PENYEDIA JASA KONSTRUKSI

PEKERJAAN : REHABILITASI DAN RENOVASI PRASARANA MADRASAH PROVINSI PAPUA BARAT 1 PENYEDIA JASA KONSULTAN MANAJEMEN KONSTRUKSI
NAMA SEKOLAH : SMTKN PELITA SEMBAB MANOKWARI
PENYEDIA JASA KONSTRUKSI : PT. KEMER TIRI EMAS
NOMOR KONTRAK : HK.02.03/RR.PRAS.MADRASAH.1/PPK-PS/PPP-PB/03
TANGGAL KONTRAK : 06 JUNI 2022
PENYEDIA JASA KONSULTAN MK : CV. SIARA KONSULTAN - PT. INDO PAPUA CONSUTANT, KSO.
TAHUN ANGGARAN : 2022
REKAPITULASI KEMAJUAN PEKERJAAN PERIODE MINGGU KE-4
Masa Kontrak : 205 Hari Kalender
Waktu Realisasi : 28 Hari Kalender ( 27 Juni s/d 03 Juli 2022 )
Sisa Waktu : 177 Hari Kalender
KONTRAK AWAL PROGRES MINGGUAN
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN JUMLAH BOBOT
BOBOT BOBOT BOBOT TERHADAP ITEM PEKERJAAN
HARGA (%) (%)
(%) ( %) (%)
a b c d e f g=e+f h=g/d(%)
A RENOVASI GEDUNG A (3 RKB) 882,127,269.13 27.61 - 0.02 0.02 0.06%
I PEKERJAAN PERSIAPAN 13,799,233.00 0.43 - 0.02 0.02 3.62%
II PEKERJAAN TANAH 36,534,649.30 1.14 - - - 0.00%
III PEKERJAAN PONDASI 71,470,086.92 2.24 - - - 0.00%
IV PEKERJAAN BETON 136,566,264.99 4.27 - - - 0.00%
V PEKERJAAN DINDING 149,547,570.05 4.68 - - - 0.00%
VI PEKERJAAN PINTU DAN JENDELA 48,378,652.50 1.51 - - - 0.00%
VII PEKERJAAN RANGKA ATAP 148,743,793.00 4.66 - - - 0.00%
VIII PEKERJAAN PLAFOND 73,094,536.42 2.29 - - - 0.00%
IX PEKERJAAN LANTAI / KERAMIK 130,837,767.25 4.10 - - - 0.00%
X PEKERJAAN INSTALASI LISTRIK 13,399,895.00 0.42 - - - 0.00%
XI PEKERJAAN PENGGANTUNG / PENGUNCI 16,238,100.00 0.51 - - - 0.00%
XII PEKERJAAN PENGECATAN 42,565,888.70 1.33 - - - 0.00%
XIII PEKERJAAN LAIN - LAIN 950,832.00 0.03 - - - 0.00%
B RENOVASI GEDUNG B (2 RKB) 584,841,132.80 18.31 - - - 0.00%
I PEKERJAAN PERSIAPAN 6,428,755.00 0.20 - - - 0.00%
II PEKERJAAN TANAH 25,275,130.76 0.79 - - - 0.00%
III PEKERJAAN PONDASI 47,458,035.09 1.49 - - - 0.00%
IV PEKERJAAN BETON 93,879,904.57 2.94 - - - 0.00%
V PEKERJAAN DINDING 101,003,546.80 3.16 - - - 0.00%
VI PEKERJAAN PINTU DAN JENDELA 32,635,949.60 1.02 - - - 0.00%
VII PEKERJAAN RANGKA ATAP 94,796,525.00 2.97 - - - 0.00%
VIII PEKERJAAN PLAFOND 50,769,324.68 1.59 - - - 0.00%
IX PEKERJAAN LANTAI / KERAMIK 86,987,725.30 2.72 - - - 0.00%
X PEKERJAAN INSTALASI LISTRIK 9,049,930.00 0.28 - - - 0.00%
XI PEKERJAAN PENGGANTUNG / PENGUNCI 6,026,000.00 0.19 - - - 0.00%
XII PEKERJAAN PENGECATAN 29,579,474.00 0.93 - - - 0.00%
XIII PEKERJAAN LAIN - LAIN 950,832.00 0.03 - - - 0.00%

