Anda di halaman 1dari 83

1 PEMBUATAN 1 M1 PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 METER

NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA KERJA
Pekerja OH 0.2000 Rp 85,000.00 Rp 17,000.00
Tukang kayu OH 0.4000 Rp 130,000.00 Rp 52,000.00
Kepala tukang OH 0.0200 Rp 150,000.00 Rp 3,000.00
Mandor OH 0.0200 Rp 110,000.00 Rp 2,200.00
JUMLAH HARGA TENAGA Rp 74,200.00
B BAHAN
Dolken kayu 8-10 cm Btg 1.2500 Rp 8,715.00 Rp 10,893.75
Semen portland Kg 2.5000 Rp 1,500.00 Rp 3,750.00
Seng gelombang Lbr 1.2000 Rp 47,000.00 Rp 56,400.00
Pasir beton M³ 0.0050 Rp 214,286.00 Rp 1,071.43
Koral beton M³ 0.0090 Rp 120,020.00 Rp 1,080.18
Kayu balok 5/7 M³ 0.0720 Rp 1,200,000.00 Rp 86,400.00
Paku biasa 2” – 5” Kg 0.0600 Rp 19,800.00 Rp 1,188.00
Meni Ltr 0.4500 Rp 25,000.00 Rp 11,250.00
JUMLAH HARGA BAHAN Rp 161,139.61
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 235,339.61
E OVERHEAD & PROFIT ( D x % ) 10% Rp 23,533.96
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 258,873.57

2 PENGUKURAN DAN PEMASANGAN 1 M1 BOUWPLANK


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.1000 Rp 85,000.00 Rp 8,500.00
Tukang kayu OH 0.1000 Rp 130,000.00 Rp 13,000.00
Kepala tukang OH 0.0100 Rp 150,000.00 Rp 1,500.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00
JUMLAH HARGA TENAGA KERJA Rp 23,550.00
B BAHAN
Kayu balok 5/7 M³ 0.0120 Rp 1,200,000.00 Rp 14,400.00
Paku 2”-3” Kg 0.0200 Rp 19,800.00 Rp 396.00
Kayu papan 3/20 M³ 0.0070 Rp 3,500,000.00 Rp 24,500.00
JUMLAH HARGA BAHAN Rp 39,296.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 62,846.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 6,284.60
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 69,130.60

3 PENGGALIAN 1 M3 TANAH BIASA SEDALAM 1 M


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.7500 Rp 85,000.00 Rp 63,750.00
Mandor OH 0.0250 Rp 110,000.00 Rp 2,750.00
JUMLAH HARGA TENAGA KERJA Rp 66,500.00
B BAHAN
- - - Rp - Rp -
JUMLAH HARGA BAHAN Rp -
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 66,500.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 6,650.00
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 73,150.00
4 PENGGALIAN 1 M3 TANAH BIASA SEDALAM 2 M
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.9000 Rp 85,000.00 Rp 76,500.00
Mandor OH 0.0450 Rp 110,000.00 Rp 4,950.00
JUMLAH HARGA TENAGA KERJA Rp 81,450.00
B BAHAN
- - - Rp - Rp -
JUMLAH HARGA BAHAN Rp -
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 81,450.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 8,145.00
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 89,595.00

5 PENGURUGAN KEMBALI 1 M3 GALIAN TANAH


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.2500 Rp 85,000.00 Rp 21,250.00
Mandor OH 0.0083 Rp 110,000.00 Rp 913.00
JUMLAH HARGA TENAGA KERJA Rp 22,163.00
B BAHAN
- - - Rp - Rp -
JUMLAH HARGA BAHAN Rp -
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 22,163.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 2,216.30
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 24,379.30

6 PEMADATAN TANAH 1 M3 TANAH ( PER 20 CM )


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.1000 Rp 85,000.00 Rp 8,500.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00
JUMLAH HARGA TENAGA KERJA Rp 9,050.00
B BAHAN
- - - Rp - Rp -
JUMLAH HARGA BAHAN Rp -
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 9,050.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 905.00
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 9,955.00

7 PENGURUGAN 1 M3 DENGAN PASIR URUG


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.3000 Rp 85,000.00 Rp 25,500.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00
JUMLAH HARGA TENAGA KERJA Rp 26,600.00
B BAHAN
Pasir urug M³ 1.2000 Rp 1,000.00 Rp 1,200.00
JUMLAH HARGA BAHAN Rp 1,200.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 27,800.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 2,780.00
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 30,580.00
8 PEMASANGAN 1 M3 PONDASI BATU BELAH CAMPURAN 1 SP : 4 PP
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 1.5000 Rp 85,000.00 Rp 127,500.00
Tukang batu OH 0.7500 Rp 130,000.00 Rp 97,500.00
Kepala tukang OH 0.0750 Rp 150,000.00 Rp 11,250.00
Mandor OH 0.0750 Rp 110,000.00 Rp 8,250.00
JUMLAH HARGA TENAGA KERJA Rp 244,500.00
B BAHAN
Batu belah M³ 1.2000 Rp 218,571.00 Rp 262,285.20
Semen portland Kg 163.0000 Rp 1,500.00 Rp 244,500.00
Pasir pasang M³ 0.5200 Rp 214,286.00 Rp 111,428.72
JUMLAH HARGA BAHAN Rp 618,213.92
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 862,713.92
E OVERHEAD & PROFIT ( D x % ) 10% Rp 86,271.39
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 948,985.31

9 PEMASANGAN 1 M3 BATU KOSONG ( ANSTAMPING )


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.7800 Rp 85,000.00 Rp 66,300.00
Tukang batu OH 0.3900 Rp 130,000.00 Rp 50,700.00
Kepala tukang OH 0.0390 Rp 150,000.00 Rp 5,850.00
Mandor OH 0.0390 Rp 110,000.00 Rp 4,290.00
JUMLAH HARGA TENAGA KERJA Rp 127,140.00
B BAHAN
Batu belah M³ 1.2000 Rp 218,571.00 Rp 262,285.20
Pasir urug M³ 0.4320 Rp 151,429.00 Rp 65,417.33
JUMLAH HARGA BAHAN Rp 327,702.53
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 454,842.53
E OVERHEAD & PROFIT ( D x % ) 10% Rp 45,484.25
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 500,326.78

10 MEMBUAT 1 M3 BETON MUTU F'c = 9,8 MPa ( K-125 ), SLUMP ( 12 ± 2 ) CM, W/C = 0,78
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 1.6500 Rp 85,000.00 Rp 140,250.00
Tukang batu OH 0.2750 Rp 130,000.00 Rp 35,750.00
Kepala tukang OH 0.0280 Rp 150,000.00 Rp 4,200.00
Mandor OH 0.0830 Rp 110,000.00 Rp 9,130.00
JUMLAH HARGA TENAGA KERJA Rp 189,330.00
B BAHAN
Semen portland Kg 276.0000 Rp 1,500.00 Rp 414,000.00
Pasir beton Kg 828.0000 Rp 153.06 Rp 126,734.86
Kerikil Kg 1,012.0000 Rp 161.53 Rp 163,463.30
Air Ltr 215.0000 Rp 1,000.00 Rp 215,000.00
JUMLAH HARGA BAHAN Rp 919,198.16
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 1,108,528.16
E OVERHEAD & PROFIT ( D x % ) 10% Rp 110,852.82
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 1,219,380.98
11 MEMBUAT 1 M3 BETON MUTU F'c = 19,3 Mpa ( K-225 ), SLUMP ( 12 ± 2 ) CM, W/C = 0,58
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 1.6500 Rp 85,000.00 Rp 140,250.00
Tukang batu OH 0.2750 Rp 130,000.00 Rp 35,750.00
Kepala tukang OH 0.0280 Rp 150,000.00 Rp 4,200.00
Mandor OH 0.0830 Rp 110,000.00 Rp 9,130.00
JUMLAH HARGA TENAGA KERJA Rp 189,330.00
B BAHAN
Semen portland Kg 371.0000 Rp 1,500.00 Rp 556,500.00
Pasir beton Kg 698.0000 Rp 153.06 Rp 106,836.88
Kerikil Kg 1,047.0000 Rp 161.53 Rp 169,116.68
Air Ltr 215.0000 Rp 1,000.00 Rp 215,000.00
JUMLAH HARGA BAHAN Rp 1,047,453.55
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 1,236,783.55
E OVERHEAD & PROFIT ( D x % ) 10% Rp 123,678.36
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 1,360,461.91

12 MEMBUAT 1 M3 BETON MUTU F'c = 21,7 Mpa ( K-250 ), SLUMP ( 12 ± 2 ) CM, W/C = 0,56
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 1.6500 Rp 85,000.00 Rp 140,250.00
Tukang batu OH 0.2750 Rp 130,000.00 Rp 35,750.00
Kepala tukang OH 0.0280 Rp 150,000.00 Rp 4,200.00
Mandor OH 0.0830 Rp 110,000.00 Rp 9,130.00
JUMLAH HARGA TENAGA KERJA Rp 189,330.00
B BAHAN
Semen portland Kg 384.0000 Rp 1,500.00 Rp 576,000.00
Pasir beton Kg 692.0000 Rp 153.06 Rp 105,918.51
Kerikil Kg 1,039.0000 Rp 161.53 Rp 167,824.48
Air Ltr 215.0000 Rp 1,000.00 Rp 215,000.00
JUMLAH HARGA BAHAN Rp 1,064,742.98
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 1,254,072.98
E OVERHEAD & PROFIT ( D x % ) 10% Rp 125,407.30
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 1,379,480.28

13 PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0700 Rp 85,000.00 Rp 5,950.00
Tukang besi OH 0.0700 Rp 130,000.00 Rp 9,100.00
Kepala tukang OH 0.0070 Rp 150,000.00 Rp 1,050.00
Mandor OH 0.0040 Rp 110,000.00 Rp 440.00
JUMLAH HARGA TENAGA KERJA Rp 16,540.00
B BAHAN
Besi beton Kg 10.5000 Rp 19,367.00 Rp 203,353.50
Kawat beton Kg 1.1500 Rp 26,100.00 Rp 30,015.00
JUMLAH HARGA BAHAN Rp 233,368.50
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 249,908.50
E OVERHEAD & PROFIT ( D x % ) 10% Rp 24,990.85
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 274,899.35
Rp 27,489.94
14 PEMASANGAN 1 M2 BEKISTING UNTUK PONDASI
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.5200 Rp 85,000.00 Rp 44,200.00
Tukang kayu OH 0.2600 Rp 130,000.00 Rp 33,800.00
Kepala tukang OH 0.0260 Rp 150,000.00 Rp 3,900.00
Mandor OH 0.0260 Rp 110,000.00 Rp 2,860.00
JUMLAH HARGA TENAGA KERJA Rp 84,760.00
B BAHAN
Papan Kayu Kelas III M³ 0.0400 Rp 3,500,000.00 Rp 140,000.00
Paku 5 -10 cm Kg 0.3000 Rp 15,750.00 Rp 4,725.00
Minyak bekisting Ltr 0.1000 Rp 9,240.00 Rp 924.00
JUMLAH HARGA BAHAN Rp 145,649.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 230,409.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 23,040.90
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 253,449.90

15 PEMASANGAN 1 M2 BEKISTING UNTUK SLOOF


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.5200 Rp 85,000.00 Rp 44,200.00
Tukang kayu OH 0.2600 Rp 130,000.00 Rp 33,800.00
Kepala tukang OH 0.0260 Rp 150,000.00 Rp 3,900.00
Mandor OH 0.0260 Rp 110,000.00 Rp 2,860.00
JUMLAH HARGA TENAGA KERJA Rp 84,760.00
B BAHAN
Papan Kayu Kelas III M³ 0.0450 Rp 3,500,000.00 Rp 157,500.00
Paku 5 -10 cm Kg 0.3000 Rp 15,750.00 Rp 4,725.00
Minyak bekisting Ltr 0.1000 Rp 9,240.00 Rp 924.00
JUMLAH HARGA BAHAN Rp 163,149.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 247,909.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 24,790.90
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 272,699.90

16 PEMASANGAN 1 M2 BEKISTING UNTUK KOLOM


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.6600 Rp 85,000.00 Rp 56,100.00
Tukang kayu OH 0.3300 Rp 130,000.00 Rp 42,900.00
Kepala tukang OH 0.0330 Rp 150,000.00 Rp 4,950.00
Mandor OH 0.0330 Rp 110,000.00 Rp 3,630.00
JUMLAH HARGA TENAGA KERJA Rp 107,580.00
B BAHAN
Papan Kayu Kelas III M³ 0.0400 Rp 3,500,000.00 Rp 140,000.00
Paku 5 -12 cm Kg 0.4000 Rp 15,750.00 Rp 6,300.00
Minyak bekisting Ltr 0.2000 Rp 9,240.00 Rp 1,848.00
Balok kayu kelas II M³ 0.0150 Rp 4,000,000.00 Rp 60,000.00
Plywood tebal 9 mm Lbr 0.3500 Rp 98,000.00 Rp 34,300.00
Dolken kayu 8-10 cm Btg 2.0000 Rp 8,715.00 Rp 17,430.00
JUMLAH HARGA BAHAN Rp 259,878.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 367,458.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 36,745.80
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 404,203.80
17 PEMASANGAN 1 M2 BEKISTING UNTUK BALOK
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.6600 Rp 85,000.00 Rp 56,100.00
Tukang kayu OH 0.3300 Rp 130,000.00 Rp 42,900.00
Kepala tukang OH 0.0330 Rp 150,000.00 Rp 4,950.00
Mandor OH 0.0330 Rp 110,000.00 Rp 3,630.00
JUMLAH HARGA TENAGA KERJA Rp 107,580.00
B BAHAN
Papan Kayu Kelas III M³ 0.0400 Rp 3,500,000.00 Rp 140,000.00
Paku 5 -12 cm Kg 0.4000 Rp 15,750.00 Rp 6,300.00
Minyak bekisting Ltr 0.2000 Rp 9,240.00 Rp 1,848.00
Balok kayu kelas II M³ 0.0180 Rp 4,000,000.00 Rp 72,000.00
Plywood tebal 9 mm Lbr 0.3500 Rp 98,000.00 Rp 34,300.00
Dolken kayu 8-10 cm Btg 2.0000 Rp 8,715.00 Rp 17,430.00
JUMLAH HARGA BAHAN Rp 271,878.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 379,458.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 37,945.80
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 417,403.80

18 PEMASANGAN 1 M2 BEKISTING UNTUK LANTAI


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.6600 Rp 85,000.00 Rp 56,100.00
Tukang kayu OH 0.3300 Rp 130,000.00 Rp 42,900.00
Kepala tukang OH 0.0330 Rp 150,000.00 Rp 4,950.00
Mandor OH 0.0330 Rp 110,000.00 Rp 3,630.00
JUMLAH HARGA TENAGA KERJA Rp 107,580.00
B BAHAN
Papan Kayu Kelas III M³ 0.0400 Rp 3,500,000.00 Rp 140,000.00
Paku 5 -12 cm Kg 0.4000 Rp 15,750.00 Rp 6,300.00
Minyak bekisting Ltr 0.2000 Rp 9,240.00 Rp 1,848.00
Balok kayu kelas II M³ 0.0150 Rp 4,000,000.00 Rp 60,000.00
Plywood tebal 9 mm Lbr 0.3500 Rp 98,000.00 Rp 34,300.00
Dolken kayu 8-10 cm Btg 6.0000 Rp 8,715.00 Rp 52,290.00
JUMLAH HARGA BAHAN Rp 294,738.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 402,318.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 40,231.80
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 442,549.80

19 PEMASANGAN 1 M2 BEKISTING UNTUK TANGGA


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.6600 Rp 85,000.00 Rp 56,100.00
Tukang kayu OH 0.3300 Rp 130,000.00 Rp 42,900.00
Kepala tukang OH 0.0330 Rp 150,000.00 Rp 4,950.00
Mandor OH 0.0330 Rp 110,000.00 Rp 3,630.00
JUMLAH HARGA TENAGA KERJA Rp 107,580.00
B BAHAN
Papan Kayu Kelas III M³ 0.0300 Rp 3,500,000.00 Rp 105,000.00
Paku 5 -12 cm Kg 0.4000 Rp 15,750.00 Rp 6,300.00
Minyak bekisting Ltr 0.1500 Rp 9,240.00 Rp 1,386.00
Balok kayu kelas II M³ 0.0150 Rp 4,000,000.00 Rp 60,000.00
Plywood tebal 9 mm Lbr 0.3500 Rp 98,000.00 Rp 34,300.00
Dolken kayu 8-10 cm Btg 2.0000 Rp 8,715.00 Rp 17,430.00
JUMLAH HARGA BAHAN Rp 224,416.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 331,996.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 33,199.60
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 365,195.60
20 PEMASANGAN 1 KG RANGKA KUDA - KUDA BAJA SIKU
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0600 Rp 85,000.00 Rp 5,100.00
Tukang las kontruksi OH 0.0600 Rp 130,000.00 Rp 7,800.00
Kepala tukang OH 0.0600 Rp 150,000.00 Rp 9,000.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00
JUMLAH HARGA TENAGA KERJA Rp 22,230.00
B BAHAN
Besi baja Siku 60 x 60 , 6 m Kg 1.5100 Rp 58,500.00 Rp 88,335.00
JUMLAH HARGA BAHAN Rp 88,335.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 110,565.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 11,056.50
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 121,621.50

21 PEMASANGAN 1 BUAH FRAMELESS DOOR


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Upah Pasang Pintu + Hardware % 1.0000 Rp 3,573,000.00 Rp 3,573,000.00
JUMLAH HARGA TENAGA KERJA Rp 3,573,000.00
B BAHAN
Profil aluminium M 6.7000 Rp 62,000.00 Rp 415,400.00
Kaca Temperred 12 mm M² 4.3100 Rp 460,000.00 Rp 1,982,600.00
Floor Hinges Set 2.0000 Rp 774,000.00 Rp 1,548,000.00
Overpanel Set 2.0000 Rp 205,000.00 Rp 410,000.00
Top Patch Fitting Set 2.0000 Rp 780,000.00 Rp 1,560,000.00
Bottom Patch Fitting Set 2.0000 Rp 300,000.00 Rp 600,000.00
Bottom Patch Lock + Cylinder Set 2.0000 Rp 165,000.00 Rp 330,000.00
Pull Handle Set 2.0000 Rp 150,000.00 Rp 300,000.00
JUMLAH HARGA BAHAN Rp 7,146,000.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 10,719,000.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 1,071,900.00
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 11,790,900.00

22 PEMASANGAN 1 M2 KUSEN PINTU ALLUMINIUM


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0430 Rp 85,000.00 Rp 3,655.00
Tukang khusus alluminium OH 0.0430 Rp 130,000.00 Rp 5,590.00
Kepala tukang OH 0.0043 Rp 150,000.00 Rp 645.00
Mandor OH 0.0021 Rp 110,000.00 Rp 231.00
JUMLAH HARGA TENAGA KERJA Rp 10,121.00
B BAHAN
Profil aluminium M 1.1000 Rp 62,000.00 Rp 68,200.00
Sekrup fixer Bh 2.0000 Rp 3,700.00 Rp 7,400.00
Sealant Tube 0.0600 Rp 29,295.00 Rp 1,757.70
JUMLAH HARGA BAHAN Rp 77,357.70
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 87,478.70
E OVERHEAD & PROFIT ( D x % ) 10% Rp 8,747.87
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 96,226.57

23 PEMASANGAN 1 M2 RANGKA BESI HOLLOW 1 x 40.40.2 MM, MODUL 60 x 60 CM UNTUK PLAFON


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.3500 Rp 85,000.00 Rp 29,750.00
Tukang besi OH 0.3500 Rp 130,000.00 Rp 45,500.00
Kepala tukang OH 0.0350 Rp 150,000.00 Rp 5,250.00
Mandor OH 0.0180 Rp 110,000.00 Rp 1,980.00
JUMLAH HARGA TENAGA KERJA Rp 82,480.00
B BAHAN
Rangka metal hollow 40.40.2 mm M1 4.0000 Rp 29,000.00 Rp 116,000.00
Acsesoris ( perkuatan, las dll ) % 4.0000 Rp 29,000.00 Rp 116,000.00
JUMLAH HARGA BAHAN Rp 232,000.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 314,480.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 31,448.00
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 345,928.00
24 PEMASANGAN 1 M2 DINDING BATA MERAH ( 5 x 11 x 22 ) CM TEBAL 1 BATU CAMPURAN 1 SP : 3 PP
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.6000 Rp 85,000.00 Rp 51,000.00
Tukang batu OH 0.2000 Rp 130,000.00 Rp 26,000.00
Kepala tukang OH 0.0200 Rp 150,000.00 Rp 3,000.00
Mandor OH 0.0300 Rp 110,000.00 Rp 3,300.00
JUMLAH HARGA TENAGA KERJA Rp 83,300.00
B BAHAN
Bata merah Bh 140.0000 Rp 750.00 Rp 105,000.00
Semen portland Kg 32.9500 Rp 1,500.00 Rp 49,425.00
Pasir pasang M³ 0.0910 Rp 214,286.00 Rp 19,500.03
JUMLAH HARGA BAHAN Rp 173,925.03
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 257,225.03
E OVERHEAD & PROFIT ( D x % ) 10% Rp 25,722.50
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 282,947.53

25 PEMASANGAN 1 M2 DINDING BATA MERAH ( 5 x 11 x 22 ) CM TEBAL 1 BATU CAMPURAN 1 SP : 5 PP


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.6000 Rp 85,000.00 Rp 51,000.00
Tukang batu OH 0.2000 Rp 130,000.00 Rp 26,000.00
Kepala tukang OH 0.0200 Rp 150,000.00 Rp 3,000.00
Mandor OH 0.0300 Rp 110,000.00 Rp 3,300.00
JUMLAH HARGA TENAGA KERJA Rp 83,300.00
B BAHAN
Bata merah Bh 140.0000 Rp 750.00 Rp 105,000.00
Semen portland Kg 22.2000 Rp 1,500.00 Rp 33,300.00
Pasir pasang M³ 0.1020 Rp 214,286.00 Rp 21,857.17
JUMLAH HARGA BAHAN Rp 160,157.17
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 243,457.17
E OVERHEAD & PROFIT ( D x % ) 10% Rp 24,345.72
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 267,802.89
26 PEMASANGAN 1 M2 PLESTERAN CAMPURAN 1 SP : 3 PP, TEBAL 20 MM
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.4000 Rp 85,000.00 Rp 34,000.00
Tukang batu OH 0.2000 Rp 130,000.00 Rp 26,000.00
Kepala tukang OH 0.0200 Rp 150,000.00 Rp 3,000.00
Mandor OH 0.0220 Rp 110,000.00 Rp 2,420.00
JUMLAH HARGA TENAGA KERJA Rp 65,420.00
B BAHAN
Semen portland Kg 10.3680 Rp 1,500.00 Rp 15,552.00
Pasir pasang M³ 0.0310 Rp 214,286.00 Rp 6,642.87
JUMLAH HARGA BAHAN Rp 22,194.87
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 87,614.87
E OVERHEAD & PROFIT ( D x % ) 10% Rp 8,761.49
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 96,376.35

