DEVISI 7. STRUKTUR
7.1.(5a)1 Beton Struktur fc’30 Mpa M3 620,56 3.624.139,00 2.248.995.697,84 42,47 7,078 7,078 7,078 7,078 7,078 7,078
7.1 (10) Beton fc’10 MPa (untuk lantai kerja) M3 124,12 2.328.069,00 288.959.924,28 5,46 1,091 1,091 1,091 1,091 1,091
7.3 (1) Baja Tulangan Polos BJTP 280 Kg 1.334,53 24.993,00 33.353.908,29 0,63 0,157 0,157 0,157 0,157
7.3 (3) Baja Tulangan Sirip BJTS 420A Kg 55.907,10 26.724,00 1.494.061.340,40 28,21 3,527 3,527 3,527 3,527 3,527 3,527 3,527 3,527
7.6.(16).a Pemancangan Tiang Pancang Beton Bertulang Pracetak ukuran 350 mm x 350 mm M1 216,00 175.330,00 37.871.280,00 0,72 0,18 0,179 0,179 0,179
7.9.(1) Pasangan Batu M3 39,46 1.687.053,00 66.571.111,38 1,26 1,257
7.12.(3) Perletakan Elastomerik Sintetis ( Uk. 400 X 400 X 50 mm ) Buah 14,00 1.293.652,00 18.111.128,00 0,34 0,342
7.13.(1) Sandaran (Railing) M1 49,80 295.847,00 14.733.180,60 0,28 0,278
7.16.(1a) Cutting Spun Pile Buah 24,00 171.130,00 4.107.120,00 0,08 0,078
7.16.(2a) Pipa Drainase Baja diameter 75 mm M1 19,20 157.552,00 3.024.998,40 0,06 0,057
DEVISI 11. PEMBANGUNAN PAGAR KANTOR KESATUAN PELAKSANAAN PENGAMANAN PELABUHAN (KP3)
A. PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan bouwplank Ls 1,00 2.400.000,00 2.400.000,00 0,05 0,045
2 Pembersihan Akhir Ls 1,00 1.500.000,00 1.500.000,00 0,03 0,028
E. PEKERJAAN PENGECATAN
1 Ca Tembok M2 405,50 49.988,00 20.270.134,00 0,38 0,191 0,191