KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYAT

DIREKTORAT JENDERAL BINA MARGA


BALAI PELAKSANAAN JALAN NASIONAL XII
SATUAN KERJA PELAKSANAAN JALAN NASIONAL PERBATASAN KALIMANTAN UTARA

TABEL REALISASI PEKERJAAN


PERIODE BULAN MARET 2019

PAKET PEKERJAAN : PEMELIHARAAN RUTIN JALAN LONG BOH - METULANG - LONG NAWANG MINGGU KE : 15 ( LIMA BELAS )
SUMBER DANA : APBN PROGRESS RENCANA (%) : 27.671
RUAS JALAN : LONG BOH - METULANG - LONG NAWANG - LONG PUJUNGAN PROGRESS REALISASI (%) : 28.726
TAHUN ANGGARAN : 2019 DEVIASI (%) : 1.056
TANGGAL : 06 MEI S/D 12 MEI

NO. HARGA VOLUME PROGRESS FISIK SISA


MATA URAIAN SAT. SATUAN KONTRAK JUMLAH HARGA BOBOT S/D MINGGU BOBOT MINGGU BOBOT S/D MINGGU BOBOT BOBOT
ADD - 01
PEMB. ( Rp. ) AWAL (%) LALU (%) INI (%) INI (%) (%)

DIVISI 1. UMUM
1.2 Mobilisasi Ls 267,000,000.00 1.00 1.00 267,000,000.00 4.647 0.601 2.793 - - 0.601 2.793 1.854
1.19 Keselamatan dan Kesehatan Kerja Ls 63,200,000.00 1.00 1.00 63,200,000.00 1.100 0.292 0.321 0.021 0.023 0.313 0.344 0.756

JUMLAH DIVISI 330,200,000.00 5.747 3.114 0.023 3.137 2.610


DIVISI 2. DRAINASE
2.1.(1) Galian Untuk Saluran Air M3 85,826.00 8,600.00 8,600.00 738,103,600.00 12.847 - - - - - - 12.847

JUMLAH DIVISI 738,103,600.00 12.847 - - - 12.847


DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK
3.1.(1a) Galian Biasa M3 82,914.70 21,830.66 21,830.66 1,810,082,309.15 31.504 7,810.288 11.271 2,075.213 2.995 9,885.500 14.266 17.238
3.2.(1a) Timbunan Biasa Dari Sumber Galian M3 54,664.50 10,325.00 10,325.00 564,410,962.50 9.823 3,394.238 3.229 948.188 0.902 4,342.425 4.131 5.692
3.2.(2a) Timbunan Pilihan Dari Sumber Galian M3 56,210.00 10,325.00 10,325.00 580,368,250.00 10.101 3,377.650 3.304 1,021.150 0.999 4,398.800 4.303 5.798
3.3.(1) Penyiapan Badan Jalan M3 1,599.40 840,000.00 840,000.00 1,343,496,000.00 23.383 103,760.000 2.888 - 103,760.000 2.888 20.495

JUMLAH DIVISI 4,298,357,521.65 74.812 20.693 4.896 25.589 49.223


DIVISI 9. PEKERJAAN HARIAN
9.1 (4) a Dump Truck Kapasitas 3-4 m3 Jam 341,125.00 175.00 175.00 59,696,875.00 1.039 - - - - - - 1.039
9.1 (8) Motor Grader min 100 PK Jam 647,233.00 175.00 175.00 113,265,775.00 1.971 - - - - - - 1.971
9.1 (11) Alat Penggali ( Excavator ) 80 - 140 PK Jam 640,588.00 175.00 175.00 112,102,900.00 1.951 - - - - - - 1.951
9.1 (14) Penggilas Bervibrasi 5-8 Ton Jam 536,137.00 175.00 175.00 93,823,975.00 1.633 - - - - - - 1.633

JUMLAH DIVISI 378,889,525.00 6.594 - - - 6.594


JUMLAH TOTAL 5,745,550,646.65 100.000 23.808 4.919 28.726 71.274

Diketahui Oleh, Diperiksa Oleh, Dibuat Oleh,


Koordinator Lapangan TIM PENGAWAS Kontraktor Pelaksana
PPK Perbatasan 1 Kalimantan Utara PELAKSANAAN JALAN PERBATASAN KALTARA CV. RANTAU BERSAUDARA

SAMSUL ALAM ARIA MAPAS NEGARA, ST., M.Si FARID ALIUSMAN


NIP. 19701012 201410 1 001 NIP. 19820709 201001 1 019 Kepala Pelaksana