27 PEMASANGAN 1 M2 PLESTERAN CAMPURAN 1 SP : 5 PP, TEBAL 20 CM


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.4000 Rp 85,000.00 Rp 34,000.00
Tukang batu OH 0.2000 Rp 130,000.00 Rp 26,000.00
Kepala tukang OH 0.0200 Rp 150,000.00 Rp 3,000.00
Mandor OH 0.0220 Rp 110,000.00 Rp 2,420.00
JUMLAH HARGA TENAGA KERJA Rp 65,420.00
B BAHAN
Semen portland Kg 6.9120 Rp 1,500.00 Rp 10,368.00
Pasir pasang M³ 0.0350 Rp 214,286.00 Rp 7,500.01
JUMLAH HARGA BAHAN Rp 17,868.01
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 83,288.01
E OVERHEAD & PROFIT ( D x % ) 10% Rp 8,328.80
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 91,616.81

28 PEMASANGAN 1 M2 ACIAN
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.2000 Rp 85,000.00 Rp 17,000.00
Tukang batu OH 0.1000 Rp 130,000.00 Rp 13,000.00
Kepala tukang OH 0.0100 Rp 150,000.00 Rp 1,500.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00
JUMLAH HARGA TENAGA KERJA Rp 32,600.00
B BAHAN
Semen portland Kg 3.2500 Rp 1,500.00 Rp 4,875.00
JUMLAH HARGA BAHAN Rp 4,875.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 37,475.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 3,747.50
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 41,222.50
29 PEMASANGAN 1 M2 LANTAI UBIN TERALUX MARMER UKURAN 60 CM x 60 CM
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.2400 Rp 85,000.00 Rp 20,400.00
Tukang batu OH 0.1200 Rp 130,000.00 Rp 15,600.00
Kepala tukang OH 0.0120 Rp 150,000.00 Rp 1,800.00
Mandor OH 0.0120 Rp 110,000.00 Rp 1,320.00
JUMLAH HARGA TENAGA KERJA Rp 39,120.00
B BAHAN
Keramik 60 x 60 cm Bh 3.1000 Rp 20,500.00 Rp 63,550.00
Semen portland Kg 9.6000 Rp 1,500.00 Rp 14,400.00
Semen warna Kg 1.5000 Rp 24,150.00 Rp 36,225.00
Pasir pasang M³ 0.0450 Rp 214,286.00 Rp 9,642.87
JUMLAH HARGA BAHAN Rp 123,817.87
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 162,937.87
E OVERHEAD & PROFIT ( D x % ) 10% Rp 16,293.79
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 179,231.66

30 PEMASANGAN 1 M2 LANTAI UBIN TERALUX MARMER UKURAN 40 CM x 40 CM


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.2500 Rp 85,000.00 Rp 21,250.00
Tukang batu OH 0.1250 Rp 130,000.00 Rp 16,250.00
Kepala tukang OH 0.0130 Rp 150,000.00 Rp 1,950.00
Mandor OH 0.0130 Rp 110,000.00 Rp 1,430.00
JUMLAH HARGA TENAGA KERJA Rp 40,880.00
B BAHAN
Keramik 40 x 40 cm Bh 6.6300 Rp 6,250.00 Rp 41,437.50
Semen portland Kg 9.8000 Rp 1,500.00 Rp 14,700.00
Semen warna Kg 1.3000 Rp 24,150.00 Rp 31,395.00
Pasir pasang M³ 0.0450 Rp 214,286.00 Rp 9,642.87
JUMLAH HARGA BAHAN Rp 97,175.37
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 138,055.37
E OVERHEAD & PROFIT ( D x % ) 10% Rp 13,805.54
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 151,860.91

31 PEMASANGAN 1 M2 LANTAI UBIN WARNA UKURAN 20 CM x 20 CM


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.2700 Rp 85,000.00 Rp 22,950.00
Tukang batu OH 0.1350 Rp 130,000.00 Rp 17,550.00
Kepala tukang OH 0.0140 Rp 150,000.00 Rp 2,100.00
Mandor OH 0.0140 Rp 110,000.00 Rp 1,540.00
JUMLAH HARGA TENAGA KERJA Rp 44,140.00
B BAHAN
Keramik 20 x 20 cm Bh 26.5000 Rp 1,600.00 Rp 42,400.00
Semen portland Kg 10.4000 Rp 1,500.00 Rp 15,600.00
Semen warna Kg 1.0000 Rp 24,150.00 Rp 24,150.00
Pasir pasang M³ 0.0450 Rp 214,286.00 Rp 9,642.87
JUMLAH HARGA BAHAN Rp 91,792.87
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 135,932.87
E OVERHEAD & PROFIT ( D x % ) 10% Rp 13,593.29
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 149,526.16

32 PEMASANGAN 1 M1 PLINT UBIN WARNA UKURAN 10 CM x 60 CM


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0900 Rp 85,000.00 Rp 7,650.00
Tukang batu OH 0.0900 Rp 130,000.00 Rp 11,700.00
Kepala tukang OH 0.0090 Rp 150,000.00 Rp 1,350.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00
JUMLAH HARGA TENAGA KERJA Rp 21,250.00
B BAHAN
Keramik 10 x 60 cm Bh 1.7000 Rp 6,000.00 Rp 10,200.00
Semen portland Kg 1.1400 Rp 1,500.00 Rp 1,710.00
Semen warna Kg 0.1000 Rp 24,150.00 Rp 2,415.00
Pasir pasang M³ 0.0030 Rp 214,286.00 Rp 642.86
JUMLAH HARGA BAHAN Rp 14,967.86
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 36,217.86
E OVERHEAD & PROFIT ( D x % ) 10% Rp 3,621.79
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 39,839.64
33 PEMASANGAN 1 M2 LANGIT - LANGIT GYPSUM BOARD UKURAN ( 120 x 240 x 9 ) MM, TEBAL 9 MM
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.1000 Rp 85,000.00 Rp 8,500.00
Tukang kayu OH 0.0500 Rp 130,000.00 Rp 6,500.00
Kepala tukang OH 0.0050 Rp 150,000.00 Rp 750.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00
JUMLAH HARGA TENAGA KERJA Rp 16,300.00
B BAHAN
Gypsum board Lbr 0.3640 Rp 60,649.00 Rp 22,076.24
Paku tripleks Kg 0.1100 Rp 28,750.00 Rp 3,162.50
JUMLAH HARGA BAHAN Rp 25,238.74
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 41,538.74
E OVERHEAD & PROFIT ( D x % ) 10% Rp 4,153.87
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 45,692.61

34 PEMASANGAN 1 M' LIST LANGIT - LANGIT KAYU PROFIL


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0500 Rp 85,000.00 Rp 4,250.00
Tukang kayu OH 0.0500 Rp 130,000.00 Rp 6,500.00
Kepala tukang OH 0.0050 Rp 150,000.00 Rp 750.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00
JUMLAH HARGA TENAGA KERJA Rp 11,830.00
B BAHAN
List kayu profil M 1.0500 Rp 15,000.00 Rp 15,750.00
Paku campur Kg 0.0100 Rp 15,750.00 Rp 157.50
JUMLAH HARGA BAHAN Rp 15,907.50
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 27,737.50
E OVERHEAD & PROFIT ( D x % ) 10% Rp 2,773.75
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 30,511.25

35 PEMASANGAN 1 M² ATAP SPUNDACK


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.1200 Rp 85,000.00 Rp 10,200.00
Tukang kayu OH 0.0600 Rp 130,000.00 Rp 7,800.00
Kepala tukang OH 0.0060 Rp 150,000.00 Rp 900.00
Mandor OH 0.0060 Rp 110,000.00 Rp 660.00
JUMLAH HARGA TENAGA KERJA Rp 19,560.00
B BAHAN
Atap Spundack M 1.6200 Rp 67,850.00 Rp 109,917.00
Paku Spundack Kg 0.0200 Rp 40,000.00 Rp 800.00
JUMLAH HARGA BAHAN Rp 110,717.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 130,277.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 13,027.70
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 143,304.70

36 PEMASANGAN 1 M1 NOK ALUMUNIUM


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.1000 Rp 85,000.00 Rp 8,500.00
Tukang kayu OH 1.0000 Rp 130,000.00 Rp 130,000.00
Kepala tukang OH 0.1000 Rp 150,000.00 Rp 15,000.00
Mandor OH 0.0500 Rp 110,000.00 Rp 5,500.00
JUMLAH HARGA TENAGA KERJA Rp 159,000.00
B BAHAN
Nok standar 40 x 18 cm Bh 1.2000 Rp 75,000.00 Rp 90,000.00
Paku 5 -12 cm Kg 0.0400 Rp 15,750.00 Rp 630.00
JUMLAH HARGA BAHAN Rp 90,630.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 249,630.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 24,963.00
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 274,593.00

37 PEMBUATAN DAN PEMASANGAN 1 M3 KUSEN PINTU DAN KUSEN JENDELA, KAYU KELAS II DAN III
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 6.0000 Rp 85,000.00 Rp 510,000.00
Tukang kayu OH 18.0000 Rp 130,000.00 Rp 2,340,000.00
Kepala tukang OH 1.8000 Rp 150,000.00 Rp 270,000.00
Mandor OH 0.3000 Rp 110,000.00 Rp 33,000.00
JUMLAH HARGA TENAGA KERJA Rp 3,153,000.00
B BAHAN
Balok kayu kelas II M³ 1.2000 Rp 4,000,000.00 Rp 4,800,000.00
Paku 5 -10 cm Kg 1.2500 Rp 15,750.00 Rp 19,687.50
Lem kayu Kg 1.0000 Rp 25,000.00 Rp 25,000.00
JUMLAH HARGA BAHAN Rp 4,844,687.50
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 7,997,687.50
E OVERHEAD & PROFIT ( D x % ) 10% Rp 799,768.75
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 8,797,456.25
38 PEMBUATAN DAN PEMASANGAN 1 M2 DAUN PINTU PANEL, KAYU KELAS I ATAU II
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 1.0000 Rp 85,000.00 Rp 85,000.00
Tukang kayu OH 3.0000 Rp 130,000.00 Rp 390,000.00
Kepala tukang OH 0.3000 Rp 150,000.00 Rp 45,000.00
Mandor OH 0.0500 Rp 110,000.00 Rp 5,500.00
JUMLAH HARGA TENAGA KERJA Rp 525,500.00
B BAHAN
Papan Kayu Kelas I M³ 0.0400 Rp 5,775,000.00 Rp 231,000.00
Lem kayu Kg 0.0500 Rp 25,000.00 Rp 1,250.00
JUMLAH HARGA BAHAN Rp 232,250.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 757,750.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 75,775.00
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 833,525.00

39 PEMASANGAN 1 M LISPLANK UKURAN 3 x 30 CM, KAYU KELAS I ATAU KELAS II


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.1000 Rp 85,000.00 Rp 8,500.00
Tukang kayu OH 0.2000 Rp 130,000.00 Rp 26,000.00
Kepala tukang OH 0.0200 Rp 150,000.00 Rp 3,000.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00
JUMLAH HARGA TENAGA KERJA Rp 38,050.00
B BAHAN
Papan Kayu Kelas I M³ 0.0110 Rp 5,775,000.00 Rp 63,525.00
Paku 5 -10 cm Kg 0.0500 Rp 15,750.00 Rp 787.50
JUMLAH HARGA BAHAN Rp 64,312.50
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 102,362.50
E OVERHEAD & PROFIT ( D x % ) 10% Rp 10,236.25
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 112,598.75

40 PEMASANGAN 1 BUAH KUNCI TANAM BIASA


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0100 Rp 85,000.00 Rp 850.00
Tukang kayu OH 0.5000 Rp 130,000.00 Rp 65,000.00
Kepala tukang OH 0.0500 Rp 150,000.00 Rp 7,500.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00
JUMLAH HARGA TENAGA KERJA Rp 73,900.00
B BAHAN
Kunci tanam biasa Bh 1.0000 Rp 90,000.00 Rp 90,000.00
JUMLAH HARGA BAHAN Rp 90,000.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 163,900.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 16,390.00
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 180,290.00

41 PEMASANGAN 1 BUAH KUNCI KAMAR MANDI


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0050 Rp 85,000.00 Rp 425.00
Tukang kayu OH 0.5000 Rp 130,000.00 Rp 65,000.00
Kepala tukang OH 0.0500 Rp 150,000.00 Rp 7,500.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00
JUMLAH HARGA TENAGA KERJA Rp 73,255.00
B BAHAN
Kunci tanam KM Bh 1.0000 Rp 37,500.00 Rp 37,500.00
JUMLAH HARGA BAHAN Rp 37,500.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 110,755.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 11,075.50
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 121,830.50

42 PEMASANGAN 1 BUAH KUNCI SILINDER


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0050 Rp 85,000.00 Rp 425.00
Tukang kayu OH 0.5000 Rp 130,000.00 Rp 65,000.00
Kepala tukang OH 0.0500 Rp 150,000.00 Rp 7,500.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00
JUMLAH HARGA TENAGA KERJA Rp 73,255.00
B BAHAN
Kunci silinder Bh 1.0000 Rp 18,000.00 Rp 18,000.00
JUMLAH HARGA BAHAN Rp 18,000.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 91,255.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 9,125.50
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 100,380.50
43 PEMASANGAN 1 BUAH ENGSEL PINTU
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0150 Rp 85,000.00 Rp 1,275.00
Tukang kayu OH 0.1500 Rp 130,000.00 Rp 19,500.00
Kepala tukang OH 0.0150 Rp 150,000.00 Rp 2,250.00
Mandor OH 0.0008 Rp 110,000.00 Rp 88.00
JUMLAH HARGA TENAGA KERJA Rp 23,113.00
B BAHAN
Engsel pintu Bh 1.0000 Rp 34,500.00 Rp 34,500.00
JUMLAH HARGA BAHAN Rp 34,500.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 57,613.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 5,761.30
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 63,374.30

44 PEMASANGAN 1 BUAH DOOR CLOSER


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0500 Rp 85,000.00 Rp 4,250.00
Tukang kayu OH 0.5000 Rp 130,000.00 Rp 65,000.00
Kepala tukang OH 0.0500 Rp 150,000.00 Rp 7,500.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00
JUMLAH HARGA TENAGA KERJA Rp 77,080.00
B BAHAN
Door closer Bh 1.0000 Rp 120,500.00 Rp 120,500.00
JUMLAH HARGA BAHAN Rp 120,500.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 197,580.00
E OVERHEAD & PROFIT ( D x % ) 15% Rp 29,637.00
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 227,217.00

45 PEMASANGAN 1 M2 KACA TEBAL 3 MM


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0150 Rp 85,000.00 Rp 1,275.00
Tukang kayu OH 0.1500 Rp 130,000.00 Rp 19,500.00
Kepala tukang OH 0.0150 Rp 150,000.00 Rp 2,250.00
Mandor OH 0.0008 Rp 110,000.00 Rp 88.00
JUMLAH HARGA TENAGA KERJA Rp 23,113.00
B BAHAN
Kaca tebal 3 mm M² 1.1000 Rp 75,000.00 Rp 82,500.00
Sealant Kg 0.0500 Rp 29,295.00 Rp 1,464.75
JUMLAH HARGA BAHAN Rp 83,964.75
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 107,077.75
E OVERHEAD & PROFIT ( D x % ) 10% Rp 10,707.78
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 117,785.53

46 PEMASANGAN 1 M2 KACA TEBAL 5 MM


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0150 Rp 85,000.00 Rp 1,275.00
Tukang kayu OH 0.1500 Rp 130,000.00 Rp 19,500.00
Kepala tukang OH 0.0150 Rp 150,000.00 Rp 2,250.00
Mandor OH 0.0008 Rp 110,000.00 Rp 88.00
JUMLAH HARGA TENAGA KERJA Rp 23,113.00
B BAHAN
Kaca tebal 5 mm M² 1.1000 Rp 93,240.00 Rp 102,564.00
Sealant Kg 0.0500 Rp 29,295.00 Rp 1,464.75
JUMLAH HARGA BAHAN Rp 104,028.75
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 127,141.75
E OVERHEAD & PROFIT ( D x % ) 10% Rp 12,714.18
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 139,855.93

47 PEMASANGAN 1 M2 KACA TEBAL 8 MM


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0250 Rp 85,000.00 Rp 2,125.00
Tukang kayu OH 0.2500 Rp 130,000.00 Rp 32,500.00
Kepala tukang OH 0.0250 Rp 150,000.00 Rp 3,750.00
Mandor OH 0.0013 Rp 110,000.00 Rp 143.00
JUMLAH HARGA TENAGA KERJA Rp 38,518.00
B BAHAN
Kaca Temperred 12 mm M² 1.1000 Rp 460,000.00 Rp 506,000.00
Sealant Kg 0.0700 Rp 29,295.00 Rp 2,050.65
JUMLAH HARGA BAHAN Rp 508,050.65
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 546,568.65
E OVERHEAD & PROFIT ( D x % ) 10% Rp 54,656.87
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 601,225.52
48 1 M2 PENGECATAN BIDANG KAYU BARU (1 LAPIS PLAMUR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0700 Rp 85,000.00 Rp 5,950.00
Tukang cat OH 0.0090 Rp 110,348.00 Rp 993.13
Kepala tukang OH 0.0060 Rp 150,000.00 Rp 900.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00
JUMLAH HARGA TENAGA KERJA Rp 8,173.13
B BAHAN
Meni Kg 0.2000 Rp 25,000.00 Rp 5,000.00
Plamur Kg 0.1500 Rp 19,320.00 Rp 2,898.00
Cat dasar Kg 0.1700 Rp 59,850.00 Rp 10,174.50
Cat penutup Kg 0.2600 Rp 59,850.00 Rp 15,561.00
Kuas Bh 0.0100 Rp 10,000.00 Rp 100.00
Thiner Kg 0.0300 Rp 30,000.00 Rp 900.00
Ampelas Lbr 0.2000 Rp 6,500.00 Rp 1,300.00
JUMLAH HARGA BAHAN Rp 35,933.50
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 44,106.63
E OVERHEAD & PROFIT ( D x % ) 10% Rp 4,410.66
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 48,517.30

49 PENGECATAN 1 M2 TEMBOK BARU ( 1 LAPIS PLAMUR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP )
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0200 Rp 85,000.00 Rp 1,700.00
Tukang cat OH 0.0630 Rp 110,348.00 Rp 6,951.92
Kepala Tukang OH 0.0063 Rp 150,000.00 Rp 945.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00
JUMLAH HARGA TENAGA KERJA Rp 9,926.92
B BAHAN
Plamur Kg 0.1000 Rp 19,320.00 Rp 1,932.00
Cat dasar Kg 0.1000 Rp 21,735.00 Rp 2,173.50
Cat penutup Kg 0.2600 Rp 21,735.00 Rp 5,651.10
JUMLAH HARGA BAHAN Rp 9,756.60
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 19,683.52
E OVERHEAD & PROFIT ( D x % ) 10% Rp 1,968.35
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 21,651.88
50 PEMASANGAN 1 BUAH CLOSET JONGKOK TERASO
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 1.0000 Rp 85,000.00 Rp 85,000.00
Tukang batu OH 1.5000 Rp 130,000.00 Rp 195,000.00
Kepala Tukang OH 0.1500 Rp 150,000.00 Rp 22,500.00
Mandor OH 0.0500 Rp 110,000.00 Rp 5,500.00
JUMLAH HARGA TENAGA KERJA Rp 308,000.00
B BAHAN
Closet jongkok teraso Unit 1.0000 Rp 150,000.00 Rp 150,000.00
Semen portland Kg 6.0000 Rp 1,500.00 Rp 9,000.00
Pasir pasang M³ 0.0100 Rp 214,286.00 Rp 2,142.86
Bata merah Bh 7.0000 Rp 750.00 Rp 5,250.00
JUMLAH HARGA BAHAN Rp 166,392.86
C PERALATAN
- - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 474,392.86
E OVERHEAD & PROFIT ( D x % ) 10% Rp 47,439.29
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 521,832.15

51 PEMASANGAN 1 BUAH URINOIR


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 1.0000 Rp 85,000.00 Rp 85,000.00
Tukang batu OH 1.0000 Rp 130,000.00 Rp 130,000.00
Kepala Tukang OH 0.1000 Rp 150,000.00 Rp 15,000.00
Mandor OH 0.0500 Rp 110,000.00 Rp 5,500.00
JUMLAH HARGA TENAGA KERJA Rp 235,500.00
B BAHAN
Urinoir Unit 1.0000 Rp 2,500,000.00 Rp 2,500,000.00
Semen portland Kg 6.0000 Rp 1,500.00 Rp 9,000.00
Pasir pasang M³ 0.0100 Rp 214,286.00 Rp 2,142.86
Perlengkapan % 30.0000 Rp 753,342.86 Rp 226,002.86
JUMLAH HARGA BAHAN Rp 2,737,145.72
C PERALATAN
- - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 2,972,645.72
E OVERHEAD & PROFIT ( D x % ) 10% Rp 297,264.57
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 3,269,910.29

52 PEMASANGAN 1 BUAH WASTAFEL


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 1.0000 Rp 85,000.00 Rp 85,000.00
Tukang batu OH 1.0000 Rp 130,000.00 Rp 130,000.00
Kepala Tukang OH 0.1000 Rp 150,000.00 Rp 15,000.00
Mandor OH 0.0500 Rp 110,000.00 Rp 5,500.00
JUMLAH HARGA TENAGA KERJA Rp 235,500.00
B BAHAN
Wastafel Unit 1.0000 Rp 500,000.00 Rp 500,000.00
Semen portland Kg 6.0000 Rp 1,500.00 Rp 9,000.00
Pasir pasang M³ 0.0100 Rp 214,286.00 Rp 2,142.86
Perlengkapan % 12.0000 Rp 61,337.14 Rp 7,360.46
JUMLAH HARGA BAHAN Rp 518,503.32
C PERALATAN
- - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 754,003.32
E OVERHEAD & PROFIT ( D x % ) 10% Rp 75,400.33
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 829,403.65

53 PEMASANGAN 1 BUAH FLOOR DRAIN


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0100 Rp 85,000.00 Rp 850.00
Tukang batu OH 0.1000 Rp 130,000.00 Rp 13,000.00
Kepala Tukang OH 0.0100 Rp 150,000.00 Rp 1,500.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00
JUMLAH HARGA TENAGA KERJA Rp 15,900.00
B BAHAN
Floor drain Unit 1.0000 Rp 45,000.00 Rp 45,000.00
JUMLAH HARGA BAHAN Rp 45,000.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 60,900.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 6,090.00
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 66,990.00

