I PEKERJAAN PENDAHULUAN
1 Pek. Pengukuran dan Pemasangan Bowplank 54.00 M1 53,000.00 2,862,000.00 1.48 54.00 1.48 - - 54.00 1.48 100.00 2,862,000.00
II PEKERJAAN PONDASI
1 Pek. Galian Tanah Pondasi 14.44 M3 50,000.00 722,000.00 0.37 14.44 0.37 - - 14.44 0.37 100.00 722,000.00
2 Pek. Cerucuk Kayu Dia. 10-15 cm 111.00 Btg 50,000.00 5,550,000.00 2.87 111.00 2.87 - - 111.00 2.87 100.00 5,550,000.00
3 Pek. Urugan Pasir Di Bawah Pondasi 1.47 M3 120,000.00 176,400.00 0.09 1.47 0.09 - - 1.47 0.09 100.00 176,400.00
4 Pek. Cor Lantai Kerja Beton K-100 1.47 M3 680,000.00 999,600.00 0.52 1.47 0.52 - - 1.47 0.52 100.00 999,600.00
6 Pek. Pondasi Lajur Pas. 1 Bata 1 : 2 21.74 M2 150,000.00 3,261,000.00 1.69 21.74 1.69 - - 21.74 1.69 100.00 3,261,000.00
7 Pek. Urugan Tanah Bekas Galian 8.34 M3 40,000.00 333,600.00 0.17 8.34 0.17 - - 8.34 0.17 100.00 333,600.00
IX PEKERJAAN LANTAI
1 Pek. Urugan Tanah Bawah Lantai 20.92 M3 100,000.00 2,092,000.00 1.08 20.92 1.08 - - 20.92 1.08 100.00 2,092,000.00
2 Pek. Urugan Pasir Bawah Lantai 3.53 M3 120,000.00 423,600.00 0.22 - - 3.53 0.22 3.53 0.22 100.00 423,600.00
3 Pek. Cor Lantai Beton K-100 (Dihaluskan) 3.53 M3 680,000.00 2,400,400.00 1.24 - - 3.53 1.24 3.53 1.24 100.00 2,400,400.00
XI PEKERJAAN PENGECATAN
1 Pek. Cat Dinding dan Kolom, Dengan Cat Air 347.71 M2 36,000.00 12,517,560.00 6.48 - - 347.71 6.48 347.71 6.48 100.00 12,517,560.00
2 Pek. Cat Minyak Kozen Kayu 23.34 M2 38,000.00 886,920.00 0.46 - - 23.34 0.46 23.34 0.46 100.00 886,920.00
3 Pek. Cat Minyak Pintu Panil Kayu 26.02 M2 38,000.00 988,760.00 0.51 - - 26.02 0.51 26.02 0.51 100.00 988,760.00
4 Pek. Cat Minyak Ram Jendela 6.92 M2 38,000.00 262,960.00 0.14 - - 6.92 0.14 6.92 0.14 100.00 262,960.00
5 Pek. Cat Minyak Papan Jalusi 20.02 M2 38,000.00 760,760.00 0.39 - - 20.02 0.39 20.02 0.39 100.00 760,760.00
6 Pek. Cat Lispank GRC, Dengan Cat Air 20.30 M2 36,000.00 730,800.00 0.38 - - 20.30 0.38 20.30 0.38 100.00 730,800.00
7 Pek. Cat Minyak Singap Atap 4.09 M2 38,000.00 155,420.00 0.08 - - 4.09 0.08 4.09 0.08 100.00 155,420.00