Anda di halaman 1dari 82

LAPORAN KEMAJUAN PEKERJAAN

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT NANDA SYIFA Minggu Ke : 22 ( Dua Puluh Dua)
LOKASI : JL. RAYA GUNUNG SINDUR Dari Tanggal : 15 Juli 2018
TAHUN ANGGARAN : 2018 Sampai Tanggal : 24 Juli 2018
REALIASASI PEKERJAAN
BOBOT
NO. URAIAN PEKERJAAN MINGGU LALU MINGGU INI SAMPAI MINGGU INI KETERANGAN
(%)
BOBOT % BOBOT % BOBOT %
1 2 3 4 5 6 7
\
I PEKERJAAN PERSIAPAN 2.29 1.21 0.18 1.39

II PEKERJAAN SITE DEVELOPMENT 9.89 0.00 0.72 0.72

III GENSET DAN GAS MEDIS 2.95 0.00 0.00 0.00

IV PEKERJAAN STRUKTUR
GEDUNG A 17.93 15.18 0.82 16.00
GEDUNG B 6.20 4.35 0.65 5.00

V PEKERJAAN ARSITEKTUR
GEDUNG A 22.04 11.90 0.75 12.65
GEDUNG B 8.28 6.12 0.69 6.81

VI PEKERJAAN MEKANIKAL & ELEKTRIKAL


GEDUNG A 25.52 13.21 1.90 15.11
GEDUNG B 4.90 1.92 1.80 3.72

JUMLAH TOTAL 100.00 53.89 7.51 61.40


PROGRESS RENCANA 65.72 4.37 70.09
DEVIASI (11.83) 3.14 (8.69)

BOGOR, 24 Juli 2018


Dibuat Oleh,
PT. PENAMAS RASHATAPRISMA

ANDI TRI SETIYAWAN, ST


Project Manager

REKAPITULASI TOTAL
LAPORAN KEMAJUAN PEKERJAAN SITE DEVELOPMENT
PEKERJAAN : PEMBANGUNAN RUMAH SAKIT NANDA SYIFA Minggu Ke : 22 ( Dua Puluh Dua)
LOKASI : JL. RAYA GUNUNG SINDUR Dari Tanggal : 15 Juli 2018
TAHUN ANGGARAN : 2018 Sampai Tanggal : 24 Juli 2018
REALISASI PEKERJAAN
BOBOT
NO. JENIS PEKERJAAN SATUAN VOLUME MINGGU LALU MINGGU INI SAMPAI MINGGU INI KET.
(%)
VOLUME BOBOT % VOLUME BOBOT % VOLUME BOBOT %
1 2 3 4 5 6 7 8 9 10 11 12

I PEKERJAAN SIDE DEVELOPMENT


A Pekerjaan Persiapan
1 Papan Nama Proyek Ls 1.00 0.01 1.00 0.01 1.00 0.01
2 Pengukuran Ulang/ Uitzet Bersama Ls 1.00 0.07 1.00 0.07 1.00 0.07
3 Air kerja Ls 1.00 0.25 1.00 0.25 1.00 0.25
4 Listrik Kerja Ls 1.00 0.14 1.00 0.14 1.00 0.14
5 Pagar Proyek Seng Gelombang tinggi 2 M m' 360.00 1.16 360.00 1.16 360.00 1.16
6 Kantor Direksi Keet (R. Kontraktor, R. Konsultan, R Rapat, Musholla, KM/WC) M2 75.00 0.66 75.00 0.66 75.00 0.66
2.29 2.29 2.29

B Pekerjaan Tanah
1 Pembersihan Lokasi Pekerjaan m2 1,595.00 0.23 1595.00 0.23 1595.00 0.23
2 Urugan Tanah Lokal dan Pemadatan Menggunakan Alat Berat m3 1,311.26 3.64 1311.26 3.64 1311.26 3.64
3.87 3.87 3.87

C Pekerjaan saluran box culvert


1 Pembersihan lokasi ls 1.00 0.04 1.00 0.04 1.00 0.04
2 Pengukuran dan pemasangan bouwplank m1 14.70 0.01 14.70 0.01 14.70 0.01
3 Galian Tanah + Pembuangan dengan alat bantu m3 55.92 0.02 55.92 0.02 55.92 0.02
4 Perataan tanah dengan alat bantu m2 35.17 0.00 35.17 0.00 35.17 0.00
5 Urug pasir bawah rabat+pondasi pengaman m3 1.76 0.01 1.76 0.01 1.76 0.01
6 Urug tanah kembali m3 22.61 0.00 22.61 0.00 22.61 0.00
7 Rabat beton ( lantai kerja ) t=10 cm m3 2.41 0.03 0.00 0.00 0.00 0.00
8 Pemasangan Box Culvert Precast ukuran U 40. x 1 m m1 107.72 0.80 0.00 0.00 0.00 0.00
0.92 0.09 0.09

D Pekerjaan Jalan Paving


1 Urugan pasir bawah paving, tebal 5 cm m3 53.74 0.08
2 Pasang pavingstone tebal 8 cm K-500 m2 1,595.00 4.19
3 Pasang topi uskup m1 486.80 0.44
4 Pasang kansteen m1 107.72 0.18
5 Perataan dan pemadatan pas. Paving m2 1,595.00 0.21
5.09

9.89 3.97 3.97


LAPORAN KEMAJUAN PEKERJAAN GENSET DAN GAS MEDIS
PEKERJAAN : PEMBANGUNAN RUMAH SAKIT NANDA SYIFA Minggu Ke : 22 ( Dua Puluh Dua)
LOKASI : JL. RAYA GUNUNG SINDUR Dari Tanggal : 15 Juli 2018
TAHUN ANGGARAN : 2018 Sampai Tanggal : 24 Juli 2018
REALISASI PEKERJAAN
BOBOT
NO JENIS PEKERJAAN SATUAN VOLUME MINGGU LALU MINGGU INI SAMPAI MINGGU INI KET.
(%)
VOLUME BOBOT % VOLUME BOBOT % VOLUME
1 2 3 4 5 6 7 8 9 10 11 12

I PEKERJAAN PERSIAPAN

1 Pekerjaan Persiapan (Pembersihan, dll.) m² 75.00 0.01

2 Pengukuran dan Bouwplank m' 56.00 0.07

0.08

II PEKERJAAN STRUKTUR

III.1 LANTAI 1

1 Galian Tanah m³ 9.53 0.01

2 Urugan Pasir bawah Lt. Kerja Plat Lt. t = 5 cm m³ 2.97 0.02

3 Urugan Tanah Kembali m³ 2.86 0.00

6 Bore Pondasi Ø 60 cm, P. 6 m m' 90.00 0.18

7 Pondasi Bore Pile Ø 60 cm, P. 6 m m³ 6.36 0.22

8 Pilecap (Pondasi PS1) m³ 1.40 0.06

9 Tie Beam 20/30 (TB1) m³ 0.58 0.03

10 Tie Beam 15/25 (TB2) m³ 2.40 0.11

11 Plat Lantai Kerja t: 5 cm (dibawah PC & TB) m³ 2.97 0.03

12 Plat Lantai Genset, t: 10 cm elv. -0.05 m m³ 3.50 0.03

13 Plat Lantai Genset, t: 50 cm elv. +0.20 m m³ 4.09 0.04

14 Kolom 30 x 60 cm (K1) m³ 6.09 0.30

16 Balok 25/50 (B1) elv. +3.95 m m³ 1.20 0.06

17 Balok 20/30 (B2) elv. +3.95 m m³ 3.02 0.14

18 Balok 15/25 (B3) elv. +3.95 m m³ 0.18 0.01

19 Plat, t: 15 cm (S2) elv. +3.95 m m³ 8.22 0.41

20 Beton Tangga m³ 2.49 0.12

1.75

IV PEKERJAAN STRUKTUR R.SENTRAL GAS MEDIS

1 Galian Tanah m³ 13.65 0.01

2 Urugan Pasir bawah Lt. Kerja Plat Lt. t = 5 cm m³ 5.98 0.03

3 Urugan Tanah Kembali m³ 4.10 0.00

4 Bore Pondasi Ø 60 cm, P. 6 m m' 54.00 0.11

5 Pondasi Bore Pile Ø 60 cm, P. 6 m m³ 3.82 0.13

6 Pilecap (Pondasi PS1) m³ 0.97 0.04

7 Tie Beam 20/40 (TB1) m³ 3.36 0.15

8 Plat Lantai Kerja t: 5 cm (dibawah PC & TB) m³ 5.98 0.06

9 Plat Lantai R.Sentral Gas Medis, t: 12 cm m³ 12.96 0.13

10 Kolom 30 x 30 cm (K1) m³ 2.15 0.10

11 Balok 20/40 (B1) elv. +2.65 m m³ 2.40 0.11

12 Balok 20/30 (B2) elv. +2.65 m m³ 0.72 0.03

13 Balok 20/40 (B1) elv. +4.60 m m³ 0.72 0.03

14 Balok 20/40 (B1) elv. Mengikuti kemiringan atap m³ 0.96 0.04

15 Balok 20/30 (B2) elv. Mengikuti kemiringan atap m³ 0.84 0.04

16 Rangka atap galvalume truss (0.75mm) m2 41.25 0.08

17 Atap Genteng Metal Roof m2 41.25 0.06

18 Aluminium foil insulation sheet m' 41.25 0.02

1.20

2.95
LAPORAN KEMAJUAN REKAPTULASI STRUKTUR

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT NANDA SYIFA Minggu Ke : 22 ( Dua Puluh Dua)
LOKASI : JL. RAYA GUNUNG SINDUR Dari Tanggal : 15 Juli 2018
TAHUN ANGGARAN : 2018 Sampai Tanggal : 24 Juli 2018
REALIASASI PEKERJAAN
BOBOT
NO. URAIAN PEKERJAAN (%)
MINGGU LALU MINGGU INI SAMPAI MINGGU INI KETERANGAN
BOBOT % BOBOT % BOBOT %
1 2 3 4 5 6 7

I PEKERJAAN PERSIAPAN 0.54 0.00 0.54 0.54

II PEKERJAAN STRUKTUR

A. Gedung A
1 PEK. LANTAI 1 14.93 11.60 1.01 12.61
2 PEK. LANTAI 2 2.46 0.00 1.59 1.59

B. Gedung B
1 PEK. LANTAI 1 5.46 3.53 1.93 5.46
2 PEK. LANTAI 2 0.73 0.00 0.73 0.73

24.13 5.81 20.94

REKAPITULASI TOTAL
LAPORAN KEMAJUAN STRUKTUR GEDUNG A

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT NANDA SYIFA Minggu Ke : 22 ( Dua Puluh Dua)
LOKASI : JL. RAYA GUNUNG SINDUR Dari Tanggal : 15 Juli 2018
TAHUN ANGGARAN : 2018 Sampai Tanggal : 24 Juli 2018
REALISASI PEKERJAAN
BOBOT MINGGU LALU MINGGU INI SAMPAI MINGGU INI KET.
NO JENIS PEKERJAAN SATUAN VOLUME
(%)
VOLUME BOBOT % VOLUME BOBOT % VOLUME BOBOT %
1 2 3 4 5 6 7 8 9 10 11 12

I PEKERJAAN PERSIAPAN

1 Pekerjaan Persiapan (Pembersihan, dll.) m² 980.00 0.16 980.00 0.16 980.00 0.16

2 Pengukuran dan Bouwplank m' 325.00 0.39 325.00 0.39 325.00 0.39

0.54 0.54 0.54

II PEKERJAAN STRUKTUR

A GEDUNG A

I LANTAI 1

1 Galian Tanah pile Cap dan Tie Beam m³ 245.28 0.21 245.280 0.210 - 0.00 245.28 0.21

2 Urugan Pasir bawah Lt. Kerja Plat Lt. t = 5 cm m³ 4.58 0.02 4.576 0.024 - 0.00 4.58 0.02

3 Urugan Tanah Kembali m³ 17.66 0.01 17.664 0.011 - 0.00 17.66 0.01

4 Bore Pondasi Ø 60 cm, P. m' 480.00 0.96 480.000 0.958 - 0.00 480.00 0.96

5 Pondasi Bore Pile Ø 60 cm, P. 6 m m³ 122.08 4.14 122.083 4.139 - 0.00 122.08 4.14

6 Pilecap (Pondasi PC1) m³ 28.73 1.28 20.110 0.896 - 0.00 20.11 0.90

7 Rabat Plat Lt.1 t: 5 cm m³ 17.66 0.18 0.000 0.000 8.83 0.09 8.83 0.09

8 Tie Beam 30/45 (TB1) m³ 11.91 0.53 8.335 0.371 - 0.00 8.33 0.37

9 Tie Beam 30/45 (TB2) m³ 10.37 0.46 7.258 0.323 - 0.00 7.26 0.32

10 Tie Beam 20/30 (TB3) m³ 3.00 0.13 2.100 0.094 - 0.00 2.10 0.09

11 Plat Lantai Kerja t: 5 cm (dibawah PC & TB) m³ 17.66 0.18 12.365 0.123 - 0.00 12.36 0.12

12 Kolom 40 X 50 cm (K1) m³ 16.56 0.80 11.592 0.563 - 0.00 11.59 0.56

13 Balok 30/50 (B1) elv. +3.95 m m³ 18.59 0.93 13.010 0.649 - 0.00 13.01 0.65

14 Balok 30/45 (B2) elv. +3.95 m m³ 12.19 0.61 8.533 0.425 - 0.00 8.53 0.42

15 Balok 25/35 (B3) elv. +3.95 m m³ 7.90 0.36 5.531 0.251 - 0.00 5.53 0.25

16 Balok 20/30 (B4) elv. +3.95 m m³ 5.42 0.25 3.793 0.173 - 0.00 3.79 0.17

17 Plat, t: 12 cm (S1) elv. +3.95 m m³ 53.28 2.66 37.296 1.860 - 0.00 37.30 1.86

18 Beton Tangga (Depan) m³ 3.22 0.18 0.000 0.000 2.26 0.13 2.26 0.13

19 Pondasi batu kali m³ 35.84 0.36 17.920 0.179 25.09 0.25 43.01 0.43

20 Plat Lantai Kerja t: 10 cm m³ 50.40 0.50 35.280 0.350 35.28 0.35 70.56 0.70

21 Ram lt 1 ke 2 m3 4.32 0.20 0.000 0.000 4.32 0.20 4.32 0.20

14.93 11.60 1.01 12.61

II.2 LANTAI 2

1 Kolom 30 x 60 cm (K1) m³ 12.96 0.63 2.59 0.13 2.59 0.13

2 Balok 25/35 (B3) elv. +7.50 m m³ 2.10 0.10 1.68 0.08 1.68 0.08

3 Balok 20/30 (B4) elv. +7.50 m m³ 2.40 0.12 1.92 0.09 1.92 0.09

4 Balok 30/50 (B1) elv. +7.95 m m³ 17.10 0.85 13.68 0.68 13.68 0.68

5 Balok 25/35 (B3) elv. +7.95 m m³ 1.05 0.05 0.84 0.04 0.84 0.04

6 Balok 20/30 (B4) elv. +7.95 m m³ 6.24 0.29 4.99 0.23 4.99 0.23

7 Ring Balok 20/30 (B4) elv. +8.95 m m³ 6.24 0.30 4.99 0.24 4.99 0.24

8 Plat, t: 12 cm (S1) elv. +7.50 m m³ 2.52 0.13 2.02 0.10 2.02 0.10

2.46 0.00 1.59 1.59

TOTAL 17.93 11.60 3.14 14.74


LAPORAN KEMAJUAN STRUKTUR GEDUNG B

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT NANDA SYIFA Minggu Ke : 22 ( Dua Puluh Dua)
LOKASI : JL. RAYA GUNUNG SINDUR Dari Tanggal : 15 Juli 2018
TAHUN ANGGARAN : 2018 Sampai Tanggal : 24 Juli 2018
REALISASI PEKERJAAN
BOBOT MINGGU LALU MINGGU INI SAMPAI MINGGU INI KET.
NO JENIS PEKERJAAN SATUAN VOLUME
(%)
VOLUME BOBOT % VOLUME BOBOT % VOLUME BOBOT %
1 2 3 4 5 6 7 8 9 10 11 12

I PEKERJAAN STRUKTUR

I .1 LANTAI 1

1 Galian Tanah pile Cap dan Tie Beam m³ 56.72 0.05 56.7169 0.0486 - 0.00 56.72 0.05

2 Urugan Pasir bawah Lt. Kerja t = 5 cm m³ 1.29 0.01 1.2870 0.0067 - 0.00 1.29 0.01

3 Urugan Tanah Kembali m³ 4.97 0.00 4.9680 0.0031 - 0.00 4.97 0.00

4 Pembuangan Tanah m³ 51.75 0.02 51.7489 0.0171 - 0.00 51.75 0.02

5 Bore Pondasi Ø 60 cm, P. 10 m m' 180.00 0.36 180.0000 0.3593 - 0.00 180.00 0.36

6 Pondasi Bore Pile Ø 60 cm, P. 6 m m³ 50.87 1.72 50.8680 1.7244 - 0.00 50.87 1.72

7 Pilecap (Pondasi PC1) m³ 10.77 0.48 10.7730 0.4801 - 0.00 10.77 0.48

8 Rabat Plat Lt.1 t: 5 cm m³ 4.97 0.06 0.0000 0.0000 4.97 0.06 4.97 0.06

9 Tie Beam 30/45 (TB1) m³ 6.36 0.28 6.3585 0.2829 - 0.00 6.36 0.28

10 Tie Beam 20/30 (TB2) m³ 1.64 0.07 1.6380 0.0729 - 0.00 1.64 0.07

11 Plat Lantai Kerja t: 5 cm (dibawah PC & TB) m³ 4.97 0.06 4.9680 0.0579 - 0.00 4.97 0.06

12 Kolom 30 x 60 cm (K1) m³ 6.80 0.33 4.7628 0.2314 2.04 0.10 6.80 0.33

13 Balok 30/50 (B1) elv. +3.95 m m³ 9.11 0.45 0.0000 0.0000 9.11 0.45 9.11 0.45

14 Balok 25/35 (B3) elv. +3.95 m m³ 0.66 0.03 0.0000 0.0000 0.66 0.03 0.66 0.03

15 Balok 20/30 (B4) elv. +3.95 m m³ 0.66 0.03 0.0000 0.0000 0.66 0.03 0.66 0.03

16 Plat, t: 12 cm (S1) elv. +3.95 m m³ 19.05 1.06 0.0000 0.0000 19.05 1.06 19.05 1.06

17 Pondasi batu kali m³ 21.75 0.24 21.7500 0.2449 - 0.00 21.75 0.24

18 Plat Lantai Kerja t: 10 cm m³ 10.45 0.12 0.0000 0.0000 10.45 0.12 10.45 0.12

19 Plat Lantai Selasar elv.3.95 m m3 1.53 0.08 0.0000 0.0000 1.53 0.08 1.53 0.08

5.46 3.53 1.93 5.46

II.2 LANTAI 2

1 Kolom 30 x 60 cm (K1) m³ 2.88 0.14 2.88 0.14 2.88 0.14

2 Balok 30/50 (B1) elv. +7.95 m m³ 2.40 0.11 2.40 0.11 2.40 0.11

3 Balok 20/30 (B4) elv. +7.50 m m³ 1.68 0.08 1.68 0.08 1.68 0.08

4 Balok 30/50 (B1) elv. +7.95 m m³ 4.95 0.25 4.95 0.25 4.95 0.25

5 Balok 25/35 (B3) elv. +7.95 m m³ 0.35 0.02 0.35 0.02 0.35 0.02

6 Ring Balok 20/30 (B4) elv. +8.95 m m³ 0.84 0.04 0.84 0.04 0.84 0.04

7 Plat, t: 12 cm (S1) elv. +7.50 m Talang dan Lisplank m³ 1.80 0.10 1.80 0.10 1.80 0.10

0.73 0.00 0.73 0.73

TOTAL 6.20 3.53 2.67 6.20


LAPORAN KEMAJUAN REKAPTULASI ARSITEKTUR

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT NANDA SYIFA Minggu Ke : 22 ( Dua Puluh Dua)
LOKASI : JL. RAYA GUNUNG SINDUR Dari Tanggal : 15 Juli 2018
TAHUN ANGGARAN : 2018 Sampai Tanggal : 24 Juli 2018
REALIASASI PEKERJAAN
BOBOT
NO. URAIAN PEKERJAAN (%)
MINGGU LALU MINGGU INI SAMPAI MINGGU INI KETERANGAN
BOBOT % BOBOT % BOBOT %
1 2 3 4 5 6 7

II PEKERJAAN ARSITEKTUR

A Gedung A

I. LANTAI
1 PEKERJAAN PASANGAN DINDING 1.34 0 1.26738462704143 1.26738462704143
2 PEKERJAAN PLAFOND 1.55 0 0 0
3 PEKERJAAN PENUTUP LANTAI DAN DINDING 2.38 0 0 0
4 PEKERJAAN PENGECATAN 0.46 0 0 0
5 PEKERJAAN KUSEN - DAUN PINTU DAN JENDELA 1.62 0 0 0
6 PEKERJAAN RAILLING TANGGA 1.07 0 0 0
7 PEKERJAAN SANITARI 0.26 0 0 0

II. LANTAI 2
1 PEKERJAAN PASANGAN DINDING 1.98 0 0 0
2 PEKERJAAN PLAFOND 1.42 0 0 0
3 PEKERJAAN PENUTUP LANTAI DAN DINDING 2.55 0 0 0
4 PEKERJAAN PENGECATAN 0.85 0 0 0
5 PEKERJAAN KUSEN - DAUN PINTU DAN JENDELA 2.53 0 0 0
6 PEKERJAAN RAILLING TANGGA 0.83 0 0 0
7 PEKERJAAN SANITARI 0.47 0 0 0
8 PEKERJAAN ATAP 2.75 0 0 0

22.04 0.00 1.27 1.27

B Gedung B
I. LANTAI
1 PEKERJAAN PASANGAN DINDING 1.36 0 0 0
2 PEKERJAAN PLAFOND 0.25 0 0 0
3 PEKERJAAN PENUTUP LANTAI DAN DINDING 0.58 0 0 0
4 PEKERJAAN PENGECATAN 0.27 0 0 0
5 PEKERJAAN KUSEN - DAUN PINTU DAN JENDELA 0.76 0 0 0
6 PEKERJAAN SANITARI 0.10 0 0 0

II. LANTAI 2
1 PEKERJAAN PASANGAN DINDING 1.35 0 0 0
2 PEKERJAAN PLAFOND 0.26 0 0 0
3 PEKERJAAN PENUTUP LANTAI DAN DINDING 1.26 0 0 0
4 PEKERJAAN PENGECATAN 0.36 0 0 0
5 PEKERJAAN KUSEN - DAUN PINTU DAN JENDELA 0.81 0 0 0
7 PEKERJAAN SANITARI 0.32 0 0 0
8 PEKERJAAN ATAP 0.60 0 0 0

8.28

REKAPITULASI TOTAL
LAPORAN KEMAJUAN ARSITEKTUR GEDUNG A

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT NANDA SYIFA Minggu Ke : 22 ( Dua Puluh Dua)
LOKASI : JL. RAYA GUNUNG SINDUR Dari Tanggal : 15 Juli 2018
TAHUN ANGGARAN : 2018 Sampai Tanggal : 24 Juli 2018
REALISASI PEKERJAAN
BOBOT
NO JENIS PEKERJAAN VOLUME SATUAN MINGGU LALU MINGGU INI SAMPAI MINGGU INI KET.
(%)
VOLUME BOBOT % VOLUME BOBOT % VOLUME BOBOT %
1 2 3 4 5 6 7 8 9 10 11 12

I LANTAI 1
A PEKERJAAN PASANGAN DINDING

1 Pasangan Bata Ringan 238.80 m² 0.36 0.00 0.22 0.00 0.22

2 Plesteran 477.60 m² 0.31 0.00 0.19 0.00 0.19

3 Acian 477.60 m² 0.26 0.00 0.16 0.00 0.16

4 Benangan 521.60 m' 0.11 0.00 0.07 0.00 0.07

5 Kolom Praktis Uk. 12x15 cm 125.97 m' 0.21 0.00 0.13 0.00 0.13

6 Ring Balok Uk. 12x15 cm 1.57 m³ 0.08 0.00 0.05 0.00 0.05

7 Rabatan keliling bangunan 98.00 m2 0.27 0.00 0.16 0.00 0.16

8 Saluran keliling bangunan, U-30 100.00 m1 0.11 0.00 0.07 0.00 0.07

9 Bak kontrol 40x40 8.00 bh 0.01 0.00 0.01 0.00 0.01

9 Grill penutup saluran 100.00 m1 0.38 0.00 0.23 0.00 0.23

1.34 1.27 1.27

B PEKERJAAN PLAFOND

1 Plafond Gypsum, Rangka Hollow 489.14 m² 0.80

2 Plafond Kalsiboard T. 9mm, Rangka hollow 14.86 m² 0.02

3 Dinding Partisi double Gypsum rangka,metal stud 321.76 m² 0.65

4 List Plafond Gypsumboard 368.00 m' 0.08

1.55

C PEKERJAAN PENUTUP LANTAI DAN DINDING

1 Lantai Granite Tile Uk.60x60 cm, Polised Warna Terang 457.14 1.68

2 Hospital Plint Uk. 8x30 cm ex Roman 368.00 m' 0.36

3 Lantai Granite Tile unt. Tangga Uk.60x60 cm, Polised Warna Terang 21.15 m² 0.08

4 Lantai Keramik Motif Uk.60x60 cm, Ex. Roman 24.00 m² 0.05

5 Lantai Keramik 25x25 Unpolised Warna Terang (Area KM/WC) 14.86 m² 0.03

6 Dinding Keramik KM/WC dll. 54.00 m² 0.12

7 Pasangan batu alam ( candi hitam 20x40 ) 11.10 m2 0.04

8 Pasangan batu alam ( andesit susun sirih horisontal ) 8.00 m2 0.03

2.38

D PEKERJAAN PENGECATAN

1 Cat Tembok Interior 111.63 m² 0.03

2 Cat Tembok Eksterior 365.97 m² 0.20

3 Cat Plafond 504.00 m² 0.14

4 Cat List Plafond 368.00 M1 0.10

0.46

E PEKERJAAN KUSEN - DAUN PINTU DAN JENDELA

1 P1 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 0.14

2 PIA - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 2.00 unit 0.10
3 P2 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 0.05