54 PEMASANGAN 1 M1 PIPA PVC TIPE AW DIAMETER 1/2 INCHI


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0360 Rp 85,000.00 Rp 3,060.00
Tukang pipa OH 0.0600 Rp 130,000.00 Rp 7,800.00
Kepala Tukang OH 0.0060 Rp 150,000.00 Rp 900.00
Mandor OH 0.0020 Rp 110,000.00 Rp 220.00
JUMLAH HARGA TENAGA KERJA Rp 11,980.00
B BAHAN
Pipa PVC 1/2 inchi M1 1.2000 Rp 5,300.00 Rp 6,360.00
Perlengkapan % 35.0000 Rp 5,300.00 Rp 1,855.00
JUMLAH HARGA BAHAN Rp 8,215.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 20,195.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 2,019.50
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 22,214.50
55 PEMASANGAN 1 M1 PIPA PVC TIPE AW DIAMETER 2 1/2 INCHI
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0810 Rp 85,000.00 Rp 6,885.00
Tukang pipa OH 0.1350 Rp 130,000.00 Rp 17,550.00
Kepala Tukang OH 0.0135 Rp 150,000.00 Rp 2,025.00
Mandor OH 0.0040 Rp 110,000.00 Rp 440.00
JUMLAH HARGA TENAGA KERJA Rp 26,900.00
B BAHAN
Pipa PVC 2 1/2 inchi M1 1.2000 Rp 39,408.00 Rp 47,289.60
Perlengkapan % 35.0000 Rp 39,408.00 Rp 13,792.80
JUMLAH HARGA BAHAN Rp 61,082.40
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 87,982.40
E OVERHEAD & PROFIT ( D x % ) 10% Rp 8,798.24
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 96,780.64

56 PEMASANGAN 1 M1 PIPA PVC TIPE AW DIAMETER 4 INCHI


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0810 Rp 85,000.00 Rp 6,885.00
Tukang pipa OH 0.1350 Rp 130,000.00 Rp 17,550.00
Kepala Tukang OH 0.0135 Rp 150,000.00 Rp 2,025.00
Mandor OH 0.0040 Rp 110,000.00 Rp 440.00
JUMLAH HARGA TENAGA KERJA Rp 26,900.00
B BAHAN
Pipa PVC 4 inchi M1 1.2000 Rp 85,256.00 Rp 102,307.20
Perlengkapan % 35.0000 Rp 85,256.00 Rp 29,839.60
JUMLAH HARGA BAHAN Rp 132,146.80
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 159,046.80
E OVERHEAD & PROFIT ( D x % ) 10% Rp 15,904.68
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 174,951.48

57 PEMASANGAN 1 BOX PANEL


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.5000 Rp 85,000.00 Rp 42,500.00
Tukang Listrik OH 1.0000 Rp 130,000.00 Rp 130,000.00
Kepala Tukang OH 1.0000 Rp 150,000.00 Rp 150,000.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00
JUMLAH HARGA TENAGA KERJA Rp 172,500.00
B BAHAN
Box Panel PVC isi 3 MCB Bh 1.0000 Rp 150,000.00 Rp 150,000.00
MCB 6A Bh 2.0000 Rp 58,725.00 Rp 117,450.00
MCB 4A Bh 2.0000 Rp 58,725.00 Rp 117,450.00
Kabel NYM 3x2,5 mm² m' 6.0000 Rp 16,600.00 Rp 99,600.00
JUMLAH HARGA BAHAN Rp 484,500.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 657,000.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 65,700.00
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 722,700.00

58 PEMASANGAN 1 BUAH LAMPU PLC 14 WATT


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 1.0000 Rp 85,000.00 Rp 850.00
Tukang Listrik OH 0.3300 Rp 130,000.00 Rp 429.00
JUMLAH HARGA TENAGA KERJA Rp 429.00
B BAHAN
Pipa listrik 5/8 inchi M' 1.7000 Rp 15,000.00 Rp 25,500.00
Kabel NYM 2x2,5 mm² M' 7.5000 Rp 8,680.00 Rp 65,100.00
Fitting Bh 1.0000 Rp 14,375.00 Rp 14,375.00
Lampu PLC 14 Watt Bh 1.0000 Rp 18,900.00 Rp 18,900.00
Klem Bh 0.3300 Rp 5,900.00 Rp 1,947.00
JUMLAH HARGA BAHAN Rp 125,822.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 126,251.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 12,625.10
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 138,876.10
58 PEMASANGAN 1 BUAH LAMPU TL 36 WATT
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 1.0000 Rp 85,000.00 Rp 850.00
Tukang Listrik OH 0.3300 Rp 130,000.00 Rp 429.00
JUMLAH HARGA TENAGA KERJA Rp 429.00
B BAHAN
Pipa listrik 5/8 inchi M' 1.7000 Rp 15,000.00 Rp 25,500.00
Kabel NYM 2x2,5 mm² M' 7.5000 Rp 8,680.00 Rp 65,100.00
Fitting Bh 1.0000 Rp 14,375.00 Rp 14,375.00
Lampu PLC 20 Watt Bh 1.0000 Rp 23,000.00 Rp 23,000.00
Klem Bh 0.3300 Rp 5,900.00 Rp 1,947.00
JUMLAH HARGA BAHAN Rp 129,922.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 130,351.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 13,035.10
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 143,386.10

59 PEMASANGAN 1 BUAH LAMPU PLC 20 WATT


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 1.0000 Rp 85,000.00 Rp 850.00
Tukang Listrik OH 0.3300 Rp 130,000.00 Rp 429.00
JUMLAH HARGA TENAGA KERJA Rp 429.00
B BAHAN
Pipa listrik 5/8 inchi M' 1.7000 Rp 15,000.00 Rp 25,500.00
Kabel NYM 2x2,5 mm² M' 7.5000 Rp 8,680.00 Rp 65,100.00
Fitting Bh 1.0000 Rp 14,375.00 Rp 14,375.00
Lampu PLC 20 Watt Bh 1.0000 Rp 23,000.00 Rp 23,000.00
Klem Bh 0.3300 Rp 5,900.00 Rp 1,947.00
JUMLAH HARGA BAHAN Rp 129,922.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 130,351.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 13,035.10
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 143,386.10
60 PEMASANGAN 1 BUAH SAKLAR TUNGGAL
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.1000 Rp 85,000.00 Rp 8,500.00
Tukang Listrik OH 0.1000 Rp 130,000.00 Rp 13,000.00
Kepala Tukang OH 0.0500 Rp 150,000.00 Rp 7,500.00
Mandor OH 0.0250 Rp 110,000.00 Rp 2,750.00
JUMLAH HARGA TENAGA KERJA Rp 21,500.00
B BAHAN
Saklar Tunggal Bh 1.0000 Rp 20,125.00 Rp 20,125.00
Isolasi Bh 0.2500 Rp 5,000.00 Rp 1,250.00
JUMLAH HARGA BAHAN Rp 21,375.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 42,875.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 4,287.50
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 47,162.50

61 PEMASANGAN 1 BUAH SAKLAR GANDA


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.1000 Rp 85,000.00 Rp 8,500.00
Tukang Listrik OH 0.1000 Rp 130,000.00 Rp 13,000.00
Kepala Tukang OH 0.0500 Rp 150,000.00 Rp 7,500.00
Mandor OH 0.0250 Rp 110,000.00 Rp 2,750.00
JUMLAH HARGA TENAGA KERJA Rp 21,500.00
B BAHAN
Saklar Ganda Bh 1.0000 Rp 23,000.00 Rp 23,000.00
Isolasi Bh 0.2500 Rp 5,000.00 Rp 1,250.00
JUMLAH HARGA BAHAN Rp 24,250.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 45,750.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 4,575.00
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 50,325.00

62 PEMASANGAN 1 BUAH STOP KONTAK


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.1000 Rp 85,000.00 Rp 8,500.00
Tukang Listrik OH 0.1000 Rp 130,000.00 Rp 13,000.00
Kepala Tukang OH 0.0500 Rp 150,000.00 Rp 7,500.00
Mandor OH 0.0250 Rp 110,000.00 Rp 2,750.00
JUMLAH HARGA TENAGA KERJA Rp 21,500.00
B BAHAN
Stop Kontak Bh 1.0000 Rp 17,250.00 Rp 17,250.00
Isolasi Bh 0.2500 Rp 5,000.00 Rp 1,250.00
JUMLAH HARGA BAHAN Rp 18,500.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 40,000.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 4,000.00
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 44,000.00

63 PEMASANGAN 1 BUAH STOP KONTAK


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.1000 Rp 85,000.00 Rp 8,500.00
Tukang Listrik OH 0.1000 Rp 130,000.00 Rp 13,000.00
Kepala Tukang OH 0.0500 Rp 150,000.00 Rp 7,500.00
Mandor OH 0.0250 Rp 110,000.00 Rp 2,750.00
JUMLAH HARGA TENAGA KERJA Rp 21,500.00
B BAHAN
Stop Kontak Bh 1.0000 Rp 17,250.00 Rp 17,250.00
Isolasi Bh 0.2500 Rp 5,000.00 Rp 1,250.00
JUMLAH HARGA BAHAN Rp 18,500.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 40,000.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 4,000.00
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 44,000.00
64 PEMASANGAN 1 BUAH MESIN JET PUMP KAP. 250 WATT
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 1.0000 Rp 85,000.00 Rp 85,000.00
Tukang Listrik OH 0.5000 Rp 130,000.00 Rp 65,000.00
Kepala Tukang OH 0.1100 Rp 150,000.00 Rp 16,500.00
Mandor OH 0.0160 Rp 110,000.00 Rp 1,760.00
JUMLAH HARGA TENAGA KERJA Rp 18,260.00
B BAHAN
Mesin Jet Pump kap. 250 watt Bh 1.0000 Rp 950,000.00 Rp 950,000.00
JUMLAH HARGA BAHAN Rp 950,000.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 968,260.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 96,826.00
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 1,065,086.00

59 PEMASANGAN 1 SET KUSEN & PINTU KAMAR MANDI (PVC)


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0050 Rp 85,000.00 Rp 425.00
Tukang kayu OH 0.5000 Rp 130,000.00 Rp 65,000.00
JUMLAH HARGA TENAGA KERJA Rp 65,425.00
B BAHAN
Pintu PVC Kamar Mandi Set 1.0000 Rp 199,900.00 Rp 199,900.00
JUMLAH HARGA BAHAN Rp 199,900.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 265,325.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 26,532.50
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 291,857.50
60 PEMASANGAN 1 BUAH TANDON AIR
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 1.0000 Rp 85,000.00 Rp 85,000.00
Tukang Listrik OH 0.5000 Rp 130,000.00 Rp 65,000.00
Kepala tukang OH 0.1100 Rp 150,000.00 Rp 16,500.00
Mandor OH 0.1600 Rp 110,000.00 Rp 17,600.00
JUMLAH HARGA TENAGA KERJA Rp 150,000.00
B BAHAN
Tangki Air 1000 Liter Set 1.0000 Rp 2,400,000.00 Rp 2,400,000.00
JUMLAH HARGA BAHAN Rp 2,400,000.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 2,550,000.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 255,000.00
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 2,805,000.00

61 PEMASANGAN 1 M GORDING CNP


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.2000 Rp 85,000.00 Rp 17,000.00
Tukang Besi OH 0.4500 Rp 130,000.00 Rp 58,500.00
Kepala tukang OH 0.0100 Rp 150,000.00 Rp 1,500.00
Mandor OH 0.0500 Rp 110,000.00 Rp 5,500.00
JUMLAH HARGA TENAGA KERJA Rp 75,500.00
B BAHAN
Besi CNP M' 1.0000 Rp 125,000.00 Rp 125,000.00
Sekrup SDS (Self Driling Screw) Bh 5.1000 Rp 3,700.00 Rp 18,870.00
JUMLAH HARGA BAHAN Rp 143,870.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 219,370.00
E OVERHEAD & PROFIT ( D x % ) 10% Rp 21,937.00
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 241,307.00

62 PEMASANGAN 1 M2 BEKISTING UNTUK DINDING


NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.6600 Rp 85,000.00 Rp 56,100.00
Tukang kayu OH 0.3300 Rp 130,000.00 Rp 42,900.00
Kepala tukang OH 0.0330 Rp 150,000.00 Rp 4,950.00
Mandor OH 0.0330 Rp 110,000.00 Rp 3,630.00
JUMLAH HARGA TENAGA KERJA Rp 107,580.00
B BAHAN
Papan Kayu Kelas III M3 0.0300 Rp 3,500,000.00 Rp 105,000.00
Paku 5 -12 cm Kg 0.4000 Rp 15,750.00 Rp 6,300.00
Minyak bekisting Ltr 0.2000 Rp 9,240.00 Rp 1,848.00
Balok kayu kelas II M3 0.0200 Rp 4,000,000.00 Rp 80,000.00
Plywood tebal 9 mm Lbr 0.3500 Rp 98,000.00 Rp 34,300.00
Dolken kayu 8-10 cm Btg 3.0000 Rp 8,715.00 Rp 26,145.00
Penjaga jarak bekisting/spacer Bh 4.0000 Rp 2,800.00 Rp 11,200.00
JUMLAH HARGA BAHAN Rp 264,793.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 372,373.00
E OVERHEAD & PROFIT ( D x % ) 15% Rp 55,855.95
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 428,228.95

63 MEMBUAT 1 M3 BETON MUTU F'c = 26,4 Mpa ( K-300 ), SLUMP ( 12 ± 2 ) CM, W/C = 0,52
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 1.6500 Rp 85,000.00 Rp 140,250.00
Tukang batu OH 0.2750 Rp 130,000.00 Rp 35,750.00
Kepala tukang OH 0.0280 Rp 150,000.00 Rp 4,200.00
Mandor OH 0.0830 Rp 110,000.00 Rp 9,130.00
JUMLAH HARGA TENAGA KERJA Rp 189,330.00
B BAHAN
Semen portland Kg 413.0000 Rp 1,500.00 Rp 619,500.00
Pasir beton Kg 681.0000 Rp 153.06 Rp 104,234.83
Kerikil Kg 1,021.0000 Rp 161.53 Rp 164,917.03
Air Ltr 215.0000 Rp 1,000.00 Rp 215,000.00
JUMLAH HARGA BAHAN Rp 1,103,651.86
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 1,292,981.86
E OVERHEAD & PROFIT ( D x % ) 15% Rp 193,947.28
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 1,486,929.14
64 PEMASANGAN 1 M1 PIPA PVC TIPE AW DIAMETER 3/4 INCHI
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.0360 Rp 85,000.00 Rp 3,060.00
Tukang pipa OH 0.0600 Rp 130,000.00 Rp 7,800.00
Kepala Tukang OH 0.0060 Rp 150,000.00 Rp 900.00
Mandor OH 0.0020 Rp 110,000.00 Rp 220.00
JUMLAH HARGA TENAGA KERJA Rp 11,980.00
B BAHAN
Pipa PVC 3/4 inchi M1 1.2000 Rp 48,000.00 Rp 57,600.00
Perlengkapan % 35.0000 Rp 7,200.00 Rp 2,520.00
JUMLAH HARGA BAHAN Rp 60,120.00
C PERALATAN
- - - Rp - Rp -
JUMLAH HARGA PERALATAN Rp -
D JUMLAH ( A + B + C ) Rp 72,100.00
E OVERHEAD & PROFIT ( D x % ) 15% Rp 10,815.00
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 82,915.00

65 PEMASANGAN 1 M2 ATAP JURAI RANGKA ATAP BAJA CANAI DINGIN PROFIL C75
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA KERJA
Pekerja OH 0.7340 Rp 85,000.00 Rp 62,390.00
Tukang besi OH 0.7340 Rp 130,000.00 Rp 95,420.00
Kepala tukang OH 0.0730 Rp 150,000.00 Rp 10,950.00
Mandor OH 0.0370 Rp 110,000.00 Rp 4,070.00
JUMLAH HARGA TENAGA KERJA Rp 172,830.00
B BAHAN
Baja ringan canai dingin C75 M2 3.0650 Rp 127,000.00 Rp 389,255.00
JUMLAH HARGA BAHAN Rp 389,255.00
C PERALATAN
Peralatan % 10.0000 Rp 12,700.00 Rp 127,000.00
JUMLAH HARGA PERALATAN Rp 127,000.00
D JUMLAH ( A + B + C ) Rp 689,085.00
E OVERHEAD & PROFIT ( D x % ) 15% Rp 103,362.75
F HARGA SATUAN PEKERJAAN ( D + E ) Rp 792,447.75
Daftar Harga Satuan Upah dan Bahan

Kegiatan
Pekerjaan
Lokasi
Tahun Anggaran

No. Uraian Satuan Harga Satuan


1 2 3 4

A. UPAH
1 Pekerja OH Rp 85,000.00
2 Tukang Kayu OH Rp 130,000.00
3 Tukang Batu OH Rp 130,000.00
4 Tukang Cat OH Rp 110,348.00
5 Tukang Besi OH Rp 130,000.00
6 Tukang Pipa OH Rp 130,000.00
7 Tukang Listrik OH Rp 130,000.00
8 Tukang las kontruksi OH Rp 130,000.00
9 Tukang khusus alluminium OH Rp 130,000.00
10 Kepala Tukang OH Rp 150,000.00
11 Mandor OH Rp 110,000.00

B. BAHAN
1 Pasir Pasang M³ Rp 214,286.00
Pasir Beton M³ Rp 214,286.00
2
Kg Rp 153.06
3 Pasir Urug M³ Rp 151,429.00
4 Urugan Tanah Biasa M³ Rp 47,250.00
5 Semen portland Kg Rp 1,500.00

6 Semen Warna Kg Rp 24,150.00

7 Batu Gunung M² Rp 218,571.00


8 Batu Belah M³ Rp 218,571.00
9 Bata merah Bh Rp 750.00
10 Koral Beton M³ Rp 120,020.00
11 Kerikil M³ Rp 290,745.00
Kg Rp 161.53
12 Sirtu Kali M³ Rp 120,020.00
13 Dolken kayu 8-10 cm Btg Rp 8,715.00
14 Minyak bekisting Ltr Rp 9,240.00

15 Keramik 20 x 20 cm Bh Rp 1,600.00
16 Keramik 40 x 40 cm Bh Rp 6,250.00
17 Keramik 60 x 60 cm Bh Rp 20,500.00
17 Keramik 10 x 60 cm Bh Rp 6,000.00

18 Tripleks Tebal 3 mm Lbr Rp 72,200.00


19 Plywood tebal 9 mm Lbr Rp 98,000.00

20 Seng Gelombang Lbr Rp 47,000.00

21 Balok kayu kelas II M³ Rp 4,000,000.00


22 Balok kayu kelas III M³ Rp 3,200,000.00
23 Kayu Balok Kalapi Untuk Kusen M³ Rp 4,025,000.00
24 Papan Kayu Kelas I M³ Rp 5,775,000.00
25 Papan Kayu Kelas II M³ Rp 3,150,000.00
26 Papan Kayu Kelas III M³ Rp 3,500,000.00
27 Kayu papan 3/20 M³ Rp 3,500,000.00
28 Papan Kayu Kelas IV Untuk Begisting M³ Rp 2,100,000.00
29 Kayu balok 5/7 M³ Rp 1,200,000.00
30 Penjaga jarak bekisting/spacer Bh Rp 2,800.00

31 Kawat Beton Kg Rp 26,100.00


32 Angker/Baut/Plat Pengikat ut Kuda-Kuda/Konsol Kg Rp 23,100.00
33 Paku Campur Kg Rp 15,750.00
34 Paku 5 -10 cm Kg Rp 15,750.00
35 Paku 5 -12 cm Kg Rp 15,750.00
36 Paku Seng Kg Rp 28,750.00
37 Paku Biasa Kg Rp 19,800.00
38 Paku biasa 2” – 5” Kg Rp 19,800.00
39 Paku 2”-3” Kg Rp 19,800.00
40 Paku Tripleks Kg Rp 28,750.00
41 Sekrup fixer Bh Rp 3,700.00
42 Sealant Tube Rp 29,295.00
43 Besi Beton Kg Rp 19,367.00
44 Profil aluminium M' Rp 62,000.00
45 Rangka metal hollow 40.40.2 mm M' Rp 29,000.00
46 Besi baja IWF Kg Rp 145,100.00

47 Besi CNP Kg Rp 125,000.00


48 Sekrup SDS (Self Driling Screw) Bh Rp 3,700.00
49 Besi baja Siku 60 x 60 , 6 m Kg Rp 351,000.00
Rp 58,500.00
49 Plamur Kg Rp 19,320.00
50 Cat Tembok Avitex Kg Rp 21,735.00
51 Cat Kayu Glotex Kg Rp 59,850.00
52 Minyak Cat Ltr Rp 3,623.00
53 Thiner Kg Rp 30,000.00
54 Meni Ltr Rp 25,000.00

55 Ampelas Lbr Rp 6,500.00


56 Kuas Bh Rp 10,000.00

57 Gypsum board Lbr Rp 60,649.00


58 List kayu profil M' Rp 15,000.00

59 Atap Spundack M' Rp 67,850.00


60 Paku Spundack Kg Rp 40,000.00
61 Nok standar 40 x 18 cm M² Rp 75,000.00
Pipa PVC 3/4 inchi M' Rp 48,000.00
62 Pipa PVC 1/2 inchi M' Rp 5,300.00
63 Pipa PVC 2 1/2 inchi M' Rp 39,408.00
64 Pipa PVC 4 inchi M' Rp 85,256.00
65 Kloset Duduk KIA Unit Rp 1,700,000.00
66 Closet jongkok teraso Unit Rp 150,000.00
67 Urinoir Unit Rp 2,500,000.00
68 Wastafel Unit Rp 500,000.00
69 Floor drain Unit Rp 45,000.00
70 Kran Kuning dia 1/2" Bh Rp 38,750.00
71 Seal Tape/Isolasi Pipa Bh Rp 9,600.00
72 Air Ltr Rp 1,000.00
73 Mesin Jet Pump kap. 250 watt Bh Rp 950,000.00
74 Tangki Air 1000 Liter Bh Rp 2,400,000.00

75 Kaca Tebal 3 mm M² Rp 75,000.00


76 Kaca Tebal 5 mm M² Rp 93,240.00
77 Kaca Tebal 8 mm M² Rp 150,000.00
78 Kaca Temperred 12 mm M² Rp 460,000.00
79 Lem Kayu Kg Rp 25,000.00
80 Besi Strip 5 mm Kg Rp 16,400.00

