Proyek / PPK : DINAS PEKERJAAN UMUM DAN PENATAAN RUANG PROVINSI GORONTALO
No. Paket Kontrak :
Nama Paket : PRESERVASI JALAN RUAS MULYONEGORO - KARYA MUKTI
Prop / Kab / Kodya : PROV GORONTALO / KAB. GORONTALO
1 Umum 218,728,042.00 1.34 0.00 0.00 0.00 0.00 0.00 0.00 218,728,042 0.83
2 Drainase 4,047,620,564.94 24.80 2,450,966,912.11 27.62 0.00 0.00 0.00 0.00 6,498,587,477 24.77
3 Pekerjaan Tanah Dan Geosintetik 1,341,005,383.43 8.22 984,054,994.25 11.09 0.00 0.00 0.00 0.00 2,325,060,378 8.86
4 Pekerjaan Preventif 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0 0.00
5 Pekerasan Berbutir Dan Perkerasan Beton Semen 2,830,639,343.52 17.34 0.00 0.00 0.00 0.00 0.00 0.00 2,830,639,344 10.79
6 Perkerasan Aspal 6,396,092,627.26 39.19 4,425,901,266.45 49.88 0.00 0.00 0.00 0.00 10,821,993,894 41.25
7 Struktur 1,432,501,501.39 8.78 973,139,706.52 10.97 0.00 0.00 0.00 0.00 2,405,641,208 9.17
8 Rehabilitasi Jembatan 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0 0.00
9 Pekerjaan Harian Dan Pekerjaan Lain-Lain 53,613,236.56 0.33 39,449,240.49 0.44 0.00 0.00 0.00 0.00 93,062,477 0.35
10 Pekerjaan Pemeliharaan Kinerja 0.00 0.00 0.00 0.00 659,638,734.23 100.00 381,232,230.63 100.00 1,040,870,965 3.97
(A) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 16,320,200,699.10 100.00 8,873,512,119.82 100.00 659,638,734.23 100.00 381,232,230.63 100.00 26,234,583,784 100.00
(B) Pajak Pertambahan Nilai ( PPN ) = 11% x (A) 1,795,222,076.90 976,086,333.18 72,560,260.77 41,935,545.37 2,885,804,216
(C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B) 18,115,422,776.00 9,849,598,453.00 732,198,995.00 423,167,776.00 29,120,388,000
(D) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B) dibulatkan 18,115,422,776.00 9,849,598,453.00 732,198,995.00 423,167,776.00 29,120,388,000
Terbilang :
DUA PULUH SEMBILAN MILYAR SERATUS DUA PULUH JUTA TIGA RATUS DELAPAN PULUH DELAPAN RIBU RUPIAH