ANALISA HARGA SATUAN (AHS) PEKERJAAN PENGECATAN

Harga Sat. Jumlah Harga Jumlah Harga


No. Uraian Jenis pekerjaan Sat. Koeff. Bahan / Upah / Alat Bahan Upah Alat Bahan + Upah
Rp. Rp. Rp. Rp. Rp.
1 2 3 4 5 6 7 8 9
X PEKERJAAN PENGECATAN
X.1 1 M2 PENGECATAN DINDING (2x)
Cat tembok Avitex Kg 0.175 Rp29,273.00 Rp5,122.78 - -
Plamir tembok Kg 0.160 Rp20,000.00 Rp3,200.00 - -
Rol cat bh 0.010 Rp25,000.00 - - Rp250.00
Ampelas lbr 0.500 Rp6,000.00 - - Rp3,000.00
Pekerja Oh 0.160 Rp150,000.00 - Rp24,000.00 -
Tukang cat Oh 0.280 Rp150,000.00 - Rp42,000.00 -
Steger werk lot 0.045 Rp27,895.00 - - Rp1,255.28
Jumlah Rp8,322.78 Rp66,000.00 Rp4,505.28 Rp78,828.05
X.2 1 M2 PENGECATAN KAYU (2x) BERIKUT MENI
Meni kayu Kg 0.167 Rp33,000.00 Rp5,511.00 - -
Plamir kayu Kg 0.083 Rp25,000.00 Rp2,075.00 - -
Cat kayu merek AVIAN Kg 0.200 Rp79,040.00 Rp15,808.00 - -
amplas kayu lbr 0.400 Rp6,000.00 - - Rp2,400.00
Thinner @ 0,9 L ltr 0.150 Rp42,700.00 Rp6,405.00 - -
Kuas 3'' bh 0.050 Rp8,500.00 - - Rp425.00
Pekerja Oh 0.200 Rp150,000.00 - Rp30,000.00 -
Tukang cat Oh 0.300 Rp150,000.00 - Rp45,000.00 -
Jumlah Rp29,799.00 Rp75,000.00 Rp2,825.00 Rp107,624.00
X.3 1 M2 PENGECATAN PLAFOND (2x)
Cat tembok Avitex Kg 0.200 Rp29,273.00 Rp5,854.60 - -
Plamir tembok Kg 0.160 Rp20,000.00 Rp3,200.00 - -
Rol cat bh 0.010 Rp25,000.00 - - Rp250.00
Ampelas lbr 0.500 Rp6,000.00 - - Rp3,000.00
Pekerja Oh 0.200 Rp150,000.00 - Rp30,000.00 -
Tukang cat Oh 0.280 Rp150,000.00 - Rp42,000.00 -
Jumlah Rp9,054.60 Rp72,000.00 Rp3,250.00 Rp84,304.60
TABEL X.2

RAB BAHAN PEKERJAAN PENGECATAN

HARGA SAT JUMLAH HARGA


NO URAIAN PEKERJAAN VOL SAT
BAHAN Biaya Bahan Bid Price Biaya Bahan Pelaksanaan
1 2 3 4 5 6 7
I. PEKERJAAN PENGECATAN
J.1 Pengecatan Dinding 691.22 m2 Rp8,323 Rp5,752,868.54 Rp5,752,868.54
J.2 Pengecatan Kusen, Daun Pintu dan Jendela 87.25 m2 Rp29,799 Rp2,599,962.75 Rp2,599,962.75
J.3 Pengecatan Plafond 52.87 m2 Rp9,055 Rp478,716.70 Rp478,716.70
Jumlah Rp8,831,548 Rp8,831,548

RAB UPAH PEKERJAAN PENGECATAN

HARGA SAT JUMLAH HARGA


NO URAIAN PEKERJAAN VOL SAT
UPAH Biaya Upah Bid Price Biaya Upah Pelaksanaan
1 2 3 4 5 6 7
I. PEKERJAAN PENGECATAN
J.1 Pengecatan Dinding 691.22 m2 Rp66,000 Rp45,620,520.00 Rp41,058,468.00
J.2 Pengecatan Kusen, Daun Pintu dan Jendela 87.25 m2 Rp75,000 Rp6,543,750.00 Rp5,889,375.00
J.3 Pengecatan Plafond 52.87 m2 Rp72,000 Rp3,806,640.00 Rp3,425,976.00
Jumlah Rp55,970,910 Rp50,373,819
TABEL X.3