4 P2A - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 0.05

5 P3 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 4.00 unit 0.13

6 P4 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 9.00 unit 0.35

7 P5 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 2.00 unit 0.03

8 BV - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 3.00 unit 0.02

9 J1 - Rangka Kusen Alumunium 20.00 unit 0.69

10 J2 - Rangka Kusen Alumunium 2.00 unit 0.05

1.62

F PEKERJAAN RAILLING TANGGA

1 Railling Tangga Bag.Dalam (Stainlessteel Ø2 + Tiang & Pengisi Ø1) 23.15 M1 0.39

2 Handrail tangga + Ramp (Stainless steel Ø 2) 64.50 M1 0.49

3 Atap kanopi rangka besi holow 4/6,4/4 finish ACP 12.00 m2 0.17

4 Louvre/ kisi-kisi holow 4/4, 2/4, fin. cat 2.40 m2 0.02

1.07

G PEKERJAAN SANITARI

1 Closet Duduk 3.00 unit 0.12

2 Wastafel 3.00 unit 0.05

3 Kran Stainless Steel (KM/WC) 3.00 bh 0.00

4 Toilet Shower / Jet Shower 3.00 bh 0.01

5 Kaca Cermin 3.00 bh 0.01

6 Tempat Sabun 3.00 bh 0.01

7 Tempat Tisue 3.00 bh 0.01

8 Floor Drain 3.00 bh 0.00

9 Talang Tegak PVC Ø 4" 32.00 m' 0.05

0.26

III.3 LANTAI 2

A PEKERJAAN PASANGAN DINDING

1 Pasangan Bata Ringan 331.80 m² 0.50

2 Plesteran (1:3) 663.60 m² 0.43

3 Acian 663.60 m² 0.46

4 Benangan 845.50 m² 0.18

5 Kolom Praktis Uk. 12x15 cm 154.97 m1 0.24

6 Ring Balok Uk. 12x15 cm 3.50 m3 0.17

1.98

B PEKERJAAN PLAFOND

1 Plafond Gypsum, Rangka Hollow 513.75 m² 0.84

2 Plafond Kalsiboard T. 9mm, Rangka hollow 21.75 m² 0.04

3 Dinding Partisi double Gypsum rangka,metal stud 215.87 m² 0.40

4 List Plafond Gypsumboard 683.40 m' 0.14

1.42

C PEKERJAAN PENUTUP LANTAI DAN DINDING

1 Lantai Granite Tile Uk.60x60 cm, Polised Warna Terang 435.50 m² 1.60

2 Hospital Plint Uk. 8x30 cm ex Roman 645.40 m² 0.62


3 Lantai Keramik 25x25 Unpolised Warna Terang (Area KM/WC) 18.00 m² 0.03

4 Dinding Keramik KM/WC dll. 76.00 m² 0.17

5 Waterproofing KM 18.00 m² 0.03

6 Pasangan Batu Alam (candi hitam 20x40) 18.70 m2 0.07

7 Pasangan Batu Alam (andesit susun sirih horisontal ) 6.00 m2 0.02

2.55

D PEKERJAAN PENGECATAN

1 Cat Tembok Interior 334.29 m² 0.09

2 Cat Tembok Eksterior 329.31 m² 0.18

3 Cat Plafond 475.00 m² 0.13

4 Cat List Plafond 512.00 m² 0.14

5 Waterproofing + Scret Atap beton 180.00 m² 0.31

0.85

E PEKERJAAN KUSEN - DAUN PINTU DAN JENDELA

1 PIA - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 0.05

2 P2 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 8.00 unit 0.44

3 P3 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 5.00 unit 0.16

4 P4 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 15.00 unit 0.59

5 P6 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 5.00 unit 0.30

6 P7 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 0.04

7 BV1 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 3.00 unit 0.02

8 J1 - Rangka Kusen Alumunium 27.00 unit 0.93

2.53

F PEKERJAAN RAILLING TANGGA

1 Railling Tangga Bag.Dalam (Stainlessteel Ø6 + Tiang & Pengisi, Fin. Cat Besi) 15.00 m² 0.25

2 Railling Tangga Bag.Tepi (Stainlessteel Ø6 + Tiang & Pengisi, Fin. Cat Besi) 22.00 m² 0.37

3 Railling Balkon (Stainlessteel Ø6 + Tiang & Pengisi, Fin. Cat Besi) 9.12 m² 0.07

4 Louvre/ kisi-kisi holow 4/4, 2/4, fin. Cat 15.00 m2 0.13

0.83

G PEKERJAAN SANITARI

1 Closet Duduk 5.00 unit 0.20

2 Wastafel + Meja Beton Finsh. Granite + Cermin (terpasang) 5.00 unit 0.11

3 Toilet Shower / Jet Shower 5.00 bh 0.03

4 Kaca Cermin 5.00 bh 0.02

5 Tempat Sabun 5.00 bh 0.01

6 Tempat Tisue 5.00 bh 0.01

7 Floor Drain 5.00 bh 0.00

8 Talang Tegak PVC Ø 4" 32.00 m' 0.05

9 Scrub station 2 person 2.00 unit 0.04

10 Roof Drain 8.00 unit 0.01

0.47

III PEKERJAAN ATAP

1 Rangka atap galvalume truss (0.75mm) 682.40 M2 1.31

2 Atap Genteng Metal Roof 682.40 M2 1.07

3 Bubungan 54.87 m1 0.08

4 Aluminium foil insulation sheet 682.40 m2 0.36

2.75
LAPORAN KEMAJUAN ARSITEKTUR GEDUNG B

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT NANDA SYIFA Minggu Ke : 22 ( Dua Puluh Dua)
LOKASI : JL. RAYA GUNUNG SINDUR Dari Tanggal : 15 Juli 2018
TAHUN ANGGARA: 2018 Sampai Tanggal : 24 Juli 2018
REALISASI PEKERJAAN
BOBOT
NO JENIS PEKERJAAN VOLUME SATUAN MINGGU LALU MINGGU INI SAMPAI MINGGU INI KET.
(%)
VOLUME BOBOT % VOLUME BOBOT % VOLUME BOBOT %

1 2 3 4 5 6 7 8 9 10 11 12

I LANTAI 1

A PEKERJAAN PASANGAN DINDING

1 Pasangan Bata Ringan 232.44 m² 0.35

2 Plesteran 464.89 m² 0.30

3 Acian 464.89 m² 0.26

4 Benangan 547.00 m' 0.12

5 Kolom Praktis Uk. 12x15 cm 60.38 m' 0.10

6 Ring Balok Uk. 12x15 cm 1.21 m³ 0.06

7 Rabatan keliling bangunan 28.77 m2 0.08

8 Saluran keliling bangunan, U-30 26.75 m1 0.03

9 Bak kontrol 40x40 4.00 bh 0.01

9 Grill penutup saluran 13.38 m1 0.05

1.36

B PEKERJAAN PLAFOND

1 Plafond Gyptile, Rangka Hollow 122.75 m² 0.20

2 Plafond Kalsiboard T. 9mm, Rangka hollow 3.75 m² 0.01

3 List Plafond Gypsumboard 222.50 m' 0.05

0.25

C PEKERJAAN PENUTUP LANTAI DAN DINDING

1 Lantai Granite Tile Uk.60x60 cm, Polised Warna Terang 109.25 m² 0.40

2 Hospital Plint Uk. 8x30 cm ex Roman 111.25 m' 0.11

3 Lantai Keramik Motif Uk.60x60 cm, Ex. Roman 6.48 m² 0.03

4 Lantai Keramik 25x25 Unpolised Warna Terang (Area KM/WC) 3.75 m² 0.01

5 Dinding Keramik KM/WC dll. 16.00 m² 0.03

0.58

D PEKERJAAN PENGECATAN

1 Cat Tembok Interior 250.89 m² 0.07

2 Cat Tembok Eksterior 214.00 m² 0.11

3 Cat Plafond 113.00 m² 0.03

4 Cat List Plafond 222.50 M1 0.06

0.27

E PEKERJAAN KUSEN - DAUN PINTU DAN JENDELA

1 PIA - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 0.05

2 P2 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 5.00 unit 0.27

3 P3 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 0.03
4 P9 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 0.04

5 BV - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 0.01

6 J1 - Rangka Kusen Alumunium 10.00 unit 0.34

7 J2 - Rangka Kusen Alumunium 1.00 unit 0.02

0.76

G PEKERJAAN SANITARI

1 Closet Duduk 1.00 unit 0.04

2 Wastafel 1.00 unit 0.02

3 Kran Stainless Steel (KM/WC) 4.00 bh 0.00

4 Toilet Shower / Jet Shower 1.00 bh 0.00

5 Kaca Cermin 1.00 bh 0.00

6 Tempat Sabun 1.00 bh 0.00

7 Tempat Tisue 1.00 bh 0.00

8 Floor Drain 2.00 bh 0.00

9 Talang Tegak PVC Ø 4" 16.00 m' 0.02

0.10

II LANTAI 2

A PEKERJAAN PASANGAN DINDING

1 Pasangan Bata Ringan 242.43 m² 0.37

2 Plesteran (1:3) 484.87 m² 0.32

3 Acian 484.87 m² 0.33

4 Benangan 652.10 m² 0.14

5 Kolom Praktis Uk. 12x15 cm 87.50 m1 0.15

6 Ring Balok Uk. 12x15 cm 1.02 m3 0.05

1.35

B PEKERJAAN PLAFOND

1 Plafond Gyptile, Rangka Hollow 111.13 m² 0.18

2 Plafond Kalsiboard T. 9mm, Rangka hollow 27.00 m² 0.05

3 List Plafond Gypsumboard 138.00 m' 0.03

0.26

C PEKERJAAN PENUTUP LANTAI DAN DINDING

1 Lantai Granite Tile Uk.60x60 cm, Polised Warna Terang 212.17 m² 0.78

2 Hospital Plint Uk. 8x30 cm ex Roman 75.00 m² 0.07

3 Lantai Keramik Motif Uk.60x60 cm, Ex. Roman 10.08 m² 0.04

4 Lantai Keramik 25x25 Unpolised Warna Terang (Area KM/WC) 27.00 m² 0.05

5 Dinding Keramik KM/WC dll. 126.00 m² 0.27

6 Waterproofing KM 27.00 m² 0.05

1.26

D PEKERJAAN PENGECATAN

1 Cat Tembok Interior 227.83 m² 0.06

2 Cat Tembok Eksterior 257.04 m² 0.14

3 Cat Plafond 138.13 m² 0.04

4 Cat List Plafond 138.00 m² 0.04

5 Waterproofing + Scret Atap beton 48.00 m² 0.08

0.36
E PEKERJAAN KUSEN - DAUN PINTU DAN JENDELA

1 PIA - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 0.05

2 P2 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 5.00 unit 0.27

3 P3 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 3.00 unit 0.09

4 J1 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 9.00 unit 0.31

5 J2 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 3.00 unit 0.07

7 BV1 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 3.00 unit 0.02

0.81

G PEKERJAAN SANITARI

1 Closet Duduk 4.00 unit 0.16

2 Wastafel 4.00 unit 0.07

3 Kran air stainless km/wc 4.00 bh 0.00

4 Toilet Shower / Jet Shower 4.00 bh 0.01

5 Kaca Cermin 4.00 bh 0.01

6 Tempat Sabun 4.00 bh 0.01

7 Tempat Tisue 4.00 bh 0.01

8 Floor Drain 4.00 bh 0.00

9 Talang Tegak PVC Ø 4" 16.00 m' 0.02

10 Roof Drain 4.00 unit 0.01

0.32

III PEKERJAAN ATAP

1 Rangka atap galvalume truss (0.75mm) 142.40 M2 0.27

2 Atap Genteng Bitumen 142.40 M2 0.22

3 Aluminium foil insulation sheet 142.40 m2 0.07

4 Genteng bubungan 22.25 m1 0.03

0.60

8.28
LAPORAN KEMAJUAN PEKERJAAN REKAPITULASI MEP

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT NANDA SYIFA Minggu Ke : 22 ( Dua Puluh Dua)
LOKASI : JL. RAYA GUNUNG SINDUR Dari Tanggal : 15 Juli 2018
TAHUN ANGGARAN : 2018 Sampai Tanggal : 24 Juli 2018
REALISASI PEKERJAAN
BOBOT
NO. URAIAN PEKERJAAN MINGGU LALU MINGGU INI SAMPAI MINGGU INI KET.
(%)
BOBOT % BOBOT % BOBOT %
1 2 3 4 5 6 7

I PEKERJAAN MEKANIKAL ELEKTRIKAL


A. Gedung A
1 PEKERJAAN TEGANGAN MENENGAH 7.37 0 0 0
2 PEKERJAAN PANEL 3.07 0 0 0
3 PEKERJAAN KABEL FEEDER 1.76 0 0 0
4 INSTALASI PENERANGAN / ARMATURE 1.54 0 0 0
5 PENANGKAL PETIR 0.27 0 0 0
6 PEKERJAAN INSTALASI GENSET 5.02 0 0 0
7 PEKERJAAN GAS MEDIS 2.14 0 0 0
8 SISTEM FIRE ALARM & EXTINGUSER 0.97 0 0 0
9 SISTEM TELEPON 0.34 0 0 0
10 DATA KOMPUTER 0.32 0 0 0
11 PEKERJAAN CCTV 0.90 0 0 0
12 TATA UDARA 0.71 0 0 0
13 PLUMBING 1.10 0 0 0
25.52

B. Gedung B
1 PEKERJAAN PANEL 0.39 0 0 0
2 PEKERJAAN KABEL FEEDER 0.44 0 0 0
3 INSTALASI PENERANGAN / ARMATURE 0.43 0 0 0
4 SISTEM FIRE ALARM & EXTINGUSER 0.50 0 0 0
5 SISTEM TELEPON 0.25 0 0 0
6 DATA KOMPUTER 0.23 0 0 0
7 SISTEM NURSE CALL 0.40 0 0 0
8 PEKERJAAN CCTV 0.05 0 0 0
9 PEKERJAAN GAS MEDIS 0.96 0 0 0
10 TATA UDARA 1.11 0 0 0
11 PLUMBING 0.15 0 0 0
4.90

REKAPITULASI TOTAL
LAPORAN KEMAJUAN MEP GEDUNG A
PEKERJAAN : PEMBANGUNAN RUMAH SAKIT NANDA SYIFA Minggu Ke : 22 ( Dua Puluh Dua)
LOKASI : JL. RAYA GUNUNG SINDUR Dari Tanggal : 15 Juli 2018
TAHUN ANGG: 2018 Sampai Tanggal : 24 Juli 2018
REALISASI PEKERJAAN
BOBOT
NO JENIS PEKERJAAN VOLUME SATUAN MINGGU LALU MINGGU INI SAMPAI MINGGU INI KET.
(%)
VOLUME BOBOT % VOLUME BOBOT % VOLUME BOBOT %
1 2 3 4 5 6 7 8 9 10 11 12
A ELEKTRIKAL

A.1 PEKERJAAN TEGANGAN MENENGAH

1 PLN
a. Biaya Penyambungan 1.00 ls 2.24
b. UJL ( Uang Jaminan Langganan 1.00 ls 0.41
2 Transformator, kapasitas 300 kVA 1.00 unit 1.17
JILP 1.00 ls 0.89
3 Sertifikat laik operasi 1.00 ls 0.44
4 Kordinasi dan Pemasangan 1.00 ls 0.29
5 Panel TM
Incoming cubicle IM-SM6 1.00 unit 0.58
Outgoing cubicle QM-SM6 to Trafo 1.00 unit 0.58
6 Cabel TM
Dari Panel TM PLN ke Panel MVMDP
N2XSEBY 3 x (1 x 95 mm2) 20.00 m¹ 0.18
Dari Panel MVMDP ke Travo 500 KVA
N2XSY 3 x (1 x 70 mm2) 60.00 m¹ 0.42
7 Grounding System 5.00 titik 0.17
7.37

A.2 PEKERJAAN PANEL


1 Panel LVMDP 1.00 unit 1.40
2 Panel Capacitor Bank 300 KVA 1.00 unit 0.41
3 Panel SDP 1.00 unit 0.29
4 Panel LP.1 1.00 unit 0.10
5 Panel LP.2 1.00 unit 0.10
8 Panel Pompa Sumpit (PP-SUMPIT) 1.00 unit 0.10
9 Panel Pompa Hydrant (PP-HY) 1.00 unit 0.12
10 Panel Pompa Transfer (PP-AB.1) 1.00 unit 0.20
11 Panel OK (Iso Transformer - Ruang Operasi) 2.00 unit 0.35
3.07

A.3 PEKERJAAN KABEL FEEDER


Kabel Feeder dari LVMDP ke :
1 Panel SDP.A NYFGbY 4x95 mm2 36.00 m¹ 0.40
2 Panel LP.1 NYFGbY 4x10 mm2 26.00 m¹ 0.04
3 Panel LP.2 NYFGbY 4x10 mm2 31.00 m¹ 0.04
4 Panel Pompa Transfer (PNYFGbY 4x16 mm2 30.00 m¹ 0.07
5 Panel Pompa Hydrant (P FRC 4x35 mm2 30.00 m¹ 0.15
7 Panel Capacitor NYY 2x(4x1Cx120 mm2) 15.00 m¹ 0.29
8 Transformer 500 KVA NYY 8 x (1C x 240 mm2) 20.00 m¹ 0.35
9 Panel Kontrol Genset (P NYY 8 x (1C x 240 mm2) 20.00 m¹ 0.35
Kabel Feeder dari SDP.3 ke :
10 Panel OK.1 (Iso Transfor NYY 2 x 35 mm2 20.00 m¹ 0.02
11 Panel OK.2 (Iso Transfor NYY 2 x 35 mm2 27.00 m¹ 0.03
Kabel Feeder dari LP.1 ke :
12 Panel Pompa Sumpit NYFGbY 4x4 mm2 33.00 m¹ 0.02
1.76

A.4 INSTALASI PENERANGAN / ARMATURE


1' a. Lantai 1
1' 1 Lampu RMI 2x18 W 9.00 bh 0.10
1' 2 Lampu DL 8 W 3.00 bh 0.01
1' 3 Lampu DL 10 W 30.00 bh 0.11
1' 8 Exhouse Fan 50 CFM 25 W + pipa exhause PVC AW Ø4" 3.00 bh 0.02
1' 9 Stop Kontak 23.00 bh 0.01
1' 10 Saklar Ganda 2.00 bh 0.00
1' 11 Saklar Tunggal 18.00 bh 0.01
1' 13 Inst. Penerangan NYM 3 x 2,5 mm2 + PVC kond. HI 20 mm 42.00 ttk 0.11
1' 14 Inst. Stop kontak NYM 3 x 2,5 mm2 + PVC kond. HI 20 mm 43.00 ttk 0.19
1' 0.55
2' b. Lantai 2
2' 1 Lampu TKI 2x18 W 12.00 bh 0.13
2' 2 Lampu DL 13 W 8.00 bh 0.02
2' 3 Lampu DL 18 W 48.00 bh 0.17
2' 4 Exhouse Fan 50 CFM 25 W + pipa exhause PVC AW Ø4" 5.00 bh 0.02
2' 5 Stop Kontak 20.00 bh 0.01
2' 6 Saklar Ganda 10.00 bh 0.004
2' 7 Saklar Tunggal 34.00 bh 0.01
2' 8 Inst. Penerangan NYM 3 x 2,5 mm2 + PVC kond. HI 20 mm 68.00 bh 0.18
2' 9 Inst. Stop kontak NYM 3 x 2,5 mm2 + PVC kond. HI 20 mm 64.00 bh 0.28
0.83

GNST c. SITE PLAN (R. GENSET, PLN, SENTRAL GAS MEDIS)


GNST 1 Lampu TL Balk 1x36 W 8.00 bh 0.08
GNST 3 Exhouse Fan, Type Industrial 3.00 bh 0.02
GNST 4 Stop Kontak 200 W 1.00 bh 0.0004
GNST 5 Saklar Ganda 4.00 bh 0.0017
GNST 6 Saklar Tunggal 2.00 bh 0.0007
BOBOT
NO JENIS PEKERJAAN VOLUME SATUAN MINGGU LALU MINGGU INI SAMPAI MINGGU INI KET.
(%)
VOLUME BOBOT % VOLUME BOBOT % VOLUME BOBOT %
GNST 7 Inst. Penerangan NYM 3 x 2,5 mm2 + PVC kond. 20 mm 8.00 ttk 0.02
GNST 8 Inst. Stop kontak NYM 3 x 2,5 mm2 + PVC kond. 20 mm 7.00 ttk 0.03
0.1559

Sub - Jumlah Pekerjaan Penerangan / Armature 1.54

A5 PENANGKAL PETIR
1 Air Terminal Radius Proteksi 70 M 1.00 unit 0.08
2 Kabel Kondutor Coaxial 2x70mm2 (teg tinggi) 35.00 m' 0.07
3 Support 1.00 ls 0.01
4 Test Box 1.00 unit 0.01
5 Grounding BC 50mm2 + copper rod 12m, klemp dll 2.00 unit 0.04
6 Lightning Strike Recorder 1.00 unit 0.02
7 Pipa Galvanis T=3m 1.00 unit 0.01
8 Ijin Depnaker 1.00 ls 0.04
0.27

A.6 PEKERJAAN INSTALASI GENSET

Pengadaan dan Pemasangan Instalasi Genset


1 Genset 300 KVA 1.00 unit 4.08
1 Panel Kontrol Genset 1.00 unit 0.64
2 Setting Genset lengkap dengan pemasangan angker 1.00 unit 0.08
3 Concreate bending clereance area radiator 1.00 Lot 0.06
4 Exhaust radiator ducting 1.00 Lot 0.09
5 Grounding body dan netral ( BC 50 mm2 P. Genset ) 2.00 Lot 0.07
5.02

PEKERJAAN GAS MEDIS

PEKERJAAN PERALATAN UTAMA DAN PENDUKUNG


01 INSTALASI UTAMA
1 Central Gas medis oxygen manual system Unit 1 0.47
Kapasita 2 x 5 tabung manua system
2 Central Gas medis N2O manual system Unit 1 0.26
Kapasita 2 x 1 tabung manua system
3 Central Gas medis udara tekan manual system Unit 1 0.51
Kapasita2 2 x 5 tabung manua system
1.24

02 INSTALASI DALAM BANGUNAN


1 LANTAI SATU
2.1 Pipa Tembaga ASTM B 819 Type L
1 - Diameter 1" M 0.00
Supporting Material Lot 0.00

2 Instalasi Jaringan Oksigen


2.2 Pipa Tembaga ASTM B 819 Type L
1 - Diameter 1" M 54.00 0.09
- Diameter 3/4" M 12.00 0.02
2 Supporting Material Lot 1.00 0.01

2.3 Instalasi Jaringan Nitrous Oxide


Pipa Tembaga ASTM B 819 Type L
1 - Diameter 3/4" M 66.00 0.11
2 Supporting Material Lot 1.00 0.005

2.4 Instalasi Jaringan Comp. Air


Pipa Tembaga ASTM B 819 Type L
1 - Diameter 3/4" M 66.00 0.11
2 Supporting Material Lot 1.00 0.005

2.5 Instalasi Jaringan Vacuum


Pipa Tembaga ASTM B 819 Type L
1 - Diameter 1" M 66.00 0.12
2 Supporting Material Lot 1.00 0.01

0.24
2 LANTAI DUA
1.1 PEKERJAAN PEMIPAAN
1.1.1 Instalasi Jaringan Oksigen
1 Pipa Tembaga ASTM B 819 Type L
- Diameter 3/8" M 21.00 0.02
- Diameter 5/8" M 24.00 0.04
- Diameter 3/4" M 16.00 0.04
- Diameter 1" M 14.00 0.06
2 Supporting Material Lot 1.00 0.01
1.1.4 Instalasi Jaringan Vacuum
1 Pipa Tembaga ASTM B 819 Type L
- Diameter 1/2" M 21.00 0.02
- Diameter 5/8" M 24.00 0.04
- Diameter 3/4" M 16.00 0.04
- Diameter 1" M 14.00 0.06
2 Supporting Material Lot 1.00 0.01
BOBOT
NO JENIS PEKERJAAN VOLUME SATUAN MINGGU LALU MINGGU INI SAMPAI MINGGU INI KET.
(%)
VOLUME BOBOT % VOLUME BOBOT % VOLUME BOBOT %
1.2 PERALATAN DALAM RUANGAN
1 Wall Outlet Oxygen (O), pin index, push type Buah 2.00 0.04
2 Wall Outlet Vacuum (V), pin index, push type, slide base Buah 2.00 0.04
3 Zona Valve 2 Gas (O, V) Set 1.00 0.09
4 Area Alarm 2 Gas (O, V) Set 1.00 0.12
5 Bedhead Unit, Aluminium, L=1200 mm Buah 2.00 0.05

0.66

Sub Total - Gas Medis 2.14

B1 SISTEM FIRE ALARM & EXTINGUSER

B1 PERALATAN UTAMA & KABEL FEEDER


PERALATAN UTAMA (Ruang Kontrol)
1 Main Control Panel ( MCP-FA ) 6 Zone 1.00 set 0.25
2 MDF-FA c/wPower and Line Surge Arrester + UPS 2 Kva + Rectifier 48V + 1.00 set 0.20
Nicad ,Grounding.

