TIME SCHEDULE

PROYEK PEMBANGUNAN RUMAH BAPAK LUKMAN


MOJOKERTO

BOBOT BULAN KE‐1 BULAN KE‐2 BULAN KE‐3 BULAN KE‐4 BULAN KE‐5 SKALA
NO. ITEM PEKERJAAN
(%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 %
I PEKERJAAN PERSIAPAN & PEMBERSIHAN 1.0549 0.94 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 100

II PEKERJAAN TANAH 4.7026 0.83 0.87 3.00 90

III PEKERJAAN PONDASI 3.3463 1.12 1.12 1.12


80
IV PEKERJAAN SLOOF, KOLOM, RINGBALK, BALOK LATEI DAN PLAT ATAP 12.6318 2.53 2.53 2.53 2.53 2.53
V PEKERJAAN PASANGAN DAN PLESTERAN 21.1963 2.11 2.11 2.11 2.11 2.63 2.63 2.63 2.629 2.248 70

VI PEKERJAAN LANTAI DAN PASANGAN DINDING 8.5264 0.03 2.28 2.28 2.04 1.84 0.05 60

VII PEKERJAAN PASANGAN PENUTUP ATAP 12.8397 2.59 2.59 4.70 2.97
50
VIII PEKERJAAN KUSEN PINTU, JENDELA DAN AKSESORIS 11.3934 3.80 3.80 3.80
40
IX PEKERJAAN PLAFON 3.9088 1.30 1.30 1.30
X PEKERJAAN PENGECATAN 9.3388 3.11 3.11 3.11 30

XI PEKERJAAN KELISTRIKAN 4.2693 2.13 2.13 20


XII PEKERJAAN SANITARY 3.3647 1.68 1.68
10
XIII PEKERJAAN PAGAR DEPAN & ROASTER 3.3098 1.65 1.65
XIV PEKERJAAN LAIN‐LAIN 0.1172 0.1172

TOTAL 100.00
PROGRESS RENCANA 1.77 0.88 4.12 5.79 5.76 4.64 4.64 7.75 5.22 7.34 9.18 5.83 8.60 10.89 6.97 5.49 1.69 1.66 1.66 0.12
PROGRESS KOMULATIF 0.00 1.77 2.65 6.77 12.56 18.32 22.96 27.60 35.35 40.57 47.91 57.08 62.92 71.52 82.41 89.38 94.87 96.56 98.22 99.88 100
PROGRESS AKTUAL
PROGRESS KOMULATIF
DEVIASI
1.0549
4.7026
3.3463
12.6318
21.1963
8.5264
12.8397
11.3934
3.9088
9.3388
4.2693
3.3647
3.3098
0.1172

100.00