KEBUTUHAN TENAGA KERJA

Koeff.
No. Uraian Jenis pekerjaan Sat. Koeff. (Awal) Volume Sat Kebutuhan Tenaga Kerja
(Akhir)

1 2 3 4 5 6 7 8=5x6
X PEKERJAAN PENGECATAN
X.1 PENGECATAN DINDING
Pekerja Oh 0.1600 0.1440 691.220 m2 99.536
Tukang cat Oh 0.2800 0.2520 691.220 m2 174.187
Err:509 Oh Err:509 Err:509 691.220 m2 Err:509
Err:509 Oh Err:509 Err:509 691.220 m2 Err:509
Jumlah Err:509
X.2 PENGECATAN KUSEN, DAUN PINTU, DAN JENDELA
Pekerja Oh 0.2000 0.1800 87.250 m2 15.705
Tukang cat Oh 0.3000 0.2700 87.250 m 2
23.558
Err:509 Oh Err:509 Err:509 87.250 m2 Err:509
Err:509 Oh Err:509 Err:509 87.250 m2 Err:509
Jumlah Err:509
X.3 PENGECATAN PLAFOND
Pekerja Oh 0.2000 0.1800 52.870 m2 9.517
Tukang cat Oh 0.2800 0.2520 52.870 m 2
13.323
Err:509 Oh Err:509 Err:509 52.870 m2 Err:509
Err:509 Oh Err:509 Err:509 52.870 m2 Err:509
Jumlah Err:509
TABEL X.4

ANALISIS PRODUKTIVITAS KERJA

Kebutuhan Harga Satuan Durasi Volume


No. Uraian Pekerja Sat Biaya Upah Sat Kebutuhan Tenaga Kerja Produktivitas Kerja Sat
Tenaga Kerja Upah (Hari) Pekerjaan (Per Hari) (Per Hari)
1 2 3 4 5 6=4x5 7 8 9 10 = 4 ÷ 7 11 = 8 ÷ 10 12
X. PEKERJAAN PENGECATAN
X.1 PENGECATAN DINDING
Pekerja Oh 99.536 Rp150,000 Rp14,930,352 33.179
Tukang cat Oh 174.187 Rp150,000 Rp26,128,116 58.062
Err:509 Oh Err:509 Err:509 Err:509 3 691.220 m2 Err:509 230.407 m2
Err:509 Oh Err:509 Err:509 Err:509 Err:509
Jumlah Err:509
X. 2 PENGECATAN KUSEN, DAUN PINTU DAN JENDELA
Pekerja Oh 15.705 Rp150,000 Rp2,355,750 7.853
Tukang cat Oh 23.558 Rp150,000 Rp3,533,625 11.779
Err:509 Oh Err:509 Err:509 Err:509 2 87.25 m2 Err:509 43.625 m2
Err:509 Oh Err:509 Err:509 Err:509 Err:509
Jumlah Err:509
X.3 PENGECATAN PLAFOND
Pekerja Oh 9.517 Rp150,000 Rp1,427,490 3.172
Tukang cat Oh 13.323 Rp150,000 Rp1,998,486 4.441
3 52.870 m2 17.623 m2
Err:509 Oh Err:509 Err:509 Err:509 Err:509
Err:509 Oh Err:509 Err:509 Err:509 Err:509
Jumlah Err:509
TABEL X.5

ANALISIS BAHAN DAN KEBUTUHAN BAHAN

Harga Satuan Durasi Kebutuhan Produktivitas/


No. Uraian Jenis pekerjaan Sat. Koeff. Volume Sat Kebutuhan Bahan Sat Bahan RAB Bahan (Hari) Bahan/Hari Sat Hari Sat

