II PEKERJAAN GALIAN DAN URUGAN (Bangunan) 4.48 0.90 0.90 0.90 0.90 0.90 90
III PEKERJAAN PASANGAN PONDASI 3.42 0.68 0.68 0.68 0.68 0.68 80
IV PEKERJAAN STRUKTUR BETON BERTULANG 26.37 1.76 1.76 1.76 1.76 1.76 1.76 1.76 1.76 1.76 1.76 1.76 1.76 1.76 1.76 1.76 75
V PEKERJAAN PASANGAN DINDING 19.26 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 2.14 70
VI PEKERJAAN KUSEN, PINTU DAN JENDELA 11.59 2.90 2.90 2.90 2.90 60
VII PEKERJAAN PENUTUP LANTAI 9.22 1.32 1.32 1.32 1.32 1.32 1.32 1.32 55
VIII PEKERJAAN PLAFOND 4.43 0.74 0.74 0.74 0.74 0.74 0.74 50
100 0
PROGRES RENCANA MINGGUAN ( % ) 0.50 2.65 3.34 3.34 3.34 3.34 2.44 1.76 1.76 1.76 6.39 6.39 6.39 6.39 5.22 5.22 4.64 5.53 8.43 7.51 7.51 6.19
PROGRES RENCANA KOMULATIF ( % ) 0.50 3.15 6.49 9.83 13.17 16.51 18.95 20.71 22.46 24.22 30.61 36.99 43.38 49.76 54.98 60.19 64.84 70.37 78.80 86.30 93.81 100.00
PROGRES REALISASI MINGGUAN ( % ) 0 0.50 3.60 2.13 1.40 2.84 3.20 1.90 2.48 3.68 6.41 2.97 3.46 2.70 4.35 3.74 4.12 6.54 6.30 9.67 9.91 8.34 9.76
PROGRES REALISASI KOMULATIF ( % ) 0 0.50 4.10 6.23 7.63 10.47 13.67 15.57 18.05 21.73 28.14 31.11 34.57 37.27 41.62 45.36 49.48 56.02 62.32 71.99 81.90 90.24 100.00
DEVIASI 0.00 0.95 -0.26 -2.20 -2.70 -2.84 -3.38 -2.66 -0.73 3.92 0.50 -2.42 -6.11 -8.14 -9.62 -10.71 -8.82 -8.05 -6.81 -4.40 -3.57 0.00
KETERANGAN
: RENCANA
: REALISASI
SANCA YUDISTIRA, ST., MT. PIPIT KOMALA DEWI, ST. TB SYAEFUL RIZAL
NIP. 1978071920051006 Site Engineer Direktur