PROGRESS MINGGU KE - 14

(5 OKTOBER 2022 - 11 OKTOBER 2022)

INSTANSI : PT MAHAKARYA GUCI PROPERTINDO Tanggal : 12 OKTOBER 2022


PEKERJAAN : RESTO SKY VIEW
LOKASI PEKERJAAN : KAWASAN WISATA AIR PANAS GUCI - TEGAL
KONSULTAN MK : WIJAYA CIPTA GRAHA
PENYEDIA JASA : ADE&PARTNERS

SATUAN HARGA SATUAN HARGA SATUAN HARGA JUMLAH SATUAN JUMLAH HARGA
JASA 4% SD MINGGU LALU MINGGU INI SD MINGGU INI
NO URAIAN PEKERJAAN VOLUME SATUAN BAHAN UPAH ALAT HARGA DIKERJAKAN
(Rp) (Rp) (Rp) (Rp) (Rp) VOL % VOL % VOL % (Rp)

A PEKERJAAN PERSIAPAN 32.411.204,65 -


1 pembersihan lokasi 857,00 m2 - 12.654,95 506,20 11.279.103,84 857,00 100,00% 0,00 0,00% 857,00 100,00% -
2 Pengukuran dan pemasangan bouwplank 136,00 m1 39.002,41 15.000,00 2.160,10 7.638.100,82 81,60 60,00% 0,00 0,00% 81,60 60,00% -
3 Listrik dan Air Kerja 6,00 bln 2.162.500,00 - 86.500,00 13.494.000,00 4,25 70,83% 0,00 0,00% 4,25 70,83% -

B PEKERJAAN STRUKTUR 329.012.287,53 77.957.465,34


1 FOOTPLAT TIPE F1 -
Galian tanah 22,50 m³ - 57.000,00 2.280,00 1.333.800,00 22,50 100,00% 0,00 0,00% 22,50 100,00% -
Bekisting 9,00 m² 42.300,00 45.000,00 423,00 3.508,92 821.087,28 9,00 100,00% 0,00 0,00% 9,00 100,00% -
Beton f'c 25MPa 3,38 m³ 715.000,00 180.000,00 7.150,00 36.086,00 3.171.237,68 3,38 100,00% 0,00 0,00% 3,38 100,00% -
Pembesian 364,54 kg 13.432,50 2.500,00 134,33 642,67 6.091.280,40 364,54 100,00% 0,00 0,00% 364,54 100,00% -
2 PILECAP TIPE F2 -
Galian tanah 91,26 m² - 57.000,00 - 2.280,00 5.409.892,80 91,26 100,00% 0,00 0,00% 91,26 100,00% -
Bekisting 42,12 m² 42.300,00 45.000,00 423,00 3.508,92 3.842.688,47 42,12 100,00% 0,00 0,00% 42,12 100,00% -
Beton f'c 25MPa 13,69 m³ 715.000,00 180.000,00 7.150,00 36.086,00 12.844.450,84 13,69 100,00% 0,00 0,00% 13,69 100,00% -
Pembesian 1538,16 kg 13.432,50 2.500,00 134,33 642,67 25.701.881,44 1538,16 100,00% 0,00 0,00% 1538,16 100,00% -
3 KOLOM K1 -
Bekisting 152,40 m² 90.165,00 45.000,00 901,65 5.442,67 21.566.019,76 152,40 100,00% 0,00 0,00% 152,40 100,00% -
Beton f'c 25MPa 11,43 m³ 715.000,00 180.000,00 7.150,00 36.086,00 10.724.037,48 11,43 100,00% 0,00 0,00% 11,43 100,00% -
Pembesian 2266,22 kg 13.432,50 2.500,00 134,33 642,67 37.867.398,56 2266,22 100,00% 0,00 0,00% 2266,22 100,00% -
4 SLOOF S1 -
Bekisting 76,00 m² 47.175,00 45.000,00 471,75 3.705,87 7.322.799,12 76,00 100,00% 0,00 0,00% 76,00 100,00% -
Beton f'c 25MPa 5,70 m³ 715.000,00 180.000,00 7.150,00 36.086,00 5.347.945,20 5,70 100,00% 0,00 0,00% 5,70 100,00% -
Pembesian 1010,23 kg 13.432,50 2.500,00 134,33 642,67 16.880.436,16 1010,23 100,00% 0,00 0,00% 1010,23 100,00% -
5 SLOOF S2 -
Bekisting 84,75 m² 47.175,00 45.000,00 471,75 3.705,87 8.165.884,55 84,75 100,00% 0,00 0,00% 84,75 100,00% -
Beton f'c 25MPa 5,09 m³ 715.000,00 180.000,00 7.150,00 36.086,00 4.775.621,24 5,09 100,00% 0,00 0,00% 5,09 100,00% -
Pembesian 930,89 kg 13.432,50 2.500,00 134,33 642,67 15.554.704,59 930,89 100,00% 0,00 0,00% 930,89 100,00% -
6 SLOOF S3 -
Bekisting 30,25 m² 47.175,00 45.000,00 471,75 3.705,87 2.914.666,76 30,25 100,00% 0,00 0,00% 30,25 100,00% -
Beton f'c 25MPa 1,65 m³ 715.000,00 180.000,00 7.150,00 36.086,00 1.548.089,40 1,65 100,00% 0,00 0,00% 1,65 100,00% -
Pembesian 192,72 kg 13.432,50 2.500,00 134,33 642,67 3.220.254,45 192,72 100,00% 0,00 0,00% 192,72 100,00% -
7 BALOK B1 6.581.338,62
Bekisting 50,00 m² 93.135,00 45.000,00 931,35 5.562,65 7.231.450,20 40,00 80,00% 5,00 10,00% 45,00 90,00% 723.145,02
Beton f'c 25MPa 4,00 m³ 715.000,00 150.000,00 7.150,00 34.886,00 3.628.144,00 0,00 0,00% 4,00 100,00% 4,00 100,00% 3.628.144,00
Pembesian 667,30 kg 13.432,50 2.500,00 134,33 642,67 11.150.248,02 533,84 80,00% 133,46 20,00% 667,30 100,00% 2.230.049,60
8 BALOK B2 8.107.603,01
Bekisting 81,00 m² 93.135,00 45.000,00 931,35 5.562,65 11.714.949,32 64,80 80,00% 8,10 10,00% 72,90 90,00% 1.171.494,93
Beton f'c 25MPa 4,86 m³ 715.000,00 150.000,00 7.150,00 34.886,00 4.408.194,96 0,00 0,00% 4,86 100,00% 4,86 100,00% 4.408.194,96
Pembesian 756,43 kg 13.432,50 2.500,00 134,33 642,67 12.639.565,57 605,14 80,00% 151,29 20,00% 756,43 100,00% 2.527.913,11
9 PLAT A1 t=13cm 63.268.523,71
Bekisting 190,66 m² 126.165,00 45.000,00 1.261,65 6.897,07 34.189.859,69 76,26 40,00% 95,33 50,00% 171,59 90,00% 17.094.929,85
Beton f'c 25MPa 23,40 m³ 715.000,00 150.000,00 7.150,00 34.886,00 21.224.642,40 0,00 0,00% 23,40 100,00% 23,40 100,00% 21.224.642,40
Pembesian 1659,00 kg 13.432,50 2.500,00 134,33 642,67 27.721.057,18 165,90 10,00% 1493,10 90,00% 1659,00 100,00% 24.948.951,46