1 2 3 4 5 6 7=5x4 7 8 9 10 11 12 13 14
X PEKERJAAN PENGECATAN
X.1 PENGECATAN DINDING
Cat tembok Avitex Kg 0.175 691.22 m2 120.964 Kg Rp29,273 Rp3,540,965 40.321 Kg
Plamir tembok Kg 0.16 691.22 m2 110.595 Kg Rp20,000 Rp2,211,904 3 36.865 Kg 230.41 m2
Jumlah Rp5,752,869
X.2 PENGECATAN KUSEN, DAUN PINTU DAN JENDELA
Meni kayu Kg 0.1670 87.25 m2 14.571 Kg Rp33,000 Rp480,835 7.285 Kg
Plamir kayu Kg 0.0830 87.25 m2 7.242 Kg Rp25,000 Rp181,044 3.621 Kg 43.63 m2
Cat kayu merek AVIAN Kg 0.2000 87.25 m2 17.450 Kg Rp79,040 Rp1,379,248 2 8.725 Kg
Thinner @ 0,9 L ltr 0.15 87.25 m2 13.088 ltr Rp42,700 Rp558,836 6.544 ltr
Jumlah Rp2,599,963
X.3 PENGECATAN PLAFOND
Cat tembok Avitex Kg 0.2000 52.87 m2 10.574 Kg Rp29,273 Rp309,533 5.287 Kg
17.62 m2
Plamir tembok Kg 0.1600 52.87 m2 8.459 Kg Rp20,000 Rp169,184 3 4.230 Kg
Jumlah Rp478,717
TABEL X.6
REKAPITULASI
REKAPITULASI UPAH TENAGA KERJA PEKERJAAN PENGECATAN

Harga Satuan Jumlah Biaya


No. Jenis Pekerja Sat Jumlah Pekerja Sat RAB Upah
Upah Pekerja/Hari Upah/Hari
1 Pekerja Oh 124.757 Oh Rp150,000 Rp18,713,592 20.793 Rp3,118,932
2 Tukang cat Oh 211.068 Oh Rp150,000 Rp31,660,227 35.178 Rp5,276,705
3 Err:509 Oh Err:509 Oh Err:509 Err:509 Err:509 Err:509
4 Err:509 Oh Err:509 Oh Err:509 Err:509 Err:509 Err:509
Jumlah Err:509 Jumlah Err:509

REKAPITULASI BAHAN PEKERJAAN PENGECATAN

No. Jenis Bahan Sat Jumlah Bahan Sat Harga Satuan RAB Bahan Jumlah Biaya
Bahan Bahan/Hari Bahan/Hari
1 Cat tembok Avitex Kg 131.538 Kg Rp29,273 Rp3,850,497 21.923 Rp641,750
2 Plamir tembok Kg 119.054 Kg Rp20,000 Rp2,381,088 19.842 Rp396,848
3 Meni kayu Kg 14.571 Kg Rp33,000 Rp480,835 2.428 Rp80,139
4 Plamir kayu Kg 7.242 Kg Rp25,000 Rp181,044 1.207 Rp30,174
5 Cat kayu merek AVIAN Kg 17.450 Kg Rp79,040 Rp1,379,248 2.908 Rp229,875
6 Thinner @ 0,9 L ltr 13.088 ltr Rp42,700 Rp558,836 2.181 Rp93,139
Jumlah Rp8,831,548 Jumlah Rp1,471,925
RAB BAHAN PEKERJAAN PENGECATAN

HARGA SAT JUMLAH HARGA


NO URAIAN PEKERJAAN VOL SAT
BAHAN Biaya Bahan Bid Price Biaya Bahan Pelaksanaan
1 2 3 4 5 6 7
I. PEKERJAAN PENGECATAN
J.1 Pengecatan Dinding 1228.206 m2 Rp4,795 Rp5,889,247.77 Rp5,889,247.77
J.2 Pengecatan Kusen, Daun Pintu dan Jendela 163.86 m2 Rp14,468 Rp2,370,726.48 Rp2,370,726.48
J.3 Pengecatan Plafond 330.183 m2 Rp5,160 Rp1,703,744.28 Rp1,703,744.28
Jumlah Rp9,963,719 Rp9,963,719
RAB UPAH PEKERJAAN PENGECATAN

