PAKET PEKERJAAN : PEMELIHARAAN RUTIN JALAN LONG BOH - METULANG - LONG NAWANG MINGGU KE : 15 ( LIMA BELAS )
SUMBER DANA : APBN PROGRESS RENCANA (%) : 27.671
RUAS JALAN : LONG BOH - METULANG - LONG NAWANG - LONG PUJUNGAN PROGRESS REALISASI (%) : 28.726
TAHUN ANGGARAN : 2019 DEVIASI (%) : 1.056
TANGGAL : 06 MEI S/D 12 MEI
DIVISI 1. UMUM
1.2 Mobilisasi Ls 267,000,000.00 1.00 1.00 267,000,000.00 4.647 0.601 2.793 - - 0.601 2.793 1.854
1.19 Keselamatan dan Kesehatan Kerja Ls 63,200,000.00 1.00 1.00 63,200,000.00 1.100 0.292 0.321 0.021 0.023 0.313 0.344 0.756