Page 1 SMTKN PELITA SEMBAB MANOKWARI


KONTRAK AWAL PROGRES MINGGUAN
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN JUMLAH BOBOT
BOBOT BOBOT BOBOT TERHADAP ITEM PEKERJAAN
HARGA (%)
(%) ( %) (%) (%)
a b c d e f g=e+f h=g/d(%)
C RENOVASI GEDUNG C ( 1 RUANG GURU + 1 RKB) 586,476,824.00 18.36 - - - 0.00%
I PEKERJAAN PERSIAPAN 6,428,755.00 0.20 - - - 0.00%
II PEKERJAAN TANAH 25,275,130.76 0.79 - - - 0.00%
III PEKERJAAN PONDASI 49,093,726.29 1.54 - - - 0.00%
IV PEKERJAAN BETON 93,879,904.57 2.94 - - - 0.00%
V PEKERJAAN DINDING 101,003,546.80 3.16 - - - 0.00%
VI PEKERJAAN PINTU DAN JENDELA 32,635,949.60 1.02 - - - 0.00%
VII PEKERJAAN RANGKA ATAP 94,796,525.00 2.97 - - - 0.00%
VIII PEKERJAAN PLAFOND 50,769,324.68 1.59 - - - 0.00%
IX PEKERJAAN LANTAI / KERAMIK 86,987,725.30 2.72 - - - 0.00%
X PEKERJAAN INSTALASI LISTRIK 9,049,930.00 0.28 - - - 0.00%
XI PEKERJAAN PENGGANTUNG / PENGUNCI 6,026,000.00 0.19 - - - 0.00%
XII PEKERJAAN PENGECATAN 29,579,474.00 0.93 - - - 0.00%
XIII PEKERJAAN LAIN - LAIN 950,832.00 0.03 - - - 0.00%
D RENOVASI KM/WC 469,370,050.83 14.69 - 0.06 0.06 0.38%
I PEKERJAAN PERSIAPAN 3,552,813.00 0.11 - 0.06 0.06 50.00%
II PEKERJAAN TANAH 23,764,494.42 0.74 - - - 0.00%
III PEKERJAAN PONDASI 50,761,434.15 1.59 - - - 0.00%
IV PEKERJAAN BETON 102,990,719.52 3.22 - - - 0.00%
V PEKERJAAN DINDING 68,155,430.14 2.13 - - - 0.00%
VI PEKERJAAN PINTU DAN JENDELA 17,286,492.40 0.54 - - - 0.00%
VII PEKERJAAN RANGKA ATAP 32,463,740.00 1.02 - - - 0.00%
VIII PEKERJAAN PLAFOND 29,210,075.70 0.91 - - - 0.00%
IX PEKERJAAN LANTAI / KERAMIK 57,251,942.46 1.79 - - - 0.00%
X PEKERJAAN INSTALASI LISTRIK 5,652,415.00 0.18 - - - 0.00%
XI PEKERJAAN PENGGANTUNG / PENGUNCI 4,354,650.00 0.14 - - - 0.00%
XII PEKERJAAN PENGECATAN 18,204,830.60 0.57 - - - 0.00%
XIII PEKERJAAN SANITASI 55,721,013.44 1.74 - - - 0.00%
E PEKERJAAN LANDSCAPE 358,612,160.53 11.23 - - - 0.00%
I SALURAN SEKOLAH 129,380,004.53 4.05 - - - 0.00%
II POT TAMAN DEPAN KELAS 19,838,795.67 0.62 - - - 0.00%
III LAPANGAN 95,078,269.80 2.98 - - - 0.00%
IV TIANG BENDERA 6,602,659.77 0.21 - - - 0.00%
V WASTAFEL+PENYANGGA 6,727,123.76 0.21 - - - 0.00%
VI TEMPAT SAMPAH DEPAN KELAS 5,600,000.00 0.18 - - - 0.00%
VII RABAT AKSES JALAN 95,385,307.00 2.99 - - - 0.00%
F PEKERJAAN GAPURA 25,343,044.26 0.79 - - - 0.00%
I PEKERJAAN TANAH 342,876.66 0.01 - - - 0.00%
II PEKERJAAN PONDASI 2,008,590.00 0.06 - - - 0.00%
III PEKERJAAN STRUKTUR BETON 14,191,597.39 0.44 - - - 0.00%
IV PEKERJAAN PASANGAN & PLESTERAN 8,799,980.21 0.28 - - - 0.00%
G PEKERJAAN DINDING PAPAN NAMA (SIGN PAGE) 35,435,122.39 1.11 - - - 0.00%
I PEKERJAAN TANAH 380,884.00 0.01 - - - 0.00%
II PEKERJAAN PONDASI 6,697,186.00 0.21 - - - 0.00%
III PEKERJAAN STRUKTUR BETON 14,594,149.08 0.46 - - - 0.00%
IV PEKERJAAN PASANGAN & PLESTERAN 13,762,903.31 0.43 - - - 0.00%

