Anda di halaman 1dari 1

REKAFITULASI LAPORAN BULANAN KEMAJUAN FISIK PEKERJAAN

PEKERJAAN : PEMBANGUNAN GARDU PANDANG


LOKASI : AMERORO, KONAWE SULAWESI TENGGARA BULAN : KE LIMA
NOMOR KONTRAK : TP.02.01/PK.WIKA-PUTRA-AGUNG,KSO.057/IX/2022 PERIODE : Sunday, 01 January 2023 S/D Tuesday, 31 January 2023
PELAKSANA UTAMA : PT.WIKA-PUTRA-AGUNG.KSO
PELAKSANA : PT.PETIK KARYA NUSANTARA

VOLUME BOBOT LAPORAN KEMAJUAN PEKERJAAN


PEKERJAAN (%) BULAN LALU BULAN INI S/D BULAN INI
NO. URAIAN PEKERJAAN SATUAN
Vol. Fisik % Tertimb.% Vol. Fisik % Tertimb.% Vol. Fisik % Tertimb.%
1 2 3 4 5 6 7 8 9 10 11
I. PEKERJAAN STRUKTUR BAJA Kg 5,341 16.93 - - - - - 5,341 100.00 16.93
II. PEKERJAAN ATAP ACP M2 183.64 46.67 128.55 70 32.67 55.09 30.00 14.00 183.64 100.00 46.67
III. PEKERJAAN LISTPLANK KELILING M2 60.00 9.74 - - 60.00 100.00 9.74 60.00 100.00 9.74
IV. PEKERJAAN DINDING LUAR ATRIUM M2 14.37 2.33 - - 14.37 100.00 2.33 14.37 100.00 2.33
V PEKERJAAN DINDING DALAM ATRIUM M2 63.33 10.28 20.90 33 3.39 42.43 67.00 6.89 63.33 100.00 10.28
VI PEKERJAAN PLAFOND OVERSTAKE M2 54.36 8.82 - - 54.36 100.00 8.82 54.36 100.00 8.82
VII PEKERJAAN ATAP SOLARTUFF M2 32.00 3.38 19.20 60.00 2.03 12.80 40.00 1.35 32.00 100.00 3.38
VIII PEKERJAAN DINDING BATA RINGAN M2 46.28 1.85 18.05 39.00 0.72 28.23 61.00 1.13 28.23 100.00 1.85
JUMLAH 100.00 38.81 44.26 100.00

Tuesday, 31 January 2023

PT.WIKA-PUTRA-AGUNG.KSO PT.PETIK KARYA NUSANTARA PT.PETIK KARYA NUSANTARA

……………………………… DEDY KURNIAWAN MAYUDIAWAN


ENGGINER PROJECT MANAGER

You created this PDF from an application that is not licensed to print to novaPDF printer (http://www.novapdf.com)