instan (MU 301) M2 44.00 44.00 136,244.88 5,994,774.77 0.081 - - - - - -

4 Pek. Acian Dinding dengan Semen Instan (MU 270) M2 44.00 44.00 67,601.15 2,974,450.67 0.040 - - - - - -

5 Pek. Kolom Praktis 11/15 Beton Mutu f’c = 21,7 Mpa (K250) M3 0.45 0.45 16,053,275.53 7,223,973.99 0.098 - - - - - -

6 Pek. Rabat Lantai Beton f’c = 14,5 Mpa (K175) M3 0.8 0.80 3,127,991.67 2,502,393.33 0.034 - - - - - -

7 Pek. Sloof 15/20 Beton Mutu f’c = 21,7 Mpa (K250) M3 0.78 0.78 10,852,291.57 8,464,787.42 0.115 - - - - - -

8 Pek. Ring Balk 10/20 Beton Mutu f’c = 21,7 Mpa (K250) M3 0.52 0.52 10,408,696.79 5,412,522.33 0.073 - - - - - -

9 Pek. Plat Beton f’c = 21,7 Mpa (K250) M3 1.68 1.68 11,726,386.29 19,700,328.96 0.267 - - - - - -

10 Pas. Pipa PVC Ø 4" Class AW Setara (Limbah Padat) M1 39.00 27.00 81,316.49 2,195,545.16 0.030 - - - - - -

11 Pas. Pipa PVC Ø 3" Class AW Setara (Limbah Talang) M1 146.40 70.50 63,158.24 4,452,655.73 0.060 - - - - - -

12 Pas. Pipa PVC Ø 2" Class AW Setara (Limbah Cair) M1 676.94 113.00 40,249.36 4,548,177.95 0.062 - - - - - -

13 Pas. Pipa PVC Ø 2" Class AW Setara (Air Bersih) M1 90.32 0.00 40,249.36 - - -

14 Pas. Pipa PVC Ø 3/4" Class AW Setara (Air Bersih) M1 69.08 40.00 22,412.82 896,512.87 0.012 - - - - - -
15 Pas. Closet Duduk Komplit Tabung Air Standar SNI Bh 4.00 4.00 3,190,179.52 12,760,718.10 0.173 - - - - - -