Pengadaan dan pemasangan TBFA sesuai gambar dan spesifikasi


1 TB-FA.1 c/w Addrs.Module 1.00 unit 0.06
2 TB-FA.2 c/w Addrs.Module 1.00 unit 0.06

KABEL FEEDER DARI MCP-FA KE


1 NYA 4 (1 x 2,5 mm2) + PVC ConduitTB.FA-1 1.00 ttk 0.01
2 NYA 4 (1 x 2,5 mm2) + PVC ConduitTB.FA-2 1.00 ttk 0.01
4 NYA 4 (1 x 2,5 mm2) + PVC ConduitPanel Control Genset 1.00 ttk 0.01
5 NYA 4 (1 x 2,5 mm2) + PVC ConduitPompa Kebakaran 1.00 ttk 0.01
6 NYA 4 (1 x 2,5 mm2) + PVC ConduitLVMDP 1.00 ttk 0.01
7 NYA 4 (1 x 2,5 mm2) + PVC ConduitLIFT 1.00 ttk 0.01
0.61

D.2 Lantai 1
1 Instalasi Fire Alarm Kabel NYM 2 x 1,5 mm² dalam conduit PVC HI 20 mm² 8.00 ttk 0.04
2 Rate of Rise Heat Detector 281B-PL 8.00 bh 0.03
3 Break Glass 2.00 bh 0.01
4 Alarm Bell SSM24-6 2.00 bh 0.02
5 Indicator Lamp G1R-VM 2.00 bh 0.02
6 Portable Fire Extinguiser 5 kg / CO2 3.00 bh 0.07
0.19
D.3 Lantai 2
1 Instalasi Fire Alarm Kabel NYM 2 x 1,5 mm² dalam conduit PVC HI 20 mm² 8.00 ttk 0.03
2 Rate of Rise Heat Detector 281B-PL 8.00 bh 0.03
3 Break Glass 2.00 bh 0.01
4 Alarm Bell SSM24-6 2.00 bh 0.02
5 Indicator Lamp G1R-VM 2.00 bh 0.02
6 Portable Fire Extinguiser 5 kg / CO2 3.00 bh 0.07
0.17

Sub Total - Fire Alarm 0.97

B2 SISTEM TELEPON
B2.1 Peralatan Utama
.-PABX kapasitas 2 line / 10 extention : 1.00 unit 0.14
.-Lengkap dengan ;
- 1 Rak Cabinet
- 1 Unit Operator Console
- 1 Unit Back up Battery
- Surge Arrester
.-Main Distribution Frame Kapasitas 1 x 20 pair 1.00 unit 0.01
.-Instalasi peralatan utama 1.00 bh 0.01
Kabel Utama
Kabel Jelly Armoured (10 x 2 xd.0,6 mm) Dari Box Telkom ke PABX
Kabel dari MDF dalam conduit PVC HI dia. 20 mm dengan kabel :
- ITC 20 ( 2 x d. 0,6 mm) ke TB. TP -1 10.00 m1 0.01
- ITC 20 ( 2 x d. 0,6 mm) ke TB. TP -2 15.00 m1 0.01
0.18

B2.2 Lantai 1
1 Telepon Outlets ( FCC Standard ) /w Surround 1 Gang - 6 Wire 5.00 ttk 0.01
2 Instalasi Kabel Telepon ITC 2 x 2 x 0.6 mm² dalam conduit PVC HI 20 mm² 5.00 ttk 0.04
3 Pesawat Extention 5.00 bh 0.02
4 TB 20 Pair 1.00 bh 0.01
0.07
B2.3 Lantai 2
1 Telepon Outlets ( FCC Standard ) /w Surround 1 Gang - 6 Wire 3.00 ttk 0.01
2 Instalasi Kabel Telepon ITC 2 x 2 x 0.6 mm² dalam conduit PVC HI 20 mm² 3.00 ttk 0.02
3 Pesawat Extention 3.00 bh 0.01
4 TB 20 Pair 1.00 bh 0.01
0.05
BOBOT
NO JENIS PEKERJAAN VOLUME SATUAN MINGGU LALU MINGGU INI SAMPAI MINGGU INI KET.
(%)
VOLUME BOBOT % VOLUME BOBOT % VOLUME BOBOT %

Sub Total - Telepon 0.34

B3 DATA KOMPUTER
B3.1 Lantai 1
1 Instalasi Data 5.00 ttk 0.02
2 Outlet Data 5.00 ttk 0.01
0.02
B3.2 Lantai 2
1 Instalasi Data 2.00 ttk 0.01
2 Outlet Data 2.00 ttk 0.00
4 Hub Switch 1.00 unit 0.06
5 UPS 220V 1.00 unit 0.12
6 Server 1.00 unit 0.12
0.30

Sub Total - Data Komputer 0.32

B5 PEKERJAAN CCTV

B5.1 PERALATAN UTAMA


a. Digital Video Recorder 16 chanel Unit 1.00 0.20
b. LCD TV Monitor 32 '' Unit 1.00 0.05
c. 2 Channel Zoom Controller Unit 1.00 0.09
d. CPU Computer and Programing Unit 1.00 0.12
e. IP TV Headend Unit 1.00 0.08
f. Patch Panel 24 Port Nos 1.00 0.02
g UPS 1 kva Unit 1.00 0.05
h Adaptor 12 VA Unit 1.00 0.07
0.69

B5.2 LANTAI 1
a CCTV COLOUR CAMERA INDOOR c/w Fixed DOME Unit 1.00 0.04
b CCTV COLOUR CAMERA OUTDOOR c/w PAN and TILT Unit 2.00 0.04
c CCTV Outlet Installation, UTP CAT 6 in PVC HI conduit 20mm Nos 2.00 0.01
0.09

B5.3 LANTAI 2
a CCTV COLOUR CAMERA INDOOR Unit 2.00 0.04
b CCTV COLOUR CAMERA OUTDOOR c/w PAN and TILT Unit 1.00 0.02
c CCTV Outlet Installation, UTP CAT 6 in PVC HI conduit 20mm Nos 2.00 0.01
0.07

Sub Total - CCTV 0.90

C2 TATA UDARA
C2.1 Lantai 1
A AIR CONDITIONING
1 AC Split 1 PK 12.00 unit 0.55
2 AC Split 0.5PK 4.00 unit 0.14
B INSTALASI AIR CONDITIONING
1 Instalasi Daya AC + Pemasangan 16.00 ttk 0.12
2 Instalasi Pipa Refrigerant lengkap dengan isolasi 16.00 ttk 0.33
ARMAFLEX / AEROFLEX tebal 19 mm.
KETEBALAN PIPA astm B260
1.14
C2.2 Lantai 2
A AIR CONDITIONING
1 AC Split 1 PK 4.00 unit 0.18
2 AC Split 0.5PK 10.00 unit 0.36
B INSTALASI AIR CONDITIONING
1 Instalasi Daya AC + Pemasangan 6.00 ttk 0.04
2 Instalasi Pipa Refrigerant lengkap dengan isolasi 6.00 ttk 0.12
ARMAFLEX / AEROFLEX tebal 19 mm.
KETEBALAN PIPA astm B260
0.71

0.71

D PLUMBING

D1 AIR BERSIH
a. RUANG POMPA
1 Pompa Transfer 1 & 2 2.00 unit 0.35
Capasitas : 1,5 M3 / Menit
Head : 30 M
2 Header Ø 100 x 2.000 mm 1.00 lot 0.07
3 Gate Valve Ø 2" 5.00 nos 0.07
4 Gate Valve Ø 1 1/2" 2.00 nos 0.02
5 Gate Valve Ø 1" 1.00 nos 0.00
6 Gate Valve Ø 3/4" 1.00 nos 0.00
7 Check Valve Ø 2" 2.00 nos 0.03
8 Strainer Ø 2" 2.00 nos 0.02
9 Flexible Joint Ø 2" 4.00 nos 0.02
10 Pressure Gauge 2.00 nos 0.02
11 Pressure Switch 2.00 nos 0.03
12 Floating Valve Ø 2" 2.00 nos 0.02
13 Foot valve Ø 2" 2.00 nos 0.05
BOBOT
NO JENIS PEKERJAAN VOLUME SATUAN MINGGU LALU MINGGU INI SAMPAI MINGGU INI KET.
(%)
VOLUME BOBOT % VOLUME BOBOT % VOLUME BOBOT %
14 Pipa GIP medium Ø 2" 10.00 m1 0.02
15 Pipa GIP medium Ø 1 1/2" 10.00 m1 0.02
16 Fitting 1.00 lot 0.01
17 Control Panel 1.00 unit 0.03
18 WLC (all ground reservoir tank) 1.00 unit 0.01
20 Supporting Material 1.00 lot 0.01
0.81

b. SITE PLAN & RISER


1 Pipa GIP medium Ø 1 1/2" 42.00 m1 0.06
2 Pipa GIP medium Ø 2" 28.00 m1 0.05
3 Gate Valve Ø 2" 3.00 nos 0.04
4 Gate Valve Ø 1 1/2" 2.00 nos 0.02
5 Fitting 1.00 lot 0.02
6 Supporting Material 1.00 lot 0.01
0.20

c. LANTAI 1
1 Pipa PPR PN Ø 15 mm 4.00 m1 0.002
2 Pipa PPR PN Ø 20 mm 62.00 m1 0.033
3 Pipa PPR PN Ø 25 mm 2.00 m1 0.002
4 Pipa PPR PN Ø 32 mm 5.00 m1 0.01
5 Pipa PPR PN Ø 40 mm 48.00 m1 0.08
6 Gate Valve Ø 40 mm 1.00 nos 0.01
7 Fitting 1.00 lot 0.02
8 Supporting Material 1.00 lot 0.02
0.17

d. LANTAI 2
1 Pipa PPR PN Ø 15 mm 1.00 m1 0.0004
2 Pipa PPR PN Ø 20 mm 41.60 m1 0.02
3 Pipa PPR PN Ø 25 mm 41.50 m1 0.03
4 Pipa PPR PN Ø 32 mm 50.00 m1 0.06
5 Fitting 1.00 nos 0.005
6 Supporting Material 1.00 lot 0.02
1.00 lot 0.02
0.16

Sub Total - Air Bersih 1.34

D2 AIR KOTOR
a. LAY OUT SITE PLAN

1 Pompa Sumpit, Cap. 300L / M 1.00 unit 0.26


2 Automatic water level control panel FOR 1.00 unit 0.15
sumpit pump (parallel alternate operation
system)
3 Gate Valve Ø 80 mm 2.00 nos 0.02
4 Check Valve Ø 80 mm 2.00 nos 0.02
5 Pipa PVC Class AW Ø 100 mm 6.00 m1 0.01
6 Pipa PVC Class AW Ø 80 mm 27.00 m1 0.03
7 Pipa PVC Class AW Ø 50 mm 5.00 m1 0.00
8 Fitting 1.00 lot 0.01
9 Supporting Material 1.00 lot 0.01
0.51

b. PIPA RISER
1 Pipa PVC Class AW Ø 100 mm 14.00 m1 0.02
2 Pipa PVC Class AW Ø 80 mm 12.00 m1 0.01
3 Pipa PVC Class D Ø 50 mm 12.00 m1 0.01
4 Fitting 1.00 lot 0.01
5 Supporting Material 1.00 lot 0.01
0.07

c. LANTAI 1
1 Pipa PVC Class AW Ø 100 mm 64.00 m1 0.11
2 Pipa PVC Class AW Ø 80 mm 65.50 m1 0.08
3 Pipa PVC Class AW Ø 50 mm 54.00 m1 0.04
4 Fitting 1.00 lot 0.04
5 Clean Out Ø 100 mm (Steinless) 2.00 nos 0.01
6 Clean Out Ø 50 mm (Steinless) 2.00 nos 0.01
7 Supporting Material 1.00 lot 0.03
0.31

d. LANTAI 2
1 Pipa PVC Class AW Ø 100 mm 62.00 m1 0.11
2 Pipa PVC Class AW Ø 80 mm 14.00 m1 0.02
3 Pipa PVC Class AW Ø 50 mm 30.00 m1 0.02
4 Fitting 1.00 lot 0.03
5 Clean Out Ø 100 mm (Steinless) 2.00 nos 0.01
6 Clean Out Ø 80 mm (Steinless) 1.00 nos 0.00
7 Clean Out Ø 50 mm (Steinless) 2.00 nos 0.01
8 Supporting Material 1.00 lot 0.02
0.21

1.10
LAPORAN KEMAJUAN MEP GEDUNG A
PEKERJAAN : PEMBANGUNAN RUMAH SAKIT NANDA SYIFA Minggu Ke : 22 ( Dua Puluh Dua)
LOKASI : JL. RAYA GUNUNG SINDUR Dari Tanggal : 15 Juli 2018
TAHUN ANGGARAN : 2018 Sampai Tanggal : 24 Juli 2018
REALISASI PEKERJAAN
NO JENIS PEKERJAAN VOLUME SATUAN BOBOT MINGGU LALU MINGGU INI SAMPAI MINGGU INI KET.
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
1 2 3 4 5 6 7 8 9 10 11 12
A ELEKTRIKAL

A.2 PEKERJAAN PANEL


1 Panel SDP.B 1.00 unit 0.292
2 Panel LP.1 1.00 unit 0.100
Sub Total Pekerjaan Panel 0.394

A.3 PEKERJAAN KABEL FEEDER


Kabel Feeder dari LVMDP ke :
1 Panel SDP.B NYFGbY 4x95 mm2 36.00 m¹ 0.403
2 Panel LP.1 NYFGbY 4x10 mm2 26.00 m¹ 0.037
Sub Total Kabel Feeder 0.441

A.4 INSTALASI PENERANGAN / ARMATURE


a. Lantai 1
1 Lampu TL Louvre 2x18 W 9.00 bh 0.100
5 Lampu DL 8 W 1.00 bh 0.003
6 Lampu DL 10 W 5.50 bh 0.020
8 Exhouse Fan 50 CFM 25 W + pipa exhause PVC AW Ø4" 1.00 bh 0.006
9 Stop Kontak 200 W 9.00 bh 0.004
11 Saklar Tunggal 8.00 bh 0.003
13 Inst. Penerangan NYM 3 x 2,5 mm2 + PVC kond. HI 20 mm 15.00 ttk 0.040
14 Inst. Stop kontak NYM 3 x 2,5 mm2 + PVC kond. HI 20 mm 9.00 ttk 0.040
0.216

b. Lantai 2
1 Lampu TL Louvre 2x18 W 15.00 bh 0.166
3 Lampu DL 13 W 9.00 bh 0.026
4 Lampu DL 18 W 18.00 bh 0.064
6 Exhouse Fan 50 CFM 25 W + pipa exhause PVC AW Ø4" 9.00 bh 0.058
7 Stop Kontak 200 W 34.00 bh 0.017
8 Saklar Ganda 9.00 bh 0.004
9 Saklar Tunggal 13.00 bh 0.005
12 Inst. Penerangan NYM 3 x 2,5 mm2 + PVC kond. HI 20 mm 42.00 ttk 0.112
13 Inst. Stop kontak NYM 3 x 2,5 mm2 + PVC kond. HI 20 mm 34.00 ttk 0.149
0.601

Sub Total Instalasi Penerangan 0.431

B1 SISTEM FIRE ALARM & EXTINGUSER

B1 PERALATAN UTAMA & KABEL FEEDER


PERALATAN UTAMA (Ruang Kontrol)
1 MDF-FA c/wPower and Line Surge Arrester + UPS 2 Kva + Rectifier 48V + 1.00 set 0.204
Nicad ,Grounding.

Pengadaan dan pemasangan TBFA sesuai gambar dan spesifikasi


1 TB-FA.1 c/w Addrs.Module 1.00 unit 0.058

KABEL FEEDER DARI MCP-FA KE


1 NYA 4 (1 x 2,5 mm2) + PVC Conduit High Impact dia 20 mmTB.FA-1 1.00 ttk 0.006
4 NYA 4 (1 x 2,5 mm2) + PVC Conduit High Impact dia 20 mmPanel Control Genset 1.00 ttk 0.006
5 NYA 4 (1 x 2,5 mm2) + PVC Conduit High Impact dia 20 mmPompa Kebakaran 1.00 ttk 0.006
6 NYA 4 (1 x 2,5 mm2) + PVC Conduit High Impact dia 20 mmLVMDP 1.00 ttk 0.006
0.36

D.2 Lantai 1
1 Instalasi Fire Alarm Kabel NYM 2 x 1,5 mm² dalam conduit PVC HI 20 mm² 8.00 ttk 0.045
2 Rate of Rise Heat Detector 281B-PL 6.00 bh 0.021
3 Break Glass 1.00 bh 0.003
4 Alarm Bell SSM24-6 1.00 bh 0.008
5 Indicator Lamp G1R-VM 1.00 bh 0.012
6 Portable Fire Extinguiser 5 kg / CO2 2.00 bh 0.047
0.136

Sub total Fire Alarm 0.50


NO JENIS PEKERJAAN VOLUME SATUAN BOBOT MINGGU LALU MINGGU INI SAMPAI MINGGU INI KET.
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT

B2 SISTEM TELEPON

B2.2 Lantai 1
1 Telepon Outlets ( FCC Standard ) /w Surround 1 Gang - 6 Wire 9.00 ttk 0.021
2 Instalasi Kabel Telepon ITC 2 x 2 x 0.6 mm² dalam conduit PVC HI 20 mm² 9.00 ttk 0.063
3 Pesawat Extention 9.00 bh 0.032
4 TB 20 Pair 1.00 bh 0.009
0.124

Lantai 2
1 Telepon Outlets ( FCC Standard ) /w Surround 1 Gang - 6 Wire 9.00 ttk 0.021
2 Instalasi Kabel Telepon ITC 2 x 2 x 0.6 mm² dalam conduit PVC HI 20 mm² 9.00 ttk 0.063
3 Pesawat Extention 9.00 bh 0.032
4 TB 20 Pair 1.00 bh 0.009
0.124

Sub Total Telepon 0.248

B3 DATA KOMPUTER
B3.1 Lantai 1
1 Instalasi Data 1.00 ttk 0.004
2 Outlet Data 1.00 ttk 0.001
3 Komputer 1.00 unit 0.047
4 UPS 220V 1.00 unit 0.117
5 Hub Switch 1.00 unit 0.058
Sub Total Data Komputer 0.231

B4 SISTEM NURSE CALL


B4.1 Lantai 1
1 Nurse Call Outlets 2.00 ttk 0.001
2 Nurse Call Instalation 14.00 ttk 0.131
3 Switch Pasien 14.00 bh 0.034
4 Reset 2.00 bh 0.007
5 Lampu Tanda Panggilan 1.00 bh 0.003
6 Master Call Station 1.00 bh 0.019
7 TB NC 1.00 set 0.007
0.202

B4.1 Lantai 2
1 Nurse Call Outlets 2.00 ttk 0.001
2 Nurse Call Instalation 14.00 ttk 0.131
3 Switch Pasien 14.00 bh 0.034
4 Reset 2.00 bh 0.007
5 Lampu Tanda Panggilan 1.00 bh 0.003
6 Master Call Station 1.00 bh 0.019
7 TB NC 1.00 set 0.007
0.202

Sub Total Nurse Call 0.404

B5 PEKERJAAN CCTV

B5.2 LANTAI 1
a CCTV COLOUR CAMERA INDOOR c/w Unit 1.00 0.020
b CCTV COLOUR CAMERA OUTDOOR c/w PAN and TILT Unit 1.00 0.020
c CCTV Outlet Installation, UTP CAT 6 in PVC HI conduit 20mm Nos 2.00 0.014
Sub Total CCTV 0.054

C2 TATA UDARA
C2.1 Lantai 1
A AIR CONDITIONING
1 Capacity : 1/2 pk, ac split 1.00 unit 0.036
3 Capacity : 1 pk, ac split 9.00 unit 0.415
B INSTALASI AIR CONDITIONING
1 Instalasi Daya AC + Pemasangan 10.00 ttk 0.050
2 Instalasi Pipa Refrigerant lengkap dengan isolasi 10.00 ttk 0.134
ARMAFLEX / AEROFLEX tebal 19 mm.
KETEBALAN PIPA astm B260
0.635

Lantai 2
A AIR CONDITIONING
1 Capacity : 1/2 pk, ac split 1.00 unit 0.036
3 Capacity : 1 pk, ac split 6.00 unit 0.277
B INSTALASI AIR CONDITIONING
1 Instalasi Daya AC + Pemasangan 9.00 ttk 0.045
2 Instalasi Pipa Refrigerant lengkap dengan isolasi 9.00 ttk 0.121
ARMAFLEX / AEROFLEX tebal 19 mm. 0.478
KETEBALAN PIPA astm B260
Sub Total Tata Udara 1.11

C3 PEKERJAAN GAS MEDIS


NO JENIS PEKERJAAN VOLUME SATUAN BOBOT MINGGU LALU MINGGU INI SAMPAI MINGGU INI KET.
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
INSTALASI DALAM BANGUNAN
1 LANTAI SATU
1.1 PEKERJAAN PEMIPAAN
1.1.1 Instalasi Jaringan Oksigen
1 Pipa Tembaga ASTM B 819 Type L
- Diameter 3/8" M 21.00 0.015
- Diameter 5/8" M 24.00 0.039
- Diameter 3/4" M 16.00 0.037
- Diameter 1" M 14.00 0.060
2 Supporting Material Lot 1.00 0.012
1.2 PERALATAN DALAM RUANGAN
1 Wall Outlet Oxygen (O), pin index, push type Buah 5.00 0.099
2 Bedhead Unit, Aluminium, L=1200 mm Buah 10.00 0.216
2 LANTAI DUA
1.1 Instalasi Jaringan Oksigen
Pipa Tembaga ASTM B 819 Type L M 21.00 0.015
- Diameter 3/8" M 24.00 0.039
- Diameter 5/8" M 16.00 0.037
- Diameter 3/4" M 14.00 0.060
- Diameter 1" Lot 1.00 0.012
Supporting Material
1.2 PERALATAN DALAM RUANGAN
1 Wall Outlet Oxygen (O), pin index, push type Buah 5.00 0.099
2 Bedhead Unit, Aluminium, L=1200 mm Buah 10.00 0.216
Sub Total Gas Medis 0.958

D PLUMBING

D1 AIR BERSIH

c. LANTAI 1
1 Pipa PPR PN Ø 15 mm 12.50 m1 0.005
2 Pipa PPR PN Ø 20 mm 12.00 m1 0.006
3 Pipa PPR PN Ø 25 mm 11.00 m1 0.008
4 Pipa PPR PN Ø 32 mm 10.00 m1 0.012
5 Gate Valve Ø 32 mm 1.00 nos 0.005
6 Fitting 1.00 lot 0.006
7 Supporting Material 1.00 lot 0.004
0.047

c. LANTAI 2
1 Pipa PPR PN Ø 15 mm 12.50 m1 0.005
2 Pipa PPR PN Ø 20 mm 12.00 m1 0.006
3 Pipa PPR PN Ø 25 mm 11.00 m1 0.008
4 Pipa PPR PN Ø 32 mm 10.00 m1 0.012
5 Gate Valve Ø 32 mm 1.00 nos 0.005
6 Fitting 1.00 lot 0.006
7 Supporting Material 1.00 lot 0.004
0.047

Sub Total Air Bersih 0.094

D2 AIR KOTOR

c. LANTAI 1
1 Pipa PVC Class AW Ø 100 mm 6.00 m1 0.010
2 Pipa PVC Class AW Ø 80 mm 6.00 m1 0.007
3 Pipa PVC Class AW Ø 50 mm 6.00 m1 0.004
4 Pipa PVC Class D Ø 40 mm 3.00 m1 0.002
5 Supporting Material 1.00 lot 0.003
6 Fitting 1.00 0.006
0.027
B. LANTAI 2
1 Pipa PVC Class AW Ø 100 mm 6.00 m1 0.010
2 Pipa PVC Class AW Ø 80 mm 6.00 m1 0.007
3 Pipa PVC Class AW Ø 50 mm 6.00 m1 0.004
4 Pipa PVC Class D Ø 40 mm 3.00 m1 0.002
5 Supporting Material 1.00 lot 0.003
6 Pipa PPR PN Ø 25 mm 6.00 m1 0.036
0.027

Sub Total Air Kotor 0.053

Sub Total - Plumbing 0.147


RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT NANDA SYIFA

LOKASI : JL.PEMUDA ,GN SINDUR BOGOR JAWA BARAT

PEMBERI TUGAS : PT.PETRIZ JAYA MEDIKA

Tahun Anggaran :

NO JENIS PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA KETERANGAN

1 2 3 4 5 6
III.1 PEKERJAAN PERSIAPAN
1 Pengukuran 209.00 m' 13,750.00 2,873,750.00

