Koeff.
No. Uraian Jenis pekerjaan Sat. Koeff. (Awal) Volume Sat Kebutuhan Tenaga Kerja
(Akhir)
1 2 3 4 5 6 7 8=5x6
X PEKERJAAN PENGECATAN
X.1 PENGECATAN DINDING
Pekerja Oh 0.1600 0.1440 691.220 m2 99.536
Tukang cat Oh 0.2800 0.2520 691.220 m2 174.187
Err:509 Oh Err:509 Err:509 691.220 m2 Err:509
Err:509 Oh Err:509 Err:509 691.220 m2 Err:509
Jumlah Err:509
X.2 PENGECATAN KUSEN, DAUN PINTU, DAN JENDELA
Pekerja Oh 0.2000 0.1800 87.250 m2 15.705
Tukang cat Oh 0.3000 0.2700 87.250 m 2
23.558
Err:509 Oh Err:509 Err:509 87.250 m2 Err:509
Err:509 Oh Err:509 Err:509 87.250 m2 Err:509
Jumlah Err:509
X.3 PENGECATAN PLAFOND
Pekerja Oh 0.2000 0.1800 52.870 m2 9.517
Tukang cat Oh 0.2800 0.2520 52.870 m 2
13.323
Err:509 Oh Err:509 Err:509 52.870 m2 Err:509
Err:509 Oh Err:509 Err:509 52.870 m2 Err:509
Jumlah Err:509
TABEL X.4
1 2 3 4 5 6 7=5x4 7 8 9 10 11 12 13 14
X PEKERJAAN PENGECATAN
X.1 PENGECATAN DINDING
Cat tembok Avitex Kg 0.175 691.22 m2 120.964 Kg Rp29,273 Rp3,540,965 40.321 Kg
Plamir tembok Kg 0.16 691.22 m2 110.595 Kg Rp20,000 Rp2,211,904 3 36.865 Kg 230.41 m2
Jumlah Rp5,752,869
X.2 PENGECATAN KUSEN, DAUN PINTU DAN JENDELA
Meni kayu Kg 0.1670 87.25 m2 14.571 Kg Rp33,000 Rp480,835 7.285 Kg
Plamir kayu Kg 0.0830 87.25 m2 7.242 Kg Rp25,000 Rp181,044 3.621 Kg 43.63 m2
Cat kayu merek AVIAN Kg 0.2000 87.25 m2 17.450 Kg Rp79,040 Rp1,379,248 2 8.725 Kg
Thinner @ 0,9 L ltr 0.15 87.25 m2 13.088 ltr Rp42,700 Rp558,836 6.544 ltr
Jumlah Rp2,599,963
X.3 PENGECATAN PLAFOND
Cat tembok Avitex Kg 0.2000 52.87 m2 10.574 Kg Rp29,273 Rp309,533 5.287 Kg
17.62 m2
Plamir tembok Kg 0.1600 52.87 m2 8.459 Kg Rp20,000 Rp169,184 3 4.230 Kg
Jumlah Rp478,717
TABEL X.6
REKAPITULASI
REKAPITULASI UPAH TENAGA KERJA PEKERJAAN PENGECATAN
No. Jenis Bahan Sat Jumlah Bahan Sat Harga Satuan RAB Bahan Jumlah Biaya
Bahan Bahan/Hari Bahan/Hari
1 Cat tembok Avitex Kg 131.538 Kg Rp29,273 Rp3,850,497 21.923 Rp641,750
2 Plamir tembok Kg 119.054 Kg Rp20,000 Rp2,381,088 19.842 Rp396,848
3 Meni kayu Kg 14.571 Kg Rp33,000 Rp480,835 2.428 Rp80,139
4 Plamir kayu Kg 7.242 Kg Rp25,000 Rp181,044 1.207 Rp30,174
5 Cat kayu merek AVIAN Kg 17.450 Kg Rp79,040 Rp1,379,248 2.908 Rp229,875
6 Thinner @ 0,9 L ltr 13.088 ltr Rp42,700 Rp558,836 2.181 Rp93,139
Jumlah Rp8,831,548 Jumlah Rp1,471,925
RAB BAHAN PEKERJAAN PENGECATAN
Harga
Kebutuhan Produktivitas
No. Uraian Jenis pekerjaan Sat. Koeff. Volume Sat Kebutuhan Bahan Sat Satuan RAB Bahan Durasi (Hari) Sat Sat
Bahan Bahan/Hari /Hari
1 2 3 4 5 6 7=5x4 7 8 9 10 11 12 13 14
X PEKERJAAN PENGECATAN
X.1 PENGECATAN DINDING
Cat tembok vinilex Kg 0.175 1228.21 m2 214.936 Kg Rp14,600 Rp3,138,066 53.734 Kg
Plamir tembok Kg 0.16 1228.21 m2 196.513 Kg Rp14,000 Rp2,751,181 4 49.128 Kg 307.05 m2
Jumlah Rp5,889,248
X.2 PENGECATAN KUSEN, DAUN PINTU DAN JENDELA
Meni kayu Kg 0.1670 163.86 m2 27.365 Kg Rp23,000 Rp629,386 9.122 Kg
Plamir kayu Kg 0.0830 163.86 m2 13.600 Kg Rp19,000 Rp258,407 4.533 Kg
54.62 m2
Cat kayu merek SEIV Kg 0.2000 163.86 m2 32.772 Kg Rp40,000 Rp1,310,880 3 10.924 Kg
Minyak cat terpentin ltr 0.15 163.86 m2 24.579 ltr Rp7,000 Rp172,053 8.193 ltr
Jumlah Rp2,370,726
X.3 PENGECATAN PLAFOND
Cat tembok vinilex Kg 0.2000 330.18 m2 66.037 Kg Rp14,600 Rp964,134 22.012 Kg
82.55 m2
Plamir tembok Kg 0.1600 330.18 m2 52.829 Kg Rp14,000 Rp739,610 4 17.610 Kg
Jumlah Rp1,703,744