16 Pek. Pasang Kran Air 1/2" Bh 4.00 4.00 162,644.07 650,576.26 0.009 - - - - - -

17 Pek. Socket Kran Air 1/2" Bh 8.00 8.00 85,644.07 685,152.53 0.009 - - - - - -

18 Pek. Fausit Shocket Air 1/2" Bh 4.00 4.00 17,837.31 71,349.24 0.001 - - - - - -

19 Pas. Floor Drain 2" Aluminium Bh 5.00 5.00 92,441.04 462,205.20 0.006 - - - - - -

20 Pas, Roof Drain Ø 3 " besi tuang Bh 24.00 11.00 97,941.04 1,077,351.44 0.015 - - - - - -

21 Pas. Washtafel Komplit Kran Standar SNI Bh 5.00 5.00 1,054,667.53 5,273,337.67 0.071 - - - - - -

22 Pas. Bak Cuci Aluminium Set Bh 5.00 5.00 621,070.71 3,105,353.57 0.042 - - - - - -

23 Pas. Grease Trap Unit 1.00 1.00 502,837.31 502,837.31 0.007 - - - - - -

24 Pas. Spoel Hoek Janitor Bh 1.00 1.00 9,032,229.44 9,032,229.44 0.122 - - - - - -

25 Pek. Hand Relling Stainles Toilet Pjg 60cm Bh 4.00 4.00 246,386.04 985,544.16 0.013 - - - - - -

JUMLAH PEKERJAAN 2 UNIT SEPTICTANK DAN SANITAIR 120,609,078.07 1.63 - - -

IX INSTALASI LISTRIK -

1 Pas. Titik Lampu Titik 92.00 92.00 1,095,105.53 100,749,709.17 1.364 - - - - - -

2 Pas. MCB Bh 2.00 2.00 926,739.93 1,853,479.86 0.025 - - - - - -

3 Pas. Arde Panel Unit 1.00 1.00 378,337.31 378,337.31 0.005 - - - - - -

4 Pas. Sakelar Ganda Bh 25.00 25.00 281,792.08 7,044,802.01 0.095 - - - - - -

5 Pas. Sakelar Tunggal Bh 19.00 19.00 287,292.08 5,458,549.53 0.074 - - - - - -

6 Pas. Stop Kontak Bh 50.00 50.00 281,792.08 14,089,604.02 0.191 - - - - - -

7 Pas. Fitting Emergency + NICAD baterai Bh 4.00 4.00 112,837.31 451,349.24 0.006 - - - - - -

8 Pas. Fire Extinguisher Powder Kapasitas 3 Kg Bh 1.00 1.00 1,232,229.44 1,232,229.44 0.017 - - - - - -

9 Pas. Lampu LED 24 Watt Bh 6.00 6.00 102,837.31 617,023.86 0.008 - - - - - -

10 Pas. Lampu LED 14 Watt Bh 70.00 70.00 87,837.31 6,148,611.65 0.083 - - - - - -

11 Pas. Lampu LED 10 Watt Bh 23.00 23.00 67,837.31 1,560,258.11 0.021 - - - - - -

JUMLAH PEKERJAAN INSTALASI LISTRIK 139,583,954.20 1.89 - - -

X PEKERJAAN PENANGKAL PETIR

1 Pek. Splitter Lighting Protection Unit 2.00 2.00 2,000,000.00 4,000,000.00 0.054 - - - - - -

2 Pek. Kabel BC 1 X 50 mm2 M1 52.00 52.00 100,000.00 5,200,000.00 0.070 - - - - - -


3 Pek. Instalasi Lengkap dengan Material Bantu Unit 1.00 1.00 3,000,000.00 3,000,000.00 0.041 - - - - - -

4 Grounding System + Bak Kontrol Unit 1.00 1.00 4,000,000.00 4,000,000.00 0.054 - - - - - -

JUMLAH PEKERJAAN PENANGKAL PETIR 16,200,000.00 0.22 - - -

XI PEKERJAAN JALAN MASUK

1 Pek. Galian Perataan Tanah (Stripping) dan Pembersihan Jalan Masuk M3 112.00 83.25 82,775.00 6,891,018.75 0.093 61.10 0.068 2.24 0.003 63.34 0.071 76.1

2 Pek. Pasangan Batu Kastin Mortar Tipe N (5,2 Mpa) M3 21.60 76.27 3,096,872.03 236,209,229.94 3.198 21.29 0.893 14.08 0.590 35.37 1.483 46.4

3 Pek. Urugan Pasir Dibawah Paving Block M3 19.20 11.25 1,785,818.40 20,090,457.01 0.272 - - - - - -

4 Pek. Pasangan Pavingblock Hexagon (Blok Beton) Natural tebal 8cm M2 192.00 225.00 430,547.29 96,873,140.11 1.312 - - - - - -

5 Pek. Plester Kastin 1 Pc : 4 PP Tebal 15 Cm M2 124.80 124.80 109,926.54 13,718,832.13 0.186 - - - - - -

6 Pek. Acian Kastin M2 124.80 124.80 47,279.26 5,900,451.15 0.080 - - - - - -

7 Pek. Beton 25/25 cm Beton Mutu f’c = 21,7 Mpa (K250) ( Umpak ) M3 3.30 3.30 13,570,974.57 44,784,216.08 0.606 - - - - - -

8 Pek. Kolom Kayu 8/12 m3 1.69 1.69 10,616,291.21 17,941,532.14 0.243 - - - - - -

9 Pek. Rangka Atap Kayu 6/10 m3 2.28 2.28 10,616,291.21 24,205,143.96 0.328 - - - - - -

10 Pek. Gording Kayu 6 / 10 m3 4.03 4.03 9,682,309.94 39,019,709.06 0.528 - - - - - -

11 Pek. Bubungan Atap Ounduline m1 96.00 96.00 375,402.58 36,038,647.29 0.488 - - - - - -

12 Pek. Atap Ounduline m2 345.60 327.41 215,617.76 70,595,523.33 0.956 - - - - - -

Pekerjaan Galian Untuk Pas. Batu Kastin m3 0.00 30.09 82,775.00 2,490,534.20 0.034 10.11 0.011 10.11 0.011 20.22 0.023 67.2

Pekerjaan Galian Tanah Saluran m3 0.00 2.02 82,775.00 167,205.50 0.002 1.50 0.002 - 1.50 0.002 74.3

Pek. Pasangan Batu Saluran Mortar Tipe N (5,2 Mpa) m3 0.00 2.72 3,096,872.03 8,414,201.31 0.114 - - - - - -

Pek. Plester Saluran 1 Pc : 4 PP Tebal 15 Cm M2 0.00 39.13 109,926.54 4,301,425.49 0.058 - - - - - -

Pek. Acian Saluran M2 0.00 39.13 47,279.26 1,850,037.29 0.025 - - - - - -

Pekerjaan Galian Tanah Pondasi Tangga m3 0.00 7.24 82,775.00 598,959.90 0.008 - - - - - -

Pek. Pasangan Batu Saluran Mortar Tipe N (5,2 Mpa) m3 0.00 12.96 3,096,872.03 40,135,461.51 0.543 - - - - - -