81 Lampu PLC 14 Watt Bh Rp 18,900.00


82 Lampu PLC 20 Watt Bh Rp 23,000.00
83 Isolasi Bh Rp 5,000.00
Pipa listrik 5/8 inchi Btg Rp 15,000.00
84
M'
85 Kabel NYM 2x2,5 mm² M' Rp 8,680.00
86 Kabel NYM 3x2,5 mm² M' Rp 16,600.00
87 T dus Bh Rp 6,500.00
88 L bow Bh Rp 1,000.00
89 Las Dop Bh Rp 24,990.00
90 Klem Bh Rp 5,900.00
91 Mongkok Bh Rp 1,900.00
92 Pipa Union Untuk Kabel Ttk Rp 178,904.00
93 Saklar Tunggal Bh Rp 20,125.00
94 Saklar Ganda Bh Rp 23,000.00
95 Stop Kontak Bh Rp 17,250.00
96 Fitting Bh Rp 14,375.00
97 Lampu PLC 14 Watt Bh Rp 33,235.00
98 Box Panel PVC isi 3 MCB Bh Rp 150,000.00
99 MCB 6A Bh Rp 58,725.00
100 MCB 4A Bh Rp 58,725.00
Lampu TL 36 Watt bh Rp 75,000.00
Grendel pintu tanam stainless Bh Rp 50,000.00
101 Floor Hinges Set Rp 774,000.00
102 Overpanel Set Rp 205,000.00
103 Top Patch Fitting Set Rp 780,000.00
104 Bottom Patch Fitting Set Rp 300,000.00
105 Bottom Patch Lock + Cylinder Set Rp 165,000.00
106 Pull Handle Set Rp 150,000.00
107 Kunci tanam biasa Bh Rp 90,000.00
108 Kunci silinder Bh Rp 18,000.00
109 Kunci tanam KM Bh Rp 37,500.00
110 Engsel Pintu Bh Rp 34,500.00
111 Door Closer Bh Rp 120,500.00
112 Pintu PVC Kamar Mandi Bh Rp 199,900.00
1 PAGAR KELILING 548.42
JUMLAH 548.42 m'
2 BOWPLANK

vertikal
= 66.00 x 2.00
= 132.00
Alur Vertikal
= 301.13 433.13

horizontal
= 67.00 x 2.00
= 134.00
Alur Horizontal
= 330.39 464.39
JUMLAH 897.52 m'
3 Galian Tanah Pondasi Garis

Alur Vertikal (a)


= 301.13
Alur Horizontal (b)
= 330.39
Alur Keseluruhan (a+b)
= 631.52

Luas Penampang Galian


= p x l
= 0.95 x 1.10
= 1.05

Volume
= alur x luas penampang
= 631.52 x 1.05
= 659.93
659.93
JUMLAH 659.93 m3

4 Galian Poer Plat

jumlah poer plat


= 82.00 buah
volume galian
= p x l x t
= 1.40 x 1.50 x 1.95
= 4.10 m3

V. Total
= jumlah x Volume
= 82.00 x 4.10
= 335.79 m3 335.79
JUMLAH 335.79 m3

5 urugan kembali pondasi garis

volume
= 1/3 x Volume galian pondasi
= 1/3 x 659.93
= 219.98 219.98
JUMLAH 219.98 m3

6 Urugan Kembali Pondasi Poer Plat

jumlah poer plat


= 82.00 buah

Volume
= 1.91 m3

V. tot.
= jumlah x volume
= 82.00 x 1.91
= 156.52 m3 156.52
JUMLAH 156.52 m3

7 Urugan Pasir Bawah Pondasi

v = p x l x t
= 631.52 x 1.10 x 0.05
= 34.73 m3 34.73
JUMLAH 34.73 m3

8 Urugan Pasir Bawah Lantai

V = Luas x Tebal

Luas = 1434.61 + 757.08


= 2191.68
tebal = 0.05

V = 2191.68 x 0.05
= 109.58 m3 109.58
JUMLAH 109.58 m3

9 Pas. Pondasi Batu Gunung

v = Luas x Alur
= 0.63 x 659.93
= 417.41 m3 417.41
JUMLAH 417.41 m3

10 Pas. Batu Kosong

v = Luas x Alur
= 0.22 x 659.93
= 145.19 m3 145.19
JUMLAH 145.19 m3

11 Lantai Kerja

Jumlah Pondasi Poer Plat = 82 bh

V = P x L x T x Jumlah Pondasi
= 1.50 x 1.40 x 0.1 x 82
= 17.22 m3 17.22
JUMLAH 17.22 m3

12 Pondasi Poer Plat


- Beton
v = bdg datar + Bidang miring x Jumlah Kolom
= 0.468 + 0.08 x 82
= 45.24 m3 45.24
JUMLAH 45.24 m3
- Bekisting
v = Luas bdg Datar + Luas bdg Miring x Jumlah Kolom
= 1.50 + 1.1902 x 82
= 220.60 m2 220.60
JUMLAH 220.60 m2
- Besi
besi 16
- Lebar 140
= 1.18 x 4
= 4.71 m

= 2.68 x 5
= 13.41 m

= 1.17 x 8
= 9.39 m

- Lebar 150
= 1.28 x 4
= 5.14 m
= 2.88 x 5
= 14.39 m

= 1.27 x 8
= 10.19 m

- Panjang Total
= 57.22 m

- Koefisien Besi 16
= 1.587 kg/m

Berat Besi
= P x Koef. x Jumlah Kolom
= 57.22 x 1.587 x 82
= 4822.54 kg 4822.54
JUMLAH 4822.54 kg

13 Kolom Pedestal Poer Plat


- Beton
v = p x l x t x Jumlah Kolom
= 0.60 x 0.60 x 2.31 x 82
= 68.19 m3 68.19
JUMLAH 68.19 m3
- Bekisting
v = p x t x sisi x Jumlah Kolom
= 0.60 x 2.31 x 4 x 82
= 454.61 m2 454.61
JUMLAH 454.61 m2
- Besi Tulangan
besi 16
- p = Tinggi x jumlah besi
= 2.75 x 6
= 16.50 m
- Koefisien Besi 16
= 1.59 kg/m
Berat Besi
= P x Koef. x jumlah kolom
= 16.50 x 1.59 x 82
= 2147.21 kg 2147.21 kg
besi 19
- p = 2.75 x 14
= 38.50 m
- Koefisien Besi 19
= 2.22 kg/m
Berat Besi
= P x Koef. x jumlah kolom
= 38.50 x 2.22 x 82
= 85.59 kg 85.59 kg
- Besi Begel
besi 10
- p = 0.46 x 4 + 0.02 x 2
= 1.88
- Jumlah begel
= Tinggi ˸ jarak
= 2.75 : 0.1
= 27.50
= 28 bh

- Koefisien Besi 10
= 0.62 kg/m
Berat Besi
= P x Koef. x Jumlah begel x jumlah kolom
= 1.88 x 0.62 x 28.00 x 82
= 2676.22 kg 2676.22
JUMLAH 4909.01 kg

14 Sloef 25/50
- Beton
v = tinggi x lebar x Alur
= 0.50 x 0.25 x 872.77
= 109.10 m3 109.10
JUMLAH 109.10 m3
- Bekisting
v = Alur x t x sisi
= 872.77 x 0.50 x 2
= 872.77 m2 872.77
JUMLAH 872.77 m2
- Besi Tulangan
besi 16
- p = Alur x jumlah
= 872.77 x 10
= 8727.67 m
- Koefisien Besi 16
= 1.587 kg/m
Berat Besi
= P x Koef.
= 8727.67 x 1.587
= 13850.81 kg 13850.81 kg
besi 12
- p = Alur x jumlah
= 872.77 x 2
= 1745.53 m
- Koefisien Besi 12
= 0.89 kg/m
Berat Besi
= P x Koef.
= 1745.53 x 0.89
= 1553.52 kg 1553.52 kg
- Besi Begel
besi 8 jarak 10
- p = panjang x sisi + lengkung x 2
= 1.34 x 4 + 0.02 x 2
= 5.40 m

- Jumlah begel = Alur ˸ jarak


= 436.38 : 0.1
= 4363.83
= 4364 bh

- Koefisien Besi 8 = 0.40 kg/m

Berat Besi = P x Koef. x Jumlah begel


= 5.40 x 0.40 x 4364
= 9426.24 kg 9426.24 kg

besi 8 jarak 20
- p = panjang x sisi + lengkung x 2
= 1.34 x 4 + 0.02 x 2
= 5.40 m
- Jumlah begel
= Alur ˸ jarak
= 436.38 : 0.2
= 2181.92
= 2182 bh

- Koefisien Besi 8
= 0.40 kg/m
Berat Besi
= P x Koef. x Jumlah begel
= 5.40 x 0.40 x 2182
= 4713.12 kg 4713.12
JUMLAH 29543.69 kg

15 Kolom lt 1
- Kolom Utama
- Beton
Jumlah = 82.00 bh
V = p x l x t x Jumlah
= 0.60 x 0.6 x 4.1 x 82.00
= 121.03 m3 121.03
JUMLAH 121.03 m3
- Bekisting
Jumlah = 82.00 bh
v = l x t x sisi x Jumlah
= 0.60 x 4.10 x 4 x 82.00
= 806.88 m2 806.88
JUMLAH 806.88 m2
- Besi Tulangan
besi 16
- p = Tinggi x jumlah
= 4.10 x 6
= 24.60 m
- Koefisien Besi 16
= 1.587 kg/m
Berat Besi
= P x Koef. x jumlah kolom
= 24.60 x 1.587 x 82
= 3201.30 kg 3201.30 kg
besi 19
- p = Tinggi x jumlah
= 4.10 x 14
= 57.40 m
- Koefisien Besi 19
= 2.22 kg/m
Berat Besi
= P x Koef. x jumlah kolom
= 57.40 x 2.22 x 82
= 10463.2164 kg 10463.22 kg
- Besi Begel
besi 10
- p = 0.47 x 4 + 0.02 x 2
= 1.92
- Jumlah begel
= Tinggi ˸ jarak
= 4.10 : 0.1
= 41.00
= 41 bh
- Koefisien Besi 10
= 0.62 kg/m

Berat Besi
= P x Koef. x Jumlah begel x jumlah kolom
= 1.92 x 0.62 x 41.00 x 82
= 4002.12 kg 4002.12
JUMLAH 17666.64 kg

16 Kolom lt 1
- Kolom Praktis
a Beton
Jumlah = 132.00 bh
V = p x l x t x Jumlah
= 0.15 x 0.15 x 3.6 x 132.00
= 10.69 m3 10.69
JUMLAH 10.69 m3
b Bekisting
Jumlah = 132.00 bh
v = l x t x sisi x Jumlah
= 0.15 x 3.60 x 4 x 132.00
= 285.12 m2 285.12
JUMLAH 285.12 m2
c Besi Tulangan
besi 12
- Panjang = Tinggi x jumlah
= 3.60 x 4
= 14.40 m
- Koefisien Besi 12
= 0.89 kg/m
- Berat Besi
= P x Koef. x jumlah kolom
= 14.40 x 0.89 x 132.00
= 1691.71 kg 1691.71 kg
- Besi Begel
besi 8
- p = 0.11 x 4 + 0.02 x 2
= 0.48
- Jumlah begel
= Tinggi ˸ jarak
= 3.60 : 0.2
= 18.00
= 18 bh
- Koefisien Besi 8
= 0.40 kg/m

Berat Besi
= P x Koef. x Jumlah begel x jumlah kolom
= 0.48 x 0.40 x 18.00 x 132.00
= 456.19 kg 456.19
JUMLAH 2147.90 kg

17 Balok Latey
- Beton
v = tinggi x lebar x Alur
= 0.15 x 0.15 x 177.60
= 4.00 m3 4.00
JUMLAH 4.00 m3
- Bekisting
v = Alur x t x sisi
= 177.60 x 0.15 x 2
= 53.28 m2 53.28
JUMLAH 53.28 m2
- Besi Tulangan
besi 12
- p = Alur x jumlah
= 177.60 x 4
= 710.40 kg
- Koefisien Besi 12
= 0.89 kg/m
Berat Besi
= P x Koef.
= 710.40 x 0.89
= 632.26 kg 632.26 kg
- Besi Begel
besi 8 jarak 10
- p = panjang x sisi + lengkung x 2
= 0.11 x 4 + 0.02 x 2
= 0.48 m
- Jumlah begel = Alur ˸ jarak
= 88.80 : 0.1
= 888.00
= 888 bh
- Koefisien Besi 8 = 0.40 kg/m

Berat Besi = P x Koef. x Jumlah begel


= 0.48 x 0.40 x 888
= 170.50 kg 170.50 kg

besi 8 jarak 15
- p = panjang x sisi + lengkung x 2
= 0.11 x 4 + 0.02 x 2
= 0.48 m
- Jumlah begel
= Alur ˸ jarak
= 88.80 : 0.15
= 592.00
= 592 bh
- Koefisien Besi 8 = 0.40 kg/m
- Berat Besi = P x Koef. x Jumlah begel
= 0.48 x 0.40 x 592
= 113.66 kg 113.66
JUMLAH 916.42 kg

18 Rabat Bawah Lantai

V = Luas x Tebal

Luas = 1434.61 + 757.08


= 2191.68 m2
tebal = 0.06

V = 2191.68 x 0.06
= 131.50 m3 131.50
JUMLAH 131.50 m3

19 Tangga
- Beton
- anak tangga
Jumlah AT = 22.00 bh
panjang = 2.15 m
tinggi = 0.18 m
Lebar = 0.30 m
V = Lebar x tinggi : 2 x panjang
= 0.30 x 0.18 : 2 x 2.15
= 0.06 m3

V tot. = V x Jumlah AT
= 0.06 x 22.00
= 1.28 m3 1.28 m3

- Plat
V1 = Panjang x Lebar x Tebal Plat
= 4.55 x 2.2 x 0.1
= 1.001 m3
V2 = Panjang x Lebar x Tebal Plat
= 1.75 x 2.2 x 0.1
= 0.385 m3
V3 = Panjang x Lebar x Tebal Plat
= 4.55 x 2.2 x 0.1
= 1.001 m3
V tot. = v1 + v2 + v2
= 1.00 + 0.385 + 1.001
= 2.38700 m3 2.39
JUMLAH 3.66 m3
- Bekisting
- anak tangga
V1 = p x t x jumlah AT
= 2.20 x 0.3 x 14
= 9.24 m2
V2 = p x t x jumlah AT
= 2.15 x 0.3 x 8
= 5.16 m2

V tot. = v1 + v2
= 9.24 + 5.16
= 14.40 m2 14.40
- plat
v = 27.21 m2 27.21
JUMLAH 41.61 m2
- Pembesian
- anak tangga
Besi 12
- v = panjang x jumlah AT
= 0.77 x 22
= 16.94 m
- jumlah besi = panjang : jarak
= 2.20 : 0.15
= 14.67
= 15 bh
- Koefisien Besi 12 = 0.89 kg/m

- Berat Besi = P x Koef. x Jumlah Besi


= 16.94 x 0.89 x 15
= 226.15 kg 226.15 kg
- Plat
Besi 16
jumlah besi (1a) = 2.70 : 0.15
= 18.00 bh
= 18 bh
jumlah besi (2a) = 5.01 : 0.15
= 33.37 bh
= 34 bh
jumlah besi (1b) = 2.64 : 0.15
= 17.60 bh
= 18 bh
jumlah besi (2b) = 4.26 : 0.15
= 28.40 bh
= 29 bh
V1 = panjang besi x jumlah besi (1a)
= 5.01 x 18
= 90.11 m 180.22419 m
V2 = panjang besi x jumlah besi (2a)
= 2.70 x 34
= 91.80 m 183.60000 m
V3 = panjang besi x jumlah besi (1b)
= 4.26 x 18
= 76.68 m 153.36000 m
V4 = panjang besi x jumlah besi (2b)
= 2.64 x 29
= 76.56 m 153.12000 m
670.30419 m
- Koefisien Besi 16 = 1.587 kg/m

- Berat Besi = P x Koef.


= 670.30 x 1.587
= 1063.77 kg 1063.77 kg
JUMLAH 1289.92 kg

20 Kusen Pintu
- Set
- P1 = 1.00 bh 1.00 bh
- P5 = 17.00 bh 17.00 bh
- Kayu
- P2
Jumlah = 5.00 bh
volume = Panjang x Lebar x Tinggi
= 6.02 x 0.05 x 0.15
= 0.05 m3 0.23 m3
- P3
Jumlah = 28.00 bh
volume = Panjang x Lebar x Tinggi
= 5.60 x 0.05 x 0.15
= 0.04 m3 1.18 m3
JUMLAH 1.40 m3
- Aluminium
- P4
Jumlah = 17.00 bh
volume = 2.00 x tinggi + Lebar
= 2.00 x 2.15 + 2.1
= 6.40 m 108.80 m

21 Daun Pintu
- Kayu
- P2
Jumlah = 5.00 bh
volume = tinggi x lebar
= 2.21 x 1.64
= 3.62 m2 18.12 m2
- P3
Jumlah = 28.00 bh
volume = tinggi x lebar
= 2.21 x 1.12
= 2.48 m2 69.31 m2
- P4
Jumlah = 4.00 bh
volume = tinggi x lebar
= 2.21 x 0.82
= 1.81 m2 7.25 m2
JUMLAH 94.68 m2

22 Kusen Jendela
- J2
Jumlah = 2.00 bh
volume = 13.65 + 1.9 + 4.25
= 19.80 m 39.60 m
- J3
Jumlah = 6.00 bh
volume = 6.90 + 1.9 + 1.7
= 10.50 m 63.00 m
- J4
Jumlah = 2.00 bh
volume = 4.65 + 1.9 + 0.85
= 7.40 m 14.80 m
JUMLAH 117.40 m

23 Kusen Ventilasi
- V1
Jumlah = 10.00 bh
volume = 0.80 + 1
= 1.80 m 18.00 m
JUMLAH 150.20 m

24 Pas Bata 1:3


Volume = Alur x Tinggi - Lubangan
= 114.90 x 3.7 - 29.4125
= 395.71 m2 395.71 m2
JUMLAH 395.71 m2

25 Pas Bata 1:5


Volume = Alur x Tinggi - Lubangan
= 114.90 x 3.7 - 27.4125
= 397.71 m2 397.71 m2
JUMLAH 397.71 m2

26 Pas Plesteran 1:3


Volume = Pas Bata 1:3 x 2
= 395.71 x 2
= 791.42 m2 791.42 m2
JUMLAH 791.42 m2

27 Pas Plesteran 1:5


Volume = Pas Bata 1:5 x 2
= 397.71 x 2
= 795.42 m2 795.42 m2
JUMLAH 795.42 m2

28 Pekerjaan Acian
Volume = Pas Bata 1:3 + Pas Bata 1:5
= 791.42 + 795.42013
= 1586.84 m2 1586.84 m2
JUMLAH 1586.84 m2

29 Pekerjaan Pengecetan Tembok


Volume = Pekerjaan Acian
= 1586.84
= 1586.84 m2 1586.84 m2
JUMLAH 1586.84 m2

30 Pekerjaan Pengecetan Kayu


- Kusen
- P2
Jumlah = 5.00 bh
Volume = Alur Kusen x Tebal x Sisi
= 6.22 x 0.05 x 2
= 0.62 m2 3.11 m2
- P3
Jumlah = 28.00 bh
Volume = Alur Kusen x Tebal x Sisi
= 5.70 x 0.05 x 2
= 0.57 m2 15.96 m2

- Daun Pintu
- P2
Jumlah = 5.00 bh
Volume = p x t x sisi
= 1.62 x 2.22 x 2
= 7.19 m2 35.96 m2
- P3
Jumlah = 28.00 bh
Volume = p x t x sisi
= 1.10 x 2.22 x 2
= 4.88 m2 136.75 m2
- P4
Jumlah = 4.00 bh
Volume = p x t x sisi
= 0.80 x 2.12 x 2
= 3.39 m2 13.57 m2
JUMLAH 205.35 m2

31 Pekerjaan Tegel
- Tegel 60 x 60
Volume = Luasan tegel
= 2072.91 - 12.24 + 190.33 + 141.61638165288
= 2392.62 m2 2392.62 m2
- Tegel 40 x 40
Volume = Luasan tegel
= 39.76
= 39.76 m2 39.76 m2
- Tegel 20 x 20
Volume = Luasan tegel
= 53.32
= 53.32 m2 53.32 m2
- Dinding Tegel 20x20
Volume = alur x tinggi - lubangan
= 75.60 x 2.67 - 27.4125
= 174.43 m2 174.43 m2
- Plint 10x 40
Volume = alur
= 735.01 + 29.45 + 81.6
= 846.06 m 846.06 m

32 Plafond
- Rangka
Volume = Luasan - Lubangan
= 2191.44 - 60.84
= 2130.60 m2 2130.60 m2
- Plafond
Volume = Luasan - Lubangan
= 2191.44 - 60.84
= 2130.60 m2 2130.60 m2
- List Plafond
Volume = Alur Plafond
= 1137.6272294478 m' 1137.63 m'

33 Kaca
- J2
Volume = p x l x Jumlah Kaca x Jumlah Kusen
= 0.68 x 0.38 x 12 x 2
= 6.20 m2 6.20 m2
- J3
Volume = p x l x Jumlah Kaca x Jumlah Kusen
= 0.68 x 0.38 x 6 x 6
= 9.30 m2 9.30 m2
- J4
Volume = p x l x Jumlah Kaca x Jumlah Kusen
= 0.68 x 0.38 x 4 x 2
= 2.07 m2 2.07 m2
- Ventilasi Kamar Mandi
Volume = p x l x Jumlah Kaca x Jumlah Kusen
= 0.42 x 0.32 x 1 x 10
= 1.34 m2 1.34 m2
JUMLAH 18.92 m2

B LANTAI 2
1 Balok Lantai
a. Balok Induk
1 Beton
Volume = tinggi x lebar x Alur
= 0.50 x 0.25 x 859.26
= 107.41 m3 107.41
JUMLAH 107.41 m3
2 Bekisting
Volume = Alur x t x sisi x Alas
= 859.26 x 0.50 x 2 x 0.25
= 214.82 m2 214.82
JUMLAH 214.82 m2
3 Besi Tulangan
besi 16
- p = Alur x jumlah
= 859.26 x 10
= 8592.61 m

- Koefisien Besi 16 = 1.587 kg/m

Berat Besi = P x Koef.


= 8592.61 x 1.587
= 13636.47 kg 13636.47 kg
besi 12
- p = Alur x jumlah
= 859.26 x 2
= 1718.52 m

- Koefisien Besi 12 = 0.89 kg/m

Berat Besi = P x Koef.


