HARGA SATUAN
NO URAIAN SATUAN VOLUME
( Rp. )
1 Main Truss C-75 -75 m' 2.80 Rp.
2 Roof Bottom/ Reng R 33-0.45 m' 5.10 Rp.
3 Self drilling screw dia 6 x 20 mm ( truss screw ) bh 25.00 Rp.
4 Self drilling screw dia 4 x 16 mm ( Roof Bottom Screw ) bh 35.00 Rp.
5 Dynabol dia 12 x 120 mm bh 1.00 Rp.
6 Tukang Oh 0.25 Rp.
7 Tukang Besi Profile Oh 0.18 Rp.
8 Kepala Tukang Besi Profile Oh 0.12 Rp.
9 Alat Bantu ( Mesin Bor Listrik) / Genset Ls 1.00 Rp.
Total
Keuntungan Max 10%
Total Harga
Dibulatkan
HARGA SATUAN
NO URAIAN SATUAN VOLUME
( Rp. )
1 Galvalum m2 1.00 Rp.
2 Paku Seng kg 0.12 Rp.
3 Pekerja Oh 0.14 Rp.
4 Tukang Kayu Oh 0.07 Rp.
5 Kepala Tukang Oh 0.01 Rp.
6 Mandor Oh 0.01 Rp.
Total
Keuntungan Max 10%
Total Harga
Dibulatkan
Rini Setyowati, ST
RENCANA ANGGARAN BIAYA PEKERJAAN ATAP GALVALUM
Rini Setyowati, ST
HARGA
( Rp. )
7,600,000.00
2,700,000.00
1,504,000.00
0.00
0.00
0.00
11,804,000.00
1,180,400.00
12,984,400.00
12,984,000.00
Rini Setyowati, ST