Page 2 SMTKN PELITA SEMBAB MANOKWARI


KONTRAK AWAL PROGRES MINGGUAN
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN JUMLAH BOBOT
BOBOT BOBOT BOBOT TERHADAP ITEM PEKERJAAN
HARGA (%)
(%) ( %) (%) (%)
a b c d e f g=e+f h=g/d(%)
H PEKERJAAN PAGAR 215,866,121.31 6.76 - - - 0.00%
I PEKERJAAN TANAH 3,647,592.64 0.11 - - - 0.00%
II PEKERJAAN PONDASI 58,797,936.00 1.84 - - - 0.00%
III PEKERJAAN STRUKTUR BETON 72,267,142.62 2.26 - - - 0.00%
IV PEKERJAAN PASANGAN & PLESTERAN 81,153,450.05 2.54 - - - 0.00%
I PEKERJAAN MENARA AIR 36,606,788.12 1.15 - - - 0.00%
I PEKERJAAN PERSIAPAN 1,114,608.00 0.03 - - - 0.00%
II PEKERJAAN TANAH 361,984.80 0.01 - - - 0.00%
III PEKERJAAN PONDASI 242,940.00 0.01 - - - 0.00%
IV PEKERJAAN BETON 25,100,530.89 0.79 - - - 0.00%
V PEKERJAAN DINDING 5,354,235.43 0.17 - - - 0.00%
VI PEKERJAAN TANDON 4,432,489.00 0.14 - - - 0.00%
3,194,678,513.37 100.00 - 0.07 0.07 0.07%

Manokwari, 03 Juli 2022


Mengetahui : Diperiksa Oleh : Dibuat Oleh :
KOORDINATOR DIREKSI TEKNIS PENYEDIA JASA KONSULTAN MANAJEMEN KONSTRUKSI PENYEDIA JASA KONSTRUKSI
SATKER PELAKSANAAN PRASARANA PERMUKIMAN CV. SIARA KONSULTAN - PT. INDO PAPUA CONSUTANT, KSO. PT. KEMER TIRI EMAS
PROVINSI PAPUA BARAT

MARIANE EMILIA N.T.,ST.,MT. MAKALEBU SAMMA, ST. JHON EDYSON P. S., ST.
NIP. 19881108 202012 2004 Team Leader Project Manager

Page 3 SMTKN PELITA SEMBAB MANOKWARI


PENYEDIA JASA KONSTRUKSI

PEKERJAAN : REHABILITASI DAN RENOVASI PRASARANA MADRASAH PROVINSI PAPUA BARAT 1 PENYEDIA JASA KONSULTAN MANAJEMEN KONSTRUKSI
NAMA SEKOLAH : SMTKN PELITA SEMBAB MANOKWARI
PENYEDIA JASA KONSTRUKSI : PT. KEMER TIRI EMAS
NOMOR KONTRAK : HK.02.03/RR.PRAS.MADRASAH.1/PPK-PS/PPP-PB/03
TANGGAL KONTRAK : 06 JUNI 2022
PENYEDIA JASA KONSULTAN MK : CV. SIARA KONSULTAN - PT. INDO PAPUA CONSUTANT, KSO.
TAHUN ANGGARAN : 2022
LAPORAN KEMAJUAN PEKERJAAN PERIODE MINGGU KE-4
Masa Kontrak : 205 Hari Kalender
Waktu Realisasi : 28 Hari Kalender ( 27 Juni s/d 03 Juli 2022 )
Sisa Waktu : 177 Hari Kalender
KONTRAK AWAL PROGRES MINGGUAN
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )
a b c d e f=dxe g h i=h/dxg j k=j/dxg l=h+j m=i+k n=m/g
A RENOVASI GEDUNG A (3 RKB)
I PEKERJAAN PERSIAPAN JUMLAH I 13,799,233.00 0.43 - 0.02 0.02 3.62%
1. 3.1. Pek. Pemasangan Bowplank m1 98.00 69,663.00 6,826,974.00 0.21 - - - - - 0.00%
2. 3.2. Papan Nama Proyek Ls 1.00 500,000.00 500,000.00 0.02 - - 1.00 0.02 1.00 0.02 100.00%
3. 3.3. Penyediaan Sarana Air dan Listrik Kerja Ls 1.00 4,250,000.00 4,250,000.00 0.13 - - - - - 0.00%
4. 3.4. Bongkar bangunan lama ( Dinding ) m3 49.02 24,450.00 1,198,539.00 0.04 - - - - - 0.00%
5. 3.5. Bongkar bangunan lama ( Beton ) m3 4.56 224,500.00 1,023,720.00 0.03 - - - - - 0.00%

II PEKERJAAN TANAH JUMLAH II 36,534,649.30 1.14 - - - 0.00%


1. 3.6. Pek. Galian Tanah Pondasi m3 139.45 99,770.00 13,912,926.50 0.44 - - - - - 0.00%
2. 3.7. Pek. Urugan Kembali bekas Galian m3 34.86 46,800.00 1,631,448.00 0.05 - - - - - 0.00%
3. 3.8. Pek. Urugan Pasir Bawah Pondasi m3 9.50 383,108.00 3,639,526.00 0.11 - - - - - 0.00%
4. 3.9. Pek. Urugan Sirtu Dipadatkan m3 42.04 412,720.00 17,350,748.80 0.54 - - - - - 0.00%