= 1718.52 x 0.89
= 1529.48 kg 1529.48 kg
- Besi Begel
besi 8 jarak 10
- Volume = panjang + lengkung
= 1.34 + 0.04
= 1.38 m

- Jumlah begel = Alur ˸ jarak


= 429.63 : 0.1
= 4296.31
= 4297 bh

- Koefisien Besi 8 = 0.40 kg/m

Berat Besi = P x Koef. x Jumlah begel


= 1.38 x 0.40 x 4297
= 2371.94 kg 2371.94 kg

besi 8 jarak 20
- p = panjang + lengkung
= 1.34 + 0.04
= 1.38 m
- Jumlah begel
= Alur ˸ jarak
= 429.63 : 0.2
= 2148.15
= 2149 bh

- Koefisien Besi 8 = 0.40 kg/m

Berat Besi = P x Koef. x Jumlah begel


= 1.38 x 0.40 x 2149
= 1186.25 kg 1186.25
JUMLAH 18724.15 kg

b. Balok Anak
1 Beton
Volume = tinggi x lebar x Alur
= 0.40 x 0.25 x 914.89
= 91.49 m3 91.49
JUMLAH 91.49 m3
2 Bekisting
Volume = Alur x t x sisi x Alas
= 914.89 x 0.40 x 2 x 0.25
= 182.98 m2 182.98
JUMLAH 182.98 m2
3 Besi Tulangan
besi 16
- p = Alur x jumlah
= 914.89 x 9
= 8233.97 kg

- Koefisien Besi 16 = 1.587 kg/m

Berat Besi = P x Koef.


= 8233.97 x 1.587
= 13067.30 kg 13067.30 kg
besi 12
- p = Alur x jumlah
= 914.89 x 2
= 1829.77 m

- Koefisien Besi 12 = 0.89 kg/m

Berat Besi = P x Koef.


= 1829.77 x 0.89
= 1628.50 kg 1628.50 kg
- Besi Begel
besi 8 jarak 10
- p = panjang + lengkung
= 1.34 + 0.04
= 1.38 m

- Jumlah begel = Alur ˸ jarak


= 457.44 : 0.1
= 4574.43
= 4575 bh

- Koefisien Besi 8 = 0.40 kg/m

Berat Besi = P x Koef. x Jumlah begel


= 1.38 x 0.40 x 4575
= 2525.40 kg 2525.40 kg

besi 8 jarak 20
- p = panjang + lengkung
= 1.34 + 0.04
= 1.38 m
- Jumlah begel
= Alur ˸ jarak
= 457.44 : 0.2
= 2287.21
= 2288 bh

- Koefisien Besi 8 = 0.40 kg/m

Berat Besi = P x Koef. x Jumlah begel


= 1.38 x 0.40 x 2288
= 1262.98 kg 1262.98
JUMLAH 18484.17 kg

2 Plat Lantai 2
a Beton
volume = Luas x tebal - lubangan
= 2247.24 x 0.12 - 98.621874993705
= 171.05 m3 171.05
JUMLAH 171.05 m3
b Bekisting
volume = Luasan
= 1974.31 m2 1974.31
JUMLAH 1974.31 m2
c Besi
Besi 10
- modul 6x6 = 54.00 bh
Bawah 2 Lapis
Panjang = p + Lengkungan x jumlah besi x 2
= 6.00 + 0.06 x 40 x 2
= 484.80 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 484.80 x 54.00 x 0.62
= 16231.10 kg 16231.10 kg
Atas 2 Lapis
Panjang FULL = p + Lengkungan x jumlah besi x 2
= 6.00 + 0.06 x 20 x 2
= 242.40 m

Panjang TURUN = p + lengkungan x jumlah besi x 2


= 6.03 + 0.6 x 16 x 2
= 212.28 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 454.68 x 54.00 x 0.62
= 15222.53 kg 15222.53 kg
- modul 4.7x6.18 = 2.00 bh
Bawah 2 Lapis
Panjang 1 = p + Lengkungan x jumlah besi
= 6.18 + 0.06 x 31
= 193.44 m

Panjang 2 = p + Lengkungan x jumlah besi


= 4.70 + 0.06 x 41
= 195.16 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 388.60 x 2.00 x 0.62
= 481.86 kg 481.86 kg
Atas 2 Lapis
Panjang FULL 1 = p + Lengkungan x jumlah besi
= 6.00 + 0.06 x 20
= 121.20 m
Panjang FULL 2 = p + Lengkungan x jumlah besi
= 4.70 + 0.06 x 21
= 99.96 m

Panjang TURUN 1 = p + lengkungan x jumlah besi


= 6.03 + 0.6 x 15
= 99.50 m
Panjang TURUN 2 = p + lengkungan x jumlah besi
= 4.74 + 0.6 x 9
= 48.02 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 368.69 x 2.00 x 0.62
= 457.17 kg 457.17 kg
- modul 3x6 = 2.00 bh
Bawah 2 Lapis
Panjang 1 = p + Lengkungan x jumlah besi
= 6.00 + 0.06 x 20
= 121.20 m

Panjang 2 = p + Lengkungan x jumlah besi


= 3.00 + 0.06 x 40
= 122.40 m
Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 243.60 x 2.00 x 0.62
= 302.06 kg 302.06 kg
Atas 2 Lapis
Panjang FULL 1 = p + Lengkungan x jumlah besi
= 6.00 + 0.06 x 10
= 60.60 m
Panjang FULL 2 = p + Lengkungan x jumlah besi
= 3.00 + 0.06 x 20
= 61.20 m

Panjang TURUN 1 = p + lengkungan x jumlah besi


= 6.03 + 0.6 x 7
= 46.44 m
Panjang TURUN 2 = p + lengkungan x jumlah besi
= 3.03 + 0.6 x 15
= 54.50 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 222.74 x 2.00 x 0.62
= 276.20 kg 276.20 kg
- modul 4x6 = 2.00 bh
Bawah 2 Lapis
Panjang 1 = p + Lengkungan x jumlah besi
= 6.00 + 0.06 x 27
= 161.60 m

Panjang 2 = p + Lengkungan x jumlah besi


= 4.00 + 0.06 x 40
= 162.40 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 324.00 x 2.00 x 0.62
= 401.76 kg 401.76 kg
Atas 2 Lapis
Panjang FULL 1 = p + Lengkungan x jumlah besi
= 6.00 + 0.06 x 20
= 121.20 m
Panjang FULL 2 = p + Lengkungan x jumlah besi
= 4.00 + 0.06 x 20
= 81.20 m

Panjang TURUN 1 = p + lengkungan x jumlah besi


= 6.03 + 0.6 x 5
= 33.17 m
Panjang TURUN 2 = p + lengkungan x jumlah besi
= 4.03 + 0.6 x 15
= 69.50 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 305.07 x 2.00 x 0.62
= 378.29 kg 378.29 kg
- modul 3.18x4 = 2.00 bh
Bawah 2 Lapis
Panjang 1 = p + Lengkungan x jumlah besi
= 3.18 + 0.06 x 27
= 86.40 m

Panjang 2 = p + Lengkungan x jumlah besi


= 4.00 + 0.06 x 21
= 86.07 m

Koefisien Besi 10 = 0.62 kg/m


Berat = Panjang x Jmlh Modul x Koefisien
= 172.47 x 2.00 x 0.62
= 213.87 kg 213.87 kg
Atas 2 Lapis
Panjang 1 = p + Lengkungan x jumlah besi
= 3.18 + 0.06 x 27
= 86.40 m

Panjang 2 = p + Lengkungan x jumlah besi


= 4.00 + 0.06 x 21
= 86.07 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 172.47 x 2.00 x 0.62
= 213.87 kg 213.87 kg
- modul 2.47x6 = 2.00 bh
Bawah 2 Lapis
Panjang 1 = p + Lengkungan x jumlah besi
= 2.47 + 0.06 x 40
= 101.20 m

Panjang 2 = p + Lengkungan x jumlah besi


= 6.00 + 0.06 x 16
= 99.79 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 200.99 x 2.00 x 0.62
= 249.23 kg 249.23 kg
Atas 2 Lapis
Panjang 1 = p + Lengkungan x jumlah besi
= 2.47 + 0.06 x 40
= 101.20 m

Panjang 2 = p + Lengkungan x jumlah besi


= 6.00 + 0.06 x 16
= 99.79 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 200.99 x 2.00 x 0.62
= 249.23 kg 249.23 kg
JUMLAH 34677.16 kg

3 Plat Teras
a Beton
Volume = Luasan x Tebal
= 269.80 x 0.12
= 32.38 m3 32.38
JUMLAH 32.38 m3
b Bekisting
Volume = Luasan + Penahan Luar
= 254.62 + 7.2
= 261.80 m2 261.80
JUMLAH 261.80 m2
c Besi
Besi 10
Bawah 2 Lapis
Panjang = P + Lengkungan x Jumlah Besi x 2
= 1759.26 + 0.06 x 150 x 2
= 3536.52 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Koefisien


= 3536.52 x 0.62
= 2192.64 kg 2192.64 kg
Atas 2 Lapis
Panjang = P + Lengkungan x Jumlah Besi x 2
= 1763.67 + 0.06 x 283 x 2
= 3561.30 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Koefisien


= 3561.30 x 0.62
= 2208.00 kg 2208.00 kg
JUMLAH 4400.64 kg

4 Balok Latey
- Beton
v = tinggi x lebar x Alur
= 0.15 x 0.15 x 182.66
= 4.11 m3 4.11
JUMLAH 4.11 m3
- Bekisting
v = Alur x t x sisi
= 182.66 x 0.15 x 2
= 54.80 m2 54.80
JUMLAH 54.80 m2
- Besi Tulangan
besi 12
- p = Alur x jumlah besi
= 182.66 x 4
= 730.65 kg
- Koefisien Besi 12
= 0.89 kg/m
Berat Besi
= P x Koef.
= 730.65 x 0.89
= 650.28 kg 650.28 kg
- Besi Begel
besi 8 jarak 10
- p = panjang x sisi + lengkung x 2
= 0.11 x 4 + 0.02 x 2
= 0.48 m
- Jumlah begel = Alur ˸ jarak
= 91.33 : 0.1
= 913.31
= 913 bh
- Koefisien Besi 8 = 0.40 kg/m

Berat Besi = P x Koef. x Jumlah begel


= 0.48 x 0.40 x 913
= 175.30 kg 175.30 kg

besi 8 jarak 15
- p = panjang x sisi + lengkung x 2
= 0.11 x 4 + 0.02 x 2
= 0.48 m
- Jumlah begel
= Alur ˸ jarak
= 91.33 : 0.15
= 608.88
= 609 bh
- Koefisien Besi 8 = 0.40 kg/m
- Berat Besi = P x Koef. x Jumlah begel
= 0.48 x 0.40 x 609
= 116.93 kg 116.93
JUMLAH 942.50 kg

5 Kolom lt 2
- Kolom Utama
- Beton
Jumlah = 82.00 bh
V = p x l x t x Jumlah
= 0.60 x 0.6 x 4.00 x 48.00
= 69.12 m3 69.12
JUMLAH 69.12 m3
- Bekisting
Jumlah = 82.00 bh
v = l x t x sisi x Jumlah
= 0.60 x 4.00 x 4 x 48.00
= 460.80 m2 460.80
JUMLAH 460.80 m2
- Besi Tulangan
besi 16
- p = Tinggi x jumlah
= 4.00 x 6
= 24.00 m
- Koefisien Besi 16
= 1.578 kg/m
Berat Besi
= P x Koef. x jumlah kolom
= 24.00 x 1.578 x 48.00
= 1817.86 kg 1817.86 kg
besi 19
- p = Tinggi x jumlah
= 4.00 x 14
= 56.00 m
- Koefisien Besi 19
= 2.22 kg/m
Berat Besi
= P x Koef. x jumlah kolom
= 56.00 x 2.22 x 48.00
= 5975.424 kg 5975.42 kg
- Besi Begel
besi 10
- p = 0.47 x 4 + 0.02 x 2
= 1.92
- Jumlah begel
= Tinggi ˸ jarak
= 4.00 : 0.1
= 40.00
= 40 bh
- Koefisien Besi 10
= 0.62 kg/m

Berat Besi
= P x Koef. x Jumlah begel x jumlah kolom
= 1.92 x 0.62 x 40.00 x 48
= 2285.57 kg 2285.57
JUMLAH 10078.85 kg

6 Kolom lt 2
- Kolom Praktis
a Beton
Jumlah = 138.00 bh
V = p x l x t x Jumlah
= 0.15 x 0.15 x 3.6 x 138.00
= 11.18 m3 11.18
JUMLAH 11.18 m3
b Bekisting
Jumlah = 138.00 bh
v = l x t x sisi x Jumlah
= 0.15 x 3.60 x 4 x 138.00
= 298.08 m2 298.08
JUMLAH 298.08 m2
c Besi Tulangan
besi 12
- Panjang = Tinggi x jumlah
= 3.60 x 4
= 14.40 m
- Koefisien Besi 12
= 0.89 kg/m
- Berat Besi
= P x Koef. x jumlah kolom
= 14.40 x 0.89 x 138.00
= 1768.61 kg 1768.61 kg
- Besi Begel
besi 8
- p = 0.11 x 4 + 0.02 x 2
= 0.48
- Jumlah begel
= Tinggi ˸ jarak
= 3.60 : 0.2
= 18.00
= 18 bh
- Koefisien Besi 8
= 0.40 kg/m

Berat Besi
= P x Koef. x Jumlah begel x jumlah kolom
= 0.48 x 0.40 x 18.00 x 138.00
= 476.93 kg 476.93
JUMLAH 2245.54 kg

7 Kusen Pintu
- Set
- P5 = 16.00 bh 16.00 bh
- Kayu
- P2 s
Jumlah = 6.00 bh
volume = Panjang x Lebar x Tinggi
= 6.02 x 0.05 x 0.15
= 0.05 m3 0.27 m3
- P3
Jumlah = 18.00 bh
volume = Panjang x Lebar x Tinggi
= 5.60 x 0.05 x 0.15
= 0.04 m3 0.76 m3
JUMLAH 1.03 m3
- Aluminium
- P4
Jumlah = 2.00 bh
volume = 2.00 x tinggi + Lebar
= 2.00 x 2.15 + 2.1
= 6.40 m 12.80 m

8 Daun Pintu
- Kayu
- P2
Jumlah = 6.00 bh
volume = tinggi x lebar
= 2.21 x 1.64
= 3.62 m2 21.75 m2
- P3
Jumlah = 18.00 bh
volume = tinggi x lebar
= 2.21 x 1.12
= 2.48 m2 44.55 m2
- P4
Jumlah = 2.00 bh
volume = tinggi x lebar
= 2.21 x 0.82
= 1.81 m2 3.62 m2
JUMLAH 69.92 m2

9 Kusen Jendela Aluminium


- J1
Jumlah = 4.00 bh
volume = 58.52 m 234.08 m
- J3
Jumlah = 3.00 bh
volume = 6.90 + 1.9 + 1.7
= 10.50 m 31.50 m
- J4
Jumlah = 1.00 bh
volume = 4.65 + 1.9 + 0.85
= 7.40 m 7.40 m
JUMLAH 272.98 m
10 Kusen Ventilasi
- V1
Jumlah = 7.00 bh
volume = 0.80 + 1
= 1.80 m 12.60 m
JUMLAH 292.98 m

11 Pas Bata 1:3


Volume = Alur x Tinggi - Lubangan
= 105.43 x 3.7 - 27.2
= 362.89 m2 362.89 m2
JUMLAH 362.89 m2

12 Pas Bata 1:5


Volume = Alur x Tinggi - Lubangan
= 348.87 x 3.7 - 124.8775
= 1165.95 m2 1165.95 m2
JUMLAH 1165.95 m2

13 Pas Plesteran 1:3


Volume = Pas Bata 1:3 x 2
= 362.89 x 2
= 725.78 m2 725.78 m2
JUMLAH 725.78 m2

14 Pas Plesteran 1:5


Volume = Pas Bata 1:5 x 2
= 1165.95 x 2
= 2331.90 m2 2331.90 m2
JUMLAH 2331.90 m2

15 Pekerjaan Acian
Volume = Pas Bata 1:3 + Pas Bata 1:5
= 725.78 + 2331.90475
= 3057.69 m2 3057.69 m2
JUMLAH 3057.69 m2

16 Pekerjaan Pengecetan Tembok


Volume = Pekerjaan Acian
= 3057.69
= 3057.69 m2 3057.69 m2
JUMLAH 3057.69 m2

17 Pekerjaan Pengecetan Kayu


- Kusen
- P2
Jumlah = 6.00 bh
Volume = Alur Kusen x Tebal x Sisi
= 6.22 x 0.05 x 2
= 0.62 m2 3.73 m2
- P3
Jumlah = 18.00 bh
Volume = Alur Kusen x Tebal x Sisi
= 5.70 x 0.05 x 2
= 0.57 m2 10.26 m2

- Daun Pintu
- P2
Jumlah = 6.00 bh
Volume = p x t x sisi
= 1.62 x 2.22 x 2
= 7.19 m2 43.16 m2
- P3
Jumlah = 18.00 bh
Volume = p x t x sisi
= 1.10 x 2.22 x 2
= 4.88 m2 87.91 m2
- P4
Jumlah = 2.00 bh
Volume = p x t x sisi
= 0.80 x 2.12 x 2
= 3.39 m2 6.78 m2
JUMLAH 151.84 m2

18 Pekerjaan Tegel
- Tegel 60 x 60
Volume = Luasan tegel
= 1996.14 + 44.357519737235 + 17.28 + 9.8
= 2067.57 m2 2067.57 m2
- Tegel 40 x 40
Volume = Luasan tegel
= 40.00
= 40.00 m2 40.00 m2
- Tegel 20 x 20
Volume = Luasan tegel
= 51.03
= 51.03 m2 51.03 m2
- Dinding Tegel 20x20
Volume = alur x tinggi - lubangan
= 115.26 x 2.67 - 25.8
= 281.94 m2 281.94 m2
- Plint 10x 40
Volume = alur
= 643.60 + 172.58 + 55.2
= 871.38 m 871.38 m

19 Plafond
- Rangka
Volume = Luasan
= 2174.73
= 2174.73 m2 2174.73 m2
- Plafond
Volume = Luasan
= 2174.73
= 2174.73 m2 2174.73 m2
- List Plafond
Volume = Alur Plafond
= 1098.6 m' 1098.60 m'

20 Kaca
- J1
Volume = Luasan x Jumlah Kusen
= 18.67 x 2
= 37.34 m2 37.34 m2
- J3
Volume = p x l x Jumlah Kaca x Jumlah Kusen
= 0.68 x 0.38 x 6 x 3
= 4.65 m2 4.65 m2
- J4
Volume = p x l x Jumlah Kaca x Jumlah Kusen
= 0.68 x 0.38 x 4 x 1
= 1.03 m2 1.03 m2
- Ventilasi Kamar Mandi
Volume = p x l x Jumlah Kaca x Jumlah Kusen
= 0.42 x 0.32 x 1 x 7
= 0.94 m2 0.94 m2
JUMLAH 43.97 m2

B TOP FLOOR

1 Balok Anak
1 Beton
Volume = tinggi x lebar x Alur
= 0.40 x 0.25 x 1231.02
= 123.10 m3 123.10
JUMLAH 123.10 m3
2 Bekisting
Volume = Alur x t x sisi x Alas
= 1231.02 x 0.40 x 2 x 0.25
= 246.20 m2 246.20
JUMLAH 246.20 m2
3 Besi Tulangan
besi 16
- p = Alur x jumlah
= 1231.02 x 9
= 11079.19 kg

- Koefisien Besi 16 = 1.587 kg/m

Berat Besi = P x Koef.


= 11079.19 x 1.587
= 17582.68 kg 17582.68 kg
besi 12
- p = Alur x jumlah
= 1231.02 x 2
= 2462.04 m

- Koefisien Besi 12 = 0.89 kg/m

Berat Besi = P x Koef.


= 2462.04 x 0.89
= 2191.22 kg 2191.22 kg
- Besi Begel
besi 8 jarak 10
- p = panjang + lengkung
= 1.34 + 0.04
= 1.38 m

- Jumlah begel = Alur ˸ jarak


= 615.51 : 0.1
= 6155.11
= 6156 bh

- Koefisien Besi 8 = 0.40 kg/m

Berat Besi = P x Koef. x Jumlah begel


= 1.38 x 0.40 x 6156
= 3398.11 kg 3398.11 kg

besi 8 jarak 20
- p = panjang + lengkung
= 1.34 + 0.04
= 1.38 m
- Jumlah begel
= Alur ˸ jarak
= 615.51 : 0.2
= 3077.55
= 3078 bh

- Koefisien Besi 8 = 0.40 kg/m

Berat Besi = P x Koef. x Jumlah begel


= 1.38 x 0.40 x 3078
= 1699.06 kg 1699.06
JUMLAH 24871.06 kg

2 Kolom Top Floor


- Kolom Utama
- Beton
Jumlah = 34.00 bh
V = p x l x t x Jumlah
= 0.60 x 0.6 x 0.47 x 34.00
= 5.75 m3 5.75
JUMLAH 5.75 m3
- Bekisting
Jumlah = 82.00 bh
v = l x t x sisi x Jumlah
= 0.60 x 0.47 x 4 x 34.00
= 38.35 m2 38.35
JUMLAH 38.35 m2
- Besi Tulangan
besi 16
- p = Tinggi x jumlah
= 0.47 x 6
= 2.82 m
- Koefisien Besi 16
= 1.578 kg/m
Berat Besi
= P x Koef. x jumlah kolom
= 2.82 x 1.578 x 34.00
= 151.30 kg 151.30 kg
besi 19
- p = Tinggi x jumlah
= 0.47 x 14
= 6.58 m
- Koefisien Besi 19
= 2.22 kg/m
Berat Besi
= P x Koef. x jumlah kolom
= 6.58 x 2.22 x 34.00
= 497.32956 kg 497.33 kg
- Besi Begel
besi 10
- p = 0.47 x 4 + 0.02 x 2
= 1.92
- Jumlah begel
= Tinggi ˸ jarak
= 0.47 : 0.1
= 4.70
= 5 bh
- Koefisien Besi 10
= 0.62 kg/m

Berat Besi
= P x Koef. x Jumlah begel x jumlah kolom
= 1.92 x 0.62 x 5.00 x 34
= 202.37 kg 202.37
JUMLAH 851.00 kg

3 Ring Balok
1 Beton
Volume = tinggi x lebar x Alur
= 0.15 x 0.15 x 252.00
= 5.67 m3 5.67
JUMLAH 5.67 m3
2 Bekisting
Volume = Alur x t x sisi
= 252.00 x 0.15 x 2
= 75.60 m2 75.60
JUMLAH 75.60 m2
3 Besi Tulangan
besi 16
- p = Alur x jumlah
= 252.00 x 8
= 2016.00 kg

- Koefisien Besi 16 = 1.587 kg/m

Berat Besi = P x Koef.