2 Pembersihan 1.00 ls 12,000,000.00 12,000,000.00

Sub - Jumlah 14,873,750.00

III.2 LANTAI 1

A PEKERJAAN PASANGAN DINDING

1 Pasangan Bata Ringan 387.84 m² 134,064.98 51,995,491.77

2 Plesteran 775.68 m² 66,513.70 51,593,080.76

3 Acian 775.68 m² 58,924.03 45,705,955.89

4 Benangan 742.50 m' 18,090.60 13,432,270.50

5 Kolom Praktis Uk. 12x15 cm 148.35 m' 149,102.80 22,119,400.38

6 Ring Balok Uk. 12x15 cm 2.35 m³ 5,423,631.79 12,740,111.08

7 Rabatan keliling bangunan 70.50 m2 1,095,540.73 77,235,621.38

8 Saluran keliling bangunan, U-30 70.50 m1 97,500.00 6,873,750.00

9 Bak kontrol 40x40 10.00 bh 145,000.00 1,450,000.00

10 Grill penutup saluran 70.50 m1 325,000.00 22,912,500.00

Sub - Jumlah 197,586,310.39 -

B PEKERJAAN PLAFOND

1 Plafond Gyptile, Rangka Hollow 237.25 m² 169,529.14 40,220,788.47

2 Plafond Kalsiboard T. 9mm, Rangka hollow 12.00 m² 149,349.75 1,792,197.00

3 List Plafond Gypsumboard 445.00 m' 17,622.00 7,841,790.00

Sub - Jumlah 49,854,775.47

C PEKERJAAN PENUTUP LANTAI DAN DINDING

1 Lantai Granite Tile Uk.60x60 cm, Polised Warna Terang 237.25 m² 454,051.13 107,723,629.41

2 Hospital Plint Uk. 8x30 cm ex Roman 445.00 m' 82,760.00 36,828,200.00

3 Lantai Keramik Motif Uk.60x60 cm, Ex. Roman 10.08 m² 172,532.25 1,739,125.08

4 Lantai Keramik 25x25 Unpolised Warna Terang (Area KM/WC) 12.00 m² 191,675.00 2,300,100.00

5 Dinding Keramik KM/WC dll. 56.00 m² 220,740.85 12,361,487.60

Sub - Jumlah 160,952,542.09

D PEKERJAAN PENGECATAN

1 Cat Tembok Interior 548.08 m² 23,379.40 12,813,688.03

2 Cat Tembok Eksterior 227.60 m² 52,404.33 11,927,225.51


3 Cat Plafond 249.25 m² 23,379.40 5,827,315.45

4 Cat List Plafond 445.00 M1 23,379.40 10,403,833.00

Sub - Jumlah 40,972,061.99


E PEKERJAAN KUSEN - DAUN PINTU DAN JENDELA

1 PIA - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 4,351,340.10 4,351,340.10

2 P2 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 4.00 unit 4,665,409.80 18,661,639.22

3 P3 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 4.00 unit 2,707,445.68 10,829,782.70

4 P9 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 3,375,340.84 3,375,340.84

5 BV - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 4.00 unit 546,133.89 2,184,535.54

6 J1 - Rangka Kusen Alumunium 14.00 unit 2,956,854.59 41,395,964.23

Sub - Jumlah 80,798,602.62

G PEKERJAAN SANITARI

1 Closet Duduk 4.00 unit 3,386,845.00 13,547,380.00

2 Wastafel 4.00 unit 1,577,346.76 6,309,387.04

3 Kran Stainless Steel (KM/WC) 4.00 bh 83,798.00 335,192.00

4 Toilet Shower / Jet Shower 4.00 bh 298,298.00 1,193,192.00

5 Kaca Cermin 4.00 bh 288,282.50 1,153,130.00

6 Tempat Sabun 4.00 bh 155,000.00 620,000.00

7 Tempat Tisue 4.00 bh 252,000.00 1,008,000.00

8 Floor Drain 4.00 bh 107,470.00 429,880.00

9 Talang Tegak PVC Ø 4" 40.00 m' 124,300.00 4,972,000.00

Sub - Jumlah 29,568,161.04

III.3 LANTAI 2

A PEKERJAAN PASANGAN DINDING

1 Pasangan Bata Ringan 360.47 m² 134,064.98 48,325,731.21

2 Plesteran (1:3) 720.93 m² 66,513.70 47,951,721.74

3 Acian 720.93 m² 58,924.03 42,480,100.95

4 Benangan 973.43 M1 18,090.60 17,609,932.76

5 Kolom Praktis Uk. 12x15 cm 175.95 m1 149,102.80 26,234,637.66

6 Ring Balok Uk. 12x15 cm 2.35 m3 5,423,631.79 12,740,111.08

Sub - Jumlah 195,342,235.41


B PEKERJAAN PLAFOND

1 Plafond Gyptile, Rangka Hollow 233.75 m² 145,986.39 34,124,318.66

2 Plafond Kalsiboard T. 9mm, Rangka hollow 22.50 m² 149,349.75 3,360,369.38

3 List Plafond Gypsumboard 198.00 m' 17,622.00 3,489,156.00

Sub - Jumlah 40,973,844.04

C PEKERJAAN PENUTUP LANTAI DAN DINDING

1 Lantai Granite Tile Uk.60x60 cm, Polised Warna Terang 222.23 m² 454,051.13 100,903,781.51

2 Hospital Plint Uk. 8x30 cm ex Roman 163.00 m² 82,760.00 13,489,880.00

3 Lantai Keramik Motif Uk.60x60 cm, Ex. Roman 11.52 m² 172,532.25 1,987,571.52

4 Lantai Keramik 25x25 Unpolised Warna Terang (Area KM/WC) 22.50 m² 191,675.00 4,312,687.50

5 Dinding Keramik KM/WC dll. 84.00 m² 220,740.85 18,542,231.40

6 Waterproofing KM 22.50 m²

Sub - Jumlah 139,236,151.93

D PEKERJAAN PENGECATAN

1 Cat Tembok Interior 455.33 m² 23,379.40 10,645,342.20

2 Cat Tembok Eksterior 265.60 m² 52,404.33 13,918,590.05

3 Cat Plafond 256.25 m² 23,379.40 5,990,971.25

4 Cat List Plafond 198.00 m² 23,379.40 4,629,121.20

5 Waterproofing + Scret Atap beton 118.25 m² 148,000.00 17,501,000.00

Sub - Jumlah 52,685,024.70

E PEKERJAAN KUSEN - DAUN PINTU DAN JENDELA

1 PIA - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 4,351,340.10 4,351,340.10

2 P2 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 6.00 unit 4,665,409.80 27,992,458.82

3 P3 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 6.00 unit 2,707,445.68 16,244,674.05

4 P8 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 3,612,299.46 3,612,299.46

5 J1 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 21.00 unit 2,956,854.59 62,093,946.34

7 BV1 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 6.00 unit 546,133.89 3,276,803.31

Sub - Jumlah 117,571,522.08

F Err:509

1 Railling Balkon (Stainlessteel Ø2", isi Ø 1") 17.50 M1 1,450,000.00 25,375,000.00

Sub - Jumlah 25,375,000.00

G PEKERJAAN SANITARI

1 Closet Duduk 6.00 unit 3,386,845.00 20,321,070.00

2 Wastafel 6.00 unit 1,577,346.76 9,464,080.56

3 Kran air stainless km/wc 6.00 bh 83,798.00 502,788.00

4 Toilet Shower / Jet Shower 6.00 bh 298,298.00 1,789,788.00

5 Kaca Cermin 6.00 bh 288,282.50 1,729,695.00

6 Tempat Sabun 6.00 bh 155,000.00 930,000.00

7 Tempat Tisue 6.00 bh 252,000.00 1,512,000.00

8 Floor Drain 6.00 bh 107,470.00 644,820.00


9 Talang Tegak PVC Ø 4" 40.00 m' 124,300.00 4,972,000.00

10 Roof Drain 10.00 unit 148,156.25 1,481,562.50

Sub - Jumlah 43,347,804.06

III PEKERJAAN ATAP

1 Rangka atap galvalume truss (0.75mm) 284.80 M2 165,000.00 46,992,000.00

2 Atap Genteng Bitumen 284.80 M2 135,000.00 38,448,000.00

3 Aluminium foil insulation sheet 284.80 m2 45,000.00 12,816,000.00

4 Genteng bubungan 44.50 m1 120,000.00 5,340,000.00

Sub - Jumlah 155,554,186.56

IV PEKERJAAN SEPTIC TANK

1 Bio Tank kapasitas 5m3 1.00 unit

Sub - Jumlah -
RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT NANDA SYIFA

LOKASI : JL.PEMUDA ,GN SINDUR BOGOR JAWA BARAT

PEMBERI TUGAS : PT.PETRIZ JAYA MEDIKA

Tahun Anggaran :

NO JENIS PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA KETERANGAN

1 2 3 4 5 6
III.1 PEKERJAAN PERSIAPAN
1 Pengukuran 209.00 m' 13,750.00 2,873,750.00

2 Pembersihan 1.00 ls 12,000,000.00 12,000,000.00

Sub - Jumlah 14,873,750.00

III.2 LANTAI 1

A PEKERJAAN PASANGAN DINDING

1 Pasangan Bata Ringan 375.89 m² 134,064.98 50,393,415.32

2 Plesteran 751.78 m² 66,513.70 50,003,403.33

3 Acian 751.78 m² 58,924.03 44,297,671.58

4 Benangan 845.50 m' 18,090.60 15,295,602.30

5 Kolom Praktis Uk. 12x15 cm 207.00 m' 149,102.80 30,864,279.60

6 Ring Balok Uk. 12x15 cm 2.48 m³ 5,423,631.79 13,423,488.69

7 Rabatan keliling bangunan 68.50 m2 1,095,540.73 75,044,539.92

8 Saluran keliling bangunan, U-30 53.50 m1 97,500.00 5,216,250.00

9 Bak kontrol 40x40 8.00 bh 145,000.00 1,160,000.00

9 Grill penutup saluran 53.50 m1 325,000.00 17,387,500.00

Sub - Jumlah 303,086,150.74 -

B PEKERJAAN PLAFOND

1 Plafond Gyptile, Rangka Hollow 245.50 m² 169,529.14 41,619,403.87

2 Plafond Kalsiboard T. 9mm, Rangka hollow 3.75 m² 149,349.75 560,061.56

3 List Plafond Gypsumboard 445.00 m' 17,622.00 7,841,790.00

Sub - Jumlah 50,021,255.43

C PEKERJAAN PENUTUP LANTAI DAN DINDING

1 Lantai Granite Tile Uk.60x60 cm, Polised Warna Terang 245.50 m² 454,051.13 111,469,551.19

2 Hospital Plint Uk. 8x30 cm ex Roman 445.00 m' 82,760.00 36,828,200.00

3 Lantai Keramik Motif Uk.60x60 cm, Ex. Roman 12.96 m² 172,532.25 2,236,017.96

4 Lantai Keramik 25x25 Unpolised Warna Terang (Area KM/WC) 3.75 m² 191,675.00 718,781.25

5 Dinding Keramik KM/WC dll. 16.00 m² 220,740.85 3,531,853.60

Sub - Jumlah 154,784,404.00

D PEKERJAAN PENGECATAN

1 Cat Tembok Interior 523.78 m² 23,379.40 12,245,568.61

2 Cat Tembok Eksterior 228.00 m² 52,404.33 11,948,187.24


3 Cat Plafond 249.25 m² 23,379.40 5,827,315.45

4 Cat List Plafond 445.00 M1 23,379.40 10,403,833.00

Sub - Jumlah 40,424,904.30


E PEKERJAAN KUSEN - DAUN PINTU DAN JENDELA

1 PIA - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 4,351,340.10 4,351,340.10

2 P2 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 8.00 unit 4,665,409.80 37,323,278.43

3 P3 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 8.00 unit 2,707,445.68 21,659,565.40

4 P9 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 3,375,340.84 3,375,340.84

5 BV - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 546,133.89 546,133.89

6 J1 - Rangka Kusen Alumunium 20.00 unit 2,956,854.59 59,137,091.75

Sub - Jumlah 126,392,750.41

G PEKERJAAN SANITARI

1 Closet Duduk 8.00 unit 3,386,845.00 27,094,760.00

2 Wastafel 8.00 unit 1,577,346.76 12,618,774.08

3 Kran Stainless Steel (KM/WC) 8.00 bh 83,798.00 670,384.00

4 Toilet Shower / Jet Shower 8.00 bh 298,298.00 2,386,384.00

5 Kaca Cermin 8.00 bh 288,282.50 2,306,260.00

6 Tempat Sabun 8.00 bh 155,000.00 1,240,000.00

7 Tempat Tisue 8.00 bh 252,000.00 2,016,000.00

8 Floor Drain 8.00 bh 107,470.00 859,760.00

9 Talang Tegak PVC Ø 4" 40.00 m' 124,300.00 4,972,000.00

Sub - Jumlah 54,164,322.08

III.3 LANTAI 2

A PEKERJAAN PASANGAN DINDING

1 Pasangan Bata Ringan 305.49 m² 134,064.98 40,955,509.21

2 Plesteran (1:3) 610.98 m² 66,513.70 40,638,540.43

3 Acian 610.98 m² 58,924.03 36,001,403.85

4 Benangan 973.43 M1 18,090.60 17,609,932.76

5 Kolom Praktis Uk. 12x15 cm 106.95 m1 149,102.80 15,946,544.46

6 Ring Balok Uk. 12x15 cm 2.03 m3 5,423,631.79 11,031,667.07

Sub - Jumlah 162,183,597.78


B PEKERJAAN PLAFOND

1 Plafond Gyptile, Rangka Hollow 252.50 m² 169,529.14 42,806,107.85

2 Plafond Kalsiboard T. 9mm, Rangka hollow 3.75 m² 149,349.75 560,061.56

3 List Plafond Gypsumboard 163.00 m' 17,622.00 2,872,386.00

Sub - Jumlah 46,238,555.41

C PEKERJAAN PENUTUP LANTAI DAN DINDING

1 Lantai Granite Tile Uk.60x60 cm, Polised Warna Terang 240.98 m² 454,051.13 109,417,240.10

2 Hospital Plint Uk. 8x30 cm ex Roman 155.00 m² 82,760.00 12,827,800.00

3 Lantai Keramik Motif Uk.60x60 cm, Ex. Roman 11.52 m² 345,000.00 3,974,400.00

4 Lantai Keramik 25x25 Unpolised Warna Terang (Area KM/WC) 3.75 m² 191,675.00 718,781.25

5 Dinding Keramik KM/WC dll. 16.00 m² 220,740.85 3,531,853.60

6 Waterproofing KM 3.75 m² 148,000.00 555,000.00

Sub - Jumlah 131,025,074.95

D PEKERJAAN PENGECATAN

1 Cat Tembok Interior 344.98 m² 23,379.40 8,065,425.41

2 Cat Tembok Eksterior 266.00 m² 52,404.33 13,939,551.78

3 Cat Plafond 256.25 m² 23,379.40 5,990,971.25

4 Cat List Plafond 163.00 m² 23,379.40 3,810,842.20

5 Waterproofing + Scret Atap beton 123.75 m² 148,000.00 18,315,000.00

Sub - Jumlah 50,121,790.64

E PEKERJAAN KUSEN - DAUN PINTU DAN JENDELA

1 PIA - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 4,351,340.10 4,351,340.10

2 P2 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 5.00 unit 4,665,409.80 23,327,049.02

3 P3 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 2,707,445.68 2,707,445.68

4 P7 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 4.00 unit 3,573,870.51 14,295,482.04

5 J1 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 21.00 unit 3,375,340.84 70,882,157.69

7 BV1 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 546,133.89 546,133.89

Sub - Jumlah 116,109,608.41

F Err:509

1 Railling Balkon (Stainlessteel Ø6 + Tiang & Pengisi, Fin. Cat Besi) 17.50 M1 1,450,000.00 25,375,000.00

Sub - Jumlah 25,375,000.00

G PEKERJAAN SANITARI

1 Closet Duduk 1.00 unit 3,386,845.00 3,386,845.00

2 Wastafel 1.00 unit 1,577,346.76 1,577,346.76

3 Kran air stainless km/wc 1.00 bh 83,798.00 83,798.00

4 Toilet Shower / Jet Shower 1.00 bh 298,298.00 298,298.00

5 Kaca Cermin 1.00 bh 288,282.50 288,282.50

6 Tempat Sabun 1.00 bh 155,000.00 155,000.00

7 Tempat Tisue 1.00 bh 252,000.00 252,000.00

8 Floor Drain 1.00 bh 107,470.00 107,470.00


9 Talang Tegak PVC Ø 4" 40.00 m' 124,300.00 4,972,000.00

10 Roof Drain 10.00 unit 148,156.25 1,481,562.50

Sub - Jumlah 12,602,602.76

III PEKERJAAN ATAP

1 Rangka atap galvalume truss (0.75mm) 284.80 M2 165,000.00 46,992,000.00

2 Atap Genteng Bitumen 284.80 M2 135,000.00 38,448,000.00

3 Aluminium foil insulation sheet 284.80 m2 45,000.00 12,816,000.00

4 Genteng bubungan 44.50 m1 120,000.00 5,340,000.00

Sub - Jumlah 123,011,635.26

IV PEKERJAAN SEPTIC TANK

1 Bio Tank kapasitas 5m3 1.00

Sub - Jumlah -
RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT NANDA SYIFA

LOKASI : JL.PEMUDA ,GN SINDUR BOGOR JAWA BARAT

PEMBERI TUGAS : PT.PETRIZ JAYA MEDIKA

Tahun Anggaran :

NO JENIS PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA KETERANGAN

1 2 3 4 5 6
III.1 PEKERJAAN PERSIAPAN
1 Pengukuran 204.00 m' 13,750.00 2,805,000.00

2 Pembersihan 1.00 ls 12,000,000.00 12,000,000.00

Sub - Jumlah 14,805,000.00

III.2 LANTAI 1

A PEKERJAAN PASANGAN DINDING

1 Pasangan Bata Ringan 499.00 m² 135,714.98 67,721,772.53

2 Plesteran 998.00 m² 55,852.72 55,741,014.56

3 Acian 998.00 m² 58,924.03 58,806,181.94

4 Benangan 1,109.45 m' 18,635.10 20,674,711.70

5 Kolom Praktis Uk. 12x15 cm 165.90 m' 147,364.80 24,447,820.32

6 Ring Balok Uk. 12x15 cm 2.37 m³ 5,315,125.04 12,596,846.36

Sub - Jumlah 239,988,347.40 -

B PEKERJAAN PLAFOND

1 Plafond Gyptile, Rangka Hollow 143.15 m² 163,941.14 23,468,174.19

2 Plafond Kalsiboard T. 9mm, Rangka hollow 13.50 m² 149,349.75 2,016,221.63

3 List Plafond Gypsumboard 368.00 m' 17,622.00 6,484,896.00

Sub - Jumlah 31,969,291.82

C PEKERJAAN PENUTUP LANTAI DAN DINDING

1 Lantai Granite Tile Uk.60x60 cm, Polised Warna Terang 0.90 m² 315,213.25 283,691.93

2 Hospital Plint Uk. 8x30 cm ex Roman 357.00 m' 82,760.00 29,545,320.00

3 Lantai Granite Tile unt. Tangga Uk.60x60 cm, Polised Warna Terang 45.00 m² 315,213.25 14,184,596.25

4 Lantai Keramik Uk.40x40 cm, Polised Warna Terang 205.40 m² 172,532.25 35,438,124.15

5 Lantai Keramik Unpolised Warna Terang (Area KM/WC) 8.55 m² 157,025.00 1,342,563.75

6 Dinding Keramik KM/WC dll. 58.00 m² 186,309.75 10,805,965.50

Sub - Jumlah 91,600,261.58

D PEKERJAAN PENGECATAN

1 Cat Tembok Interior 921.60 m² 22,785.95 20,999,531.52

2 Cat Tembok Eksterior 614.40 m² 45,809.50 28,145,356.80

3 Cat Plafond 13.50 m² 22,785.95 307,610.33

4 Cat List Plafond 25.76 m² 22,785.95 586,966.07

Sub - Jumlah 50,039,464.72


E PEKERJAAN KUSEN - DAUN PINTU DAN JENDELA

1 P1 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 12,372,063.62 12,372,063.62

2 PIA - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 5.00 unit 4,276,821.42 21,384,107.11

3 P2 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 25.00 unit 4,582,293.66 114,557,341.53

4 P2A - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 4,362,581.60 4,362,581.60

5 P3 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 16.00 unit 2,659,708.92 42,555,342.72

6 P4 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 8.00 unit 3,325,199.43 26,601,595.46

7 P5 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 2.00 unit 1,267,283.89 2,534,567.77

8 P7 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 8.00 unit 3,518,238.58 28,145,908.65

9 P9 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 2.00 unit 3,834,796.83 7,669,593.66

10 BV1 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 16.00 unit 543,703.77 8,699,260.24

11 J1 - Rangka Kusen Alumunium 68.00 unit 2,929,666.70 199,217,335.33

12 J2 - Rangka Kusen Alumunium 4.00 unit 1,939,437.48 7,757,749.91

Sub - Jumlah 475,857,447.59

F PEKERJAAN FINISHING DAN PERABOT MELEKAT

1 Railling Tangga Bag.Dalam (Stainlessteel Ø6 + Tiang & Pengisi, Fin. Cat Besi) 5.40 m² 810,000.00 4,374,000.00

Sub - Jumlah 4,374,000.00

G PEKERJAAN SANITARI

1 Closet Duduk 4.00 unit 2,045,807.50 8,183,230.00

2 Wastafel + Meja Beton Finsh. Granite + Cermin (terpasang) 3.00 unit 1,126,594.26 3,379,782.78

3 Kran Stainless Steel (KM/WC) 4.00 bh 71,986.75 287,947.00

4 Toilet Shower / Jet Shower 4.00 bh 286,486.75 1,145,947.00

5 Kaca Cermin 3.00 bh 288,282.50 864,847.50

6 Iron Zing (1 lubang) 1.00 bh 475,268.75 475,268.75

7 Tempat Sabun 4.00 bh 120,000.00 480,000.00

8 Tempat Tisue 4.00 bh 252,000.00 1,008,000.00

9 Kran Air Leher Angsa 1.00 bh 159,986.75 159,986.75

10 Floor Drain 4.00 bh 65,656.25 262,625.00

11 Talang Tegak PVC Ø 4" 22.00 m' 124,300.00 2,734,600.00

12 Bak Pengumpul (Kaps.5m3) 1.00 unit 4,990,000.00 4,990,000.00

13 Saluran Keliling Bangunan U30 47.00 m' 65,000.00 3,055,000.00

14 Bak Kontrol Uk.40x40 cm 7.00 unit 150,000.00 1,050,000.00

Sub - Jumlah 28,077,234.78

III.3 LANTAI 2

A PEKERJAAN PASANGAN DINDING

1 Pasangan Bata Ringan 35.20 m² 135,714.98 4,777,167.12

2 Plesteran (1:3) 422.75 m² 55,852.72 23,611,737.38

3 Acian 98.50 m² 58,924.03 5,804,016.96

4 Benangan 845.50 m² 18,635.10 15,755,977.05


5 Kolom Praktis Uk. 12x15 cm m1 147,364.80 -

6 Ring Balok Uk. 12x15 cm 91.50 m3 5,315,125.04 486,333,941.55

Sub - Jumlah 536,282,840.06


B PEKERJAAN PLAFOND

1 Plafond Gyptile, Rangka Hollow 156.35 m² 145,986.39 22,824,972.08

2 Plafond Kalsiboard T. 9mm, Rangka hollow 4.36 m² 149,349.75 651,164.91

3 List Plafond Gypsumboard 268.50 m' 17,622.00 4,731,507.00

Sub - Jumlah 28,207,643.99

C PEKERJAAN PENUTUP LANTAI DAN DINDING

1 Lantai Granite Tile Uk.60x60 cm, Polised Warna Terang 0.90 m² 315,213.25 283,691.93

2 Hospital Plint Uk. 8x30 cm ex Roman 11.76 m² 82,760.00 973,257.60

3 Lantai Granite Tile unt. Tangga Uk.60x60 cm, Polised Warna Terang 266.00 m' 315,213.25 83,846,724.50

4 Lantai Keramik Unpolised Warna Terang (Area KM/WC) 45.00 m² 157,025.00 7,066,125.00

5 Dinding Keramik KM/WC dll. 24.65 m² 186,309.75 4,592,535.34

6 Waterproofing KM m²

Sub - Jumlah 96,762,334.36

D PEKERJAAN PENGECATAN

1 Cat Tembok Interior 592.44 m² 22,785.95 13,499,308.22

2 Cat Tembok Eksterior 394.96 m² 45,809.50 18,092,920.12

3 Cat Plafond 4.30 m² 22,785.95 97,979.59

4 Cat List Plafond 18.90 m² 22,785.95 430,654.46

5 Waterproofing + Scret Atap beton 9.80 m² 148,000.00 1,450,400.00

Sub - Jumlah 33,571,262.38

E PEKERJAAN KUSEN - DAUN PINTU DAN JENDELA

1 PIA - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 4.00 unit 4,276,821.42 17,107,285.69

2 P2 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 30.00 unit 4,582,293.66 137,468,809.83

3 P3 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 20.00 unit 2,659,708.92 53,194,178.40

4 P4 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 19.00 unit 3,325,199.43 63,178,789.22

5 P6 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 4.00 unit 5,073,084.56 20,292,338.22

6 P7 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 3,518,238.58 3,518,238.58

7 P8 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 1.00 unit 3,612,299.46 3,612,299.46

8 BV1 - Rangka Kusen Alumunium dan Daun (Lengkap Assesoris) 21.00 unit 543,703.77 11,417,779.07

9 J1 - Rangka Kusen Alumunium 91.00 unit 2,929,666.70 266,599,669.34

10 J2 - Rangka Kusen Alumunium 1.00 unit 1,939,437.48 1,939,437.48

Sub - Jumlah 578,328,825.27

F PEKERJAAN FINISHING DAN PERABOT MELEKAT

1 Railling Tangga Bag.Dalam (Stainlessteel Ø6 + Tiang & Pengisi, Fin. Cat Besi) 18.90 m² 810,000.00 15,309,000.00

2 Railling Tangga Bag.Tepi (Stainlessteel Ø6 + Tiang & Pengisi, Fin. Cat Besi) 29.00 m² 810,000.00 23,490,000.00

3 Railling Balkon (Stainlessteel Ø6 + Tiang & Pengisi, Fin. Cat Besi) 9.12 m² 810,000.00 7,387,200.00

Sub - Jumlah 46,186,200.00

G PEKERJAAN SANITARI

1 Closet Duduk 1.00 unit 3,360,720.00 3,360,720.00

2 Wastafel + Meja Beton Finsh. Granite + Cermin (terpasang) 3.00 unit 1,851,670.26 5,555,010.78
3 Toilet Shower / Jet Shower 1.00 bh 450,000.00 450,000.00

4 Kaca Cermin 3.00 bh 288,282.50 864,847.50

5 Tempat Sabun 1.00 bh 120,000.00 120,000.00

6 Tempat Tisue 1.00 bh 252,000.00 252,000.00

7 Floor Drain 1.00 bh 65,656.25 65,656.25

8 Talang Tegak PVC Ø 4" 8.00 m' 124,300.00 994,400.00

9 Spoel Hoek + Kran 1.00 unit 1,550,000.00 1,550,000.00


10 Gutter 5x15 cm 4.50 m' 55,000.00 247,500.00

11 Roof Drain 2.00 unit 148,156.25 296,312.50

Sub - Jumlah 13,756,447.03

Sub - Jumlah 2,029,818,253.57


RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT NANDA SYIFA

LOKASI : JL.PEMUDA ,GN SINDUR BOGOR JAWA BARAT

PEMBERI TUGAS : PT.PETRIZ JAYA MEDIKA

NO JENIS PEKERJAAN SATUAN VOLUME HARGA JUMLAH KETERANGAN

1 2 3 4 5 6=4x5

I PEKERJAAN PERSIAPAN

1 Pekerjaan Persiapan (Pembersihan, dll.) m² 209.00 13,750.00 2,873,750.00

2 Pengukuran dan Bouwplank m' 63.50 101,813.58 6,465,162.33

Sub - Jumlah 9,338,912.33

II PEKERJAAN STRUKTUR

I LANTAI 1

1 Galian Tanah pile Cap dan Tie Beam m³ 124.03 73,425.00 9,106,810.97

2 Urugan Pasir bawah Lt. Kerja t = 5 cm m³ 4.10 445,170.00 1,822,971.15

3 Urugan Tanah Kembali m³ 15.48 53,350.00 825,858.00

4 Pembuangan Tanah m³ 108.55 28,325.00 3,074,643.34

5 Bore Pondasi Ø 60 cm, P. 10 m m' 300.00 171,072.00 51,321,600.00

6 Pondasi Bore Pile Ø 60 cm, P. 6 m m³ 115.40 2,905,177.00 335,242,899.92

7 Pilecap (Pondasi PC1) m³ 17.96 3,819,315.50 68,575,809.80

8 Rabat Plat Lt.1 t: 5 cm m³ 15.48 999,190.50 15,467,468.94

9 Tie Beam 30/45 (TB1) m³ 11.60 3,813,117.95 44,218,822.36

10 Tie Beam 20/30 (TB2) m³ 1.95 3,813,117.95 7,435,580.01

11 Plat Lantai Kerja t: 5 cm (dibawah PC & TB) m³ 15.48 999,190.50 15,467,468.94

12 Kolom 30 x 60 cm (K1) m³ 11.34 4,164,500.82 47,225,439.29

13 Balok 30/50 (B1) elv. +3.95 m m³ 18.60 4,274,473.84 79,505,213.49

14 Balok 25/35 (B3) elv. +3.95 m m³ 1.53 3,882,934.47 5,945,743.40

15 Balok 20/30 (B4) elv. +3.95 m m³ 1.32 3,915,044.23 5,167,858.38

16 Plat, t: 12 cm (S1) elv. +3.95 m m³ 31.59 4,753,691.10 150,169,101.79

17 Pondasi batu kali m³ 13.92 965,002.50 13,432,834.80

18 Plat Lantai Kerja t: 10 cm m³ 20.90 999,190.50 20,883,081.45

19 Plat Lantai Selasar elv.3.95 m m³ 1.53 4,753,691.10 7,273,147.38

Sub - Jumlah 882,162,353.41

II.2 LANTAI 2

1 Kolom 30 x 60 cm (K1) m³ 11.52 4,164,500.82 47,975,049.43

2 Balok 30/50 (B1) elv. +7.95 m m³ 9.45 3,882,934.47 36,693,730.73

3 Balok 20/30 (B4) elv. +7.50 m m³ 6.48 4,164,500.82 26,985,965.31

4 Balok 30/50 (B1) elv. +7.95 m m³ 17.10 4,274,473.84 73,093,502.73

5 Balok 25/35 (B3) elv. +7.95 m m³ 0.83 3,882,934.47 3,227,689.28

6 Ring Balok 20/30 (B4) elv. +8.95 m m³ 3.24 4,164,500.82 13,492,982.65

7 Plat, t: 12 cm (S1) elv. +7.50 m Talang dan Lisplank m³ 8.04 4,753,691.10 38,219,676.43

Sub - Jumlah 239,688,596.55

TOTAL 1,131,189,862.29
RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT NANDA SYIFA