III PEKERJAAN PONDASI JUMLAH III 71,470,086.92 2.24 - - - 0.00%


1. 3.10. Pek. Pas. Pondasi Batu Kosong Batu Kali/ Aanstampeng m3 17.23 732,943.00 12,628,607.89 0.40 - - - - - 0.00%
2. 3.11. Pembesian Overstage Pondasi kg 103.89 22,075.00 2,293,371.75 0.07 - - - - - 0.00%
3. 3.12. Pek. Pas. Pondasi Batu Kali 1 Pc 3 Ps m3 39.02 1,301,064.00 50,767,517.28 1.59 - - - - - 0.00%
4. 3.13. Pondasi Rolag Batu Tela m2 30.65 188,600.00 5,780,590.00 0.18 - - - - - 0.00%

IV PEKERJAAN BETON JUMLAH IV 136,566,264.99 4.27 - - - 0.00%


1. 3.14. Pek. Beton Sloof Ruangan Fc 21,7 Mpa m3 3.23 1,517,097.00 4,900,223.31 0.15 - - - - - 0.00%
3.15. Pembesian kg 548.29 22,075.00 12,103,501.75 0.38 - - - - - 0.00%
3.16. Bekisting sloof m2 43.00 145,957.00 6,276,151.00 0.20 - - - - - 0.00%
2. 3.17. Pek. Beton Sloof Teras Fc 21,7 MPa (SL 2) m3 1.05 1,517,097.00 1,592,951.85 0.05 - - - - - 0.00%
3.18. Pembesian kg 144.44 22,075.00 3,188,513.00 0.10 - - - - - 0.00%
3.19. Bekisting sloof m2 12.40 145,957.00 1,809,866.80 0.06 - - - - - 0.00%
3. 3.20. Pek. Beton Kolom Utama (K1) Fc 21,7 MPa m3 5.30 1,517,097.00 8,040,614.10 0.25 - - - - - 0.00%
3.21. Pembesian kg 832.73 22,075.00 18,382,514.75 0.58 - - - - - 0.00%
3.22. Bekisting Kolom m2 95.40 203,834.00 19,445,763.60 0.61 - - - - - 0.00%
4. 3.23. Pek. Beton Kolom Teras (K3) Fc 21,7 MPa m3 1.14 1,517,097.00 1,729,490.58 0.05 - - - - - 0.00%
3.24. Pembesian kg 173.28 22,075.00 3,825,156.00 0.12 - - - - - 0.00%
3.25. Bekisting Kolom m2 22.80 203,834.00 4,647,415.20 0.15 - - - - - 0.00%

Page 4 SMTKN PELITA SEMBAB MANOKWARI


KONTRAK AWAL PROGRES MINGGUAN
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )
a b c d e f=dxe g h i=h/dxg j k=j/dxg l=h+j m=i+k n=m/g
5. 3.26. Pek. Beton Kolom Praktis (K2) Fc 21,7 MPa m3 0.76 1,517,097.00 1,152,993.72 0.04 - - - - - 0.00%
3.27. Pembesian kg 171.63 22,075.00 3,788,732.25 0.12 - - - - - 0.00%
3.28. Bekisting Kolom m2 12.24 203,834.00 2,494,928.16 0.08 - - - - - 0.00%
6. 3.29. Pek. Beton Balok Latei Fc 21,7 MPa m3 0.62 1,517,097.00 940,600.14 0.03 - - - - - 0.00%
3.30. Pembesian kg 139.65 22,075.00 3,082,773.75 0.10 - - - - - 0.00%
3.31. Bekisting Balok m2 8.55 205,278.00 1,755,126.90 0.05 - - - - - 0.00%
7. 3.32. Pek. Beton Ring Balok Fc 21,7 MPa m3 4.18 1,517,097.00 6,341,465.46 0.20 - - - - - 0.00%
3.33. Pembesian kg 759.77 22,075.00 16,771,922.75 0.52 - - - - - 0.00%
3.34. Bekisting Balok m2 69.64 205,278.00 14,295,559.92 0.45 - - - - - 0.00%

V PEKERJAAN DINDING JUMLAH V 149,547,570.05 4.68 - - - 0.00%


1. 3.35. Pas. Dinding 1/4 Batubela 1:4 m2 262.66 188,623.00 49,543,717.18 1.55 - - - - - 0.00%
2. 3.36. Pas. Dinding 1/4 Batutela 1:2 m2 46.25 200,987.00 9,295,648.75 0.29 - - - - - 0.00%
3. 3.37. Pek. Plesteran Dinding 1:4 m2 527.82 86,645.00 45,732,963.90 1.43 - - - - - 0.00%
4. 3.38. Pek. Plesteran Dinding 1:2 m2 92.50 92,841.00 8,587,792.50 0.27 - - - - - 0.00%
5. 3.39. Pek. Acian Dinding m2 617.82 51,046.00 31,537,239.72 0.99 - - - - - 0.00%
6. 3.40. Pek. Acian Kolom Utama m2 48.00 51,046.00 2,450,208.00 0.08 - - - - - 0.00%
7. 3.41. Pek. Pasang Logo PUPR Steinless Steel bh 2.00 1,200,000.00 2,400,000.00 0.08 - - - - - 0.00%