C PEKERJAAN BAJA 265.016.539,41 -


1 KOLOM K2 (iwf 200.250.6.9) 2386,80 kg 18.761,25 10.000,00 187,61 1.157,95 71.858.950,82 2336,93 97,91% 0,00 0,00% 2336,93 97,91% -
2 KOLOM K3 pipa baja diameter20cm 212,50 kg 18.761,25 10.000,00 187,61 1.157,95 6.397.698,61 208,06 97,91% 0,00 0,00% 208,06 97,91% -
3 RAFTER iwf 200.150.6.9 2937,60 kg 19.518,13 10.000,00 195,18 1.188,53 90.777.240,78 2876,22 97,91% 0,00 0,00% 2876,22 97,91% -
4 BALOK iwf 200.100.5,5.8 1661,40 kg 18.761,25 10.000,00 187,61 1.157,95 50.019.465,76 1626,69 97,91% 0,00 0,00% 1626,69 97,91% -
5 GORDING CNP 100.50.20.2,3 1169,28 kg 18.761,25 10.000,00 187,61 1.157,95 35.203.298,98 0,00 0,00% 0,00 0,00% 0,00 0,00% -
SATUAN HARGA SATUAN HARGA SATUAN HARGA JUMLAH SATUAN JUMLAH HARGA
JASA 4% SD MINGGU LALU MINGGU INI SD MINGGU INI
NO URAIAN PEKERJAAN VOLUME SATUAN BAHAN UPAH ALAT HARGA DIKERJAKAN
(Rp) (Rp) (Rp) (Rp) (Rp) VOL % VOL % VOL % (Rp)
6 WIN BRACING Ø16MM 205,40 kg 18.761,25 10.000,00 187,61 1.157,95 6.183.940,21 0,00 0,00% 0,00 0,00% 0,00 0,00% -
7 Sagrod Ø10mm 148,08 kg 19.518,13 10.000,00 195,18 1.188,53 4.575.944,25 0,00 0,00% 0,00 0,00% 0,00 0,00% -