JADWAL WAKTU PELAKSANAAN PEKERJAAN

PEKERJAAN : PENYUSUNAN DETAILED ENGINEERING DESIGN ( DED )INSTALASI PENGOLAHAN AIR LIMBAH (IPAL)
DOMESTIK DAN MCK KABUPATEN NGANJUK
LOKASI : PONDOK PESANTREN AL-QOMAR RIDHO DESA ROWOMARTO KEC. PATIANROWO KAB. NGANJUK
TANGGAL : 21 September-25 September 2022
TAHUN ANGGARAN : 2022

1 (September) 2 (Oktober) 3 (November)


NO. URAIAN PEKERJAAN BOBOT (%)
1 2 3 4 5 6 7 8 9
21-25 26-02 03-09 10-16 17-23 24-30 31-06 07-13 14-18
A. PEKERJAAN IPAL
I. PEKERJAAN PERSIAPAN 0,28 0,28
II. PEKERJAAN TANAH 3,23 1,08 1,08 1,08
III. PEKERJAAN BETON 30,13 6,03 6,03 6,03 6,03 6,03
IV PEKERJAAN PASANGAN DINDING DAN PENUTUP LANTAI DAN DINDING 16,15 2,69 2,69 2,69 2,69 2,69 2,69
V PEKERJAAN PERLENGKAPAN 5,48 1,83 1,83 1,83
B. PEKERJAAN MCK
I PEKERJAAN BETON 8,83 1,77 1,77 1,77 1,77 1,77
II PEKERJAAN PASANGAN DINDING DAN PENUTUP LANTAI DAN DINDING 18,36 4,59 4,59 4,59 4,59
III PEKERJAAN PASANGAN PINTU DAN PENGECATAN 5,82 1,45 1,45 1,45 1,45
IV PEKERJAAN SANITASI DAN INSTALASI PERPIPAAN 3,81 1,90 1,90
V PEKERJAAN ATAP DAN LANGIT-LANGIT 6,65 6,65
VI PEKERJAAN LISTRIK 0,42 0,42
C. PEKERJAAN PEMIPAAN
I PEKERJAAN PEMIPAAN 0,85 0,43 0,43
RENCANA 100,00 0,28 5,53 11,56 16,57 15,50 16,53 18,49 11,83 3,70
KOMULATIF RENCANA 0 0,28 5,82 17,38 33,95 49,45 65,98 84,46 96,30 100,00
REALISASI
KOMULATIF REALISASI 0
DEVIASI

.................,....................... 2022
Mengetahui/Menyetujui : Diperiksa Oleh: Dibuat Oleh :
PEJABAT PEMBUAT KOMITMEN KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
(PPK) CV. ...................................... CV. ..............................

.......................................... ........................................ ...................................


NIP. .................................... Direktur Direktur