VI PEKERJAAN PINTU DAN JENDELA JUMLAH VI 48,378,652.50 1.51 - - - 0.00%


1. 3.42. Pek. Kusen Kayu Besi ( P 1 ) Kayu Besi 5/10 m3 0.12 12,884,500.00 1,546,140.00 0.05 - - - - - 0.00%
2. 3.43. Pek. Kusen Kayu Besi ( J 1 ) Kayu Besi 5/10 m3 0.67 12,884,500.00 8,632,615.00 0.27 - - - - - 0.00%
3. 3.44. Pek. Kusen Kayu Besi ( J 2 ) Kayu Besi 5/10 m3 0.08 12,884,500.00 1,030,760.00 0.03 - - - - - 0.00%
4. 3.45. Pek. Jalusi Kayu Besi ( P 1 ) m2 1.57 1,012,600.00 1,589,782.00 0.05 - - - - - 0.00%
5. 3.46. Pek. Jalusi Kayu Besi ( J 1 ) m2 9.07 1,012,600.00 9,184,282.00 0.29 - - - - - 0.00%
6. 3.47. Pek. Jalusi Kayu Besi ( J 2 ) m2 2.27 1,012,600.00 2,298,602.00 0.07 - - - - - 0.00%
7. 3.48. Pek. Jalusi Kayu Besi ( J 3 ) m2 2.16 1,012,600.00 2,187,216.00 0.07 - - - - - 0.00%
8. 3.49. Pek. Daun Pintu Kayu ( P 1) m2 8.40 846,340.00 7,109,256.00 0.22 - - - - - 0.00%
9. 3.50. Pek. Daun Jendela Kayu Besi (J1 ) m2 13.39 760,850.00 10,187,781.50 0.32 - - - - - 0.00%
10. 3.51. Pek. Kaca Bening tb 5 mm Ex.Asahimas m2 18.85 244,680.00 4,612,218.00 0.14 - - - - - 0.00%

VII PEKERJAAN RANGKA ATAP JUMLAH VII 148,743,793.00 4.66 - - - 0.00%


1. 3.52. Pas. Kuda-kuda Ky. Besi 5/10. 3/10 m3 1.26 11,222,500.00 14,140,350.00 0.44 - - - - - 0.00%
2. 3.53. Pas.Gording Ky. Besi 5/10 m3 2.44 12,460,500.00 30,403,620.00 0.95 - - - - - 0.00%
3. 3.54. Pas. Kaso + Reng (Matoa) m2 411.51 122,450.00 50,389,399.50 1.58 - - - - - 0.00%
4. 3.55. Pasang lisplank Kayu Matoa uk.2x3x20 cm m1 86.38 99,800.00 8,620,724.00 0.27 - - - - - 0.00%
5. 3.56. Pasang Genteng Metal Tb. 4 mm Berglazur m2 411.51 102,450.00 42,159,199.50 1.32 - - - - - 0.00%
6. 3.57. Pasang Bubungan Metal Tb. 4 mm Berglazur m1 29.00 104,500.00 3,030,500.00 0.09 - - - - - 0.00%

VIII PEKERJAAN PLAFOND JUMLAH VIII 73,094,536.42 2.29 - - - 0.00%


1. 3.58. Pek. Rangka Plafond Ky Matoa 5/5 m2 327.57 146,884.00 48,114,791.88 1.51 - - - - - 0.00%
2. 3.59. Pek. Penutup Plafond Dalam Tripleks 4 mm m2 208.41 59,384.00 12,376,219.44 0.39 - - - - - 0.00%
3. 3.60. Pek. Penutup Plafond Luar Tripleks 4 mm m' 119.15 59,384.00 7,075,603.60 0.22 - - - - - 0.00%
4. 3.61. Pek. List Plafond m' 185.19 29,850.00 5,527,921.50 0.17 - - - - - 0.00%

IX PEKERJAAN LANTAI / KERAMIK JUMLAH IX 130,837,767.25 4.10 - - - 0.00%


1. 3.62. Pek. Urugan Pasir bawah lantai m3 26.24 383,108.00 10,052,753.92 0.31 - - - - - 0.00%
2. 3.63. Pek. Rabat Beton Lantai Fc 21,7 MPa m3 33.89 1,517,097.00 51,414,417.33 1.61 - - - - - 0.00%
3. 3.64. Pek. Lantai Keramik 40x40 cm m2 270.60 238,660.00 64,581,396.00 2.02 - - - - - 0.00%
4. 3.65. Pas. Plin Keramik 10cm x 40cm m1 130.00 36,840.00 4,789,200.00 0.15 - - - - - 0.00%

X PEKERJAAN INSTALASI LISTRIK JUMLAH X 13,399,895.00 0.42 - - - 0.00%


1. 3.66. Pas. MCB + Box Sekring bh 1.00 350,000.00 350,000.00 0.01 - - - - - 0.00%
2. 3.67. Pek. Instalasi Lampu dan Stop Kontak ttk 30.00 331,800.00 9,954,000.00 0.31 - - - - - 0.00%

