5 DIVISI 7. STRUKTUR
7.1 (7) a Beton mutu sedang fc’20 MPa 3.57 3.57 0
JUMLAH 100.00
JUMLAH KEMAJUAN MINGGUAN 0.03 0.40 0.31 0.92 6.67 6.67 6.67 10.18 10.18 10.18 10.18 10.18 10.18 10.18 3.57 1.55 1.55 0.40
JUMLAH KOMULATIF MINGGUAN 0.03 0.44 0.75 1.66 8.34 15.01 21.68 31.86 42.04 52.21 62.39 72.57 82.75 92.93 96.50 98.05 99.60 100.00
ANSORI, SH
Direktur
REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)
Jumlah Harga
No. Divisi URAIAN PEKERJAAN Pekerjaan
(Rupiah)
1 UMUM Rp 7,399,106.30
3 PEKERJAAN TANAH Rp 30,452,251.80
4 PELEBARAN PERKERASAN DAN BAHU JALAN Rp 8,170,210.40
5 PERKERASAN BERBUTIR Rp 811,987,906.50
7 STRUKTUR Rp 31,766,525.00
(A) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) Rp 889,776,000.00
(B) Pajak Pertambahan Nilai ( PPN ) = 10% x (A) Rp 88,977,600.00
(C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B) Rp 978,753,600.00
DIBULATKAN Rp 978,753,600.00
Terbilang :
Err:511
ANSORI, SH
Direktur
RENCANA ANGGARAN BIAYA (RAB)
HARGA DAN KUANTITAS
KEGIATAN : PENINGKATAN JALAN
PEKERJAAN : PENINGKATAN JALAN BENDANPETE - BUARAN
VOLUME : JALAN BETON, PANJANG : 255 M' , LEBAR : 5 M
LOKASI : KECAMATAN NALUMSARI KABUPATEN JEPARA
TAHUN : 2019
1 DIVISI 1. UMUM
Taksir Papan Nama 1.00 Buah Rp 300,000.00 Rp 300,000.00
Taksir Mobilisasi 1.00 Set Rp 7,099,106.30 Rp 7,099,106.30
Jumlah Harga Pekerjaan DIVISI 1 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp 7,399,106.30
Jumlah Harga Pekerjaan DIVISI 3 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp 30,452,251.80
Jumlah Harga Pekerjaan DIVISI 4 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp 8,170,210.40
4 DIVISI 5. PERKERASAN BERBUTIR
5.3.(1) Perkerasan Beton Semen 318.75 M3 Rp 1,988,910.00 Rp 633,965,062.50
5.3.(3) Lapis Pondasi bawah Beton Kurus (fc' 10 Mpa) 130.05 M3 Rp 1,368,880.00 Rp 178,022,844.00
Jumlah Harga Pekerjaan DIVISI 5 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp 811,987,906.50
5 DIVISI 7. STRUKTUR
7.1 (7) a Beton mutu sedang fc’20 MPa 17.50 M3 1,815,230.00 Rp 31,766,525.00
Jumlah Harga Pekerjaan DIVISI 7 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Rp 31,766,525.00
TERBILANG :
Sembilan Ratus Tujuh Puluh Delapan Juta Tujuh Ratus Lima Puluh Tiga Ribu
Enam Ratus Rupiah
ANSORI, SH
Direktur
BILL OF QUANTITY
DIVISI 1. UMUM
Taksir Papan Nama LS 1.0 300,000 300,000
Taksir Mobilisasi LS 1.0 7,099,106 7,099,106.30
Jumlah Harga Pekerjaan DIVISI 1 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 7,399,106
Jumlah Harga Pekerjaan DIVISI 3 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 483,590
Jumlah Harga Pekerjaan DIVISI 4 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 613,840
Jumlah Harga Pekerjaan DIVISI 5 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 3,357,790
DIVISI 7. STRUKTUR
7.1 (7) a Beton mutu sedang fc’20 MPa M3 1.0 1,815,230.00 1,815,230
Jumlah Harga Pekerjaan DIVISI 7 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 1,815,230
ANSORI, SH
Direktur