LOKASI : JL.PEMUDA ,GN SINDUR BOGOR JAWA BARAT

PEMBERI TUGAS : PT.PETRIZ JAYA MEDIKA

NO JENIS PEKERJAAN SATUAN VOLUME HARGA JUMLAH KETERANGAN

1 2 3 4 5 6=4x5

I PEKERJAAN PERSIAPAN

1 Pekerjaan Persiapan (Pembersihan, dll.) m² 209.00 13,750.00 2,873,750.00

2 Pengukuran dan Bouwplank m' 63.50 101,813.58 6,465,162.33

Sub - Jumlah 9,338,912.33

II PEKERJAAN STRUKTUR

I LANTAI 1

1 Galian Tanah pile Cap dan Tie Beam m³ 142.00 73,425.00 10,426,625.34

2 Urugan Pasir bawah Lt. Kerja t = 5 cm m³ 10.47 445,170.00 4,658,704.05

3 Urugan Tanah Kembali m³ 8.28 53,350.00 441,738.00

4 Pembuangan Tanah m³ 133.72 28,325.00 3,787,725.22

5 Bore Pondasi Ø 60 cm, P. 10 m m' 300.00 171,072.00 51,321,600.00

6 Pondasi Bore Pile Ø 60 cm, P. 6 m m³ 115.40 2,905,177.00 335,242,899.92

7 Pilecap (Pondasi PC1) m³ 17.96 3,819,315.50 68,575,809.80

8 Rabat Plat Lt.1 t: 5 cm m³ 8.28 999,190.50 8,273,297.34

9 Tie Beam 30/45 (TB1) m³ 11.60 3,813,117.95 44,218,822.36

10 Tie Beam 20/30 (TB2) m³ 3.51 3,813,117.95 13,384,044.02

11 Plat Lantai Kerja t: 5 cm (dibawah PC & TB) m³ 8.28 999,190.50 8,273,297.34

12 Kolom 30 x 60 cm (K1) m³ 10.67 4,164,500.82 44,414,401.23

13 Balok 30/50 (B1) elv. +3.95 m m³ 18.60 4,274,473.84 79,505,213.49

14 Balok 25/35 (B3) elv. +3.95 m m³ 1.53 3,882,934.47 5,945,743.40

15 Balok 20/30 (B4) elv. +3.95 m m³ 1.32 3,915,044.23 5,167,858.38

16 Plat, t: 12 cm (S1) elv. +3.95 m m³ 31.59 4,753,691.10 150,169,101.79

17 Pondasi batu kali m³ 50.90 965,002.50 49,113,802.24

18 Plat Lantai Kerja t: 10 cm m³ 20.90 999,190.50 20,883,081.45

19 Plat Lantai Selasar elv.3.95 m m³ 1.53 4,753,691.10 7,273,147.38

Sub - Jumlah 911,076,912.75

II.2 LANTAI 2

1 Kolom 30 x 60 cm (K1) m³ 11.52 4,164,500.82 47,975,049.43

2 Balok 30/50 (B1) elv. +7.95 m m³ 9.45 3,882,934.47 36,693,730.73

3 Balok 20/30 (B4) elv. +7.50 m m³ 6.48 4,164,500.82 26,985,965.31

4 Balok 30/50 (B1) elv. +7.95 m m³ 17.10 4,274,473.84 73,093,502.73

5 Balok 25/35 (B3) elv. +7.95 m m³ 0.83 3,882,934.47 3,227,689.28

6 Ring Balok 20/30 (B4) elv. +8.95 m m³ 3.24 4,164,500.82 13,492,982.65

7 Plat, t: 12 cm (S1) elv. +7.50 m Talang dan Lisplank m³ 8.04 4,753,691.10 38,219,676.43

Sub - Jumlah 239,688,596.55

TOTAL 1,160,104,421.63
DAFTAR ANALISA HARGA SATUAN PEKERJAAN PERSIAPAN
MENURUT SNI

NO URAIAN HARGA SAT Upah Bahan JML HARGA


(Rp) (Rp) (Rp) (Rp)
a b c d e f
A.002 1 m' PAGAR SEMENTARA SENG GELOMBANG t = 2.00 m'
Bahan
1.250 bt Kayu dolken ø 8 - 10/400 cm 22,300 27,875
2.500 kg Semen Pc 1,600 4,000
0.005 m³ Pasir beton 315,000 1,575
0.009 m³ Steinslag pecah tangan 2/3 341,000 3,069
0.039 m³ Kayu kasau 3,000,000 117,000
0.060 kg Paku 15,500 930
0.450 kg Meny besi 31,600 14,220
1.200 lbr Seng gelombang 64,500 77,400
Upah
0.020 Oh Mandor 120,000 2,400
0.020 Oh Kepala tukang kayu 95,000 1,900
0.200 Oh Tukang kayu 100,000 20,000
0.400 Oh Pekerja 85,000 34,000
SUB JUMLAH 58,300 246,069 304,369
A.004 1 m' PENGUKURAN DAN PASANG BOUWPLANG
Bahan
0.008 m³ Kayu kasau meranti 3,000,000 24,000
0.005 m³ Papan meranti 2,200,000 9,900
0.020 kg Paku 15,500 310
Upah
0.005 Oh Mandor 100,000 500
0.010 Oh Kepala tukang kayu 90,000 900
0.100 Oh Tukang kayu 80,000 8,000
0.100 Oh Pekerja 60,000 6,000
SUB JUMLAH 15,400 34,210 49,610
A.005 1 m² PEMBUATAN KANTOR SEMENTARA DG LANTAI PLESTERAN
Bahan
0.180 m³ Kayu balok 3,000,000 540,000
0.300 kg Paku 15,500 4,650
35.000 kg Semen Pc 1,600 56,000
0.150 m³ Pasir pasang 295,000 44,250
0.100 m³ Pasir beton 295,000 29,500
0.150 m³ Steinslag pecah tangan 2/3 295,000 44,250
30.000 bh Bata merah 900 27,000
0.500 lbr Seng gelombang 64,500 32,250
0.075 m² Jendela nako 260,400 19,530
0.150 m² Kaca polos 3 mm 69,400 10,410
1.500 lbr Multiplek 4 mm 86,800 130,200
2.000 bh Grendel pintu 19,800 39,600
2.000 bh Engsel pintu 49,600 99,200
Upah
0.050 Oh Mandor 120,000 6,000
0.300 Oh Kepala tukang 100,000 30,000
1.000 Oh Tukang kayu 95,000 95,000
1.000 Oh Tukang batu 95,000 95,000
2.000 Oh Pekerja 85,000 170,000
SUB JUMLAH 396,000 1,076,840 1,472,840
A.008 1 m² PEMBERSIHAN LAPANGAN
Upah
0.080 Oh Mandor 120,000 9,600
0.000 Oh Kepala tukang 100,000 -
0.000 Oh Tukang 95,000 -
0.200 Oh Pekerja 85,000 17,000
SUB JUMLAH 26,600 - 26,600
DAFTAR ANALISA HARGA SATUAN PEKERJAAN TANAH

NO URAIAN HARGA SAT Upah Bahan JML HARGA


(Rp) (Rp) (Rp) (Rp)
a b c d e f
A.019 1 m³ GALIAN TANAH BIASA SEDALAM 2.00 m
Upah
0.052 Oh Mandor 120,000 6,240
0.526 Oh Pekerja 85,000 44,710
SUB JUMLAH 50,950 - 50,950
A.026 1 m³ URUGAN TANAH KEMBALI
Upah
0.019 Oh Mandor 120,000 2,280
0.192 Oh Pekerja 85,000 16,320
SUB JUMLAH 18,600 - 18,600
A.028 1 m³ URUGAN PASIR
Bahan
1.200 m³ Pasir urug 210,000 252,000
Upah
0.010 Oh Mandor 120,000 1,200
0.300 Oh Pekerja 85,000 25,500
SUB JUMLAH 26,700 252,000 278,700
A.032 1 m³ URUGAN SIRTU
Bahan
1.200 m³ Tanah Siirtu 295,000 354,000
Upah
0.025 Oh Mandor 120,000 3,000
0.250 Oh Pekerja 85,000 21,250
SUB JUMLAH 24,250 354,000 378,250
A.652 1 m³ CUT and FILL
Bahan
Alat
0.013 hr Sewa Excavator 350,000 4,410
0.008 hr Sewa Whell Loader 275,000 2,063
0.006 hr Sewa Motor Grader 350,000 2,065
0.006 hr Sewa Vibro Roller 275,000 1,760
0.001 hr Sewa Water Tanker 175,000 88
Upah
0.010 Oh Mandor 120,000 1,212
0.000 Oh Kepala tukang batu 100,000 -
0.000 Oh Tukang batu 95,000 -
0.026 Oh Pekerja 85,000 2,168
SUB JUMLAH 3,380 10,385 13,765
A.652 1 m³ URUGAN TANAH LOKAL + PEMADATAN DENGAN ALAT BERAT
Bahan
1.200 m³ Tanah urug 170,000 204,000
Alat
0.012 hr Sewa Vibro Roller 250,000 3,000
0.022 hr Sewa Escavator 325,000 7,150
Upah
0.021 Oh Mandor 120,000 2,520
0.250 Oh Pekerja 85,000 21,250
SUB JUMLAH 23,770 214,150 237,920
1 m³ URUGAN TANAH LOKAL + PEMADATAN
Bahan
1.200 m³ Tanah urug 170,000 204,000
0.250 jam Stamper 24,800 6,200
Upah
0.060 Oh Mandor 120,000 7,200
0.800 Oh Pekerja 85,000 68,000
75,200 210,200 285,400
A.586 1 m² PASANG PAVING STONE ( Warna 8 cm K-300 )
Bahan
1.050 m2 Paving K300 141,000 148,050
0.035 m³ Pasir pasang 315,000 11,025
Upah
0.020 Oh Mandor 120,000 2,400
0.020 Oh Kepala tukang batu 100,000 2,000
NO URAIAN HARGA SAT Upah Bahan JML HARGA
(Rp) (Rp) (Rp) (Rp)
a b c d e f
0.200 Oh Tukang batu 95,000 19,000
0.500 Oh Pekerja 85,000 42,500
SUB JUMLAH 65,900 159,075 224,975

A.586 1 m' PASANG STOPPER ( Warna 8 cm K-300 )


Bahan
0.001 m3 Pasir Pasang 141,000 141
3.340 bh Stopper/uskup 15,000 50,100
Upah
0.001 Oh Mandor 120,000 120
0.010 Oh Kepala tukang batu 100,000 1,000
0.100 Oh Tukang batu 95,000 9,500
0.200 Oh Pekerja 85,000 17,000
SUB JUMLAH 27,620 50,241 77,861
1 m' PASANG KANSTEEN
Bahan
2.500 m2 PC 1,600 4,000
0.001 m³ Pasir pasang 341,000 341
2.000 BJ Kansteen 10X20X50 cm 55,800 111,600
Upah
0.001 Oh Mandor 120,000 120
0.010 Oh Kepala tukang batu 100,000 1,000
0.100 Oh Tukang batu 95,000 9,500
0.150 Oh Pekerja 85,000 12,750
SUB JUMLAH 23,370 115,941 139,311
1 m' PASANG SALURAN BUIS BETON 1/2 BULAT 30 CM
Bahan
2.500 m2 PC 1,600 4,000
0.001 m³ Pasir pasang 341,000 341
2.000 BJ Buis Beton 1/2 Lingkaran 30 cm 68,200 136,400
Upah
0.001 Oh Mandor 120,000 120
0.010 Oh Kepala tukang batu 100,000 1,000
0.100 Oh Tukang batu 95,000 9,500
0.150 Oh Pekerja 85,000 12,750
SUB JUMLAH 23,370 140,741 164,111
1 m2 PERATAAN & PEMADATAN PAVING
Bahan
0.250 jam Stamper 24,800 6,200
Upah
0.005 Oh Mandor 120,000 600
0.050 Oh Pekerja 85,000 4,250
SUB JUMLAH 4,850 6,200 11,050
ANALISA HARGA SATUAN

HARGA SATUAN JUMLAH HARGA


NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

PEKERJAAN PERSIAPAN

JENIS PEKERJAAN A,2,2,1,4 : 1 m' Pengukuran


A TENAGA
1 Pekerja L01 OH 0.1000 85,000.00 8,500.00
2 Mandor L04 OH 0.0500 120,000.00 6,000.00
JUMLAH HARGA TENAGA 14,500.00

B Jumlah (A) 14,500.00


C Overhead dan Profit % 10.0000 14,500.00 1,450.00
D Harga Satuan Pekerjaan (B+C) 15,950.00

JENIS PEKERJAAN : 1 m2 Pembongkaran Pasangan Dinding Bata


A TENAGA
1 Pekerja L01 OH 0.1500 85,000.00 12,750.00
2 Mandor L04 OH 0.0075 120,000.00 900.00
JUMLAH HARGA TENAGA 13,650.00

B Jumlah (A) 13,650.00


C Overhead dan Profit % 10.0000 13,650.00 1,365.00
D Harga Satuan Pekerjaan (B+C) 15,015.00

JENIS PEKERJAAN : 1 m2 Pembongkaran Pasangan Homogenous Tile


A TENAGA
1 Pekerja L01 OH 0.1300 85,000.00 11,050.00
2 Mandor L04 OH 0.0065 120,000.00 780.00
JUMLAH HARGA TENAGA 11,830.00

B Jumlah (A) 11,830.00


C Overhead dan Profit % 10.0000 11,830.00 1,183.00
D Harga Satuan Pekerjaan (B+C) 13,013.00

JENIS PEKERJAAN : 1 m2 Pembongkaran Pasangan Keramik Dinding


A TENAGA
1 Pekerja L01 OH 0.1800 85,000.00 15,300.00
2 Mandor L04 OH 0.0090 120,000.00 1,080.00
JUMLAH HARGA TENAGA 16,380.00

B Jumlah (A) 16,380.00


C Overhead dan Profit % 10.0000 16,380.00 1,638.00
D Harga Satuan Pekerjaan (B+C) 18,018.00

JENIS PEKERJAAN : 1 m2 Pembongkaran Plafond + Rangka halaman 489 dari 684


A TENAGA
1 Pekerja L01 OH 0.0938 85,000.00 7,968.75
2 Mandor L04 OH 0.0075 120,000.00 900.00
JUMLAH HARGA TENAGA 8,868.75

B Jumlah (A) 8,868.75


C Overhead dan Profit % 10.0000 8,868.75 886.88
D Harga Satuan Pekerjaan (B+C) 9,755.63
ANALISA HARGA SATUAN

HARGA SATUAN JUMLAH HARGA


NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

PEKERJAAN PERSIAPAN

JENIS PEKERJAAN A,2,2,1,9 : 1 m2 Pembersihan Lapangan dan Perataan halaman 371 dari 684
A. TENAGA
1 Pekerja L01 OH 0.1000 85,000.00 8,500.00
2 Mandor L04 OH 0.0500 120,000.00 6,000.00
JUMLAH HARGA TENAGA 14,500.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 14,500.00


E Overhead dan Profit % 10.0000 14,500.00 1,450.00
F Harga Satuan Pekerjaan (D+E) 15,950.00

JENIS PEKERJAAN A,2,2,1,4 : 1 m1 Pengukuran dan pemasangan Bouwplank halaman 371 dari 684
A. TENAGA
1 Pekerja L01 OH 0.1000 85,000.00 8,500.00
2 Tukang Kayu L02 OH 0.1000 95,000.00 9,500.00
3 Kepala Tukang L03 OH 0.0100 100,000.00 1,000.00
4 Mandor L04 OH 0.0050 120,000.00 600.00
JUMLAH HARGA TENAGA 19,600.00
B BAHAN
1 Kayu Balok 5/7 m3 0.0120 3,000,000.00 36,000.00
2 Paku Kg 0.0200 16,500.00 330.00
3 Kayu Papan 3/20 m3 0.0070 3,300,000.00 23,100.00
JUMLAH HARGA BAHAN 59,430.00
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 79,030.00


E Overhead dan Profit % 10.0000 79,030.00 7,903.00
F Harga Satuan Pekerjaan (D+E) 86,933.00

PEKERJAAN TANAH

JENIS PEKERJAAN A,2,3,1,1 : 1 m3 Penggalian tanah biasa sedalam 1 meter halaman 371 dari 684
A. TENAGA
1 Pekerja L01 OH 0.7500 85,000.00 63,750.00
2 Mandor L04 OH 0.0250 120,000.00 3,000.00
JUMLAH HARGA TENAGA 66,750.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 66,750.00


E Overhead dan Profit % 10.0000 66,750.00 6,675.00
F Harga Satuan Pekerjaan (D+E) 73,425.00

JENIS PEKERJAAN A,2,3,1,1 : 1 m3 Penggalian tanah biasa sedalam 3 meter halaman 371 dari 684
A. TENAGA
1 Pekerja L01 OH 1.0500 85,000.00 89,250.00
2 Mandor L04 OH 0.0670 120,000.00 8,040.00
JUMLAH HARGA TENAGA 97,290.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA PERALATAN -
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

D Jumlah (A+B+C) 97,290.00


E Overhead dan Profit % 10.0000 97,290.00 9,729.00
F Harga Satuan Pekerjaan (D+E) 107,019.00

JENIS PEKERJAAN : Titik Pembuatan Lubang Strous Ø 60 cm, Kedalaman 10 m halaman 371 dari 684
A. TENAGA
1 Pekerja L01 OH 1.4400 85,000.00 122,400.00
2 Mandor L04 OH 0.0720 120,000.00 8,640.00
JUMLAH HARGA TENAGA 131,040.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
1 Sewa Alat Bantu Strous Pile Ø 60 cm Jam 1.2000 150,000.00 180,000.00
JUMLAH HARGA PERALATAN 180,000.00

D Jumlah (A+B+C) 311,040.00


E Overhead dan Profit % 10.0000 311,040.00 31,104.00
F Harga Satuan Pekerjaan (D+E) 342,144.00
Harga Satuan Pekerjaan Per-m1 171,072.00

JENIS PEKERJAAN : Titik Pembuatan Lubang Strous Ø 40 cm, Kedalaman 3 m


A. TENAGA
1 Pekerja L01 OH 1.4400 85,000.00 122,400.00
2 Mandor L04 OH 0.0720 120,000.00 8,640.00
JUMLAH HARGA TENAGA 131,040.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
1 Sewa Alat Bantu Strous Pile Ø 40 cm Jam 1.2000 82,050.00 98,460.00
JUMLAH HARGA PERALATAN 98,460.00

D Jumlah (A+B+C) 229,500.00


E Overhead dan Profit % 10.0000 229,500.00 22,950.00
F Harga Satuan Pekerjaan (D+E) 252,450.00
Harga Satuan Pekerjaan Per-m1 84,150.00

JENIS PEKERJAAN A,2,3,1,8 : 1 m3 Pembuangan Tanah halaman 380 dari 684


A. TENAGA
1 Pekerja L01 OH 0.3300 85,000.00 28,050.00
2 Mandor L04 OH 0.0100 120,000.00 1,200.00
JUMLAH HARGA TENAGA 29,250.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 29,250.00


E Overhead dan Profit % 10.0000 29,250.00 2,925.00
F Harga Satuan Pekerjaan (D+E) 32,175.00

JENIS PEKERJAAN A,2,3,1,9 : 1 m3 Pengurugan Kembali halaman 380 dari 684


A. TENAGA
1 Pekerja L01 OH 0.5000 85,000.00 42,500.00
2 Mandor L04 OH 0.0500 120,000.00 6,000.00
JUMLAH HARGA TENAGA 48,500.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 48,500.00


E Overhead dan Profit % 10.0000 48,500.00 4,850.00
F Harga Satuan Pekerjaan (D+E) 53,350.00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JENIS PEKERJAAN A,2,3,1,11 : 1 m3 Pengurugan Pasir Urug halaman 381 dari 684
A. TENAGA
1 Pekerja L01 OH 0.3000 85,000.00 25,500.00
2 Mandor L04 OH 0.0100 120,000.00 1,200.00
JUMLAH HARGA TENAGA 26,700.00
B BAHAN
1 Pasir Urug m3 1.2000 315,000.00 378,000.00
JUMLAH HARGA BAHAN 378,000.00
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 404,700.00


E Overhead dan Profit % 10.0000 404,700.00 40,470.00
F Harga Satuan Pekerjaan (D+E) 445,170.00

JENIS PEKERJAAN A,2,3,1,14 : 1 m3 Pengurugan Sirtu Padat halaman 382 dari 684
A. TENAGA
1 Pekerja L01 OH 0.2500 85,000.00 21,250.00
2 Mandor L04 OH 0.0250 120,000.00 3,000.00
JUMLAH HARGA TENAGA 24,250.00
B BAHAN
1 Pasir Urug m3 1.2000 92,990.00 111,588.00
JUMLAH HARGA BAHAN 111,588.00
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 135,838.00


E Overhead dan Profit % 10.0000 135,838.00 13,583.80
F Harga Satuan Pekerjaan (D+E) 149,421.80

PEKERJAAN BESI

JENIS PEKERJAAN A,4,2,1,1 : 1 kg Besi Profil halaman 418 dari 684


A. TENAGA
1 Pekerja L01 OH 0.0600 85,000.00 5,100.00
2 Tukang Besi L02 OH 0.0600 95,000.00 5,700.00
3 Kepala Tukang L03 OH 0.0060 100,000.00 600.00
4 Mandor L04 OH 0.0030 120,000.00 360.00
JUMLAH HARGA TENAGA 11,760.00
B BAHAN
1 Besi Profil kg 1.1500 18,051.00 20,758.65
JUMLAH HARGA BAHAN 20,758.65
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 32,518.65


E Overhead dan Profit % 10.0000 32,518.65 3,251.87
F Harga Satuan Pekerjaan (D+E) 35,770.52

JENIS PEKERJAAN A,4,2,1,2 : 1 kg Rangka Baja WF halaman 419 dari 684


A. TENAGA
1 Pekerja L01 OH 0.0600 85,000.00 5,100.00
2 Tukang Besi L02 OH 0.0600 95,000.00 5,700.00
3 Kepala Tukang L03 OH 0.0060 100,000.00 600.00
4 Mandor L04 OH 0.0030 120,000.00 360.00
JUMLAH HARGA TENAGA 11,760.00
B BAHAN
1 Besi Baja WF kg 1.1500 14,057.90 16,166.59
JUMLAH HARGA BAHAN 16,166.59
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 27,926.59


E Overhead dan Profit % 10.0000 27,926.59 2,792.66
F Harga Satuan Pekerjaan (D+E) 30,719.24
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JENIS PEKERJAAN : 1 kg Gording Kanal C
A. TENAGA
1 Pekerja L01 OH 0.0600 85,000.00 5,100.00
2 Tukang Besi L02 OH 0.0600 95,000.00 5,700.00
3 Kepala Tukang L03 OH 0.0060 100,000.00 600.00
4 Mandor L04 OH 0.0030 120,000.00 360.00
JUMLAH HARGA TENAGA 11,760.00
B BAHAN
1 Besi Gording Kanal C kg 1.1500 12,690.40 14,593.96
JUMLAH HARGA BAHAN 14,593.96
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 26,353.96


E Overhead dan Profit % 10.0000 26,353.96 2,635.40
F Harga Satuan Pekerjaan (D+E) 28,989.36

JENIS PEKERJAAN : 1 m Ikatan Gording Ø 10


A. TENAGA
1 Pekerja L01 OH 0.0300 85,000.00 2,550.00
2 Tukang Besi L02 OH 0.0300 95,000.00 2,850.00
3 Kepala Tukang L03 OH 0.0030 100,000.00 300.00
4 Mandor L04 OH 0.0020 120,000.00 240.00
JUMLAH HARGA TENAGA 5,940.00
B BAHAN
1 Besi Beton kg 0.6170 7,658.00 4,724.99
2 Baut bh 1.5000 5,360.60 8,040.90
JUMLAH HARGA BAHAN 12,765.89
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 18,705.89


E Overhead dan Profit % 10.0000 18,705.89 1,870.59
F Harga Satuan Pekerjaan (D+E) 20,576.47

JENIS PEKERJAAN : 1 m Ikatan Besi Sling Ø 22 mm


A. TENAGA
1 Pekerja L01 OH 0.0300 85,000.00 2,550.00
2 Tukang Besi L02 OH 0.0300 95,000.00 2,850.00
3 Kepala Tukang L03 OH 0.0030 100,000.00 300.00
4 Mandor L04 OH 0.0020 120,000.00 240.00
JUMLAH HARGA TENAGA 5,940.00
B BAHAN
1 Ikatan Besi Sling Ø 22 mm m1 1.0500 158,465.90 166,389.20
JUMLAH HARGA BAHAN 166,389.20
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 172,329.20


E Overhead dan Profit % 10.0000 172,329.20 17,232.92
F Harga Satuan Pekerjaan (D+E) 189,562.11