= 2016.00 x 1.587
= 3199.39 kg 3199.39 kg
besi 12
- p = Alur x jumlah
= 252.00 x 2
= 504.00 m

- Koefisien Besi 12 = 0.89 kg/m

Berat Besi = P x Koef.


= 504.00 x 0.89
= 448.56 kg 448.56 kg
- Besi Begel
besi 8 jarak 10
- p = panjang + lengkung
= 0.64 + 0.04
= 0.68 m

- Jumlah begel = Alur ˸ jarak


= 126.00 : 0.1
= 1260.00
= 1260 bh

- Koefisien Besi 8 = 0.40 kg/m

Berat Besi = P x Koef. x Jumlah begel


= 0.68 x 0.40 x 1260
= 342.72 kg 342.72 kg

besi 8 jarak 20
- p = panjang + lengkung
= 0.64 + 0.04
= 0.68 m
- Jumlah begel
= Alur ˸ jarak
= 126.00 : 0.2
= 630.00
= 630 bh

- Koefisien Besi 8 = 0.40 kg/m

Berat Besi = P x Koef. x Jumlah begel


= 0.68 x 0.40 x 630
= 171.36 kg 171.36
JUMLAH 4162.03 kg

4 Plat Top Floor


a Beton
volume = Luas x tebal
= 1140.27 x 0.12
= 136.83 m3 136.83
JUMLAH 136.83 m3
b Bekisting
volume = Luasan
= 1017.84 m2 1017.84
JUMLAH 1017.84 m2

c Besi Bawah
Besi 10
- modul 6x6 = 19.00 bh
Bawah 2 Lapis
Panjang = p + Lengkungan x jumlah besi x 2
= 6.00 + 0.06 x 40 x 2
= 484.80 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 484.80 x 19.00 x 0.62
= 5710.94 kg 5710.94 kg
Atas 2 Lapis
Panjang FULL = p + Lengkungan x jumlah besi x 2
= 6.00 + 0.06 x 20 x 2
= 242.40 m

Panjang TURUN = p + lengkungan x jumlah besi x 2


= 6.03 + 0.6 x 16 x 2
= 212.28 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 454.68 x 19.00 x 0.62
= 5356.07 kg 5356.07 kg
- modul 6 x 8 = 2.00 bh
Bawah 2 Lapis
Panjang 1 = p + Lengkungan x jumlah besi
= 6.00 + 0.06 x 53
= 323.20 m

Panjang 2 = p + Lengkungan x jumlah besi


= 8.00 + 0.06 x 40
= 322.40 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 645.60 x 2.00 x 0.62
= 800.54 kg 800.54 kg
Atas 2 Lapis
Panjang FULL 1 = p + Lengkungan x jumlah besi
= 6.00 + 0.06 x 24
= 145.44 m
Panjang FULL 2 = p + Lengkungan x jumlah besi
= 8.00 + 0.06 x 20
= 161.20 m

Panjang TURUN 1 = p + lengkungan x jumlah besi


= 6.00 + 0.6 x 15
= 99.00 m
Panjang TURUN 2 = p + lengkungan x jumlah besi
= 8.00 + 0.6 x 20
= 172.00 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 577.64 x 2.00 x 0.62
= 716.27 kg 716.27 kg
- modul 6 x 4 = 2.00 bh
Bawah 2 Lapis
Panjang 1 = p + Lengkungan x jumlah besi
= 6.00 + 0.06 x 27
= 161.60 m

Panjang 2 = p + Lengkungan x jumlah besi


= 4.00 + 0.06 x 40
= 162.40 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 324.00 x 2.00 x 0.62
= 401.76 kg 401.76 kg
Atas 2 Lapis
Panjang FULL 1 = p + Lengkungan x jumlah besi
= 6.00 + 0.06 x 20
= 121.20 m
Panjang FULL 2 = p + Lengkungan x jumlah besi
= 4.00 + 0.06 x 20
= 81.20 m

Panjang TURUN 1 = p + lengkungan x jumlah besi


= 6.00 + 0.6 x 10
= 66.00 m
Panjang TURUN 2 = p + lengkungan x jumlah besi
= 4.00 + 0.6 x 15
= 69.00 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 337.40 x 2.00 x 0.62
= 418.38 kg 418.38 kg
- modul 3 x 4 = 2.00 bh
Bawah 2 Lapis
Panjang 1 = p + Lengkungan x jumlah besi
= 3.00 + 0.06 x 27
= 81.60 m
Panjang 2 = p + Lengkungan x jumlah besi
= 4.00 + 0.06 x 20
= 81.20 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 162.80 x 2.00 x 0.62
= 201.87 kg 201.87 kg
Atas 2 Lapis
Panjang 1 = p + Lengkungan x jumlah besi
= 3.00 + 0.06 x 27
= 81.60 m

Panjang 2 = p + Lengkungan x jumlah besi


= 4.00 + 0.06 x 20
= 81.20 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 162.80 x 2.00 x 0.62
= 201.87 kg 201.87 kg
- modul 2.5 x 6 = 2.00 bh
Bawah 2 Lapis
Panjang 1 = p + Lengkungan x jumlah besi
= 2.50 + 0.06 x 40
= 102.40 m

Panjang 2 = p + Lengkungan x jumlah besi


= 6.00 + 0.06 x 17
= 101.00 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 203.40 x 2.00 x 0.62
= 252.22 kg 252.22 kg
Atas 2 Lapis
Panjang 1 = p + Lengkungan x jumlah besi
= 2.50 + 0.06 x 40
= 102.40 m

Panjang 2 = p + Lengkungan x jumlah besi


= 6.00 + 0.06 x 17
= 101.00 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 203.40 x 2.00 x 0.62
= 252.22 kg 252.22 kg
- modul 2 x 1.75 = 3.00 bh
Bawah 2 Lapis
Panjang 1 = p + Lengkungan x jumlah besi
= 2.00 + 0.06 x 12
= 24.03 m

Panjang 2 = p + Lengkungan x jumlah besi


= 1.75 + 0.06 x 13
= 24.13 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 48.17 x 3.00 x 0.62
= 89.59 kg 89.59 kg
Atas 2 Lapis
Panjang 1 = p + Lengkungan x jumlah besi
= 2.00 + 0.06 x 12
= 24.03 m
Panjang 2 = p + Lengkungan x jumlah besi
= 1.75 + 0.06 x 13
= 24.13 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Jmlh Modul x Koefisien


= 48.17 x 3.00 x 0.62
= 89.59 kg 89.59 kg
- Keluaran atap
Bawah 2 Lapis
Panjang 1 = p + Lengkungan x jumlah besi
= 0.87 + 0.06 x 1407
= 1308.20 m

Panjang 2 = p + Lengkungan x jumlah besi


= 211.00 + 0.06 x 6
= 1224.15 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Koefisien


= 2532.35 x 0.62
= 1570.06 kg 1570.06 kg
Atas 2 Lapis
Panjang 1 = p + Lengkungan x jumlah besi
= 0.87 + 0.06 x 1407
= 1308.20 m

Panjang 2 = p + Lengkungan x jumlah besi


= 211.00 + 0.06 x 6
= 1224.15 m

Koefisien Besi 10 = 0.62 kg/m

Berat = Panjang x Koefisien


= 2532.35 x 0.62
= 1570.06 kg 1570.06 kg
JUMLAH 17631.44 kg

4 Kusen Aluminium Luar


a Depan Kiri = 422.26 m 422.26 m
b Kiri 1 = 117.18 m 117.18 m
c Kiri 2 = 121.63 m 121.63 m
d Kiri 3 = 89.68 m 89.68 m
e Kiri Belakang = 141.48 m 141.48 m
f Belakang 1 = 158.30 m 158.30 m
g Belakang 2 = 135.10 m 135.10 m
h Kanan Belakang = 201.91 m 201.91 m
i Kanan 2 = 207.45 m 207.45 m
j Kanan 1 = 22.68 m 22.68 m
k Depan Kanan = 463.48 m 463.48 m
JUMLAH 2081.13 m

5 Kaca Kusen Luar


a Depan Kiri = 272.69 m2 272.69 m2
b Kiri 1 = 31.74 m2 31.74 m2
c Kiri 2 = 33.11 m2 33.11 m2
d Kiri 3 = 16.69 m2 16.69 m2
e Kiri Belakang = 57.47 m2 57.47 m2
f Belakang 1 = 68.64 m2 68.64 m2
g Belakang 2 = 83.95 m2 83.95 m2
h Kanan Belakang = 109.43 m2 109.43 m2
i Kanan 2 = 78.09 m2 78.09 m2
j Kanan 1 = 8.79 m2 8.79 m2
k Depan Kanan = 296.92 m2 296.92 m2
JUMLAH 1057.50 m2

6 Atap Spandek
Volume = Luasan
= 1793.20 m2 1793.20 m2
JUMLAH 1793.20 m2

7 List plank
Volume = Panjang
= 233.60 m 233.60 m
JUMLAH 233.60 m

8 Gording CNP
Volume = Panjang
= 1872.10 m 1872.10 m
JUMLAH 1872.10 m

9 Kuda - Kuda IWF


a K1 = 8.00 bh
Volume = Panjang x Jumlah Kuda-Kuda
= 14.94 x 8.00
= 285.72

Koefisien = 21.30 kg/m

Berat Besi = Panjang x Koef


= 285.72 x 21.30
= 6085.84 Kg 6085.84 Kg

b K2 = 5.00 bh
Volume = Panjang x Jumlah Kuda-Kuda
= 21.86 x 5.00
= 169.18

Koefisien = 21.30 kg/m

Berat Besi = Panjang x Koef


= 169.18 x 21.30
= 3603.53 Kg 3603.53 Kg
JUMLAH 9689.37 Kg
67 1 m2 Pasangan ACP , besi hollow 4x4 cm, rangka 60 x 60 cm
A. BAHAN
1.1000 M2 - ACP PVDF 0,3/4 mm alloy 3003 uk. 1,22 x 4,88 m2
4.0000 M1 - Besi Hollow 40 / 40 X 1,8mm
0.5000 M1 - Besi Hollow 60 / 80 X 1,8mm
1.0000 Ls - Asesories (Perkuatan,las, dll) 100% Rangka
12.0000 Bh - Rangka metal hollow 40.40.2 mm
0.0900 Kg - Meni besi
0.1800 Kg - Cat besi Glotex
4.0000 M1 - Sealant GE
B. TENAGA
1.0000 OH - Pekerja
1.0000 OH - Tukang Besi
0.7000 OH - Kepala Tukang besi
0.3500 OH - Mandor
Rp 1,173,239.87

Rp 25,437.00 27,980.70
Rp 15,000.00 60,000.00
Rp 75,000.00 37,500.00
Rp 195,500.00 195,500.00
Rp 29,000.00 348,000.00
Rp 30,000.00 2,700.00
Rp 80,700.00 14,526.00
Rp 5,468.75 21,875.00

Rp 85,000.00 85,000.00
Rp 130,000.00 130,000.00
Rp 150,000.00 105,000.00
Rp 110,000.00 38,500.00
TOTAL A + B Rp 1,066,581.70
Overhead + Profit 10% Rp 106,658.17
TOTAL Rp 1,173,239.87
1 Galian Tanah Pondasi Garis

ALUR LEBAR TINGGI


1 = 5.55 x 0.80 x 0.90 = 4.00
2 = 118.43 x 0.80 x 0.70 = 66.32
3 = 51.28 x 0.80 x 0.50 = 20.51
90.83 M3

2 Galian Tanah Poer Plat

PANJANG LEBAR TINGGI JUMLAH


1 = 1.20 x 1.20 x 1.30 x 27.00 = 50.54
2 = 1.05 x 1.05 x 1.30 x 4.00 = 5.73
56.28 M3

3 Urugan Kembali Pondasi Garis

= 1/3 x V. Galian
1 = 1/3 x 90.83 = 30.28 M3

4 Urugan Tanah Pondasi Poer Plat

VOLUME x JUMLAH
1= 0.52 x 27.00 = 14.04
2= 0.41 x 4.00 = 1.64
15.68 M3

5 Urugan Pasir Bawah Pondasi

ALUR LEBAR TEBAL


= 175.26 x 0.80 x 0.05 = 7.01 M3

6 Urugan Pasir Bawah Lantai

LUAS TEBAL
1= 547.64 x 0.10 = 54.76 M3
1 Pek. Pas. Pondasi Batu Belah Campuran 1 SP : 4 PP

ALUR LUAS
1 = 134.20 x 0.30 = 39.92
2 = 31.80 x 0.38 = 12.16
52.09 M3
2 Pek. Pas. Batu Kosong

ALUR LEBAR TEBAL


1 = 166.00 x 0.8 x 0.15 19.92 M3

3 Pek. Pas. Batu Gunung


1 STA0+0.00
1 Lantai Kerja (K-125)

PANJANG LEBAR TEBAL JUMLAH


1 = 1.20 x 1.20 x 0.05 x 27.00 = 1.94
2 = 1.05 x 1.05 x 0.05 x 4.00 = 0.22
2.16 M3
2 Pek. Pondasi Beton Poer Plat

A BETON
BIDANG 1 BIDANG 2 JUMLAH
1 = 0.24 + 0.09 x 27.00 = 8.98
2 = 0.20 + 0.07 x 4.00 = 1.06
10.04 M3

B BEKISTING
BIDANG 1 BIDANG 2 JUMLAH
1 = 0.88 + 1.14 x 27.00 = 54.60
2 = 0.72 + 0.82 x 4.00 = 6.17
60.78 M2
C BESI BETON
PANJANG JUMLAH KOEF. BESI 19
1 = 54.25 x 27.00 2.22 3251.82
2 = 39.09 x 4.00 2.22 347.10
3598.92 KG

3 Pek. Kolom Beton Pedestal 40 x 40 cm

A BETON
PANJANG LEBAR TINGGI JUMLAH
1 = 0.40 x 0.40 x 1.45 x 27.00 = 6.26
2 = 0.25 x 0.25 x 1.45 x 4.00 = 0.36
6.63 M3
B BEKISTING
PANJANG TINGGI SISI JUMLAH
1 = 0.40 x 1.45 x 4.00 x 27.00 = 62.64
2 = 0.25 x 1.45 x 4.00 x 4.00 = 5.80
68.44 M2
C BESI BETON
- TULANGAN
PANJANG JML BESI KOEF. BESI 16 JML KOLOM
1 = 1.81 x 12.00 x 1.59 x 27.00 = 930.68
2 = 1.81 x 12.00 x 1.59 x 4.00 = 137.88
- BEUGEL
PANJANG JML BEUGEL KOEF. BESI 16 JML KOLOM
1 = 1.38 x 11.00 x 1.59 x 27.00 = 650.45
2 = 0.78 x 11.00 x 1.59 x 4.00 = 54.47
1773.47 KG

4 Pek. Sloof Beton 25 x 50 cm

A BETON
ALUR LEBAR TINGGI
1 = 199.00 x 0.40 x 0.20 = 15.92 M3
B BEKISTING
ALUR TINGGI SISI
1 = 199.00 x 0.40 x 2.00 = 159.20 M2
C BESI BETON
- TULANGAN
ALUR JML BESI KOEF. BESI 16 &12
1 = 199.00 x 7.00 x 1.59 = 2210.69
2 = 199.00 x 2.00 x 0.89 = 354.22
- BEUGEL
PANJANG JML BEUGEL KOEF. BESI 8
1 = 1.08 x 663.33 x 0.40 = 286.56
2 = 1.08 x 497.50 x 0.40 = 214.92
3066.39 KG

5 Pek. Sloof Beton 15 x 20 cm


A BETON
ALUR LEBAR TINGGI
1 = 125.60 x 0.20 x 0.15 = 3.77 M3
B BEKISTING
ALUR TINGGI SISI
1 = 125.60 x 0.20 x 2.00 = 50.24 M2
C BESI BETON
- TULANGAN
ALUR JML BESI KOEF. BESI
1 = 125.60 x 8.00 x 0.89 = 894.27
- BEUGEL
PANJANG JML BEUGEL KOEF. BESI 8
1 = 0.58 x 837.33 x 0.40 = 194.26
1088.53 KG
6 Pek. Kolom Beton 40 x 40 cm
A BETON
PANJANG LEBAR TINGGI JUMLAH
1 = 0.40 x 0.40 x 4.15 x 27.00 = 17.93 M3
B BEKISTING
PANJANG TINGGI SISI JUMLAH
1 = 0.40 x 4.15 x 4.00 x 27.00 = 179.28 M2
C BESI BETON
- TULANGAN
TINGGI JML BESI KOEF. BESI 16 JML KOLOM
2 = 4.25 x 20.00 x 1.59 x 27.00 = 3642.17
- BEUGEL
PANJANG JML BEUGEL KOEF. BESI 10 JML KOLOM
1 = 1.38 x 28.33 x 0.62 x 27.00 = 654.53
4296.70 KG

7 Pek. Kolom Beton 25 x 25 cm


A BETON
PANJANG LEBAR TINGGI JUMLAH
1 = 0.25 x 0.25 x 4.15 x 4.00 = 1.04 M3
B BEKISTING
PANJANG TINGGI SISI JUMLAH
1 = 0.25 x 4.15 x 4.00 x 4.00 = 16.60 M2
C BESI BETON
- TULANGAN
TINGGI JML BESI KOEF. BESI 16 JML KOLOM
2 = 4.25 x 12.00 x 1.59 x 4.00 = 323.75
- BEUGEL
PANJANG JML BEUGEL KOEF. BESI 10 JML KOLOM
1 = 0.94 x 28.33 x 0.62 x 4.00 = 66.05
389.80 KG

8 Pek. Kolom Praktis 15 x 15 cm


A BETON
PANJANG LEBAR TINGGI JUMLAH
1 = 0.15 x 0.15 x 4.15 x 45.00 = 4.20 M3
B BEKISTING
PANJANG TINGGI SISI JUMLAH
1 = 0.15 x 3.51 x 4.00 x 45.00 = 94.88 M2
C BESI BETON
- TULANGAN
TINGGI JML BESI KOEF. BESI 12 JML KOLOM
1 = 4.25 x 4.00 x 0.89 x 45.00 = 680.85
- BEUGEL
PANJANG JML BEUGEL KOEF. BESI 10 JML KOLOM
1 = 0.54 x 28.33 x 0.62 x 45.00 = 426.87
1107.72 KG

9 Pek. Balok Latai 11 cm x 15 cm


A BETON
ALUR LEBAR TINGGI
1 = 29.00 x 0.11 x 0.15 = 0.48 M3
B BEKISTING
ALUR TINGGI SISI
1 = 29.00 x 0.15 x 2.00 = 8.70 M2
C BESI BETON
- TULANGAN
ALUR JML BESI KOEF. BESI 10
1 = 29.00 x 4.00 x 0.62 = 71.92
- BEUGEL
PANJANG JML BEUGEL KOEF. BESI 8
1 = 0.42 x 193.33 x 0.40 = 32.48
104.40 KG
10 Pek. Balok 15 cm x 15 cm
A BETON
ALUR LEBAR TINGGI
1 = 26.55 x 0.15 x 0.15 = 0.60 M3
B BEKISTING
ALUR TINGGI SISI
1 = 26.55 x 0.15 x 2.00 = 7.97 M2
C BESI BETON
- TULANGAN
ALUR JML BESI KOEF. BESI 10
1 = 26.55 x 4.00 x 0.62 = 65.85
- BEUGEL
PANJANG JML BEUGEL KOEF. BESI 8
1 = 0.42 x 177.01 x 0.40 = 29.74
95.58 KG
12 Pek. Rabat Beton Bawah Lantai (K-125)
LUAS TEBAL
1= 547.64 x 0.05 = 27.38 M3
13 Pek. Tangga Beton
A BETON
- TANGGA
PANJANG LEBAR TINGGI JUMLAH
= 1.39 x 0.30 x 0.18 x 22.00 = 0.82
- PLAT
PANJANG LEBAR TEBAL
= 2.95 x 1.25 x 0.12 = 0.44
- BALOK
PANJANG LEBAR TIGGI
= 7.50 x 0.20 x 0.40 = 0.60
1.87 M3
B BEKISTING
ALUR LEBAR
1 = 3.42 x 1.39 = 4.75
2 = 3.50 x 1.39 = 4.86
3 = 1.71 x 2.93 = 4.99
14.60 M2
C BESI
PAJANG JUMLAHKOEF. BESI 8, 12 & 16
1 = 2.23 x 9.00 x 1.59 = 31.93
2 = 3.00 x 9.00 x 1.59 = 42.90
3 = 4.30 x 9.00 x 1.59 = 61.53
4 = 1.64 x 9.00 x 1.59 = 23.46
5 = 1.79 x 9.00 x 1.59 = 25.67
6 = 4.21 x 9.00 x 1.59 = 60.20
7 = 2.29 x 9.00 x 1.59 = 32.73
8 = 3.00 x 9.00 x 1.59 = 42.90
9 = 2.95 x 22.00 x 0.89 = 57.76
10 = 1.30 x 49.00 x 0.89 = 56.69
11 = 1.30 x 49.00 x 0.89 = 56.69
12 = 4.30 x 9.00 x 1.59 = 61.53
13 = 1.08 x 29.00 x 0.40 = 12.53
14 = 3.00 x 9.00 x 1.59 = 42.93
15 = 1.08 x 20.00 x 0.40 = 8.64
618.10 KG