Page 5 SMTKN PELITA SEMBAB MANOKWARI


KONTRAK AWAL PROGRES MINGGUAN
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )
a b c d e f=dxe g h i=h/dxg j k=j/dxg l=h+j m=i+k n=m/g
3. 3.68. Pas.Stop Kontak bh 9.00 50,455.00 454,095.00 0.01 - - - - - 0.00%
4. 3.69. Pas. Saklar Tunggal bh 3.00 82,100.00 246,300.00 0.01 - - - - - 0.00%
5. 3.70. Pas. Saklar Ganda bh 3.00 84,500.00 253,500.00 0.01 - - - - - 0.00%
6. 3.71. Pas. Lampu LED 18 Watt bh 21.00 102,000.00 2,142,000.00 0.07 - - - - - 0.00%

XI PEKERJAAN PENGGANTUNG / PENGUNCI JUMLAH XI 16,238,100.00 0.51 - - - 0.00%


1. 3.72. Pas. Engsel Pintu 4 (4bh/pintu) bh 24.00 48,600.00 1,166,400.00 0.04 - - - - - 0.00%
2. 3.73. Pas. Engsel Jendela 3 (2bh/jendela) bh 80.00 77,950.00 6,236,000.00 0.20 - - - - - 0.00%
3. 3.74. Pas. Kait/ Hak Angin (2bh/jendela) bh 80.00 60,200.00 4,816,000.00 0.15 - - - - - 0.00%
4. 3.75. Pas.Set Slot Pintu (1 bh/pintu) bh 3.00 248,600.00 745,800.00 0.02 - - - - - 0.00%
5. 3.76. Pas. Grendel Pintu bh 12.00 77,950.00 935,400.00 0.03 - - - - - 0.00%
6. 3.77. Pas. Slot Jendela Kunci Tanam (2bh/jendela) bh 30.00 77,950.00 2,338,500.00 0.07 - - - - - 0.00%

XII PEKERJAAN PENGECATAN JUMLAH XII 42,565,888.70 1.33 - - - 0.00%


1. 3.78. Pek. Cat Dinding Dalam berikut plamir m2 665.82 25,780.00 17,164,839.60 0.54 - - - - - 0.00%
2. 3.79. Pek. Cat Dinding Luar ( Cat Weathershield ) m2 276.75 31,450.00 8,703,787.50 0.27 - - - - - 0.00%
3. 3.80. Pek. Cat Plafond m2 327.57 25,780.00 8,444,754.60 0.26 - - - - - 0.00%
4. 3.81. Pek. Cat Kilap Pintu dan Jendela m2 90.05 71,980.00 6,481,799.00 0.20 - - - - - 0.00%
5. 3.82. Pek. Cat Kilap Listplank m2 24.60 71,980.00 1,770,708.00 0.06 - - - - - 0.00%

XIII PEKERJAAN LAIN - LAIN JUMLAH XIII 950,832.00 0.03 - - - 0.00%


1. 3.83. Pasang Railling Ramp Pipa dia 2 m' 3.72 255,600.00 950,832.00 0.03 - - - - - 0.00%

B RENOVASI GEDUNG B (2 RKB)


I PEKERJAAN PERSIAPAN JUMLAH I 6,428,755.00 0.20 - - - 0.00%
1. 4.1. Pek. Pemasangan Bowplank m1 70.00 69,663.00 4,876,410.00 0.15 - - - - - 0.00%
2. 4.2. Bongkar bangunan lama ( Dinding ) m3 34.20 24,450.00 836,190.00 0.03 - - - - - 0.00%
3. 4.3. Bongkar bangunan lama ( Beton ) m3 3.19 224,500.00 716,155.00 0.02 - - - - - 0.00%

II PEKERJAAN TANAH JUMLAH II 25,275,130.76 0.79 - - - 0.00%


1. 4.4. Pek. Galian Tanah Pondasi m3 95.06 99,770.00 9,484,136.20 0.30 - - - - - 0.00%
2. 4.5. Pek. Urugan Kembali bekas Galian m3 23.76 46,800.00 1,111,968.00 0.03 - - - - - 0.00%
3. 4.6. Pek. Urugan Pasir Bawah Pondasi m3 6.32 383,108.00 2,421,242.56 0.08 - - - - - 0.00%
4. 4.7. Pek. Urugan Sirtu Dipadatkan m3 29.70 412,720.00 12,257,784.00 0.38 - - - - - 0.00%

III PEKERJAAN PONDASI JUMLAH III 47,458,035.09 1.49 - - - 0.00%


1. 4.8. Pek. Pas. Pondasi Batu Kosong Batu Kali / Aanstampeng m3 11.58 732,943.00 8,487,479.94 0.27 - - - - - 0.00%
2. 4.9. Pembesian Overstage Pondasi kg 72.81 22,075.00 1,607,280.75 0.05 - - - - - 0.00%
3. 4.10. Pek. Pas. Pondasi Batu Kali 1 Pc 4 Ps m3 26.40 1,239,106.00 32,712,398.40 1.02 - - - - - 0.00%
4. 4.11. Pondasi Rolag m2 24.66 188,600.00 4,650,876.00 0.15 - - - - - 0.00%