JENIS PEKERJAAN A,4,2,1,5 : 10 cm Pengelasan Dengan Las Listrik halaman 420 dari 684
A. TENAGA
1 Pekerja L01 OH 0.0400 85,000.00 3,400.00
2 Tukang Besi L02 OH 0.0200 95,000.00 1,900.00
3 Kepala Tukang L03 OH 0.0020 100,000.00 200.00
4 Mandor L04 OH 0.0020 120,000.00 240.00
JUMLAH HARGA TENAGA 5,740.00
B BAHAN
1 Kawat Las Listrik kg 0.4000 26,529.50 10,611.80
2 Solar Liter 0.3000 11,000.00 3,300.00
3 Minyak Pelumas Liter 0.0400 43,760.00 1,750.40
JUMLAH HARGA BAHAN 15,662.20
C PERALATAN
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA PERALATAN -
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

D Jumlah (A+B+C) 21,402.20


E Overhead dan Profit % 10.0000 21,402.20 2,140.22
F Harga Satuan Pekerjaan (D+E) 23,542.42
Harga satuan pekerjaan dalam satuan 1 cm 2,354.24

PEKERJAAN PENGECATAN

JENIS PEKERJAAN A,4,7,1,16 : 1 m2 Pengecatan Permukaan Baja dengan Meni Besi halaman 546 dari 684
A. TENAGA
1 Pekerja L01 OH 0.0200 85,000.00 1,700.00
2 Tukang Cat L02 OH 0.2000 95,000.00 19,000.00
3 Kepala Tukang L03 OH 0.0200 100,000.00 2,000.00
4 Mandor L04 OH 0.0025 120,000.00 300.00
JUMLAH HARGA TENAGA 23,000.00
B BAHAN
1 Meni Besi kg 0.1000 37,196.00 3,719.60
2 Kwas bh 0.0100 2,844.40 28.44
JUMLAH HARGA BAHAN 3,748.04
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 26,748.04


E Overhead dan Profit % 10.0000 26,748.04 2,674.80
F Harga Satuan Pekerjaan (D+E) 29,422.85

PEKERJAAN ADUKAN BETON

JENIS PEKERJAAN A,A,4,1,1,4 : 1 m3 Lantai Kerja Beton K100 halaman 389 dari 684
A. TENAGA
1 Pekerja L01 OH 1.2000 85,000.00 102,000.00
2 Tukang Batu L02 OH 0.2000 95,000.00 19,000.00
3 Kepala Tukang Batu L03 OH 0.0200 100,000.00 2,000.00
4 Mandor L04 OH 0.0600 120,000.00 7,200.00
JUMLAH HARGA TENAGA 130,200.00
B BAHAN
1 Portland Cement (PC) kg 230.0000 1,700.00 391,000.00
2 Pasir Cor kg 983.0000 175.00 172,025.00
3 Stenslah/batu pecah tangan 2/3 kg 1,027.0000 190.00 195,130.00
4 Air liter 200.0000 100.00 20,000.00
JUMLAH HARGA BAHAN 778,155.00
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 908,355.00


E Overhead dan Profit % 10.0000 908,355.00 90,835.50
F Harga Satuan Pekerjaan (D+E) 999,190.50

JENIS PEKERJAAN A,A,4,1,1,10 : 1 m3 Beton Mutu K300 halaman 392 dari 684
A. TENAGA
1 Pekerja L01 OH 1.6500 85,000.00 140,250.00
2 Tukang Batu L02 OH 0.2750 95,000.00 26,125.00
3 Kepala Tukang Batu L03 OH 0.0280 100,000.00 2,800.00
4 Mandor L04 OH 0.0830 120,000.00 9,960.00
JUMLAH HARGA TENAGA 179,135.00
B BAHAN
1 Portland Cement (PC) kg 395.0000 1,650.00 651,750.00
2 Pasir Cor kg 475.0000 165.00 78,375.00
3 Stenslah/batu pecah tangan 2/3 kg 952.0000 200.00 190,400.00
4 Air liter 215.0000 75.00 16,125.00
JUMLAH HARGA BAHAN 936,650.00
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 1,115,785.00


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
E Overhead dan Profit % 10.0000 1,115,785.00 111,578.50
F Harga Satuan Pekerjaan (D+E) 1,227,363.50
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

PEKERJAAN PEMBESIAN

JENIS PEKERJAAN A ,4, 1, 1, 17 : 1 m3 Pekerjaan Pembesian 10 kg Besi Polos halaman 395 dari 684
A. TENAGA
1 Pekerja L01 OH 0.0700 85,000.00 5,950.00
2 Tukang Besi L02 OH 0.0700 95,000.00 6,650.00
3 Kepala Tukang L03 OH 0.0070 100,000.00 700.00
4 Mandor L04 OH 0.0040 120,000.00 480.00
JUMLAH HARGA TENAGA 13,780.00
B BAHAN
1 besi beton (polos) kg 10.5000 9,500.00 99,750.00
2 kawat bendreat kg 0.1500 16,500.00 2,475.00
JUMLAH HARGA BAHAN 102,225.00
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 116,005.00


E Overhead dan Profit % 10.0000 116,005.00 11,600.50
F Harga Satuan Pekerjaan (D+E) 127,605.50
Harga satuan pekerjaan dalam satuan Kg 12,760.55

JENIS PEKERJAAN A ,4, 1, 1, 17 : 1 m3 Pekerjaan Pembesian 10 kg Besi Ulir halaman 395 dari 684
A. TENAGA
1 Pekerja L01 OH 0.0700 85,000.00 5,950.00
2 Tukang Besi L02 OH 0.0700 95,000.00 6,650.00
3 Kepala Tukang L03 OH 0.0070 100,000.00 700.00
4 Mandor L04 OH 0.0040 120,000.00 480.00
JUMLAH HARGA TENAGA 13,780.00
B BAHAN
1 besi beton (ulir) kg 10.5000 9,700.00 101,850.00
2 kawat bendreat kg 0.1500 16,500.00 2,475.00
JUMLAH HARGA BAHAN 104,325.00
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 118,105.00


E Overhead dan Profit % 10.0000 118,105.00 11,810.50
F Harga Satuan Pekerjaan (D+E) 129,915.50
Harga satuan pekerjaan dalam satuan Kg 12,991.55

PEKERJAAN BEKESTING

JENIS PEKERJAAN A ,4, 1, 1, 20 : 1 m2 Pekerjaan Bekesting untuk Pondasi halaman 397 dari 684
A. TENAGA
1 Pekerja L01 OH 0.5200 85,000.00 44,200.00
2 Tukang Kayu L02 OH 0.2600 95,000.00 24,700.00
3 Kepala Tukang L03 OH 0.0260 100,000.00 2,600.00
4 Mandor L04 OH 0.0260 120,000.00 3,120.00
JUMLAH HARGA TENAGA 74,620.00
B BAHAN
1 kayu kelas III m3 0.0400 3,300,000.00 132,000.00
2 paku 5 - 10cm kg 0.3000 16,410.00 4,923.00
3 minyak bekesting liter 0.1000 4,923.00 492.30
JUMLAH HARGA BAHAN 137,415.30
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 212,035.30


E Overhead dan Profit % 10.0000 212,035.30 21,203.53
F Harga Satuan Pekerjaan (D+E) 233,238.83
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JENIS PEKERJAAN : 1 m2 Pekerjaan Bekesting untuk Pondasi (Material 3x Pakai)


A. TENAGA
1 Pekerja L01 OH 0.5200 85,000.00 44,200.00
2 Tukang Kayu L02 OH 0.2600 95,000.00 24,700.00
3 Kepala Tukang L03 OH 0.0260 100,000.00 2,600.00
4 Mandor L04 OH 0.0260 120,000.00 3,120.00
JUMLAH HARGA TENAGA 74,620.00
B BAHAN
1 Kayu Kelas III m3 0.0133 3,300,000.00 44,000.00
2 Paku 5 - 10cm kg 0.3000 16,410.00 4,923.00
3 Minyak Bekesting liter 0.1000 4,923.00 492.30
JUMLAH HARGA BAHAN 49,415.30
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 124,035.30


E Overhead dan Profit % 10.0000 124,035.30 12,403.53
F Harga Satuan Pekerjaan (D+E) 136,438.83

JENIS PEKERJAAN A ,4, 1, 1, 21 : 1 m2 Pekerjaan Bekesting untuk Sloof halaman 398 dari 684
A. TENAGA
1 Pekerja L01 OH 0.5200 85,000.00 44,200.00
2 Tukang Kayu L02 OH 0.2600 95,000.00 24,700.00
3 Kepala Tukang L03 OH 0.0260 100,000.00 2,600.00
4 Mandor L04 OH 0.0260 120,000.00 3,120.00
JUMLAH HARGA TENAGA 74,620.00
B BAHAN
1 Kayu Kelas III m3 0.0450 3,300,000.00 148,500.00
2 Paku 5 - 10cm kg 0.3000 16,410.00 4,923.00
3 Minyak Bekesting liter 0.1000 4,923.00 492.30
JUMLAH HARGA BAHAN 153,915.30
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 228,535.30


E Overhead dan Profit % 10.0000 228,535.30 22,853.53
F Harga Satuan Pekerjaan (D+E) 251,388.83

JENIS PEKERJAAN : 1 m2 Pekerjaan Bekesting untuk Sloof (Material 3x Pakai)


A. TENAGA
1 Pekerja L01 OH 0.5200 85,000.00 44,200.00
2 Tukang Kayu L02 OH 0.2600 95,000.00 24,700.00
3 Kepala Tukang L03 OH 0.0260 100,000.00 2,600.00
4 Mandor L04 OH 0.0260 120,000.00 3,120.00
JUMLAH HARGA TENAGA 74,620.00
B BAHAN
1 Kayu Kelas III m3 0.0150 3,300,000.00 49,500.00
2 Paku 5 - 10cm kg 0.3000 16,410.00 4,923.00
3 Minyak Bekesting liter 0.1000 4,923.00 492.30
JUMLAH HARGA BAHAN 54,915.30
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 129,535.30


E Overhead dan Profit % 10.0000 129,535.30 12,953.53
F Harga Satuan Pekerjaan (D+E) 142,488.83
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JENIS PEKERJAAN A ,4, 1, 1, 22 : 1 m2 Pekerjaan Bekesting untuk Kolom halaman 398 dari 684
A. TENAGA
1 Pekerja L01 OH 0.6600 85,000.00 56,100.00
2 Tukang Kayu L02 OH 0.3300 95,000.00 31,350.00
3 Kepala Tukang L03 OH 0.0330 100,000.00 3,300.00
4 Mandor L04 OH 0.0330 120,000.00 3,960.00
JUMLAH HARGA TENAGA 94,710.00
B BAHAN
1 Kayu Kelas III m3 0.0400 3,300,000.00 132,000.00
2 Paku 5 - 10cm kg 0.4000 16,410.00 6,564.00
3 Minyak Bekesting liter 0.2000 4,923.00 984.60
4 Balok kayu kelas II m3 0.0150 3,300,000.00 49,500.00
5 Plywood 9mm lbr 0.3500 110,767.50 38,768.63
6 Dolken Kayu Ø 8-10cm, P. 4m batang 2.0000 16,410.00 32,820.00
JUMLAH HARGA BAHAN 260,637.23
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 355,347.23


E Overhead dan Profit % 10.0000 355,347.23 35,534.72
F Harga Satuan Pekerjaan (D+E) 390,881.95

JENIS PEKERJAAN : 1 m2 Pekerjaan Bekesting untuk Kolom (Material 3x Pakai)


A. TENAGA
1 Pekerja L01 OH 0.6600 85,000.00 56,100.00
2 Tukang Kayu L02 OH 0.3300 95,000.00 31,350.00
3 Kepala Tukang L03 OH 0.0330 100,000.00 3,300.00
4 Mandor L04 OH 0.0330 120,000.00 3,960.00
JUMLAH HARGA TENAGA 94,710.00
B BAHAN
1 Kayu Kelas III m3 0.0133 3,300,000.00 44,000.00
2 Paku 5 - 10cm kg 0.4000 16,410.00 6,564.00
3 Minyak Bekesting liter 0.2000 4,923.00 984.60
4 Balok kayu kelas II m3 0.0050 3,300,000.00 16,500.00
5 Plywood 9mm lbr 0.1167 110,767.50 12,922.88
6 Dolken Kayu Ø 8-10cm, P. 4m batang 0.6667 16,410.00 10,940.00
JUMLAH HARGA BAHAN 91,911.48
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 186,621.48


E Overhead dan Profit % 10.0000 186,621.48 18,662.15
F Harga Satuan Pekerjaan (D+E) 205,283.62

JENIS PEKERJAAN A ,4, 1, 1, 23 : 1 m2 Pekerjaan Bekesting untuk Balok halaman 399 dari 684
A. TENAGA
1 Pekerja L01 OH 0.6600 85,000.00 56,100.00
2 Tukang Kayu L02 OH 0.3300 95,000.00 31,350.00
3 Kepala Tukang L03 OH 0.0330 100,000.00 3,300.00
4 Mandor L04 OH 0.0330 120,000.00 3,960.00
JUMLAH HARGA TENAGA 94,710.00
B BAHAN
1 Kayu Kelas III m3 0.0400 3,300,000.00 132,000.00
2 Paku 5 - 10cm kg 0.4000 16,410.00 6,564.00
3 Minyak Bekesting liter 0.2000 4,923.00 984.60
4 Balok kayu kelas II m3 0.0180 3,300,000.00 59,400.00
5 Plywood 9mm lbr 0.3500 110,767.50 38,768.63
6 Dolken Kayu Ø 8-10cm, P. 4m batang 2.0000 16,410.00 32,820.00
JUMLAH HARGA BAHAN 270,537.23
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 365,247.23


E Overhead dan Profit % 10.0000 365,247.23 36,524.72
F Harga Satuan Pekerjaan (D+E) 401,771.95
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JENIS PEKERJAAN : 1 m2 Pekerjaan Bekesting untuk Balok (Material 2x Pakai)


A. TENAGA
1 Pekerja L01 OH 0.6600 85,000.00 56,100.00
2 Tukang Kayu L02 OH 0.3300 95,000.00 31,350.00
3 Kepala Tukang L03 OH 0.0330 100,000.00 3,300.00
4 Mandor L04 OH 0.0330 120,000.00 3,960.00
JUMLAH HARGA TENAGA 94,710.00
B BAHAN
1 Kayu Kelas III m3 0.0200 3,300,000.00 66,000.00
2 Paku 5 - 10cm kg 0.4000 16,410.00 6,564.00
3 Minyak Bekesting liter 0.2000 4,923.00 984.60
4 Balok kayu kelas II m3 0.0090 3,300,000.00 29,700.00
5 Plywood 9mm lbr 0.1750 110,767.50 19,384.31
6 Dolken Kayu Ø 8-10cm, P. 4m batang 1.0000 16,410.00 16,410.00
JUMLAH HARGA BAHAN 139,042.91
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 233,752.91


E Overhead dan Profit % 10.0000 233,752.91 23,375.29
F Harga Satuan Pekerjaan (D+E) 257,128.20

JENIS PEKERJAAN A ,4, 1, 1, 24 : 1 m2 Pekerjaan Bekesting untuk Lantai halaman 399 dari 684
A. TENAGA
1 Pekerja L01 OH 0.6600 85,000.00 56,100.00
2 Tukang Kayu L02 OH 0.3300 95,000.00 31,350.00
3 Kepala Tukang L03 OH 0.0330 100,000.00 3,300.00
4 Mandor L04 OH 0.0330 120,000.00 3,960.00
JUMLAH HARGA TENAGA 94,710.00
B BAHAN
1 Kayu Kelas III m3 0.0400 3,300,000.00 132,000.00
2 Paku 5 - 10cm kg 0.4000 16,410.00 6,564.00
3 Minyak Bekesting liter 0.2000 4,923.00 984.60
4 Balok kayu kelas II m3 0.0150 3,300,000.00 49,500.00
5 Plywood 9mm lbr 0.3500 110,767.50 38,768.63
6 Dolken Kayu Ø 8-10cm, P. 4m batang 6.0000 16,410.00 98,460.00
JUMLAH HARGA BAHAN 326,277.23
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 420,987.23


E Overhead dan Profit % 10.0000 420,987.23 42,098.72
F Harga Satuan Pekerjaan (D+E) 463,085.95

JENIS PEKERJAAN : 1 m2 Pekerjaan Bekesting untuk Lantai (Material 2x Pakai)


A. TENAGA
1 Pekerja L01 OH 0.6600 85,000.00 56,100.00
2 Tukang Kayu L02 OH 0.3300 95,000.00 31,350.00
3 Kepala Tukang L03 OH 0.0330 100,000.00 3,300.00
4 Mandor L04 OH 0.0330 120,000.00 3,960.00
JUMLAH HARGA TENAGA 94,710.00
B BAHAN
1 Kayu Kelas III m3 0.0200 3,300,000.00 66,000.00
2 Paku 5 - 10cm kg 0.4000 16,410.00 6,564.00
3 Minyak Bekesting liter 0.2000 4,923.00 984.60
4 Balok kayu kelas II m3 0.0075 3,300,000.00 24,750.00
5 Plywood 9mm lbr 0.1750 110,767.50 19,384.31
6 Dolken Kayu Ø 8-10cm, P. 4m batang 3.0000 16,410.00 49,230.00
JUMLAH HARGA BAHAN 166,912.91
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 261,622.91


E Overhead dan Profit % 10.0000 261,622.91 26,162.29
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) 287,785.20
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JENIS PEKERJAAN A ,4, 1, 1, 26 : 1 m2 Pekerjaan Bekesting untuk Tangga halaman 400 dari 684
A. TENAGA
1 Pekerja L01 OH 0.6600 85,000.00 56,100.00
2 Tukang Kayu L02 OH 0.3300 95,000.00 31,350.00
3 Kepala Tukang L03 OH 0.0330 100,000.00 3,300.00
4 Mandor L04 OH 0.0330 120,000.00 3,960.00
JUMLAH HARGA TENAGA 94,710.00
B BAHAN
1 Kayu Kelas III m3 0.0300 3,300,000.00 99,000.00
2 Paku 5 - 10cm kg 0.4000 16,410.00 6,564.00
3 Minyak Bekesting liter 0.1500 4,923.00 738.45
4 Balok kayu kelas II m3 0.0150 3,300,000.00 49,500.00
5 Plywood 9mm lbr 0.3500 110,767.50 38,768.63
6 Dolken Kayu Ø 8-10cm, P. 4m batang 2.0000 16,410.00 32,820.00
JUMLAH HARGA BAHAN 227,391.08
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 322,101.08


E Overhead dan Profit % 10.0000 322,101.08 32,210.11
F Harga Satuan Pekerjaan (D+E) 354,311.18

JENIS PEKERJAAN : 1 m2 Pekerjaan Bekesting untuk Tangga (Material 2x Pakai)


A. TENAGA
1 Pekerja L01 OH 0.6600 85,000.00 56,100.00
2 Tukang Kayu L02 OH 0.3300 95,000.00 31,350.00
3 Kepala Tukang L03 OH 0.0330 100,000.00 3,300.00
4 Mandor L04 OH 0.0330 120,000.00 3,960.00
JUMLAH HARGA TENAGA 94,710.00
B BAHAN
1 Kayu Kelas III m3 0.0150 3,300,000.00 49,500.00
2 Paku 5 - 10cm kg 0.4000 16,410.00 6,564.00
3 Minyak Bekesting liter 0.1500 4,923.00 738.45
4 Balok kayu kelas II m3 0.0075 3,300,000.00 24,750.00
5 Plywood 9mm lbr 0.1750 110,767.50 19,384.31
6 Dolken Kayu Ø 8-10cm, P. 4m batang 1.0000 16,410.00 16,410.00
JUMLAH HARGA BAHAN 117,346.76
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 212,056.76


E Overhead dan Profit % 10.0000 212,056.76 21,205.68
F Harga Satuan Pekerjaan (D+E) 233,262.44

JENIS PEKERJAAN A ,4, 1, 1, 24 : 1 m2 Pekerjaan Bekesting untuk Dinding halaman 400 dari 684
A. TENAGA
1 Pekerja L01 OH 0.6600 85,000.00 56,100.00
2 Tukang Kayu L02 OH 0.3300 95,000.00 31,350.00
3 Kepala Tukang L03 OH 0.0330 100,000.00 3,300.00
4 Mandor L04 OH 0.0330 120,000.00 3,960.00
JUMLAH HARGA TENAGA 94,710.00
B BAHAN
1 Kayu Kelas III m3 0.0300 3,300,000.00 99,000.00
2 Paku 5 - 10cm kg 0.4000 16,410.00 6,564.00
3 Minyak Bekesting liter 0.2000 4,923.00 984.60
4 Balok kayu kelas II m3 0.0200 3,300,000.00 66,000.00
5 Plywood 9mm lbr 0.3500 110,767.50 38,768.63
6 Dolken Kayu Ø 8-10cm, P. 4m batang 3.0000 16,410.00 49,230.00
7 Penjaga Jarak Begesting / Specer buah 4.0000 4,923.00 19,692.00
JUMLAH HARGA BAHAN 280,239.23
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 374,949.23


E Overhead dan Profit % 10.0000 374,949.23 37,494.92
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) 412,444.15
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JENIS PEKERJAAN : 1 m2 Pekerjaan Bekesting untuk Dinding (Material 2x Pakai)


A. TENAGA
1 Pekerja L01 OH 0.6600 85,000.00 56,100.00
2 Tukang Kayu L02 OH 0.3300 95,000.00 31,350.00
3 Kepala Tukang L03 OH 0.0330 100,000.00 3,300.00
4 Mandor L04 OH 0.0330 120,000.00 3,960.00
JUMLAH HARGA TENAGA 94,710.00
B BAHAN
1 Kayu Kelas III m3 0.0150 3,300,000.00 49,500.00
2 Paku 5 - 10cm kg 0.4000 16,410.00 6,564.00
3 Minyak Bekesting liter 0.2000 4,923.00 984.60
4 Balok kayu kelas II m3 0.0100 3,300,000.00 33,000.00
5 Plywood 9mm lbr 0.1750 110,767.50 19,384.31
6 Dolken Kayu Ø 8-10cm, P. 4m batang 1.5000 16,410.00 24,615.00
7 Penjaga Jarak Begesting / Specer buah 2.0000 4,923.00 9,846.00
JUMLAH HARGA BAHAN 143,893.91
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 238,603.91


E Overhead dan Profit % 10.0000 238,603.91 23,860.39
F Harga Satuan Pekerjaan (D+E) 262,464.30

PEKERJAAN BETON BERTULANG (BANGUNAN UTAMA)

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Pondasi Strous

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 48.0000 12,760.55 612,506.40
3 Pekerjaan Pembesian (Ulir) kg 82.0000 12,991.55 1,065,307.10

: 1 m3 Pekerjaan Pondasi Strous 2,905,177.00

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Pondasi Poer PC1

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg - 12,760.55 -
3 Pekerjaan Pembesian (Ulir) kg 147.0000 12,991.55 1,909,757.85
4 Pekerjaan Bekesting Pondasi (Material 3x pakai) m2 5.0000 136,438.83 682,194.15

: 1 m3 Pekerjaan Pondasi Poer PC1 3,819,315.50

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Pondasi Poer PC1A

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg - 12,760.55 -
3 Pekerjaan Pembesian (Ulir) kg 147.0000 12,991.55 1,909,757.85
4 Pekerjaan Bekesting Pondasi (Material 3x pakai) m2 5.0000 136,438.83 682,194.15

: 1 m3 Pekerjaan Pondasi Poer PC1A 3,819,315.50

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Pondasi Poer PC2

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg - 12,760.55 -
3 Pekerjaan Pembesian (Ulir) kg 197.0000 12,991.55 2,559,335.35
4 Pekerjaan Bekesting Pondasi (Material 3x pakai) m2 3.1505 136,438.83 429,855.67

: 1 m3 Pekerjaan Pondasi Poer PC2 4,216,554.52


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Pondasi Poer PC3

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg - 12,760.55 -
3 Pekerjaan Pembesian (Ulir) kg 169.0000 12,991.55 2,195,571.95
4 Pekerjaan Bekesting Pondasi (Material 3x pakai) m2 2.7071 136,438.83 369,358.60

: 1 m3 Pekerjaan Pondasi Poer PC3 3,792,294.05

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Tie Beam 30/45 TB1

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 58.0000 12,760.55 740,111.90
3 Pekerjaan Pembesian (Ulir) kg 87.5000 12,991.55 1,136,760.63
4 Pekerjaan Bekesting Sloof (Material 2x Pakai) m2 4.9750 142,488.83 708,881.93

: 1 m3 Pekerjaan Tie Beam 35/65 TB1 3,813,117.95

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Tie Beam 30/45 TB2

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 58.0000 12,760.55 740,111.90
3 Pekerjaan Pembesian (Ulir) kg 87.5000 12,991.55 1,136,760.63
4 Pekerjaan Bekesting Sloof (Material 2x Pakai) m2 4.9750 142,488.83 708,881.93

: 1 m3 Pekerjaan Tie Beam 20/40 TB2 3,813,117.95

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Tie Beam 20/30 TB3

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 41.0000 12,760.55 523,182.55
3 Pekerjaan Pembesian (Ulir) kg 121.0000 12,991.55 1,571,977.55
4 Pekerjaan Bekesting Sloof (Material 3x Pakai) m2 3.6750 142,488.83 523,646.45

: 1 m3 Pekerjaan Tie Beam 20/30 TB3 3,846,170.05

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Kolom 30x60 K1

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 64.3600 12,760.55 821,269.00
3 Pekerjaan Pembesian (Ulir) kg 81.8200 12,991.55 1,062,968.62
4 Pekerjaan Bekesting Kolom (Material 3x Pakai) m2 5.1290 205,283.62 1,052,899.70

: 1 m3 Pekerjaan Kolom 60x60 K1 4,164,500.82

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Kolom 35x75 K2

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 120.0000 12,760.55 1,531,266.00
3 Pekerjaan Pembesian (Ulir) kg 109.0000 12,991.55 1,416,078.95
4 Pekerjaan Bekesting Kolom (Material 3x Pakai) m2 8.5714 205,283.62 1,759,573.91

: 1 m3 Pekerjaan Kolom 35x75 K2 5,934,282.36

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Kolom L.35x70 K3

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 21.0000 12,760.55 267,971.55
3 Pekerjaan Pembesian (Ulir) kg 97.0000 12,991.55 1,260,180.35
4 Pekerjaan Bekesting Kolom (Material 3x Pakai) m2 9.5238 205,283.62 1,955,082.12

: 1 m3 Pekerjaan Kolom L.35x70 K3 4,710,597.52


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Kolom L.20x40 K4

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 24.0000 12,760.55 306,253.20
3 Pekerjaan Pembesian (Ulir) kg 105.0000 12,991.55 1,364,112.75
4 Pekerjaan Bekesting Kolom (Material 3x Pakai) m2 16.6667 205,283.62 3,421,393.71