DAFTAR ANALISA HARGA SATUAH PEKERJAAN ( AHSP )
Analisa EI-318
A. TENAGA
B. BAHAN
C. PERALATAN
1 Jack Hammer E26 Jam 0.2677 49,868.92 13,351.78
2 Compresor E05 Jam 0.2677 170,063.34 45,532.35
3 Dump Truck E08 Jam 0.2260 255,104.80 57,645.54
A. TENAGA
B. BAHAN
C. PERALATAN
1 Wheel Loader (E15) Jam 0.0085 583,092.86 4,958.98
2 Dump Truck (E08) Jam 0.6073 255,104.80 154,936.84
3 Motor Grader (E13) Jam 0.0040 753,288.88 2,989.24
4 Tandem (E17) Jam 0.0161 463,292.65 7,461.10
5 Water Tanker (E23) Jam 0.0070 216,323.46 1,520.35
6 Alat Bantu Ls 1.0000 0.00 0.00
A. TENAGA
B. BAHAN
C. PERALATAN
A. TENAGA
1 Pekerja (L01) jam 1.4056 11,553.57 16,239.96
2 Tukang (L02) jam 0.7028 17,267.86 12,136.04
3 Mandor (L03) jam 0.1506 18,696.43 2,815.73
B. BAHAN
1 Semen (M12) Kg 489.9500 1,438.27 704,678.51
2 Pasir (M01a) M3 0.4904 446,854.42 219,147.72
3 Agregat Kasar (M03) M3 0.7263 158,030.27 114,775.13
4 Baja Tulangan (M39a) Kg 15.8750 11,406.94 181,085.15
5 Joint Sealent (M94) Kg 0.9900 30,749.14 30,441.65
6 Cat Anti Karat (M95) Kg 0.0200 32,237.00 644.74
7 Expansion Cap (M96) M2 0.1700 5,455.49 927.43
8 Polytene 125 mikron (M97) Kg 0.4375 17,358.38 7,594.29
9 Curing Compound (M98) Ltr 0.8700 34,716.77 30,203.59
10 Multiplex 12 mm (M73) Lbr 0.1600 136,585.69 0.00
11 Kayu Acuan (M99) M3 0.0960 1,180,717.33 0.00
12 Paku (M18) Kg 1.0240 17,854.34 0.00
13 Additive (M67a) Ltr 0.9139 34,716.77 31,728.35
JUMLAH HARGA BAHAN 1,321,226.56
C. PERALATAN
1 Wheel Loader E15 jam 0.0244 583,092.86 14,234.10
2 Batching Plant E43 jam 0.0502 536,152.80 26,915.30
3 Truck Mixer E49 jam 0.4701 533,952.48 251,022.51
4 Con. Vibrator E20 jam 0.0502 38,847.18 1,950.16
5 Water Tank Truck E23 jam 0.0422 216,323.46 9,122.07
6 Conc. Paver E42 jam 0.0074 528,412.81 3,929.89
7 sewa formwork jam 0.8333 130,000.00 108,333.33
8
A. TENAGA
1 Pekerja (L01) jam 1.5060 11,553.57 17,399.96
2 Tukang (L02) jam 0.4016 17,267.86 6,934.88
3 Mandor (L03) jam 0.1004 18,696.43 1,877.15
B. BAHAN
1 Semen (M12) Kg 309.5500 1,438.27 445,215.29
2 Pasir (M01a) M3 0.4991 446,854.42 223,023.32
3 Agregat Kasar (M03) M3 0.8837 158,030.27 139,650.78
4 Multiplex 12 mm (M73) Lbr 0.1600 136,585.69 21,853.71
5 Kayu Acuan (M99) M3 0.0960 1,180,717.33 113,348.86
6 Paku (M18) Kg 0.2500 17,854.34 4,463.58
C. PERALATAN
1 Wheel Loader E15 jam 0.0244 583,092.86 14,234.10
2 Batching Plant E43 jam 0.0502 536,152.80 26,915.30
3 Truck Mixer E49 jam 0.3537 533,952.48 188,835.28
4 Con. Vibrator E20 jam 0.0502 38,847.18 1,950.16
5 Water Tank Truck E23 jam 0.0422 216,323.46 9,122.07
6 Conc. Paver E42 jam 0.0037 528,412.81 1,964.94
7 Alat Bantu Ls 1.0000 0.00 0.00
A. TENAGA
B. BAHAN
C. PERALATAN
ANSORI, SH
Direktur
HARGA DASAR SATUAN UPAH
HARGA HARGA
No. URAIAN KODE SATUAN YG DIGUNAKAN SATUAN KETERANGAN
( Rp.) ( Rp.)
DAFTAR
HARGA DASAR SATUAN BAHAN
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
ANSORI, SH
Direktur
DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA
BIAYA SEWA
(diluar PPN)
ANSORI, SH
Direktur