JUMLAH PEKERJAAN JALAN MASUK 670,225,726.14 9.08 0.97 0.60 1.58

XII PEKERJAAN PAGAR

1 Pek. Pembongkaran Pasangan Batu Pagar Eksisting Semi Mekanis M3 5.74 5.74 40,966.10 235,043.00 0.003 4.62 0.003 - 4.62 0.003 80.5

2 Pek. Pembongkaran Dinding Pagar Eksisting Semi Mekanis M3 6.38 6.38 24,439.78 155,803.57 0.002 6.38 0.002 - 6.38 0.002 100.0

3 Pek. Galian Tanah untuk Pondasi Pagar M3 355.60 123.05 82,775.00 10,185,256.81 0.138 123.05 0.138 - 123.05 0.138 100.0
4 Pek. Urugan Pasir Dibawah Pondasi Pagar M3 89.59 10.46 1,785,818.40 18,684,125.02 0.253 7.87 0.190 0.42 0.010 8.29 0.200 79.2

5 Pek. Pasangan Batu Pondasi Pagar Mortar Tipe N (5,2 Mpa) M3 51.95 76.94 3,096,872.03 238,263,656.25 3.226 58.14 2.438 4.86 0.204 63.00 2.642 81.9

6 Pek. Sloof 10/20 Beton Mutu f’c = 21,7 Mpa (K250) M3 3.16 7.16 10,852,291.57 77,745,816.79 1.053 5.03 0.739 1.23 0.181 6.26 0.920 87.4

7 Pek. Kolom Praktis 20/20 Beton Mutu f’c = 21,7 Mpa (K250) M3 5.38 6.98 11,637,950.48 81,232,894.38 1.100 5.38 0.848 0.30 0.047 5.68 0.895 81.4

8 Pek. Ring Balk 15/20 Beton Mutu f’c = 21,7 Mpa (K250) M3 3.16 7.07 8,459,913.13 59,845,425.45 0.810 4.95 0.567 - 4.95 0.567 70.0

9 Pek. Pasangan Bata Ringan (10 x 20 x 60 cm) Pagar dengan Mortar Siap Pakai M2 16.86 259.38 325,280.13 84,371,159.46 1.142 177.17 0.780 27.72 0.122 204.89 0.902 79.0

10 Pek. Plester Dinding dengan Semen Instan (MU 301) Tebal 8 mm M2 168.64 759.00 136,244.88 103,409,864.75 1.400 - - - - - -

11 Pek. Acian Dinding dengan Semen Instan (MU 270) Tebal 2 mm M2 168.64 759.00 67,601.15 51,309,274.14 0.695 - - - - - -

JUMLAH PEKERJAAN PAGAR 725,438,319.63 9.82 5.71 0.56 6.27

XIII PEKERJAAN PELATARAN

1 Pek. Galian Perataan Tanah (Stripping) dan Pembersihan Pelataran M3 10.00 10.00 82,775.00 827,750.00 0.011 10.00 0.011 - 10.00 0.011 100.0

2 Pek. Pasangan Batu Kastin PelataranMortar Tipe N (5,2 Mpa) M3 3.38 0.00 3,096,872.03 - - -

3 Pek. Urugan Pasir Dibawah Paving Block Pelataran M3 5.00 5.00 1,785,818.40 8,929,092.00 0.121 5.00 0.121 - 5.00 0.121 100.0

4 Pek. Pasangan Pavingblock Hexagon (Blok Beton) Natural tebal 8cm Pelataran M2 50.00 50.00 430,547.29 21,527,364.47 0.291 - - - - - -

5 Pek. Plester Kastin 1 Pc : 4 PP Tebal 15 Cm Pelataran M2 19.50 0.00 109,926.54 - - -

6 Pek. Acian Kastin Pelatarn M2 19.50 0.00 47,279.26 - - -

7 PeK. Tiang Bendera + Aksesoris Ls 1.00 1.00 500,000.00 500,000.00 0.007 - - - - - -

JUMLAH PEKERJAAN PELATARAN 31,784,206.47 0.43 0.13 - 0.13

XIV PEKERJAAN FINISHING

1 Pek. Cat Tembok Premium (Interior Spotless ) M2 1,667.51 1,667.51 38,514.63 64,223,529.97 0.870 - - - - - -

2 Pek. Cat Tembok Premium ( Eksterior Weather Shield) M2 216.64 216.64 38,514.63 8,343,809.35 0.113 - - - - - -

3 Pek. Cat Plafond Kualitas Baik M2 567.41 567.41 57,730.64 32,756,940.87 0.444 - - - - - -

4 Pek. Waterproofing Talang Beton (Aqua Proof) M2 174.56 174.56 17,805.48 3,108,125.41 0.042 - - - - - -

5 Pek. Cat Tembok Pagar Kualitas Baik m2 802.11 802.11 38,514.63 30,892,969.53 0.418 - - - - - -

JUMLAH PEKERJAAN FINISHING 139,325,375.13 1.89 - - -

XV PEKERJAAN LAIN-LAIN

1 Pas. Papan Nama Acrylic Unit 30.00 30.00 981,718.17 29,451,545.24 0.399 - - - - - -

2 Pembuatan Lambang Puskesmas bahan Acrylic Ls 2.00 2.00 5,000,000.00 10,000,000.00 0.135 - - - - - -
3 Pek. Pasangan ACP Tebal 4 mm Setara Untuk Motif Songke Manual M2 4.70 17.64 1,095,994.04 19,333,334.92 0.262 - - - - - -