HARGA SAT JUMLAH HARGA


NO URAIAN PEKERJAAN VOL SAT
UPAH Biaya Upah Bid Price Biaya Upah Pelaksanaan
1 2 3 4 5 6 7
I. PEKERJAAN PENGECATAN
J.1 Pengecatan Dinding 1228.206 m2 Rp21,680 Rp26,627,506.08 Rp23,964,755.47
J.2 Pengecatan Kusen, Daun Pintu dan Jendela 163.86 m2 Rp24,160 Rp3,958,857.60 Rp3,562,971.84
J.3 Pengecatan Plafond 330.183 m2 Rp23,200 Rp7,660,245.60 Rp6,894,221.04
Jumlah Rp38,246,609 Rp34,421,948

REKAPITULASI UPAH TENAGA KERJA PEKERJAAN PENGECATAN


Jumlah
No. Jenis Pekerja Sat Jumlah Pekerja Sat Harga Satuan Upah RAB Upah Pekerja/H Biaya
ari Upah/Hari
1 Pekerja Oh 265.789 Oh Rp38,000 Rp10,099,997 37.970 Rp1,442,857
2 Tukang cat Oh 436.956 Oh Rp48,000 Rp20,973,899 62.422 Rp2,996,271
3 Kepala tukang cat Oh 46.501 Oh Rp52,000 Rp2,418,038 6.643 Rp345,434
4 Mandor Oh 15.500 Oh Rp60,000 Rp930,014 2.214 Rp132,859
Jumlah Rp34,421,948 Jumlah Rp4,917,421

REKAPITULASI BAHAN PEKERJAAN PENGECATAN


Jumlah
No. Jenis Bahan Sat Jumlah Bahan Sat RAB Bahan Bahan/Ha Biaya
Harga Satuan Bahan ri Bahan/Hari
1 Cat tembok vinilex Kg 280.973 Kg Rp14,600 Rp4,102,201 40.139 Rp586,029
2 Plamir tembok Kg 249.342 Kg Rp14,000 Rp3,490,791 35.620 Rp498,684
3 Meni kayu Kg 27.365 Kg Rp23,000 Rp629,386 3.909 Rp89,912
4 Plamir kayu Kg 13.600 Kg Rp19,000 Rp258,407 1.943 Rp36,915
5 Cat kayu merek SEIV Kg 32.772 Kg Rp40,000 Rp1,310,880 4.682 Rp187,269
6 Minyak cat terpentin ltr 24.579 ltr Rp7,000 Rp172,053 3.511 Rp24,579
Jumlah Rp9,963,719 Jumlah Rp1,423,388
KEBUTUHAN TENAGA KERJA ANALISIS PRODUKTIVITAS KERJA
Kebutuha
Harga Satuan n Tenaga
No. Uraian Pekerja Sat Kebutuhan Biaya Upah Durasi (Hari) Volume Sat Kerja (Per Produktivitas Sat
Koeff. Koeff. Tenaga Kerja Pekerjaan
No. Uraian Jenis pekerjaan Sat. Volume Sat
Kebutuhan Tenaga Kerja Upah Hari) Kerja (Per Hari)
(Awal) (Akhir)
1 2 3 4 5 6=4x5 7 8 9 10 = 4 ÷ 7 11 = 8 ÷ 10 12
1 2 3 4 5 6 7 8 = 5 x 6 X. PEKERJAAN PENGECATAN
X PEKERJAAN PENGECATAN X.1 PENGECATAN DINDING
X.1 PENGECATAN DINDING Pekerja Oh 176.862 Rp38,000 Rp6,720,743 44.215
Pekerja Oh 0.1600 0.1440 1228.206 m2 176.862 Tukang cat Oh 309.508 Rp48,000 Rp14,856,380 77.377
Tukang cat Oh 0.2800 0.2520 1228.206 m2 309.508 Kepala tukang Oh 33.162 Rp52,000 Rp1,724,401 4 1228.206 m2 8.290 307.052 m2
Kepala tukang cat Oh 0.0300 0.0270 1228.206 m2 33.162 Mandor Oh 11.054 Rp60,000 Rp663,231 2.763
Mandor Oh 0.0100 0.0090 1228.206 m2 11.054 Jumlah Rp23,964,755
Jumlah 530.585 X. 2 PENGECATAN KUSEN, DAUN PINTU DAN JENDELA
X.2 PENGECATAN KUSEN, DAUN PINTU, DAN JENDELA Pekerja Oh 29.495 Rp38,000 Rp1,120,802 9.832
Pekerja Oh 0.2000 0.1800 163.860 m2 29.495 Tukang cat Oh 44.242 Rp48,000 Rp2,123,626 14.747
Tukang cat Oh 0.3000 0.2700 163.860 m2 44.242 Kepala tukang Oh 4.424 Rp52,000 Rp230,059 3 163.86 m2 1.475 54.620 m2
Kepala tukang cat Oh 0.0300 0.0270 163.860 m2 4.424 Mandor Oh 1.475 Rp60,000 Rp88,484 0.492
Mandor Oh 0.0100 0.0090 163.860 m2 1.475 Jumlah Rp3,562,972
Jumlah 79.636 X.3 PENGECATAN PLAFOND
X.3 PENGECATAN PLAFOND Pekerja Oh 59.433 Rp38,000 Rp2,258,452 14.858
Pekerja Oh 0.2000 0.1800 330.183 m2 59.433 Tukang cat Oh 83.206 Rp48,000 Rp3,993,894 20.802
4 330.183 m2 82.546 m2
Tukang cat Oh 0.2800 0.2520 330.183 m2 83.206 Kepala tukang Oh 8.915 Rp52,000 Rp463,577 2.229
Kepala tukang cat Oh 0.0300 0.0270 330.183 m2 8.915 Mandor Oh 2.972 Rp60,000 Rp178,299 0.743
Mandor Oh 0.0100 0.0090 330.183 m2 2.972 Jumlah Rp6,894,221
Jumlah 154.526