13 Pek. Tangga Beton


A BETON
- TANGGA
PANJANG LEBAR TINGGI JUMLAH
= 1.14 x 0.30 x 0.18 x 22.00 = 0.68
- PLAT
PANJANG LEBAR TEBAL
= 2.28 x 1.50 x 0.12 = 0.41
- BALOK
PANJANG LEBAR TIGGI
= 4.55 x 0.20 x 0.40 = 0.36 x2
2.90 M3
B BEKISTING
ALUR LEBAR
1 = 3.42 x 1.14 = 3.89
2 = 3.65 x 1.14 = 4.16
3 = 1.81 x 2.93 = 5.28 x2
26.66 M2
C BESI
PAJANG JUMLAHKOEF. BESI 8, 12 & 16
1 = 2.13 x 8.00 x 1.59 = 27.11
2 = 2.88 x 8.00 x 1.59 = 36.69
3 = 4.30 x 8.00 x 1.59 = 54.69
4 = 1.64 x 8.00 x 1.59 = 20.85
5 = 1.81 x 8.00 x 1.59 = 23.07
6 = 4.28 x 8.00 x 1.59 = 54.46
7 = 2.41 x 8.00 x 1.59 = 30.68
8 = 3.12 x 8.00 x 1.59 = 39.73
9 = 2.38 x 21.00 x 0.89 = 44.39
10 = 1.10 x 49.00 x 0.89 = 47.97
11 = 1.10 x 49.00 x 0.89 = 47.97
12 = 2.50 x 9.00 x 1.59 = 35.78
13 = 1.08 x 16.00 x 0.40 = 6.91
14 = 2.50 x 9.00 x 1.59 = 35.78
15 = 1.08 x 16.00 x 0.40 = 6.91 x2
1025.98 KG
11 Pek. Dinding Beton Bertulang
A BETON
PANJANG LEBAR TINGGI
1 = 3.40 x 0.15 x 3.65 = 1.86
2 = 4.10 x 0.15 x 3.65 = 2.24
3 = 4.10 x 0.15 x 3.65 = 2.24
4 = 4.10 x 0.15 x 3.65 = 2.24
5 = 0.525 x 0.15 x 3.65 = 0.29
6 = 4.50 x 0.15 x 3.65 = 2.46
7 = 1.225 x 0.15 x 3.65 = 0.67
8 = 4.10 x 0.15 x 3.65 = 2.24
9 = 4.10 x 0.15 x 3.65 = 2.24
16.51 M3
B BEKISTING
LEBAR TINGGI
1 = 6.95 x 3.65 = 25.37
2 = 8.20 x 3.65 = 29.93
3 = 8.20 x 3.65 = 29.93
4 = 8.20 x 3.65 = 29.93
5 = 1.200 x 3.65 = 4.38
6 = 9.15 x 3.65 = 33.40
7 = 2.450 x 3.65 = 8.94
8 = 8.20 x 3.65 = 29.93
9 = 8.20 x 3.65 = 29.93
221.74 M2
A BESI
PANJANG JUMLAH KOEF. BESI 12
1 = 3.56 x 50 x 0.89 = 158.39
= 3.95 x 46 x 0.89 = 181.55
2 = 4.37 x 50 x 0.89 = 218.65
= 3.95 x 54 x 0.89 = 213.13
3 = 4.37 x 50 x 0.89 = 218.65
= 3.95 x 54 x 0.89 = 213.13
4 = 4.37 x 50 x 0.89 = 218.65
= 3.95 x 54 x 0.89 = 213.13
5 = 0.69 x 50 x 0.89 = 34.34
= 3.95 x 8 x 0.89 = 31.57
6 = 4.70 x 50 x 0.89 = 235.03
= 3.95 x 60 x 0.89 = 236.81
7 = 1.537 x 50 x 0.89 = 76.84
= 3.95 x 16 x 0.89 = 63.15
8 = 4.37 x 50 x 0.89 = 218.65
= 3.95 x 54 x 0.89 = 213.13
9 = 4.37 x 50 x 0.89 = 218.65
= 3.95 x 54 x 0.89 = 213.13
2963.47 KG
1 1 Bh Pek. Pintu P2 -
3.6800 M2 - Kaca tempered bening 12 mm - -
2.0000 Set - Pull Handle p. 900mm -
2.0000 Set - Engsel tanam pintu kaca stainless -
2.0000 Bh - Pacth Fitting PT 24 -
2.0000 Bh - Pacth Fitting PT20,PT10,US10 -
TOTAL Rp -
1Pek.
Bh Pintu P2 TOTAL
5.3054 M1 - Kusen alumunium 3" 96,250.00 510,644.75
7.7744 m2 - Daun pintu multipleks 6 mm 450,000.00 3,498,480.00
2.0000 Bh - Pull Handle 150,000.00 300,000.00
1.0000 Bh - Kunci silinder 18,000.00 18,000.00
6.0000 Bh - Engsel Pintu 34,500.00 207,000.00
2.0000 Bh - Grendel pintu tanam stainless 50,000.00 100,000.00
2.0000 Bh - Door Closer 120,500.00 241,000.00
TOTAL Rp 4,875,124.75

1Pek.
Bh Pintu P4 TOTAL
4.6500 M1 - Kusen alumunium 3" 96,250.00 510,644.75
1.2797 m2 - Daun pintu multipleks 6 mm 450,000.00 575,865.00
2.0000 Bh - Pull Handle 150,000.00 300,000.00
1.0000 Bh - Kunci silinder 18,000.00 18,000.00
6.0000 Bh - Engsel Pintu 34,500.00 207,000.00
2.0000 Bh - Grendel pintu tanam stainless 50,000.00 100,000.00
2.0000 Bh - Door Closer 120,500.00 241,000.00
TOTAL Rp 1,952,509.75

1Pek.
Bh Pintu P3 TOTAL
5.8000 M1 - Kusen alumunium 3" 96,250.00 510,644.75
1.3925 m2 - Daun pintu multipleks 6 mm 450,000.00 626,620.05
2.0000 Bh - Pull Handle 150,000.00 300,000.00
1.0000 Bh - Kunci silinder 18,000.00 18,000.00
3.0000 Bh - Engsel Pintu 34,500.00 103,500.00
2.0000 Bh - Grendel pintu tanam stainless 50,000.00 100,000.00
2.0000 Bh - Door Closer 120,500.00 241,000.00
TOTAL Rp 1,899,764.80

1Pek.
Bh Jendela J1 TOTAL
94.2000 M1 - Kusen alumunium 3" 96,250.00 9,066,750.00
57.0900 m2 - Kaca Tempered 10 mm 210,000.00 11,988,900.00
TOTAL Rp 21,055,650.00

1Pek.
Bh Jendela J2 TOTAL
91.5200 M1 - Kusen alumunium 3" 96,250.00 8,808,800.00
40.0568 m2 - Kaca Tempered 10 mm 210,000.00 8,411,928.00
TOTAL Rp 17,220,728.00

1Pek.
Bh Jendela J3 TOTAL
12.0000 M1 - Kusen alumunium 3" 96,250.00 1,155,000.00
2.3472 m2 - Kaca tebal 5 mm 97,500.00 228,852.00
2.0000 Bh - Pull Handle 150,000.00 300,000.00
3.0000 Bh - Kunci silinder 18,000.00 54,000.00
6.0000 Bh - Engsel Jendela 34,500.00 207,000.00
2.0000 Bh - Grendel pintu tanam stainless 96,250.00 192,500.00
TOTAL Rp 2,137,352.00

1Pek.
Bh Jendela J4 TOTAL
16.3500 M1 - Kusen alumunium 3" 96,250.00 1,573,687.50
2.8012 m2 - Kaca tebal 5 mm 97,500.00 273,117.00
8.0000 Bh - Pull Handle 150,000.00 1,200,000.00
8.0000 Bh - Kunci silinder 18,000.00 144,000.00
16.0000 Bh - Engsel Jendela 34,500.00 552,000.00
8.0000 Bh - Grendel pintu tanam stainless 96,250.00 770,000.00
TOTAL Rp 4,512,804.50

Pek.
1 BhVentilasi V1 TOTAL
2.0000 M1 - Kusen alumunium 3" 96,250.00 192,500.00
0.1500 m2 - Kaca Tempered 10 mm 210,000.00 31,500.00
TOTAL Rp 224,000.00
1 Pek. Balok Beton 20 x 40 cm

A BETON
ALUR LEBAR TINGGI
1 = 195.05 x 0.40 x 0.20 = 15.60 M3
B BEKISTING
ALUR TINGGI SISI
1 = 195.05 x 0.40 x 2.00 = 156.04
2 = 195.05 x 0.20 x 1.00 = 39.01
195.05 M2
C BESI BETON
- TULANGAN
ALUR JML BESI KOEF. BESI 16 &12
1 = 97.53 x 7.00 x 1.587 = 1083.41
2 = 97.53 x 2.00 x 0.890 = 173.59
- BEUGEL
PANJANG JML BEUGEL KOEF. BESI 8
1 = 1.08 x 325 x 0.400 = 140.44
2 = 1.08 x 244 x 0.400 = 105.33
1502.76 KG

2 Pek. Plat Beton Lantai 2 T = 12 cm


A BETON
LUAS TEBAL
1 = 256.57 x 0.12 = 30.79 M3
B BEKISTING
LUAS
1 = 256.57 = 256.57
256.57 M2
C BESI BETON
PANJANG JML BESI KOEF. BESI 12 JML MODUL
BAWAH 2 LAPIS
4.5 x 4.5 = 4.70 x 29.00 x 0.890 x 12.00 = 1455.68
= 4.70 x 29.00 x 0.890 x 12.00 = 1455.68
4.5 x 1.5 = 1.43 x 29.00 x 0.890 x 2.00 = 73.56
= 4.70 x 9.00 x 0.890 x 2.00 = 75.29
2.5 x 4.5 = 4.43 x 15.00 x 0.890 x 2.00 = 118.15
= 2.33 x 29.00 x 0.890 x 2.00 = 120.02
ATAS 2 LAPIS
4.5 x 4.5FULL = 4.70 x 14.00 x 0.890 x 12.00 = 702.74
= 4.70 x 14.00 x 0.890 x 12.00 = 702.74
TURUN = 4.73 x 15.00 x 0.890 x 12.00 = 757.75
= 4.73 x 15.00 x 0.890 x 12.00 = 757.75
4.5 x 1.5 = 1.43 x 29.00 x 0.890 x 2.00 = 73.56
= 4.70 x 9.00 x 0.890 x 2.00 = 75.29
2.5 x 4.5 = 4.43 x 15.00 x 0.890 x 2.00 = 118.15
= 2.33 x 29.00 x 0.890 x 2.00 = 120.02
6606.38 KG

1 PEKERJAAN BALOK 15 x 15

A BETON
ALUR LEBAR TINGGI
1 = 354.21 x 0.15 x 0.15 = 7.97 M3
B BEKISTING
ALUR TINGGI SISI
1 = 354.21 x 0.15 x 2.00 = 106.26
2 = 354.21 x 0.15 x 1.00 = 53.13
159.39 M2
C BESI BETON
- TULANGAN
ALUR JML BESI KOEF. BESI 12
1 = 177.10 x 2.00 x 0.890 = 315.24
2 = 177.10 x 2.00 x 0.890 = 315.24
- BEUGEL
PANJANG JML BEUGEL KOEF. BESI 8
1 = 1.08 x 590 x 0.400 = 255.03
2 = 1.08 x 443 x 0.400 = 191.27
1076.78 KG

1 PEKERJAAN BALOK latai 11 x 15

A BETON
ALUR LEBAR TINGGI
1 = 40.27 x 0.11 x 0.15 = 0.66 M3
B BEKISTING
ALUR TINGGI SISI
1 = 40.27 x 0.15 x 2.00 = 12.08
2 = 40.27 x 0.15 x 1.00 = 6.04
18.12 M2
C BESI BETON
- TULANGAN
ALUR JML BESI KOEF. BESI 12
1 = 20.14 x 2.00 x 0.890 = 35.84
2 = 20.14 x 2.00 x 0.890 = 35.84
- BEUGEL
PANJANG JML BEUGEL KOEF. BESI 8
1 = 1.08 x 67 x 0.400 = 29.00
2 = 1.08 x 50 x 0.400 = 21.75
122.42 KG

8 PEK. KOLOM 40 x 40
A BETON
PANJANG LEBAR TINGGI JUMLAH
1 = 0.40 x 0.40 x 4.15 x 27.00 = 17.93 M3
B BEKISTING
PANJANG TINGGI SISI JUMLAH
1 = 0.40 x 4.15 x 4.00 x 27.00 = 179.28 M2
C BESI BETON
- TULANGAN
TINGGI JML BESI KOEF. BESI 16 JML KOLOM
2 = 4.25 x 20.00 x 1.59 x 27.00 = 3642.17
- BEUGEL
PANJANG JML BEUGEL KOEF. BESI 10 JML KOLOM
1 = 1.38 x 28.33 x 0.62 x 27.00 = 654.53
4296.70 KG

10 Pek. Balok 15 cm x 15 cm
A BETON
PANJANG LEBAR TINGGI JUMLAH
1 = 0.15 x 0.15 x 4.15 x 45.00 = 4.20 M3
B BEKISTING
PANJANG TINGGI SISI JUMLAH
1 = 0.15 x 3.51 x 4.00 x 45.00 = 94.88 M2
C BESI BETON
- TULANGAN
TINGGI JML BESI KOEF. BESI 12 JML KOLOM
1 = 4.25 x 4.00 x 0.89 x 45.00 = 680.85
- BEUGEL
PANJANG JML BEUGEL KOEF. BESI 10 JML KOLOM
1 = 0.54 x 28.33 x 0.62 x 45.00 = 426.87
1107.72 KG

E PEK. KOLOM 25 x 25
A BETON
PANJANG LEBAR TINGGI JUMLAH
1 = 0.25 x 0.25 x 4.15 x 4.00 = 1.04 M3
B BEKISTING
PANJANG TINGGI SISI JUMLAH
1 = 0.25 x 4.15 x 4.00 x 4.00 = 16.60 M2
C BESI BETON
- TULANGAN
TINGGI JML BESI KOEF. BESI 16 JML KOLOM
2 = 4.25 x 12.00 x 1.59 x 4.00 = 323.75
- BEUGEL
PANJANG JML BEUGEL KOEF. BESI 10 JML KOLOM
1 = 1.38 x 28.33 x 0.62 x 27.00 = 654.53
978.28 KG
2 PLAT TERAS TEBAL 12 CM
A BETON
LUAS TEBAL
1 = 24.67 x 0.12 = 2.96 M3
B BEKISTING
LUAS
1 = 24.67 = 24.67
24.67 M2
C BESI BETON
PANJANG JML BESI KOEF. BESI 12 JML MODUL
BAWAH 2 LAPIS
4.5 x 4.5 = 4.29 x 30.00 x 0.890 x 1.00 = 114.54
ATAS 2 LAPIS
4.5 x 4.5FULL = 5.75 x 22.00 x 0.890 x 1.00 = 112.59
227.13 KG
1 Pek. Pas. dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 3PP
A LANTAI 1
ALUR TINGGI LUBANGAN
1 = 1.23 x 3.67 - 0.00 = 4.50
2 = 0.80 x 3.67 - 0.00 = 2.94
3 = 1.73 x 3.67 - 0.00 = 6.33
4 = 1.80 x 3.67 - 0.00 = 6.61
5 = 2.28 x 3.50 - 1.58 = 6.39
6 = 1.35 x 3.67 - 1.58 = 3.38
7 = 1.35 x 3.67 - 0.24 = 4.71
8 = 2.28 x 3.50 - 0.00 = 7.96
9 = 0.80 x 3.67 - 0.00 = 2.94
10 = 0.73 x 3.67 - 0.00 = 2.66
11 = 0.73 x 3.67 - 0.00 = 2.66
12 = 2.28 x 3.50 - 1.58 = 6.39
13 = 0.80 x 3.67 - 0.00 = 2.94
14 = 1.35 x 3.67 - 1.58 = 3.38
15 = 2.28 x 3.50 - 0.00 = 7.96
16 = 1.35 x 3.67 - 0.24 = 4.71
17 = 1.35 x 3.67 - 0.00 = 4.95
18 = 2.23 x 3.67 - 0.00 = 8.17
19 = 3.23 x 3.67 - 0.00 = 11.84
20 = 1.85 x 3.92 - 1.58 = 5.68
21 = 1.35 x 3.92 - 0.00 = 5.29
22 = 1.85 x 3.92 - 0.00 = 7.25
23 = 1.35 x 3.92 - 0.00 = 5.29
124.92 M2

B LANTAI 2
ALUR TINGGI LUBANGAN
1 = 1.23 x 3.67 - 0.00 = 4.50
2 = 0.80 x 3.67 - 0.00 = 2.94
3 = 1.73 x 3.67 - 0.00 = 6.33
4 = 1.80 x 3.67 - 0.00 = 6.61
5 = 2.28 x 3.50 - 1.58 = 6.39
6 = 1.35 x 3.67 - 1.58 = 3.38
7 = 1.35 x 3.67 - 0.24 = 4.71
8 = 2.28 x 3.50 - 0.00 = 7.96
9 = 0.80 x 3.67 - 0.00 = 2.94
10 = 0.73 x 3.67 - 0.00 = 2.66
11 = 0.73 x 3.67 - 0.00 = 2.66
12 = 2.28 x 3.50 - 1.58 = 6.39
13 = 0.80 x 3.67 - 0.00 = 2.94
14 = 1.35 x 3.67 - 1.58 = 3.38
15 = 2.28 x 3.50 - 0.00 = 7.96
16 = 1.35 x 3.67 - 0.24 = 4.71
76.45 M2

2 Pek. Pas. dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :5PP
A LANTAI 1
ALUR TINGGI LUBANGAN
1 = 1.40 x 4.04 - 12.32 = -6.66
2 = 2.45 x 3.64 - 15.84 = -6.92
3 = 4.10 x 3.67 - 0.00 = 15.05
4 = 4.10 x 3.67 - 8.82 = 6.23
5 = 1.08 x 3.67 - 16.00 = -12.05
6 = 1.08 x 3.67 - 0.72 = 3.23
7 = 4.10 x 3.67 - 27.94 = -12.89
8 = 4.10 x 3.67 - 0.00 = 15.05
9 = 1.23 x 3.67 - 0.00 = 4.50
10 = 2.73 x 3.67 - 0.00 = 10.00
11 = 1.85 x 3.67 - 0.00 = 6.79
12 = 2.73 x 3.67 - 0.00 = 10.00
13 = 2.73 x 3.67 - 0.00 = 10.00
14 = 1.48 x 3.67 - 0.00 = 5.41
15 = 4.35 x 6.05 - 0.00 = 26.32
16 = 1.38 x 6.05 - 0.00 = 8.32
17 = 4.10 x 3.67 - 0.00 = 15.05
18 = 4.10 x 3.67 - 0.00 = 15.05
19 = 1.48 x 3.67 - 0.00 = 5.41
20 = 1.80 x 3.67 - 0.00 = 6.61
21 = 7.20 x 3.67 - 0.00 = 26.42
22 = 2.23 x 3.67 - 0.00 = 8.17
23 = 4.25 x 3.67 - 0.00 = 15.60
24 = 2.18 x 3.67 - 0.00 = 7.98
25 = 4.10 x 3.67 - 0.00 = 15.05
26 = 2.48 x 3.67 - 0.00 = 9.08
27 = 0.73 x 3.67 - 0.00 = 2.66
28 = 6.58 x 3.67 - 0.00 = 24.13
29 = 3.70 x 3.67 - 0.00 = 13.58
30 = 4.20 x 3.67 - 0.00 = 15.41
31 = 2.23 x 3.67 - 0.00 = 8.17
32 = 4.10 x 3.67 - 0.00 = 15.05
33 = 2.23 x 3.67 - 0.00 = 8.17
34 = 10.65 x 3.92 - 0.00 = 41.75
35 = 6.55 x 3.92 - 0.00 = 25.68
36 = 14.83 x 3.92 - 0.00 = 58.11
37 = 11.48 x 3.92 - 0.00 = 44.98
464.45 M2
B LANTAI 2
ALUR TINGGI LUBANGAN
1 = 110.70 x 3.63 - 9.90 = 391.94
2 = 4.35 x 3.63 - 30.87 = -15.08
3 = 1.23 x 3.63 - 20.75 = -16.30
4 = 1.23 x 3.63 - 18.46 = -14.01
5 = 1.80 x 3.63 - 2.16 = 4.37
6 = 4.25 x 3.63 - 0.00 = 15.43
7 = 2.18 x 3.63 - 0.00 = 7.90
374.25 M2
2 Pek. Plat Beton Lantai 2 T = 12 cm
A BETON
LUAS TEBAL
1 = 68.78 x 0.12 = 8.25 M3
B BEKISTING
LUAS
1 = 68.78 = 68.78
68.78 M2
C BESI BETON
PANJANG JML BESI KOEF. BESI 12 JML BESI
BAWAH 2 LAPIS
1 P 0.52 93.00 0.890 86.08
2 P 0.52 86.00 0.890 79.60
3 P 23.95 2.00 0.890 85.26
4 P 23.20 3.00 0.890 123.89
5 P 1.27 2.00 0.890 4.52
6 P 6.70 1.00 0.890 11.93
7 P 13.60 5.00 0.890 121.04
8 P 13.45 3.00 0.890 71.82 584.14
ATAS 2 LAPIS
1 L 0.52 115.00 0.890 106.44
2 L 0.52 45.00 0.890 41.65
3 L 2.27 36.00 0.890 145.46
4 L 2.42 31.00 0.890 133.54
5 L 0.52 2.00 0.890 1.85
6 L 1.34 1.00 0.890 2.39
7 L 3.10 2.00 0.890 11.04
8 L 18.78 2.00 0.890 66.86
9 L 19.45 2.00 0.890 69.24 578.46
1162.61 KG

1 PEKERJAAN BALOK 15 x 15

A BETON
ALUR LEBAR TINGGI
1 = 98.64 x 0.15 x 0.15 = 2.22 M3
B BEKISTING
ALUR TINGGI SISI
1 = 98.64 x 0.15 x 2.00 = 29.59
2 = 98.64 x 0.15 x 1.00 = 14.80
44.39 M2
C BESI BETON
- TULANGAN
ALUR JML BESI KOEF. BESI 12
1 = 49.32 x 2.00 x 0.890 = 87.79
2 = 49.32 x 2.00 x 0.890 = 87.79
- BEUGEL
PANJANG JML BEUGEL KOEF. BESI 8
1 = 1.08 x 164 x 0.400 = 71.02
2 = 1.08 x 123 x 0.400 = 53.27
299.87 KG

10 Pek. Balok 15 cm x 15 cm
A BETON
PANJANG LEBAR TINGGI JUMLAH
1 = 0.15 x 0.15 x 0.95 x 24.00 = 0.51 M3
B BEKISTING
PANJANG TINGGI SISI JUMLAH
1 = 0.15 x 0.95 x 4.00 x 24.00 = 13.68 M2
C BESI BETON
- TULANGAN
TINGGI JML BESI KOEF. BESI 12 JML KOLOM
1 = 0.95 x 4.00 x 0.89 x 24.00 = 81.17
- BEUGEL
PANJANG JML BEUGEL KOEF. BESI 10 JML KOLOM
1 = 0.54 x 6.33 x 0.62 x 24.00 = 50.89
132.06 KG

E PEK. KOLOM 25 x 25
A BETON
PANJANG LEBAR TINGGI JUMLAH
1 = 0.25 x 0.25 x 4.15 x 4.00 = 1.04 M3
B BEKISTING
PANJANG TINGGI SISI JUMLAH
1 = 0.25 x 4.15 x 4.00 x 4.00 = 16.60 M2
C BESI BETON
- TULANGAN
TINGGI JML BESI KOEF. BESI 16 JML KOLOM
2 = 4.25 x 12.00 x 1.59 x 4.00 = 323.75
- BEUGEL
PANJANG JML BEUGEL KOEF. BESI 10 JML KOLOM
1 = 1.38 x 28.33 x 0.62 x 27.00 = 654.53
978.28 KG
Kuda-Kuda Baja Siku