IV PEKERJAAN BETON JUMLAH IV 93,879,904.57 2.94 - - - 0.00%


1. 4.12. Pek. Beton Sloof Ruangan Fc 21,7 Mpa m3 2.25 1,517,097.00 3,413,468.25 0.11 - - - - - 0.00%
4.13. Pembesian kg 329.25 22,075.00 7,268,193.75 0.23 - - - - - 0.00%
4.14. Bekisting sloof m2 30.00 145,957.00 4,378,710.00 0.14 - - - - - 0.00%
2. 4.15. Pek. Beton Sloof TerasFc 21,7 MPa (SL 2) m3 0.72 1,517,097.00 1,092,309.84 0.03 - - - - - 0.00%
4.16. Pembesian kg 99.04 22,075.00 2,186,308.00 0.07 - - - - - 0.00%
4.17. Bekisting sloof m2 8.80 145,957.00 1,284,421.60 0.04 - - - - - 0.00%
3. 4.18. Pek. Beton Kolom Utama (K1) Fc 21,7 MPa m3 3.71 1,517,097.00 5,628,429.87 0.18 - - - - - 0.00%
4.19. Pembesian kg 582.91 22,075.00 12,867,738.25 0.40 - - - - - 0.00%
4.20. Bekisting Kolom m2 66.78 203,834.00 13,612,034.52 0.43 - - - - - 0.00%

Page 6 SMTKN PELITA SEMBAB MANOKWARI


KONTRAK AWAL PROGRES MINGGUAN
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )
a b c d e f=dxe g h i=h/dxg j k=j/dxg l=h+j m=i+k n=m/g
4. 4.21. Pek. Beton Kolom Teras (K3) Fc 21,7 MPa m3 0.79 1,517,097.00 1,198,506.63 0.04 - - - - - 0.00%
4.22. Pembesian kg 121.29 22,075.00 2,677,476.75 0.08 - - - - - 0.00%
4.23. Bekisting Kolom m2 15.96 203,834.00 3,253,190.64 0.10 - - - - - 0.00%
5. 4.24. Pek. Beton Kolom Praktis (K2) Fc 21,7 MPa m3 0.76 1,517,097.00 1,152,993.72 0.04 - - - - - 0.00%
4.25. Pembesian kg 171.63 22,075.00 3,788,732.25 0.12 - - - - - 0.00%
4.26. Bekisting Kolom m2 12.24 203,834.00 2,494,928.16 0.08 - - - - - 0.00%
6. 4.27. Pek. Beton Balok Latei Fc 21,7 MPa m3 0.41 1,517,097.00 622,009.77 0.02 - - - - - 0.00%
4.28. Pembesian kg 93.10 22,075.00 2,055,182.50 0.06 - - - - - 0.00%
4.29. Bekisting Balok m2 6.90 205,278.00 1,416,418.20 0.04 - - - - - 0.00%
7. 4.30. Pek. Beton Ring Balok (RB) Fc 21,7 MPa m3 3.15 1,517,097.00 4,778,855.55 0.15 - - - - - 0.00%
4.31. Pembesian kg 457.56 22,075.00 10,100,637.00 0.32 - - - - - 0.00%
4.32. Bekisting Balok m2 41.94 205,278.00 8,609,359.32 0.27 - - - - - 0.00%

V PEKERJAAN DINDING JUMLAH V 101,003,546.80 3.16 - - - 0.00%


1. 4.33. Pas. Dinding Campuran 1:4 m2 174.01 188,623.00 32,822,288.23 1.03 - - - - - 0.00%
2. 4.34. Pas. Dinding Campuran 1:2 m2 32.15 200,987.00 6,461,732.05 0.20 - - - - - 0.00%
3. 4.35. Pek. Plesteran Dinding 1:4 m2 353.02 86,645.00 30,587,417.90 0.96 - - - - - 0.00%
4. 4.36. Pek. Plesteran Dinding 1:2 m2 64.30 92,841.00 5,969,676.30 0.19 - - - - - 0.00%
5. 4.37. Pek. Acian Dinding m2 412.32 51,046.00 21,047,286.72 0.66 - - - - - 0.00%
6. 4.38. Pek. Acian Kolom Utama m2 33.60 51,046.00 1,715,145.60 0.05 - - - - - 0.00%
7. 4.39. Pek. Pasang Logo PUPR Steinless Steel bh 2.00 1,200,000.00 2,400,000.00 0.08 - - - - - 0.00%

