Nama Paket : Peningkatan Struktur Jalan Ligan - Kuala Ligan (Seksi II)
No / Tgl Kontrak : HK.02.03/Bp1.PJN.II/13/INPRES/APBN/2023 / 31 Agustus 2023
Nilai Kontrak : Rp. 16,075,497,000.00
Penyedia Jasa : PT. ACEH LINTAS SUMATERA SERTIFIKAT NO. : 01
Konsultan Supervisi : PT. LARAS SEMBADA KSO CV. MULTI PARTNER CONSULTANT TGL/BLN/THN : 25 SEPTEMBER 2023
DIVISI SKH SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI (SMKK) 0.93 150,000,000.00 - - 0.46 73,255,000.00
DIVISI 2. DRAINASE - - - - - -
DIVISI 5. PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN 30.38 4,883,280,000.00 - - 8.64 1,389,600,000.00
TERBILANG : SATU MILYAR TUJUH RATUS TIGA PULUH DELAPAN JUTA ENAM RATUS DUA PULUH RIBU TUJUH RATUS LIMA PULUH SEN
MENGETAHUI / MENYETUJUI :
PEJABAT PEMBUAT KOMITMEN (PPK) 2.1
PROVINSI ACEH
MATA PERKIRAAN HARGA SATUAN + S/D BULAN LALU BULAN INI S/D BULAN INI
JUMLAH HARGA (Rp) BOBOT (%)
PEMBA- URAIAN SATUAN KUANTITAS PPN 11% (Rp) BIAYA Bobot BIAYA Bobot BIAYA Bobot
KUANTITAS KUANTITAS KUANTITAS
YARAN AWAL AWAL AWAL AWAL (Rp) % (Rp) % (Rp) %
1 2 3 4 5 6 7 8 10 9 10 13 11 12 15 13
DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 150,000,000.00 150,000,000.00 0.93 - - - 0.50 75,000,000.00 0.47 0.50 75,000,000.00 0.47
JUMLAH 150,000,000.00 0.93 - - 75,000,000.00 0.47 75,000,000.00 0.47
MATA PERKIRAAN HARGA SATUAN + S/D BULAN LALU BULAN INI S/D BULAN INI
JUMLAH HARGA (Rp) BOBOT (%)
PEMBA- URAIAN SATUAN KUANTITAS PPN 11% (Rp) BIAYA Bobot BIAYA Bobot BIAYA Bobot
KUANTITAS KUANTITAS KUANTITAS
YARAN AWAL AWAL AWAL AWAL (Rp) % (Rp) % (Rp) %
1 2 3 4 5 6 7 8 10 9 10 13 11 12 15 13
DIVISI 7. STRUKTUR
7.1.(7a) Beton Struktur fc’20 MPa M3 96.00 2,660,000.00 255,360,000.00 1.59 - - - 27.00 71,820,000.00 0.45 27.00 71,820,000.00 0.45
7.1.(8) Beton fc’15 Mpa M3 1,059.00 1,860,000.00 1,969,740,000.00 12.25 - - - - - - - - -
7.3.(1) Baja Tulangan Polos BjTP 280 Kg 7,178.00 20,000.00 143,560,000.00 0.89 - - - 1,068.00 21,360,000.00 0.13 1,068.00 21,360,000.00 0.13
7.6.(1) Fondasi Cerucuk Penyedian dan Pemancangan M' 5,166.00 25,000.00 129,150,000.00 0.80 - - - 4,050.00 101,250,000.00 0.63 4,050.00 101,250,000.00 0.63
7.9.(1) Pasangan Batu M3 2,789.00 1,015,000.00 2,830,835,000.00 17.61 - - - 211.75 214,926,250.00 1.34 211.75 214,926,250.00 1.34
JUMLAH 5,328,645,000.00 33.15 - - 409,356,250.00 2.55 409,356,250.00 2.55