: 1 m3 Pekerjaan Kolom L.20x40 K4 6,319,123.16

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Kolom L.15x30 K5

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 32.0000 12,760.55 408,337.60
3 Pekerjaan Pembesian (Ulir) kg 187.0000 12,991.55 2,429,419.85
4 Pekerjaan Bekesting Kolom (Material 3x Pakai) m2 22.2222 205,283.62 4,561,858.28

: 1 m3 Pekerjaan Kolom L.15x30 K5 8,626,979.23

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Kolom 30x30 K6

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 110.0000 12,760.55 1,403,660.50
3 Pekerjaan Pembesian (Ulir) kg 92.0000 12,991.55 1,195,222.60
4 Pekerjaan Bekesting Kolom (Material 3x Pakai) m2 13.3333 205,283.62 2,737,114.97

: 1 m3 Pekerjaan Kolom 30x30 K6 6,563,361.57

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Kolom 60x60 K7

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 81.0000 12,760.55 1,033,604.55
3 Pekerjaan Pembesian (Ulir) kg 87.0000 12,991.55 1,130,264.85
4 Pekerjaan Bekesting Kolom (Material 3x Pakai) m2 6.6667 205,283.62 1,368,557.48

: 1 m3 Pekerjaan Kolom 60x60 K7 4,759,790.38

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Kolom 35x75 K8

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 102.0000 12,760.55 1,301,576.10
3 Pekerjaan Pembesian (Ulir) kg 90.0000 12,991.55 1,169,239.50
4 Pekerjaan Bekesting Kolom (Material 3x Pakai) m2 8.5714 205,283.62 1,759,573.91

: 1 m3 Pekerjaan Kolom 35x75 K8 5,457,753.01

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Kolom L.35x70 K9

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 21.0000 12,760.55 267,971.55
3 Pekerjaan Pembesian (Ulir) kg 85.0000 12,991.55 1,104,281.75
4 Pekerjaan Bekesting Kolom (Material 3x Pakai) m2 9.5238 205,283.62 1,955,082.12

: 1 m3 Pekerjaan Kolom L.35x70 K9 4,554,698.92

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Kolom L.20x40 K10

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 24.0000 12,760.55 306,253.20
3 Pekerjaan Pembesian (Ulir) kg 86.0000 12,991.55 1,117,273.30
4 Pekerjaan Bekesting Kolom (Material 3x Pakai) m2 16.6667 205,283.62 3,421,393.71

: 1 m3 Pekerjaan Kolom L.20x40 K10 6,072,283.71


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Kolom L.15x30 K11

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 32.0000 12,760.55 408,337.60
3 Pekerjaan Pembesian (Ulir) kg 123.0000 12,991.55 1,597,960.65
4 Pekerjaan Bekesting Kolom (Material 3x Pakai) m2 22.2222 205,283.62 4,561,858.28

: 1 m3 Pekerjaan Kolom L.15x30 K11 7,795,520.03

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Kolom 20x40 K12

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 78.0000 12,760.55 995,322.90
3 Pekerjaan Pembesian (Ulir) kg 104.0000 12,991.55 1,351,121.20
4 Pekerjaan Bekesting Kolom (Material 3x Pakai) m2 15.0000 205,283.62 3,079,254.34

: 1 m3 Pekerjaan Kolom 20x40 K12 6,653,061.94

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Balok 30/50 B1

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 52.1000 12,760.55 664,824.66
3 Pekerjaan Pembesian (Ulir) kg 79.8600 12,991.55 1,037,505.18
4 Pekerjaan Bekesting Balok (Material 2x Pakai) m2 5.2300 257,128.20 1,344,780.51

: 1 m3 Pekerjaan Balok 40/70 B1 4,274,473.84

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Balok 30/45 B2

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 51.4000 12,760.55 655,892.27
3 Pekerjaan Pembesian (Ulir) kg 79.8600 12,991.55 1,037,505.18
4 Pekerjaan Bekesting Balok (Material 2x Pakai) m2 5.2300 257,128.20 1,344,780.51

: 1 m3 Pekerjaan Balok 40/80 B1A 4,265,541.46

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Balok 25/35 B3

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 48.7200 12,760.55 621,694.00
3 Pekerjaan Pembesian (Ulir) kg 79.8600 12,991.55 1,037,505.18
4 Pekerjaan Bekesting Balok (Material 2x Pakai) m2 3.8750 257,128.20 996,371.79

: 1 m3 Pekerjaan Balok 25/50 B2 3,882,934.47

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Balok 20/30 B4

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 45.3000 12,760.55 578,052.92
3 Pekerjaan Pembesian (Ulir) kg 75.3000 12,991.55 978,263.72
4 Pekerjaan Bekesting Balok (Material 2x Pakai) m2 4.4000 257,128.20 1,131,364.10

: 1 m3 Pekerjaan Balok 20/45 B3 3,915,044.23

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Balok 20/30 B4

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 45.3000 12,760.55 578,052.92
3 Pekerjaan Pembesian (Ulir) kg 75.3000 12,991.55 978,263.72
4 Pekerjaan Bekesting Balok (Material 2x Pakai) m2 4.4300 257,128.20 1,139,077.94

: 1 m3 Pekerjaan Balok 20/30 B4 3,922,758.07


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Balok 15/30 B5

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 49.0000 12,760.55 625,266.95
3 Pekerjaan Pembesian (Ulir) kg 115.0000 12,991.55 1,494,028.25
4 Pekerjaan Bekesting Balok (Material 2x Pakai) m2 11.3333 257,128.20 2,914,119.64

: 1 m3 Pekerjaan Balok 15/30 B5 6,260,778.34

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Plat Lantai (S1) tebal 12 cm

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 115.5000 12,760.55 1,473,843.53
3 Pekerjaan Pembesian (Ulir) kg - 12,991.55 -
4 Pekerjaan Bekesting Lantai (Material 2x Pakai) m2 7.1320 287,785.20 2,052,484.07

: 1 m3 Pekerjaan Plat Lantai (S1) tebal 12 cm 4,753,691.10

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Plat Lantai (S3) tebal 10 cm

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 103.0000 12,760.55 1,314,336.65
3 Pekerjaan Pembesian (Ulir) kg - 12,991.55 -
4 Pekerjaan Bekesting Lantai (Material 2x Pakai) m2 10.0000 287,785.20 2,877,852.04

: 1 m3 Pekerjaan Plat Lantai (S3) tebal 10 cm 5,419,552.19

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Plat Lantai (S2) tebal 14 cm

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 74.0000 12,760.55 944,280.70
3 Pekerjaan Pembesian (Ulir) kg - 12,991.55 -
4 Pekerjaan Bekesting Lantai (Material 2x Pakai) m2 7.1429 287,785.20 2,055,608.60

: 1 m3 Pekerjaan Plat Lantai (S2) tebal 14 cm 4,227,252.80

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Beton Tangga

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 95.0000 12,760.55 1,212,252.25
3 Pekerjaan Pembesian (Ulir) kg 80.0000 12,991.55 1,039,324.00
4 Pekerjaan Bekesting Tangga (Material 2x Pakai) m2 8.6700 233,262.44 2,022,385.34

: 1 m3 Pekerjaan Beton Tangga 5,501,325.09

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Plat Lantai (Pit Lift) tebal 25 cm

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg - 12,760.55 -
3 Pekerjaan Pembesian (Ulir) kg 48.0000 12,991.55 623,594.40
4 Pekerjaan Bekesting Lantai (Material 2x Pakai) m2 4.0000 287,785.20 1,151,140.82

: 1 m3 Pekerjaan Plat Lantai (Pit Lift) tebal 25 cm 3,002,098.72

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Plat Dinding (Pit Lift) tebal 20 cm

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg - 12,760.55 -
3 Pekerjaan Pembesian (Ulir) kg 64.0000 12,991.55 831,459.20
4 Pekerjaan Bekesting Lantai (Material 2x Pakai) m2 10.0000 262,464.30 2,624,643.04

: 1 m3 Pekerjaan Plat Dinding (Pit Lift) tebal 20 cm 4,683,465.74


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
PEKERJAAN BETON BERTULANG (R.GENSET)

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Pondasi Strous

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 141.0000 12,760.55 1,799,237.55
3 Pekerjaan Pembesian (Ulir) kg - 12,991.55 -

: 1 m3 Pekerjaan Pondasi Strous 3,026,601.05

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Pondasi Poer PS1

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg - 12,760.55 -
3 Pekerjaan Pembesian (Ulir) kg 188.0000 12,991.55 2,442,411.40
4 Pekerjaan Bekesting Pondasi (Material 3x pakai) m2 6.6667 136,438.83 909,592.20

: 1 m3 Pekerjaan Pondasi Poer PS1 4,579,367.10

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Tie Beam 20/30 TB1

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 41.0000 12,760.55 523,182.55
3 Pekerjaan Pembesian (Ulir) kg 121.0000 12,991.55 1,571,977.55
4 Pekerjaan Bekesting Sloof (Material 3x Pakai) m2 10.0000 142,488.83 1,424,888.30

: 1 m3 Pekerjaan Tie Beam 20/30 TB1 4,747,411.90

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Tie Beam 15/25 TB2

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 53.0000 12,760.55 676,309.15
3 Pekerjaan Pembesian (Ulir) kg 138.0000 12,991.55 1,792,833.90
4 Pekerjaan Bekesting Sloof (Material 3x Pakai) m2 13.3333 142,488.83 1,899,851.07

: 1 m3 Pekerjaan Tie Beam 15/25 TB2 5,596,357.62

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Kolom 35x40 K1

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 89.0000 12,760.55 1,135,688.95
3 Pekerjaan Pembesian (Ulir) kg 74.0000 12,991.55 961,374.70
4 Pekerjaan Bekesting Kolom (Material 3x Pakai) m2 10.7143 205,283.62 2,199,467.38

: 1 m3 Pekerjaan Kolom 35x40 K1 5,523,894.53

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Kolom 15x35 K2

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 157.0000 12,760.55 2,003,406.35
3 Pekerjaan Pembesian (Ulir) kg 118.0000 12,991.55 1,533,002.90
4 Pekerjaan Bekesting Kolom (Material 3x Pakai) m2 19.0476 205,283.62 3,910,164.24

: 1 m3 Pekerjaan Kolom 15x35 K2 8,673,936.99

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Balok25/50 B1

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 93.0000 12,760.55 1,186,731.15
3 Pekerjaan Pembesian (Ulir) kg 115.0000 12,991.55 1,494,028.25
4 Pekerjaan Bekesting Balok (Material 2x Pakai) m2 8.0800 257,128.20 2,077,595.89

: 1 m3 Pekerjaan Balok25/50 B1 5,985,718.79


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Balok 20/30 B2

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 66.0000 12,760.55 842,196.30
3 Pekerjaan Pembesian (Ulir) kg 104.0000 12,991.55 1,351,121.20
4 Pekerjaan Bekesting Balok (Material 2x Pakai) m2 9.3333 257,128.20 2,399,863.24

: 1 m3 Pekerjaan Balok 20/30 B2 5,820,544.24

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Balok 15/25 B3

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 85.0000 12,760.55 1,084,646.75
3 Pekerjaan Pembesian (Ulir) kg 138.0000 12,991.55 1,792,833.90
4 Pekerjaan Bekesting Balok (Material 2x Pakai) m2 10.9333 257,128.20 2,811,268.36

: 1 m3 Pekerjaan Balok 15/25 B3 6,916,112.51

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Plat Lantai (S1) tebal 10 cm

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 103.0000 12,760.55 1,314,336.65
3 Pekerjaan Pembesian (Ulir) kg - 12,991.55 -
4 Pekerjaan Bekesting Lantai (Material 2x Pakai) m2 10.0000 287,785.20 2,877,852.04

: 1 m3 Pekerjaan Plat Lantai (S1) tebal 10 cm 5,419,552.19

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Plat Lantai (S2) tebal 15 cm

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg - 12,760.55 -
3 Pekerjaan Pembesian (Ulir) kg 106.0000 12,991.55 1,377,104.30
4 Pekerjaan Bekesting Lantai (Material 2x Pakai) m2 2.0000 287,785.20 575,570.41

: 1 m3 Pekerjaan Plat Lantai (S2) tebal 15 cm 3,180,038.21

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Plat Lantai tebal 50 cm

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg - 12,760.55 -
3 Pekerjaan Pembesian (Ulir) kg 44.0000 12,991.55 571,628.20
4 Pekerjaan Bekesting Lantai (Material 2x Pakai) m2 2.0000 287,785.20 575,570.41

: 1 m3 Pekerjaan Plat Lantai tebal 50 cm 2,374,562.11

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Plat Lantai tebal 10 cm

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 92.0000 12,760.55 1,173,970.60
3 Pekerjaan Pembesian (Ulir) kg - 12,991.55 -
4 Pekerjaan Bekesting Lantai (Material 2x Pakai) m2 10.0000 287,785.20 2,877,852.04

: 1 m3 Pekerjaan Plat Lantai tebal 10 cm 5,279,186.14

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Beton Tangga

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 61.2000 12,760.55 780,945.66
3 Pekerjaan Pembesian (Ulir) kg 80.0000 12,991.55 1,039,324.00
4 Pekerjaan Bekesting Tangga (Material 2x Pakai) m2 7.6500 233,262.44 1,784,457.66

: 1 m3 Pekerjaan Beton Tangga 4,832,090.82


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
PEKERJAAN BETON BERTULANG (R.SENTRAL GAS MEDIS)

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Pondasi Strous

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 141.0000 12,760.55 1,799,237.55
3 Pekerjaan Pembesian (Ulir) kg - 12,991.55 -

: 1 m3 Pekerjaan Pondasi Strous 3,026,601.05

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Pondasi Poer PS1

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg - 12,760.55 -
3 Pekerjaan Pembesian (Ulir) kg 188.0000 12,991.55 2,442,411.40
4 Pekerjaan Bekesting Pondasi (Material 3x pakai) m2 6.6667 136,438.83 909,592.20

: 1 m3 Pekerjaan Pondasi Poer PS1 4,579,367.10

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Tie Beam 20/40 TB1

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 58.0000 12,760.55 740,111.90
3 Pekerjaan Pembesian (Ulir) kg 98.0000 12,991.55 1,273,171.90
4 Pekerjaan Bekesting Sloof (Material 3x Pakai) m2 10.0000 142,488.83 1,424,888.30

: 1 m3 Pekerjaan Tie Beam 20/40 TB1 4,665,535.60

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Kolom 30x30 K1

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 110.0000 12,760.55 1,403,660.50
3 Pekerjaan Pembesian (Ulir) kg 92.0000 12,991.55 1,195,222.60
4 Pekerjaan Bekesting Kolom (Material 3x Pakai) m2 13.3333 205,283.62 2,737,114.97

: 1 m3 Pekerjaan Kolom 30x30 K1 6,563,361.57

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Balok 20/40 B1

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 90.0000 12,760.55 1,148,449.50
3 Pekerjaan Pembesian (Ulir) kg 120.0000 12,991.55 1,558,986.00
4 Pekerjaan Bekesting Balok (Material 2x Pakai) m2 9.5000 257,128.20 2,442,717.94

: 1 m3 Pekerjaan Balok 20/40 B1 6,377,516.94

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Balok 20/30 B2

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 66.0000 12,760.55 842,196.30
3 Pekerjaan Pembesian (Ulir) kg 104.0000 12,991.55 1,351,121.20
4 Pekerjaan Bekesting Balok (Material 2x Pakai) m2 9.3333 257,128.20 2,399,863.24

: 1 m3 Pekerjaan Balok 20/30 B2 5,820,544.24

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Plat Lantai tebal 12 cm

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 112.0000 12,760.55 1,429,181.60
3 Pekerjaan Pembesian (Ulir) kg - 12,991.55 -
4 Pekerjaan Bekesting Lantai (Material 2x Pakai) m2 8.3333 287,785.20 2,398,210.03

: 1 m3 Pekerjaan Plat Lantai tebal 12 cm 5,054,755.13


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
PEKERJAAN BETON BERTULANG (GROUND WATER TANK)

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Balok 20/40

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg 90.0000 12,760.55 1,148,449.50
3 Pekerjaan Pembesian (Ulir) kg 120.0000 12,991.55 1,558,986.00
4 Pekerjaan Bekesting Balok (Material 2x Pakai) m2 9.5000 257,128.20 2,442,717.94

: 1 m3 Pekerjaan Balok 20/40 6,377,516.94

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Plat Lantai tebal 25 cm

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg - 12,760.55 -
3 Pekerjaan Pembesian (Ulir) kg 66.0000 12,991.55 857,442.30
4 Pekerjaan Bekesting Lantai (Material 2x Pakai) m2 4.0000 287,785.20 1,151,140.82

: 1 m3 Pekerjaan Plat Lantai tebal 25 cm 3,235,946.62

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Plat Atap tebal 15 cm

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg - 12,760.55 -
3 Pekerjaan Pembesian (Ulir) kg 106.0000 12,991.55 1,377,104.30
4 Pekerjaan Bekesting Lantai (Material 2x Pakai) m2 6.6667 287,785.20 1,918,568.03

: 1 m3 Pekerjaan Plat Atap tebal 15 cm 4,523,035.83

JENIS PEKERJAAN BETON BERTULANG : 1 m3 Pekerjaan Plat Dinding tebal 20 cm

1 Pekerjaan Beton mutu K300 m3 1.0000 1,227,363.50 1,227,363.50


2 Pekerjaan Pembesian (Polos) kg - 12,760.55 -
3 Pekerjaan Pembesian (Ulir) kg 64.0000 12,991.55 831,459.20
4 Pekerjaan Bekesting Lantai (Material 2x Pakai) m2 10.0000 262,464.30 2,624,643.04

: 1 m3 Pekerjaan Plat Dinding tebal 20 cm 4,683,465.74

JENIS PEKERJAAN : 1 m' PVC Waterstop lebar 230 mm - 320 mm


A. TENAGA
1 Pekerja L01 OH 0.0800 75,000.00 6,000.00
2 Tukang batu L02 OH 0.0400 85,000.00 3,400.00
3 Kepala tukang L03 OH 0.0040 90,000.00 360.00
4 Mandor L04 OH 0.0040 100,000.00 400.00
JUMLAH HARGA TENAGA 10,160.00
B BAHAN
1 Waterstop lebar 230 - 320 mm m1 1.0500 109,400.00 114,870.00
JUMLAH HARGA BAHAN 114,870.00
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 125,030.00


E Overhead dan Profit % 10.0000 125,030.00 12,503.00
F Harga Satuan Pekerjaan (D+E) 137,533.00

JENIS PEKERJAAN : 1 m2 Waterproofing


A. TENAGA
1 Pekerja L01 OH 0.0700 75,000.00 5,250.00
2 Tukang cat L02 OH 0.0090 85,000.00 765.00
3 Kepala tukang L03 OH 0.0060 90,000.00 540.00
4 Mandor L04 OH 0.0025 100,000.00 250.00
JUMLAH HARGA TENAGA 6,805.00
B BAHAN
1 Cat Waterprofing (dasar) kg 0.1700 49,230.00 8,369.10
2 Cat Waterprofing (penutup) kg 0.2600 49,230.00 12,799.80
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA BAHAN 21,168.90
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C PERALATAN
JUMLAH HARGA PERALATAN -

D Jumlah (A+B+C) 27,973.90


E Overhead dan Profit % 10.0000 27,973.90 2,797.39
F Harga Satuan Pekerjaan (D+E) 30,771.29
DAFTAR HARGA SATUAN DASAR BAHAN DAN PERALATAN

Harga Satuan
No. Uraian Bahan, dan Peralatan Satuan Keterangan
Dasar ( Rp )
A Bahan
1 Batu Kali (utuh) M³ 210,000.00
2 Batu pecah 5/7 M³ 285,000.00
3 Batu pecah 2/3 M³ 285,000.00
4 Batu Pecah 1/1 M³ 295,000.00
5 Batu tempel m2 150,000.00
MATERIAL ALAM

6 Split (1350 kg/m3) Kg 295,000.00


7 Kerikil Timbun / Sirtu M³ 110,000.00
8 Kerikil Beton M³ 190,000.00
9 Pasir Urug M³ 210,000.00
10 Pasir Pasang M³ 315,000.00
11 Pasir Beton M³ 375,000.00
12 Beton Redymix K300 M³ 750,000.00
13 Tanah Urug M³ 215,000.00
Beton Redymix K225 M³ 715,000.00
1 Semen Portland kg 1,700.00
Semen Portland 40 kg zak 56,000.00
2 Semen Putih Kg 1,600.00
SEMEN

3 Semen Warna Kg 8,500.00


Semen grouting @25 kg zak 76,000.00
4 Tiang Pancang 25/25 cm m1 203,500.00
6 Beton Redymix K250 M³ 730,000.00
7 Beton Redymix K125 M³ 700,000.00
Mortar prime MU-380 kg 1,875.00
Prime Mortar MU-200 kg 3,950.00

1 Batu Bata Bh 800.00


2 Batako Bh 4,000.00
3 Batu bata ringan Bh 8,600.00
DINDING

4 Batu Terawang 40x40x8 Bh 25,000.00


5 Glass Block Bh 20,000.00
6 Hallow Brick / Batako bh 2,900.00
7 Dinding Partisi Gypsum Board 2 Layer t = 9 mm m2 82,500.00
8 Frame Metul Stud & Metal Runner m2 60,000.00

1 Kayu Kelas II M³ 3,000,000.00


2 Papan Kelas II M³ 3,300,000.00
3 Kayu Bekisting Kls IV M³ 2,200,000.00
4 Papan Bekisting Kls IV M³ 2,200,000.00
KAYU

5 Kayu Pancang 5/7, kelas III, panjang 4 m Batang 17,500.00


6 Kayu Panjang Bulat, Ø 5 - 15 cm, panjang 4 m Batang 17,500.00
7 Kayu untuk perancah Kayu kelas III M³ 1,850,000.00
8 Dolken D. 8 cm - 4 m btg 17,500.00

1 Triplex, Tebal 3 mm Lbr 43,500.00


2 Triplex tebal 6 mm Lbr 52,500.00
PLYWOOD

3 Plywood 4 mm Lbr 67,500.00


4 Plywood 9 mm Lbr 100,000.00
5 Teakwood tebal 4 mm Lbr 140,550.00
Harga Satuan
No. Uraian Bahan, dan Peralatan Satuan Keterangan
Dasar ( Rp )
1 Kawat Beton Kg 16,500.00
2 Besi Beton Ulir Kg 9,700.00
3 Besi Beton U 24 (POLOS) Kg 9,500.00
4 Baja Siku L.30.30.3 p=6 m kg 8,200.00
5 Besi Baja Profile Kg 9,500.00
6 Besi Strip (plat gepeng) t= 5 mm kg 10,500.00
7 Kawat besi Beugel (dia.6 mm) btg 22,000.00
BESI , BAJA , BAHAN METAL

8 Kawat besi Got (dia.8 mm) btg 25,000.00


9 Kawat Galvanis dia. 4 mm kg 13,000.00
10 Kawat duri kg 17,000.00
11 Plat Begol Kuda - kuda Kg 20,000.00
12 Besi hollow 40 x 40 x 4 mm x 6 m M1 14,000.00
13 Besi hollow 50 x 50 x 2.3 mm x 6 m M1 18,000.00
14 Pipa Baja Black Steel Pipe kg 9,500.00
15 Pipa Black Steell dia. 2 1/2" Btg 313,300.00
16 Pipa Black Steell dia. 2" Btg 227,200.00
17 Pipa Black Steell dia. 1 1/2" Btg 182,200.00
18 Baja Gording Lips Channel M1 37,000.00
19 Wire Mesh M5 (2.1 x 5.4 m) lbr 9,700.00
20 Kuku macan buah 3,800.00
Elektroda kg 65,000.00
Besi Baja UNP kg 8,500.00
Besi Baja Canal kg 8,000.00
Besi Baja WF kg 9,300.00
1 Paku Biasa Kg 16,500.00
2 Paku seng Kg 16,000.00
PAKU, MUR, BAUT, AGKUR BOLT

3 Paku Triplex Kg 16,000.00


4 Paku skrup Kg 22,000.00
5 Baut SDS Bh 150.00
6 Dynabolt M8 Bh 1,650.00
7 Baut + Mur dia.12 mm, panjang 25 cm Set 12,500.00
8 Baut + Mur dia.12 mm, panjang 12 cm Set 6,500.00
9 Paku Skrup 10 cm Kg 25,000.00
10 Form Tie Set 12,000.00
11 Angkur Kolom STD Ø22mm Bh 45,000.00
12 Baut A325 Ø19 Bh 1,200.00
13 Baut A325 Ø16 Bh 950.00

1 Buis Beton dm. 100 m'/buah 135,000.00


2 Buis Beton dm. 80 m'/buah 90,000.00
3 Buis Beton dm. 60 m'/buah 75,000.00
4 Buis Beton dm. 40 m'/buah 85,000.00
BUIS BETON / SALURAN

5 Buis Beton dm. 30 m'/buah 42,500.00


6 Buis Beton dm. 20 m'/buah 37,000.00
7 Buis Beton dm. 15 m'/buah 21,000.00
8 Buis Beton dm. 100 (tulangan) m'/buah 300,000.00
9 Buis Beton dm. 80 (tulangan) m'/buah 240,000.00
10 Buis Beton dm. 60 (tulangan) m'/buah 200,000.00
11 Buis Beton dm. 40 (tulangan) m'/buah 190,000.00
12 Buis Beton dm. 30 (tulangan) m'/buah 150,000.00
13 Buis Beton dm. 20 (tulangan) m'/buah 120,000.00
Harga Satuan
No. Uraian Bahan, dan Peralatan Satuan Keterangan
Dasar ( Rp )
1 Seng Plat (BJLS 20) Lbr 30,000.00
2 Seng Plat (BJLS 30) Lbr 37,000.00
3 Seng warna Lbr 50,400.00
4 Seng Biasa Lbr 37,900.00
5 Perabung Zincalume Warna Lbr 115,000.00
6 Flashing Atap Zincalume M' 75,000.00
7 Spandek Warna 0,4mm M2 115,000.00
8 Perabung Spandek Warna M1 98,000.00
9 Genteng Metal , uk. 1,2 x 0,4 x 0,3 lbr
ATAP

51,150.00
10 Eternit Asbes 4 mm, uk. 1,00 x 1,00 Lbr 14,000.00
11 Gypsum 9mm Lbr 75,000.00
12 Panel GRC 9mm X 1,2 X 2,4 M2 50,000.00
13 List Plafond Biasa 1 X 4 M' 12,000.00
14 List Profil 3 X 3 M' 15,000.00
15 Metal Furing M1 70,000.00
16 Bubungan genteng metal M1 65,000.00
17 Rangka Atap Baja Ringan M2 110,000.00