ANALISIS BAHAN DAN KEBUTUHAN BAHAN

Harga
Kebutuhan Produktivitas
No. Uraian Jenis pekerjaan Sat. Koeff. Volume Sat Kebutuhan Bahan Sat Satuan RAB Bahan Durasi (Hari) Sat Sat
Bahan Bahan/Hari /Hari

1 2 3 4 5 6 7=5x4 7 8 9 10 11 12 13 14
X PEKERJAAN PENGECATAN
X.1 PENGECATAN DINDING
Cat tembok vinilex Kg 0.175 1228.21 m2 214.936 Kg Rp14,600 Rp3,138,066 53.734 Kg
Plamir tembok Kg 0.16 1228.21 m2 196.513 Kg Rp14,000 Rp2,751,181 4 49.128 Kg 307.05 m2
Jumlah Rp5,889,248
X.2 PENGECATAN KUSEN, DAUN PINTU DAN JENDELA
Meni kayu Kg 0.1670 163.86 m2 27.365 Kg Rp23,000 Rp629,386 9.122 Kg
Plamir kayu Kg 0.0830 163.86 m2 13.600 Kg Rp19,000 Rp258,407 4.533 Kg
54.62 m2
Cat kayu merek SEIV Kg 0.2000 163.86 m2 32.772 Kg Rp40,000 Rp1,310,880 3 10.924 Kg
Minyak cat terpentin ltr 0.15 163.86 m2 24.579 ltr Rp7,000 Rp172,053 8.193 ltr
Jumlah Rp2,370,726
X.3 PENGECATAN PLAFOND
Cat tembok vinilex Kg 0.2000 330.18 m2 66.037 Kg Rp14,600 Rp964,134 22.012 Kg
82.55 m2
Plamir tembok Kg 0.1600 330.18 m2 52.829 Kg Rp14,000 Rp739,610 4 17.610 Kg
Jumlah Rp1,703,744