4 Pek. Motif Songke Manual (Cat Dinding Depan) Ls 1.00 1.00 3,500,000.00 3,500,000.00 0.047 - - - - - -

5 Pas. Pintu Pagar Dorong Unit 1.00 1.00 10,000,000.00 10,000,000.00 0.135 - - - - - -

Pengadaan Air Bersih Ls 1.00 1.00 5,000,000.00 5,000,000.00 0.068 1.00 0.068 - 1.00 0.068 100.0

6 Pembersihan Akhir Ls 1.00 1.00 2,655,500.00 2,655,500.00 0.036 - - - - - -

JUMLAH PEKERJAAN LAIN-LAIN 79,940,380.16 1.08 0.07 - 0.07

JUMLAH 7,385,359,939.88 100.00 41.94 5.45 47.38

a REALISASI SAMPAI DENGAN MINGGU LALU 41.94

b REALISASI MINGGU INI 5.45

c REALISASI SAMPAI DENGAN MINGGU INI 47.38


LAPORAN UMUM
NO. DOKUMEN -
NO. REVISI - MINGGU KE -
TANGGAL Friday, November 24, 2023
HALAMAN 2
PERIHAL LAPORAN KEMAJUAN FISIK PEKERJAAN MINGGUAN 21 ( Dua Puluh Satu )
PERIODE 11/23/23 - 11/24/2023

I. DATA PROYEK

II. URAIAN REALISASI PROGRES TERHADAP KONTRAK

A. Realisasi Waktu
1 Jangka Waktu Pelaksanaan 162 Hari Kalender
2 Waktu Yang Telah Berjalan 144 Hari Kalender
3 Sisa Waktu Pelaksanaan 18 Hari Kalender

B. Realisasi Progres Saat Ini


1 Presentasi Dicapai 47.38 %
2 Presentasi Menurut Rencana 96.85 %
3 Deviasi Presentasi Komulatif - 49.47 % MINUS

C. Pekerjaan Yang Sedang Dilaksanakan Saat Ini


1 Pek. Pasangan Batu Pondasi Pagar Mortar Tipe N (5,2 Mpa)
2 Pek. Balok 25/35 Cm Beton Mutu f’c = 21,7 Mpa (K250)
3 Pek. Pasangan Bata Ringan (10 x 20 x 60 cm) Pagar dengan Mortar Siap Pakai
4 Pek. Sloof 10/20 Beton Mutu f’c = 21,7 Mpa (K250)
5 Pek. Kolom Praktis 20/20 Beton Mutu f’c = 21,7 Mpa (K250)
6 Pek. Galian Perataan Tanah (Stripping) dan Pembersihan Jalan Masuk
7 Pek. Pasangan Batu Kastin Mortar Tipe N (5,2 Mpa)
8 Pekerjaan Galian Untuk Pas. Batu Kastin
9 Pekerjaan Galian Tanah Saluran

D. Rencana Kerja dan Penanganan Terhadap Masalah yang ada


Permasalahan
1 Kurangnya Fasilitas Kerja
2 Kurangnya Jumlah Tenaga Kerja Yang Profesional
3 Pengaturan Tenaga Kerja Kurang Tepat
4 Metode Kerja Kurang Tepat
5 Penerangan (Pencahayaan) waktu lembur Kurang Baik

Rencana Penanganan Terhadap Masalah (akibat deviasi progres)


1 Kontraktor Harus Menyiapkan Fasiltas kerja sesuai kebutuhan
2 Kontraktor Harus Menambah Tenaga kerja yang profesional
3 Kontraktor Mengatur Tenaga Kerja dengan Baik
4 Kontraktor Memperbaiki Metode Kerja
5 Kontraktor Menambah Jumlah Alat Pencahayaan

Saran Disampaikan dengan hormat


Kepada Kontraktor Pelaksanaan
1 Siapkan Fasiltas kerja sesuai kebutuhan
2 Menambah Tenaga kerja yang profesional
3 Mengatur Tenaga Kerja dengan Baik
4 Segera Memperbaiki Metode Kerja

Kepada Pejabat Pengambil Keputusan


1 mengevaluasi kembali terhada hasil kinerja dari kontraktor