WAKTU PELAKSANAAN (TIME SCHEDULE) -- VIII

PROYEK PEMBANGUNAN RUMAH 2 LANTAI TYPE 95

JUMLAH WAKTU PELAKSANAAN PEKERJAAN = 4 BULAN


BOBOT
NO URAIAN PEKERJAAN HARGA MARET 2024 APRIL 2024 MEI 2024 JUNI 2024 KET.
(RP.) (%) 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
A PEKERJAAN PERSIAPAN 28,666,480.00 5.02 2.51 2.51 100

B PEKERJAAN TANAH 13,696,061.63 2.40 1.20 1.20

C PEKERJAAN PONDASI 31,932,880.00 5.60 1.87 1.87 1.87

4.42 4.42 4.42 4.42 4.42 4.42 80


D PEKERJAAN BETON 151,331,645.38 26.52

E PEKERJAAN PASANGAN 143,987,375.74 25.23 5.05 5.05 5.05 5.05 5.05

F PEKERJAAN PLAFOND 27,761,341.50 4.86 1.62 1.62 1.62


60
G PEKERJAAN LANTAI 26,280,233.38 4.61 1.15 1.15 1.15 1.15

H PEKERJAAN KUSEN PINTU JENDELA DAN AKSESORIS 37,268,799.14 6.53 1.31 1.31 1.31 1.31 1.31

I PEKERJAAN CAT 49,338,316.30 8.65 2.88 2.88 2.88 40

J PEKERJAAN INSTALASI AIR 16,758,368.00 2.94 0.59 0.59 0.59 0.59 0.59

K PEKERJAAN INSTALASI LISTRIK 27,094,336.00 4.75 1.19 1.19 1.19 1.19


20
L PEKERJAAN ATAP 4,312,547.43 0.76 0.38 0.38

M PEKERJAAN FINISHING 11,737,500.00 2.06 0.69 0.69 0.69

N PEKERJAAN AKHIR 500,000.00 0.09 0.09


0
JUMLAH = 570,665,884.48 100.00
RENCANA PROGRESS MINGGUAN (%) = 0.00 2.51 2.51 1.20 3.07 6.28 6.28 9.47 11.96 12.55 12.55 9.28 3.04 3.74 6.72 5.19 3.66
RENCANA PROGRESS KOMULATIF (%) = 0.00 2.51 5.02 6.22 9.29 15.57 21.86 31.32 43.28 55.83 68.38 77.65 80.70 84.44 91.16 96.34 100.00

Blitar, 20 Februari 2024