TIME SCHEDULE

KEGIATAN PEMBANGUNAN RUANG PRAKTEK SISWA (RPS) SMK BUDI RAKSA LEMBANG
APBN TAHUN ANGGARAN 2018

No URAIAN PEKERJAAN BOBOT MG 1 MG 2 MG 3 MG 4 MG 5 MG 6 MG 7 MG 8 MG 9 MG 10 KET.

2.42 100
I PKERJAAN PERSIAPAN 2.42
2.42
10.67 10.67 10.67
II PEKERJAAN BETON 32.01
10.07 18.33 3.61
4.26 4.26 4.26 4.26 4.26
III PEKERJAAN PAS. BATA DAN PELESTERAN 21.29
5.36 7.81 4.18 3.42 0.52
2.47 2.47 2.47
IV PEKERJAAN UBIN LANTAI DAN DINDING 7.42
0.54 5.18 1.70
1.64 1.64
V PEKERJAAN KUSEN, PINTU DAN JENDELA 3.27
1.64 1.64
5.74 5.74 5.74 50
VI PEKERJAAN ATAP DAN LANGIT-LANGIT/DAK 17.21
8.61 4.30 4.30
3.89
VII PEKERJAAN PENGECATAN 3.89
3.89
3.22
VIII PEKERJAAN ELEKTRIKAL 3.22
3.22
3.82
IX MEUBELAIR 3.82
3.82
4.54
X PERENCANAAN DAN PENGAWASAN 4.54
4.54
0.91
XI BIAYA PENGELOLAAN 0.91
0.91
JUMLAH 100.00
RENCANA BOBOT MINGGUAN 13.09 10.67 14.93 5.9 6.73 4.26 14.11 8.21 5.74 16.38
RENCANA KUMULATIF BOBOT MINGGUAN 13.09 23.76 38.69 44.59 51.32 55.58 69.51 77.72 83.46 100.00
REALISASI BOBOT MINGGUAN 13.09 18.33 8.97 9.45 4.72 3.42 15.95 6.00 4.30 16.38
REALISASI KUMULATIF BBOBOT MINGGUAN 12.49 30.82 39.79 49.24 53.96 57.38 73.33 79.33 83.63 100
DEVIASI 0.60 -7.06 -1.10 -4.65 -2.64 -1.80 -3.82 -1.61 -0.17 0.00

Mengetahui,
Ketua Tim Pembangunan Ketua Tim Teknis
ARIF SARIPUDIN, SE MUHAMMAD HIDAYAT, ST
1 2 2.5
2 3 3
3 4 4
4 5 5
5 6 6
6 7 7
7 8 7
8 9 8
9 10 9
10 11 10
11 12 11
12 13 12
13 14 14
14 15 15
15 16 16
16 17 17
17 18 18
18 19 19
19 20 20
20 21 21
21 22 22
22 23 23