1 List Kaca M' 1,400.00


2 Kaca Bening, Tebal 3 mm M' 50,000.00
3 Kaca Panasab, Tebal 5 mm m² 110,000.00
4 List profil lambriseering m' 6,400.00
5 Kaca polos tebal 6 mm m2 75,000.00
KACA

6 Kaca polos tebal 3 mm m2 45,000.00


7 Kaca polos tebal 5 mm m2 65,000.00
8 Kaca Raiben tebal 6 mm m2 55,700.00
9 Kaca Raiben tebal 5 mm m2 77,810.00
10 Naco Polos (tambah rangka) Uk. 150 xcm m2 111,480.00

1 Profile Alumunium 4" m1 60,000.00


2 Alluminium Strip m1 15,000.00
3 Sealant Tube 30,000.00
4 Profil Panil M' 8,000.00
5 Panel Almunium Btg 85,000.00
6 Kunci SES 208 bh 135,000.00
7 Kunci meja bh 25,000.00
8 Engsel 4" (kuningan) / Nilon - SES bh 40,000.00
PINTU, JENDELA & ACCESSORIES

9 Engsel 3" (kuningan) / Nilon - SES bh 35,000.00


10 Engsel meja (biasa) bh 25,000.00
11 Grendel 3" (kuningan) / antik 2 Type 204 bh 30,000.00
12 Tangan-tangan meja (antik) bh 40,000.00
13 Kunci Tanam KW I Set 80,000.00
14 Kunci Pintu Ganda KW I Set 150,000.00
15 Engsel Pintu Nilon ( Lokal ) Set 15,000.00
16 Engsel Jendela Nilon ( Lokal ) Bh 13,000.00
17 Engsel Jendela Peluru Bh 20,000.00
18 Hak Angin kuningan (antik) 6" Bh 25,000.00
19 Tarikan Pintu Ganda Set 20,000.00
20 Tarikan Jendela Bh 17,000.00
21 Gerendel Pintu Bh 15,000.00
22 Gerendel Jendela Bh 12,000.00
23 Door Closer Bh 175,000.00
24 Door Holder Bh 150,000.00
Harga Satuan
No. Uraian Bahan, dan Peralatan Satuan Keterangan
Dasar ( Rp )
1 Ubin PC 20 x 20 buah 1,900.00
2 Ubin PC 30 x 30 buah 3,300.00
3 Ubin warna 20 x 20 (setara Asia Tile) buah 1,946.70
4 Ubin teraso 30 x 30 buah 5,800.00
5 Ubin warna 30 x 30 (setara Asia Tile) buah 36,000.00
KERMAIK (MATERIAL FINISHING LANTAI)

6 Jubin granit 30 x 30 (setara granito) buah 21,309.44


7 Jubin granit 40 x 40 buah 46,309.50
8 Jubin keramik 20 x 20 (setara Masterina) buah 42,000.00
9 Jubin keramik 30 x 30 (setara Masterina) buah 36,000.00
10 Jubin Keramik, dinding 10 x 20 (setara Asia Tile) buah 1,400.00
11 Stop Norsing Keramik Uk. P - 10 cm bh 13,000.00
12 Keramik Dinding KWI, Ukr 20 x 25 M² 37,500.00
13 Keramik Lantai KM / WC KW I, Ukr20 x 20 ( Motif) M² 34,000.00
14 Keramik Lantai KW I, Ukr 40 x 40 M² 40,000.00
15 Granit Lantai KW I, Ukr 60 x 60 Nero Granito M² 275,000.00
16 Parquet Solit M² 470,000.00
17 Granit Lantai KW I, Ukr 60 x 60 M² 230,000.00
18 Keramik Lantai 60 x 60 Roman M2 140,000.00
19 Keramik Lantai 20 x 20 m2 46,200.00
20 Keramik Lantai 30 x 30 m2 39,600.00
21 Plint Keramik dinding 10x30 cm ( KW I ) bh 15,000.00
Border Keramik 10x20 cm m' 30,000.00
1 Paving block tebal 6 cm type I K.225/35 Bh 900.00
2 Paving block tebal 8 cm type I K.225/35 Bh 1,200.00
3 Paving block tebal 6 cm K.225 tipe balok Bh 1,125.00
PAVING BLOK

4 Paving block tebal 8 cm K.225 tipe balok Bh 1,375.00


5 Paving block tebal 8 cm K.350 tipe balok Bh 1,625.00
6 Paving block tebal 10 cm K.350 tipe balok Bh 1,875.00
7 Paving block tebal 8 cm K.450 type balok Bh 1,875.00
8 Kanstein K 225/35 Bh 22,000.00
9 Kanstein K 225/35 Bh -

1 Lem Kayu Kg 27,000.00


2 Residu Kg 5,000.00
3 Cat dasar kg 6,000.00
4 Cat impra struktur kg 74,000.00
5 Cat Minyak / cat warna (setara planton) Kg 34,000.00
6 Cat air/cat tembok (setara matex) Kg 12,000.00
7 Cat air/cat tembok (setara Catylac) Kg 14,000.00
8 Cat Penutup Interior (dulux) Kg 14,000.00
9 Cat Penutup Eksrerior (weathershied) Kg 50,000.00
10 Pelitur Ltr -
11 Pelitur Jadi Ltr -
12 Dempul Kayu Kg 13,000.00
13 Menie Kayu Kg 16,000.00
CAT

14 Menie Besi Kg 15,000.00


15 Sabun Kg 10,000.00
16 Minyak Cat Ltr 9,000.00

1 Thiner Ltr 12,500.00


2 Ampelas Lbr 2,500.00
3 Kuas Bh 8,000.00
4 Alkali Kg 20,000.00
5 Lem Rakol kg 20,000.00
6 Tepung Sengkuit kg 9,000.00
7 Plammer kayu kg 16,000.00
8 Plamer tembok Kg 15,000.00
Harga Satuan
No. Uraian Bahan, dan Peralatan Satuan Keterangan
Dasar ( Rp )
1 Klosed Duduk setara KIA Bh 1,175,000.00
2 Klosed Jongkok porselen setara KIA Bh 180,000.00
3 Klosed Jongkok teraso setara Total/vetro Bh 145,000.00
4 Urinoir Lengkap setara TOTO Bh 1,750,000.00
5 Wastafel Lengkap setara KIA type SUSAN (1263. F.1.10) Bh 850,000.00
SANITARY

6 Bak Fiber Uk.0,65x0,65 Unit 280,000.00


7 Kran air dia. 1/2" merk San Ei Bh 110,000.00
8 Kran air dia. 3/4" merk Stenliss Bh
9 Seal Tape Bh 2,000.00
10 Floor Drain lokal Bh 80,000.00
11 Shower dobel kran Bh 165,000.00

1 Pipa PVC AW dm.1/2" M' 6,699.54


2 Pipa PVC AW dm.3/4" M' 9,525.05
3 Pipa PVC AW dm.1" M' 18,000.00
4 Pipa PVC AW 1 1/4" M' 25,000.00
5 Pipa PVC AW dm.1 1/2" M' 34,000.00
6 Pipa PVC AW dm.2" M' 40,619.28
7 Pipa PVC AW dm. 2 1/2" M' 57,276.14
PLUMBING

8 Pipa PVC AW dm.3" M' 112,120.00


9 Pipa PVC AW dm.4" M1 120,087.85
10 Pipa PVC AW dm. 5" M1 63,500.00
11 Pipa PVC AW dm.6" M1 262,693.11
12 Pipa PVC AW dm. 8" M1 152,080.00
13 Pipa PVC AW dm. 10" M1 235,180.00
14 Pipa PVC AW dm. 12" M1 331,600.00
15 Water proofing (membrane) t= 3 mm m2 65,000.00
16 Water proofing (liquit/coating) m2 30,000.00
17 Water proofing (bitumen) m2 50,000.00

SDP Floor standing, tebal pelat 2,0 mm, cat bakar


1 - 1 x MCCB 630 A, 4 P, 50 kA 3,700,000.00
2 micrologic 2.0 electronic trip unit
3 - 1 x MCCB 400 A, 3 P, 45 kA 3,650,000.00
4 micrologic 2.0 electronic trip unit
ELEKTRIKAL

5 - 1 x MCCB 100 A, 3 P, 36 kA electronic trip 1,250,000.00


6 - 1 x MCCB 63 A, 3P, 25 kA 875,000.00
7 - 5 x MCCB 40 A, 3P, 25 kA 4,250,000.00
8 - 3 x CT 630/5A 750,000.00
9 - 3 x A-meter 0 - 630 A 750,000.00
10 - 1 x V-meter 0 - 500 V + VSS 7 posisi 300,000.00
11 - 3 x fuse 2 A + fuse holder 75,000.00
12 - 3 x pilot lamp 75,000.00
13 - 1 lot busbar 1000 A full neutral, 5 bus 7,500,000.00
14 - 1 lot internal wiring + aksesoris 1,500,000.00
15 - 1 lot panel 180 x 90 x 50 cm, setara industira panel 5,000,000.00
16 - 1 lot pentanahan 1,500,000.00

LP-D (Panel Penerangan & Stop Kontak Lt-I & II )


Wall mounted, tebal pelat 2,0 mm, cat bakar
1 - 1 x MCCB 32 A, 3 P, 25 kA 450,000.00
2 - 38 x MCB 6 A, 1 P, 10 kA 5,700,000.00
3 - 3 x fuse 2 A + fuse holder 75,000.00
4 - 3 x pilot lamp 75,000.00
5 - 1 lot busbar 60 A full neutral, 5 bus 7,500,000.00
6 - 1 lot control wiring + aksesori 1,500,000.00
7 - 1 lot panel 40 x 60 x 25 cm, setara Industira Panel 2,500,000.00
8 - 1 lot pentanahan 1,500,000.00
Harga Satuan
No. Uraian Bahan, dan Peralatan Satuan Keterangan
Dasar ( Rp )
LP-S (Panel Penerangan & Stop Kontak Lt- I & II)
Wall mounted, tebal pelat 2,0 mm, cat bakar
1 - 1 x MCCB 32 A, 3 P, 25 kA 450,000.00
2 - 29 x MCB 6 A, 1 P, 10 kA 4,350,000.00
3 - 3 x fuse 2 A + fuse holder 75,000.00
4 - 3 x pilot lamp 75,000.00
5 - 1 lot busbar 60 A full neutral, 5 bus 7,500,000.00
6 - 1 lot control wiring + aksesori 1,500,000.00
7 - 1 lot panel 40 x 60 x 25 cm, setara Industira Panel 2,500,000.00
8 - 1 lot pentanahan 1,500,000.00

LP-OD (Panel Penerangan Luar)


Wall mounted, tebal pelat 2,0 mm, cat bakar
1 - 2 x MCCB 50 A, 3 P, 25 kA 2,050,000.00
2 - 1 x MCB 25 A, 3 P, 10 kA 506,000.00
3 - 4 x MCB 16 A, 3 P, 10 kA 1,640,000.00
4 - 3 x MCB 10 A, 1 P, 10 kA 450,000.00
5 - 1 x Contactor 50 A + Relay, 3 P. 2,023,000.00
6 - 3 x fuse 2 A + fuse holder 75,000.00
7 - 3 x pilot lamp 75,000.00
8 - 1 lot busbar 80 A full neutral, 5 bus 7,500,000.00
9 - 1 lot control wiring + aksesori 1,500,000.00
10 - 1 lot panel 80 x 60 x 25 cm, setara Industira Panel 3,500,000.00
11 - 1 lot pentanahan 1,500,000.00

PP-FCU (Panel Daya FCU Lt-I & II )


Wall mounted, tebal pelat 2,0 mm, cat bakar
1 - 1 x MCCB 80 A, 3 P, 25 kA electronic trip unit 1,022,000.00
2 -18 x MCB 10 A, 1 P, 10 kA 2,700,000.00
3 - 10 x MCB 6 A, 1 P, 10 kA 1,500,000.00
4 - 3 x CT 100/5A 369,000.00
5 - 3 x fuse 2 A + fuse holder 75,000.00
6 - 3 x A-meter 0 - 100 A 750,000.00
7 - 3 x pilot lamp 75,000.00
8 - 1 lot busbar 150 A full neutral, 5 bus 7,500,000.00
9 - 1 lot control wiring + aksesori 1,500,000.00
10 - 1 lot panel 50 x 70 x 25 cm, setara Industira Panel 3,000,000.00
11 - 1 lot pentanahan 1,500,000.00

1 KABEL NYFGBY 4 x 300 sqmm 1,589,500.00


2 KABEL NYY 4 x 6 sqmm 45,650.00
3 KABEL NYY 4 x 25 sqmm 150,000.00

1 Lampu TL 2 x 36 W (RMO) - setara ARTOLITE. 493,000.00


2 Down Light PLE-T 23 W - setara ARTOLITE. 350,000.00
3 Lampu SL 23 Watt + cap 1,440,000.00
4 Lampu Baret TLC 20 W - setara ARTOLITE. 335,000.00
5 Instalasi titik cahaya dalam gedung 120,000.00
6 Instalasi stop kontak 1 fasa, 200 VA, 220 V dinding 95,000.00
7 Istalasi stop kotak daya u / Air Conditioner 60,000.00
8 Stop kontak 1 phasa, 10 A, 220 V 25,000.00
9 Stop kontak AC phasa, 15 A, 220 V 30,000.00
10 Grid Switch 12 gang 25,000.00
11 Saklar Ganda 37,000.00
12 Saklar Tunggal 25,000.00

13 Tiang Lampu Antik Full Cast Iron Besi Tempa (4 bh) 4,552,500.00
14 Lampu 2 x ML 100 W, H = 4 m cabang 2 975,000.00
15 Kabel NYY 2 x 2.5 sqmm 10,800.00
16 MCB 2A, 6 KA. 377,000.00
Harga Satuan
No. Uraian Bahan, dan Peralatan Satuan Keterangan
Dasar ( Rp )
17 Lampu sorot HPI-T 1000 W Philips ex. Holland, (AMEG E40) 6,500,000.00

18 Air terminal Radius 150 m 8,500,000.00


19 BCC 50 sqmm 65,000.00
20 Pentanahan lengkap dengan bak kontrol 1,500,000.00
21 Sparing Gip med class dia 1" 15,000.00
22 Material bantu (klem, fisher, sekrup dll.) 750,000.00

1 Elektroda / kawat las RB 2,6 mm Kg 25,900.00


2 Plastik Hitam M2 10,700.00
MATERIAL LAIN-LAINnya

3 Air ltr 100.00


4 Ijuk Saringan Kg 10,810.00
5 Alang-alang ikat 7,900.00
6 Soda api kg 28,700.00
7 Minyak Bekisting Ltr 17,000.00
8 Syntetic Rubber m2 260,700.00

1 Solar Ltr 8,500.00


2 Bensin ltr 4,500.00
BBM

3 Minyak Pelumas ltr 28,000.00

B Peralatan
1 Excavator PC 200 Jam 170,000.00 Sewa
2 Hammer / Breaker Jam 400,000.00 Sewa
3 Compresor + Jack Hammer Jam 192,500.00 Sewa
4 Pile Hammer Jam 300,000.00 Sewa
5 Molen Jam 150,000.00 Sewa / Milik
6 Stamper Jam 75,000.00 Sewa / Milik
7 Bor Jam 15,000.00 Sewa / Milik
PERALATAN

8 Bor Hilty, Hammer Drill Jam 15,000.00 Sewa / Milik


9 Mesin Las Jam 17,000.00 Sewa / Milik
10 Concrete Pump Jam 250,000.00 Sewa
11 Mesin Bor Pile Jam 620,000.00 Sewa
12 Crane 25 Ton Hari 250,000.00 Sewa
13 Dump Truck Jam 312,500.00 Sewa
14 Hidrolic Hammer HSDP Jam 484,000.00 Sewa
15 Crane 25 Ton (termasuk operator dan BBM) Jam 390,000.00 Sewa
16 Crane 15 Ton (termasuk operator dan BBM) Jam 290,000.00 Sewa
17 Sewa concrete vibrator engine (termasuk BBM) Jam 20,000.00 Sewa / Milik
Water Tanker jam 120,000.00
Vibro Roller jam 220,000.00
1 Wire Mesh M6 lbr 312,000.00
PDA TES TTK 6,000,000.00 PDA
dudukan railing tangga ttk 35,000.00 DUDUKAN
PROFIL JENDELA 15,000.00
d 100 buah 1,057,416.00
d 20 buah 218,634.80 G20
d 40 buah 325,000.00 G40
d 32 buah 150,000.00 G32
d 50 buah 410,268.00 G50
d 65 buah 695,000.00 G65
d 25 buah 125,000.00
ceck valve 150 buah 670,000.00
ceck valve 100 buah 1,076,064.00
ceck valve 50 buah 401,564.00
strainer 150 buah 1,921,200.00
strainer 50 buah 295,968.75
flexibel joint 150 buah 826,312.50
Harga Satuan
No. Uraian Bahan, dan Peralatan Satuan Keterangan
Dasar ( Rp )
flexibel joint 50 buah 202,387.50
foot valve 150 buah 1,270,695.60
foot valve 50 buah 589,560.00
presaure gauge lot 55,075.00

Meter Air c/w BV dia. 20 buah 200,000.00


CO, dia. 150 buah 198,000.00 CO150
CO, dia. 100 buah 75,000.00 CO100
CO, dia. 65 buah 45,000.00 CO65
CO, dia. 50 buah 30,000.00
ROOF DRAIN D 80 buah 100,000.00
Portable Grease Trap + assesories buah 60,000.00

PIPA SCH 40 dia. 100 mm (Pipa Riser ) M 488,054.75


PIPA SCH 40 dia. 80 mm M 345,511.83
PIPA SCH 40 dia. 65 mm M 317,235.59
Indoor Hydrant Box (IHB) 750x1200x180 SET 1,769,650.00
Type CO2 Class B & C 2,3 - 2,5 kg Seamless, c/w support BH 960,000.00
Type Class ABC 2,3 - 2,5 kg Seamless, c/w support BH 450,000.00
Type CO2 Class 5 kg Seamless, c/w support BH 1,890,000.00
NYY 4 x 6 mm2 + E-NYA 2.5 mm2 M 33,000.00
NYY 4 x 16 mm2 + E-NYA 10 mm2 M 98,820.00
NYM 3 x 2,5 mm2 M 16,000.00

GIP med dia. 20 M 25,000.00


GIP med dia. 25 M 41,700.00
GIP med dia. 32 M 55,000.00
GIP med dia. 40 M 59,000.00
GIP med dia. 50 M 75,000.00
GIP med dia. 65 M 120,000.00
GIP med dia. 100 ( pipa header ) M 250,000.00

Vent cup Dia. 50 bh 5,000.00


PIPA BSP SCH 40 dia. 200 mm M 1,380,000.00
PIPA SCH 40 dia. 150 mm M 855,897.60
PIPA SCH 40 dia. 100 mm (Pipa Riser ) M 488,054.75
PIPA SCH 40 dia. 80 mm M 345,511.83
PIPA SCH 40 dia. 65 mm M 317,235.59
PIPA SCH 40 dia. 50 mm M 180,000.00
Automatic Air Vent dia 25, c/w Pressure gate, gate valve bh 231,299.96
Savety valve dia 100 bh 920,000.00
Flow Meter (FM) dia 100 bh 865,000.00
Pressure Switch bh 340,000.00
Panel KWH PLN UNIT 3,426,387.50
Panel PUTR UNIT 42,925,000.00
Panel KWH / lantai (Lt. 2 s/d 5) UNIT 9,939,000.00
Panel KWH (Lt. 1) UNIT 4,395,000.00
Panel Unit Typical UNIT 83,000.00
Panel Kebakaran UNIT 2,662,500.00
Panel Pompa Air Bersih UNIT 5,025,000.00
TAMBAHAN

Grounding System Kelistrikan UNIT 1,164,050.00


Tee W200 x W200 x W200 x H100 bh 140,000.00
Kabel Tray W200 x H100 m 140,000.00
Lampu baret isi TL Bulat-32 watt buah 68,000.00
Lampu PL 13 Watt , Fitting E-27 buah 90,000.00
Lampu baret isi TL Bulat-32 watt c/w battery charger buah 900,000.00
TL 1 x 36 W, TL Balk Type buah 93,457.25
Lampu Taman/ Penerangan Luar ( t = 2,5 m ) SL 26 watt buah 626,060.37
Harga Satuan
No. Uraian Bahan, dan Peralatan Satuan Keterangan
Dasar ( Rp )
Lampu Taman Koridor ( t = 1,5 m ) SL 26 watt buah 555,832.32
NYFGBY 3 x 2,5 mm2 untuk Lampu Taman M 29,040.29
NYY 4 x 4 mm2 ke LP-1 M 35,223.60
Grounding Box 40x40x40 cm BH 500,000.00
NYA 50 mm2 M 50,000.00
FRC 4 x 4 mm2 + NYA 4 mm2 M 480,000.00
FRC 3 x 2.5 mm2 M 225,000.00
Antena UHF BH 442,800.00
Antena VHF BH 442,800.00
MA (Master Amplifier)/Mixer BH 502,500.00
Coaxial 7C/2V, dari Antena ke Mixer BH 3,760.40
Termination & supporting material BH 350,000.00
Splitter 6 ports BH 22,300.00
TB-Splitter-TV/lt.1 BH 250,000.00
OUTLET TV BH 28,435.00
Coaxial Cable 5C2V M 3,922.80
TANKI AIR 4M3 BUAH 5,000,000.00
Septic Tank Bio Media (Air Kotor) unit 71,500,000.00
Diesel Fire Pump (DFP) unit 196,200,000.00
Jockey Pump (JP) unit 12,000,000.00
Out Hydrant Box unit 1,871,732.50
Siamese Connection (SMC) unit 1,993,275.00
Hydrant Pillar (HP) unit 2,087,795.00
LIFT PUMP unit 17,500,000.00
Tangga ke rooftank unit 250,000.00
tutup manhole unit 150,000.00

p1 unit 1,050,000.00 P1
p1a unit 945,000.00 P1A
P2 unit 220,000.00 P2
P2A unit 550,000.00 P2A
P4 unit 2,000,000.00 P4
P5 unit 1,260,000.00 P5
PP unit 3,033,000.00 PP
PPA unit 3,033,000.00 PPA
J1 unit 920,000.00 J1
J2 unit 950,000.00 J2
J3 unit 920,000.00 J3
JL unit 300,000.00 JL
BV unit 250,000.00 BV
PS2 unit 1,000,000.00 PS2
PJ1 unit 247,000.00 PJ1
PS3 unit 400,000.00 PS3
PJ2 unit 1,150,000.00 PJ2
PJ2A unit 1,020,000.00 PJ2A
PJ3 unit 1,865,000.00 PJ3
J5 unit 250,000.00 J5
- Type 1 ( panjang 4.40 cm ) unit 904,000.00
- Type 2 ( panjang 4.33 cm ) unit 865,000.00
- Type 3 ( panjang 3.70 cm ) unit 741,000.00
- Type 4 ( panjang 2.60 cm ) unit 405,000.00

Hand Railling km/wc unit 254,000.00 HRAILING


FLASHING M 63,000.00 FLASHING
Grounding Rod GIP 1' ( untuk R lebih kecil dari 3 ohm ) bh -
Connector Test Box set -
Harga Satuan
No. Uraian Bahan, dan Peralatan Satuan Keterangan
Dasar ( Rp )
Termination R.Supporting Material lot -
Kabel BC 50 mm2 m -
Air Terminal Electrostatic Lightning Protection System, Radius +/- unit -
UPAH DAN HARGA MATERIAL

HARGA SATUAN
NO URAIAN SATUAN
(Rp.)

UPAH KERJA
1 Pekerja OH 85,000.00
2 Tukang Kayu OH 95,000.00
3 Tukang Cat OH 95,000.00
4 Tukang Batu OH 95,000.00
5 Tukang Besi OH 95,000.00
6 Kepala Tukang OH 100,000.00
7 Mandor OH 120,000.00

MATERIAL DASAR
1 Sirtu m3 92,990.00
2 Pasir Urug m3 240,133.00
3 Pasir Pasang/cor (jawa) m3 229,740.00
bobot isi pasir kg/m3 164.10
4 Batu Pecah Mesin/Stenslah 1/2 m3 345,704.00
bobot isi kerikil kg/m3 256.08
5 Portland Cement (PC) @ 40 kg zak 59,076.00
dalam satuan kg 1,476.90
6 Besi Beton Polos kg 7,658.00
7 Besi Beton Ulir kg 7,876.80
8 Kawat Beton/ Bendrat kg 13,675.00
9 Paku kayu 2-5" kg 16,410.00
10 Air liter 100.00
MATERIAL CAT
1 Minyak bekisting ltr 4,923.00
2 Solar ltr 11,000.00
3 Minyak Pelumas ltr 43,760.00
4 Kuas bh 2,844.40
5 Pengencer kg 11,049.40
6 Amplas lbr 6,181.10
7 Cat Meni kg 37,196.00
8 Waterstop lebar 230 - 320 mm m1 109,400.00
9 Waterproofing kg 49,230.00
MATERIAL TRIPLEK
1 Multipleks tebal 9 mm lbr 115,000.00
2 Multipleks 12 mm lbr 150,000.00
HARGA SATUAN
NO URAIAN SATUAN
(Rp.)
MATERIAL BESI DAN ALLUMINIUM
1 Kawat Las kg 26,529.50
2 Besi Profil kg 18,051.00
3 Besi Baja WF kg 14,057.90
4 Besi Gording Kanal C kg 12,690.40
5 Jarum Keras bh 25,927.80
6 Baut bh 5,360.60
7 Baut HTB bh 13,292.10
8 Angker bh 18,598.00
9 Ikatan Besi Sling Ø 22 mm m1 158,465.90
MATERIAL KAYU
1 Kayu Papan (bekisting 2/20 ) m3 3,300,000.00
2 Kayu Usuk Meranti (5/7) m3 3,300,000.00
3 Kayu Kamper (balok 6/12) m3 8,205,000.00
4 Kayu Kamper (usuk 4/6 ) m3 8,205,000.00
5 Kayu Kamper (reng 3/5) m3 8,205,000.00
6 Kayu Kamper (papan) m3 8,205,000.00
7 Kayu Perancah batang 50,000.00
8 Penjaga Jarak Begesting / Specer buah 4,923.00
PERALATAN
1 Sewa Alat bantu Strous Pile Ø 60 cm jam 150,000.00
2 Sewa Alat bantu Strous Pile Ø 40 cm jam 82,050.00

Anda mungkin juga menyukai