Panjang Koefisien Baja SikuJMH. Kuda-Kuda Total (Kg)


1 55.804 x 5.42 x 2 604.91536
2 27.90 x 5.42 x 2 302.45768
3 26.7 x 5.42 x 4 578.856
1486.22904

Gording CNP
1 85.37
2 75.3
3 66.42
4 57.54
5 39.78
6 30.90
7 22.02
8 13.14
390.47
TEGEL LT 01 PLAFOND LT 01
TEGEL 60 7.05
379.20 5.27
49.19 35.40
428.39 2.50
10.96
TEGEL 20 4.55
3.05 10.70
4.18 8.26
3.05 13.39
4.18 3.07
2.50 4.18
16.96 3.07
4.31
DINDING TEGEL 20 25.32
5.10 18.86
0.55 300.24
7.65 457.14
5.10
0.55
7.55
7.18 PLAFOND LT 02
5.60 40.49
39.28 19.37
84.44 39.88
10.32
3.07
TEGEL LT 02 4.18
TEGEL 60 3.07
254.83 4.31
45.30
TEGEL 20 109.53
7.39 155.12
7.41 434.65
14.81

DINDING TEGEL 20
5.10
0.55
7.65
5.10
0.55
7.55
26.50
56.98
RENCANA ANGGARAN BIAYA

NAMA MAHASIS: LA ODE ABDUL LATIF


NIM : P3B1 16 030
JUDUL T.A : PERANCANGAN KANTORCABANG BANK SULTRA DI RAHA
TAHUN ANGGA: 2020

SAT
NO. URAIAN DAN JENIS PEKERJAAN VOL. HARGA SATUANJUMLAH HARGA
UAN
1 2 3 4 5 6
I. PEKERJAAN PERSIAPAN/PENDAHULUAN
1 Pembuatan Direksi Keet dan Bangsal Kerja 1.00 Ls ### Rp 15,000,000
Pembuatan 1 m² pagar sementara dari seng
2 237.77 m' Rp 258,874 Rp 61,552,369
gelombang tinggi 2 meter
3 Pengukuran dan Pemasangan Bowplank 162.00 m' Rp 69,131 Rp 11,199,157
4 Air Kerja Dan P3K 1.00 Ls Rp 2,350,000 Rp 2,350,000
5 Listrik Kerja 1.00 Ls Rp 2,000,000 Rp 2,000,000
7 Administrasi dan Foto Dokumentasi 1.00 Ls Rp 2,000,000 Rp 2,000,000
8 Papan Nama Proyek 1.00 Ls Rp 400,000 Rp 400,000
JUMLAH Rp 94,501,526
II. PEKERJAAN LANTAI 01
A PEKERJAAN TANAH & PASIR
1 Pekerjaan Galian Tanah Pondasi Garis 90.83 m³ Rp 73,150 Rp 6,644,127
2 Pekerjaan Galian Tanah Pondasi Poer Plat 56.28 m³ Rp 89,595 Rp 5,042,138
3 Pekerjaan Urugan Tanah Kembali Pondasi Gari 30.28 m³ Rp 24,379 Rp 738,114
4 Pekerjaan Urugan Tanah Pondasi Poer Plat 15.68 m³ Rp 24,379 Rp 382,365
5 Pekerjaan Urugan Pasir Alas Pondasi 7.01 m³ Rp 30,580 Rp 214,378
6 Pekerjaan Urugan Pasir Bawah Lantai 54.76 m³ Rp 30,580 Rp 1,674,672
JUMLAH Rp 14,695,793
B PEKERJAAN PONDASI
Pek. Pas. Pondasi Batu Belah Campuran 1 SP :
1 52.09 m³ Rp 948,985 Rp 49,430,747
4 PP
2 Pek. Pas. Batu Kosong 19.92 m³ Rp 500,327 Rp 9,966,509
JUMLAH Rp 59,397,256
C PEKERJAAN BETON & RABAT
1 Lantai Kerja (K-125) 2.16 m³ Rp 1,219,381 Rp 2,639,350
Pek. Pondasi Beton Poer Plat
- Beton K-250 10.04 m³ Rp 1,379,480 Rp 13,849,844
2
- Besi Beton 3598.92 kg Rp 27,490 Rp 98,934,158
- Bekisting 60.78 m² Rp 253,450 Rp 15,404,077
Pek. Kolom Beton Pedestal 40 x 40 cm
- Beton K-250 6.63 m³ Rp 1,379,480 Rp 9,141,126
3
- Besi Beton 1773.47 kg Rp 27,490 Rp 48,752,644
- Bekisting 68.44 m² Rp 404,204 Rp 27,663,708
Pek. Sloof Beton 25 x 50 cm
- Beton K-225 15.92 m³ Rp 1,360,462 Rp 21,658,554
4
- Besi Beton 3066.39 kg Rp 27,490 Rp 84,294,889
- Bekisting 159.20 m² Rp 272,700 Rp 43,413,824
Pek. Sloof Beton 15 x 20 cm
- Beton K-225 3.77 m³ Rp 1,360,462 Rp 5,126,220
5
- Besi Beton 1088.53 kg Rp 27,490 Rp 29,923,711
- Bekisting 50.24 m² Rp 272,700 Rp 13,700,443
Pek. Kolom Beton 40 x 40 cm
- Beton K-225 17.93 m³ Rp 1,360,462 Rp 24,390,361
6
- Besi Beton 4296.70 kg Rp 27,490 Rp 118,115,976
- Bekisting 179.28 m² Rp 404,204 Rp 72,465,657
Pek. Kolom Beton 25 x 25 cm
- Beton K-225 1.04 m³ Rp 1,360,462 Rp 1,411,479
7
- Besi Beton 389.80 kg Rp 27,490 Rp 10,715,540
- Bekisting 16.60 m² Rp 404,204 Rp 6,709,783
Pek. Kolom Praktis 15 x 15 cm
- Beton K-125 4.20 m³ Rp 1,219,381 Rp 5,123,686
8
- Besi Beton 1107.72 kg Rp 27,490 Rp 30,451,151
- Bekisting 94.88 m² Rp 404,204 Rp 38,350,048
Pek. Balok Latai 11 cm x 15 cm
- Beton K-125 0.48 m³ Rp 1,219,381 Rp 583,474
9
- Besi Beton 104.40 kg Rp 27,490 Rp 2,869,949
- Bekisting 8.70 m² Rp 417,404 Rp 3,631,413
Pek. Balok 15 cm x 15 cm
10
- Beton K-125 0.60 m³ Rp 1,219,381 Rp 728,450
10
- Besi Beton 95.58 kg Rp 27,490 Rp 2,627,569
- Bekisting 7.97 m² Rp 417,404 Rp 3,324,724
Pek. Dinding Beton Bertulang
- Beton K-300 16.51 m³ Rp 1,486,929 Rp 24,544,925
11
- Besi Beton 2963.47 kg Rp 27,490 Rp 81,465,609
- Bekisting 221.74 m² Rp 428,229 Rp 94,954,417
12 Pek. Rabat Beton Bawah Lantai (K-125) 27.38 m³ Rp 1,219,381 Rp 33,388,861
Pek. Plat Teras T 12 cm
- Beton K-225 2.96 m³ Rp 1,360,462 Rp 4,027,103
13
- Besi Beton 227.13 kg Rp 27,490 Rp 6,243,734
- Bekisting 24.67 m² Rp 82,480 Rp 2,034,575
Pek. Tangga Beton
- Beton K-225 4.77 m³
Rp 1,360,462 Rp 6,483,039
13
- Besi Beton 1644.08 kg
Rp 27,490 Rp 45,195,534
- Bekisting 41.26 m²
Rp 365,196 Rp 15,069,086
JUMLAH Rp 1,049,408,693
D PEKERJAAN KUSEN, PINTU, JENDELA, KACA DAN ALAT PENGGANTUNG
1 Pek. Pintu P1 2.00 Bh ### Rp 23,581,800
2 Pek. Pintu P2 8.00 Bh Rp 4,875,125 Rp 39,000,998
3 Pek. Pintu P3 2.00 Bh Rp 1,899,765 Rp 3,799,530
4 Pek. Pintu P4 4.00 Bh Rp 1,952,510 Rp 7,810,039
5 Pek. Jendela J1 1.00 Bh ### Rp 21,055,650
6 Pek. Jendela J2 1.00 Bh ### Rp 17,220,728
7 Pek. Jendela J3 2.00 Bh Rp 2,137,352 Rp 4,274,704
8 Pek. Jendela J4 4.00 Bh Rp 4,512,805 Rp 18,051,218
9 Pek. Ventilasi V1 5.00 Bh Rp 224,000 Rp 1,120,000
JUMLAH Rp 134,794,667
E PEKERJAAN PASANGAN DINDING
Pek. Pas. dinding bata merah (5x11x22) cm
1 124.92 m² Rp 282,948 Rp 35,345,522
tebal ½ batu campuran 1SP : 3PP
Pek. Pas. dinding bata merah (5x11x22) cm
2 464.45 m² Rp 267,803 Rp 124,380,382
tebal ½ batu campuran 1SP :5PP
JUMLAH Rp 159,725,905
F PEKERJAAN PLESTERAN DAN PENGECATAN
1 Pek. Pas. plesteran 1SP : 3PP tebal 20 mm 249.84 m² Rp 96,376 Rp 24,078,475
2 Pek. Pas. plesteran 1SP : 5PP tebal 20 mm 928.90 m² Rp 91,617 Rp 85,102,398
3 Pek. Pas. Acian 1094.29 m² Rp 41,223 Rp 45,109,442
3 Pek. Pengecatan Tembok 1094.29 m² Rp 21,652 Rp 23,693,470
JUMLAH Rp 177,983,784
G PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
Pek. Pemasangan lantai keramik ukuran 60 cm
1 428.39 m² Rp 179,232 Rp 76,781,385
x 60 Pemasangan
Pek. cm lantai keramik ukuran 20 cm
3 16.96 m² Rp 149,526 Rp 2,536,592
x 20 cm
4 Pek. Pemasangan Dinding keramik 20 cm x 20 84.44 m² Rp 149,526 Rp 12,626,176
5 Pek. Pemasangan Plint keramik 10 cm x 60 cm 246.53 m' Rp 14,968 Rp 3,690,029
JUMLAH Rp 95,634,181
H PEKERJAAN LANGIT-LANGIT (PLAFOND)
Pemasangan 1 m2 langit-langit gypsum board
1 ukuran (120x240x9) tebal 9 mm 457.14 m² Rp 45,693 Rp 20,887,987

2 Pemasangan 1 m2 rangka langit-langit besi 457.14 m² Rp 345,928 Rp 158,138,036


hollow 60 x 60
3 Pemasangan 1 m' List Plafond Kayu Profil 356.71 m' Rp 30,511 Rp 10,883,515
JUMLAH Rp 189,909,538
I PEKERJAAN SANITASI
1 Pek. Pemasangan Kloset Jongkok 4.00 Bh Rp 521,832 Rp 2,087,329
2 Pek. Pas. Westafel 2.00 Bh Rp 829,404 Rp 1,658,807
3 Pek. Pas. Floor Drain 4.00 Bh Rp 66,990 Rp 267,960
4 Pemasangan 1 buah Mesin Jet Pump kap. 250 1.00 Bh Rp 1,065,086 Rp 1,065,086
JUMLAH Rp 5,079,182
J PEKERJAAN ELEKTRIKAL
1 Pek. Pemasangan Box Panel (MCB) 1.00 Bh Rp 722,700 Rp 722,700
2 Pek. Pemasangan Saklar Tunggal 6.00 Bh Rp 47,163 Rp 282,975
3 Pek. Pemasangan Saklar Ganda 11.00 Bh Rp 50,325 Rp 553,575
4 Pek. Pemasangan Stop Kontak 13.00 Bh Rp 44,000 Rp 572,000
5 Pek. Pemasangan Lampu TL 2 x 36 Watt 6.00 Bh Rp 143,386 Rp 860,317
5 Pek. Pemasangan Lampu PLC 14 Watt 12.00 Bh Rp 138,876 Rp 1,666,513
6 Pek. Pemasangan Lampu PLC 20 Watt 17.00 Bh Rp 143,386 Rp 2,437,564
JUMLAH Rp 7,095,644
III. PEKERJAAN LANTAI 02
A PEKERJAAN BETON
Pek. Balok Beton 20 x 40 cm
- Beton K-225 15.60 m³ Rp 1,360,462 Rp 21,228,648
1
- Besi Beton 1502.76 kg Rp 27,490 Rp 41,310,850
- Bekisting 195.05 m² Rp 417,404 Rp 81,414,611
Pek. Plat Beton Lantai 2 T = 12 cm
- Beton K-225 30.79 m³ Rp 1,360,462 Rp 41,886,752
3
- Besi Beton 6606.38 kg Rp 27,490 Rp 181,608,984
- Bekisting 256.57 m² Rp 442,550 Rp 113,545,833
Pek. Balok 15 cm x 15 cm
- Beton K-125 7.97 m³ Rp 1,219,381 Rp 9,718,007
4
- Besi Beton 1076.78 kg Rp 27,490 Rp 29,600,739
- Bekisting 159.39 m² Rp 442,550 Rp 70,539,101
Pek. Balok Latai 11 cm x 15 cm
- Beton K-125 0.66 m³ Rp 1,219,381 Rp 810,250
5
- Besi Beton 122.42 kg Rp 27,490 Rp 3,365,449
- Bekisting 18.12 m² Rp 417,404 Rp 7,564,229
Pek. Kolom Beton 40x40cm
- Beton K-225 17.93 m³ Rp 1,360,462 Rp 24,390,361
6
- Besi Beton 4296.70 kg Rp 27,490 Rp 118,115,976
- Bekisting 179.28 m² Rp 404,204 Rp 72,465,657
Pek. Kolom Praktis 25x25 cm
- Beton K-125 1.04 m³ Rp 1,219,381 Rp 1,265,108
8
- Besi Beton 978.28 kg Rp 27,490 Rp 26,892,909
- Bekisting 16.60 m² Rp 404,204 Rp 6,709,783
Pek. Kolom Praktis 15x15 cm
- Beton K-125 17.93 m³
Rp 1,219,381 Rp 21,861,062
9
- Besi Beton 4296.70 kg
Rp 27,490 Rp 118,115,976
- Bekisting 179.28 m²
Rp 404,204 Rp 72,465,657
JUMLAH Rp 1,064,875,943
B PEKERJAAN KUSEN, PINTU, JENDELA, KACA DAN ALAT PENGGANTUNG
1 Pek. Pintu P2 5.00 Bh Rp 4,875,125 Rp 24,375,624
2 Pek. Pintu P4 4.00 Bh Rp 1,952,510 Rp 7,810,039
3 Pek. Jendela J3 2.00 Bh Rp 2,137,352 Rp 4,274,704
4 Pek. Jendela J4 7.00 Bh Rp 4,512,805 Rp 31,589,632
5 Pek. Ventilasi V1 11.00 Bh Rp 224,000 Rp 2,464,000
JUMLAH Rp 70,513,998
C PEKERJAAN PASANGAN DINDING
Pek. Pas. dinding bata merah (5x11x22) cm
1 76.45 m² Rp 282,948 Rp 21,631,339
tebal ½ batu campuran 1SP : 3PP

Pek. Pas. dinding bata merah (5x11x22) cm


2 374.25 m² Rp 267,803 Rp 100,224,093
tebal ½ batu campuran 1SP :5PP
JUMLAH Rp 121,855,432
D PEKERJAAN PLESTERAN DAN PENGECATAN
1 Pek. Pas. plesteran 1SP : 3PP tebal 20 mm 152.90 m² Rp 96,376 Rp 14,735,944
2 Pek. Pas. plesteran 1SP : 5PP tebal 20 mm 748.49 m² Rp 91,617 Rp 68,574,404
3 Pek. Pas. Acian 844.42 m² Rp 41,223 Rp 34,808,959
3 Pek. Pengecatan Tembok 844.42 m² Rp 21,652 Rp 18,283,202
JUMLAH Rp 136,402,509
E PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
Pek. Pemasangan lantai keramik ukuran 60 cm
1 254.83 m² Rp 179,232 Rp 45,673,491
x 60 Pemasangan
Pek. cm lantai keramik ukuran 20 cm
2 14.81 m² Rp 149,526 Rp 2,214,482
x 20 cm
3 Pek. Pemasangan Dinding keramik 20 cm x 20 56.98 m² Rp 149,526 Rp 8,519,253
4 Pek. Pemasangan Plint keramik 10 cm x 60 cm m' Rp 14,968 Rp -
JUMLAH Rp 56,407,226
F PEKERJAAN LANGIT-LANGIT (PLAFOND)
Pemasangan 1 m2 langit-langit gypsum board
1 ukuran (120x240x9) tebal 9 mm 434.65 m² Rp 45,693 Rp 19,860,464

2 Pemasangan 1 m2 rangka langit-langit besi 434.65 m² Rp 345,928 Rp 150,358,902


hollow 60 x 60
3 Pemasangan 1 m' List Plafond Kayu Profil m' Rp 30,511 Rp -
JUMLAH Rp 170,219,366
G PEKERJAAN SANITASI
1 Pek. Pemasangan Kloset Jongkok 2.00 Bh Rp 521,832 Rp 1,043,664
2 Pek. Pas. Westafel 2.00 Bh Rp 829,404 Rp 1,658,807
3 Pek. Pas. Floor Drain 2.00 Bh Rp 66,990 Rp 133,980
4 Pemasangan 1 m' Pipa PVC AW diameter 1/2" m' Rp 22,215 Rp -
5 Pemasangan 1 m' Pipa PVC AW diameter 2 1/2 m' Rp 96,781 Rp -
6 Pemasangan 1 m' Pipa PVC AW diameter 4" 45.15 m' Rp 174,951 Rp 7,899,059
JUMLAH Rp 10,735,511
H PEKERJAAN ELEKTRIKAL
2 Pek. Pemasangan Saklar Tunggal 1.00 Bh Rp 47,163 Rp 47,163
3 Pek. Pemasangan Saklar Ganda 8.00 Bh Rp 50,325 Rp 402,600
4 Pek. Pemasangan Stop Kontak 7.00 Bh Rp 44,000 Rp 308,000
5 Pek. Pemasangan Lampu PLC 14 Watt 4.00 Bh Rp 138,876 Rp 555,504
6 Pek. Pemasangan Lampu PLC 20 Watt 10.00 Bh Rp 143,386 Rp 1,433,861
JUMLAH Rp 2,747,128
IV. PEKERJAAN LANTAI 03/DAK BETON
A PEKERJAAN BETON
Pek. Balok Beton 15x 15cm
- Beton K-225 2.22 m³ Rp 1,360,462 Rp 3,019,409
1
- Besi Beton 299.87 kg Rp 27,490 Rp 8,243,286
- Bekisting 44.39 m² Rp 417,404 Rp 18,527,720
Pek. Kolom Praktis 15x15 cm
- Beton K-125 0.51 m³ Rp 1,219,381 Rp 625,542
3
- Besi Beton 132.06 kg Rp 27,490 Rp 3,630,255
- Bekisting 94.88 m² Rp 404,204 Rp 38,350,048
Pek. Plat Beton Top Floor T = 12 cm
- Beton K-225 8.25 m³ Rp 1,360,462 Rp 11,227,896
5
- Besi Beton 1162.61 kg Rp 27,490 Rp 31,959,991
- Bekisting 68.78 m² Rp 82,480 Rp 5,672,564
JUMLAH Rp 121,256,711
D PEKERJAAN SANITASI
1 Pemasangan Tandon Air 1000 L 2.00 Bh Rp 2,805,000 Rp 5,610,000
JUMLAH Rp 5,610,000
E PEKERJAAN RANGKA DAN PENUTUP ATAP
Pek Pemasangan Kuda-Kuda Baja Siku 60 x
1 1486.23 kg Rp 121,622 Rp 180,757,405
60 x 6 mm
2 Pek. Pemasangan Gording CNP 390.47 m' Rp 241,307 Rp 94,223,144
3 Pek. Pemasangan Gording CNP 118.55 m² Rp 792,448 Rp 93,948,642
4 Pemasangan 1 m² Atap Spundack 438.46 m² Rp 143,305 Rp 62,833,536
JUMLAH Rp 431,762,728
F PEKERJAAN FINISHING
1 Pek. Pemasangan Aluminium Composit Panel 22.00 m² Rp 1,173,240 Rp 25,813,718
2 Pek. Pemasangan GRC 16.00 Ls Rp 312,000 Rp 4,992,000
JUMLAH Rp 30,805,718
IV. PEKERJAAN AKHIR
1 Pembersihan Akhir 1.00 Ls Rp 5,000,000 Rp 5,000,000
JUMLAH Rp 5,000,000
REKAPITULASI ANGGARAN
NAMA MAHASISWA : LA ODE ABDUL LATIF
NIM : P3B1 16 030
JUDUL T.A : PERANCANGAN KANTOR CABANG BANK SULTRA DI RAHA
TAHUN ANGGARAN : 2019/2020

NO URAIAN PEKERJAAN JUMLAH HARGA ( Rp )


I PEKERJAAN PERSIAPAN Rp 94,501,526
IIPEKERJAAN TANAH Rp 14,695,793
IIIPEKERJAAN PONDASI Rp 59,397,256
IV PEKERJAAN BETON Rp 2,235,541,347
V PEKERJAAN PASANGAN DINDING Rp 159,725,905
VI PEKERJAAN PLESTERAN & PENGECETAN Rp 314,386,294
VII PEKERJAAN PENUTUP LANTAI DAN PENUTRp 152,041,408
VIIIPEKERJAAN LANGIT - LANGIT ( PLAFON ) Rp 189,909,538
IX PEKERJAAN PENUTUP ATAP Rp 431,762,728
X PEKERJAAN ELEKTRIKAL Rp 150,358,902
XI PEKERJAAN SANITASI Rp 5,079,182
XII PEKERJAAN FINISHING Rp 30,805,718
XIIIPEKERJAAN AKHIR Rp 8,500,000
REAL COST ( A ) Rp 3,846,705,597
PPN 10 % ( B ) Rp 384,670,560
IMB 1% ( C ) Rp 38,467,056
TOTAL (A+B+C) Rp 4,269,843,213
DIBULATKAN Rp 4,270,000,000
TERBILANG :

EMPAT MILIYAR DUA RATUS TUJUH PULUH RIBUH RUPIAH

Kendari, Juni 2020


Pembimbing Mahasiswa

Ir.BURHAN SAID, M.Pd LA ODE ABDUL LATIF


19650424200112 1 001 P3B1 16 030