VI PEKERJAAN PINTU DAN JENDELA JUMLAH VI 32,635,949.60 1.02 - - - 0.00%


1. 4.40. Pek. Kusen Kayu Besi ( P 1 ) Kayu Besi 5/10 m3 0.08 12,884,500.00 1,030,760.00 0.03 - - - - - 0.00%
2. 4.41. Pek. Kusen Kayu Besi ( J 1 ) Kayu Besi 5/10 m3 0.45 12,884,500.00 5,798,025.00 0.18 - - - - - 0.00%
3. 4.42. Pek. Kusen Kayu Besi ( J 2 ) Kayu Besi 5/10 m3 0.05 12,884,500.00 644,225.00 0.02 - - - - - 0.00%
4. 4.43. Pek. Jalusi Kayu Besi ( P 1 ) m2 0.92 1,012,600.00 931,592.00 0.03 - - - - - 0.00%
5. 4.44. Pek. Jalusi Kayu Besi ( J 1 ) m2 6.05 1,012,600.00 6,126,230.00 0.19 - - - - - 0.00%
6. 4.45. Pek. Jalusi Kayu Besi ( J 2 ) m2 1.51 1,012,600.00 1,529,026.00 0.05 - - - - - 0.00%
7. 4.46. Pek. Jalusi Kayu Besi ( J 3 ) m2 2.16 1,012,600.00 2,187,216.00 0.07 - - - - - 0.00%
8. 4.47. Pek. Daun Pintu Kayu ( P 1) m2 5.60 846,340.00 4,739,504.00 0.15 - - - - - 0.00%
9. 4.48. Pek. Daun Jendela Kayu Besi (J1 ) m2 8.64 760,850.00 6,573,744.00 0.21 - - - - - 0.00%
10. 4.49. Pek. Kaca Bening tb 5 mm Ex.Asahimas m2 12.57 244,680.00 3,075,627.60 0.10 - - - - - 0.00%

VII PEKERJAAN RANGKA ATAP JUMLAH VII 94,796,525.00 2.97 - - - 0.00%


1. 4.50. Pas. Kuda-kuda Ky. Besi 5/10. 3/10 m3 0.88 11,222,500.00 9,875,800.00 0.31 - - - - - 0.00%
2. 4.51. Pas.Gording Ky. Besi 5/10 m3 1.69 12,460,500.00 21,058,245.00 0.66 - - - - - 0.00%
3. 4.52. Pas. Kaso + Reng (Matoa) m2 246.00 122,450.00 30,122,700.00 0.94 - - - - - 0.00%
4. 4.53. Pasang lisplank Kayu Matoa uk.2x3x20 cm m1 64.60 99,800.00 6,447,080.00 0.20 - - - - - 0.00%
5. 4.54. Pasang Genteng Metal Tb. 4 mm Berglazur m2 246.00 102,450.00 25,202,700.00 0.79 - - - - - 0.00%
6. 4.55. Pasang Bubungan Metal Tb. 4 mm Berglazur m1 20.00 104,500.00 2,090,000.00 0.07 - - - - - 0.00%

VIII PEKERJAAN PLAFOND JUMLAH VIII 50,769,324.68 1.59 - - - 0.00%


1. 4.56. Pek. Rangka Plafond Ky Matoa 5/5 m2 226.88 146,884.00 33,325,041.92 1.04 - - - - - 0.00%
2. 4.57. Pek. Penutup Plafond Dalam Tripleks 4 mm m2 138.95 59,384.00 8,251,406.80 0.26 - - - - - 0.00%
3. 4.58. Pek. Penutup Plafond Luar Tripleks 4 mm m' 87.94 59,384.00 5,222,228.96 0.16 - - - - - 0.00%
4. 4.59. Pek. List Plafond m' 133.02 29,850.00 3,970,647.00 0.12 - - - - - 0.00%

IX PEKERJAAN LANTAI / KERAMIK JUMLAH IX 86,987,725.30 2.72 - - - 0.00%


1. 4.60. Pek. Urugan Pasir bawah lantai m3 17.49 383,108.00 6,700,558.92 0.21 - - - - - 0.00%
2. 4.61. Pek. Rabat Beton Lantai Fc 21,7 MPa m3 22.54 1,517,097.00 34,195,366.38 1.07 - - - - - 0.00%
3. 4.62. Pek. Lantai Keramik 40x40 cm m2 178.00 238,660.00 42,481,480.00 1.33 - - - - - 0.00%
4. 4.63. Pas. Plin Keramik 10cm x 40cm m2 98.00 36,840.00 3,610,320.00 0.11 - - - - - 0.00%

Page 7 SMTKN PELITA SEMBAB MANOKWARI


KONTRAK AWAL PROGRES MINGGUAN
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )
a b c d e f=dxe g h i=h/dxg j k=j/dxg l=h+j m=i+k n=m/g
X PEKERJAAN INSTALASI LISTRIK JUMLAH X 9,049,930.00 0.28 - - - 0.00%
1. 4.64. Pas. MCB + Box Sekring bh 1.00 350,000.00 350,000.00 0.01 - - - - - 0.00%
2. 4.65. Pek. Instalasi Lampu dan Stop Kontak ttk 20.00 331,800.00 6,636,000.00 0.21 - - - - - 0.00%
3. 4.66. Pas.Stop Kontak bh 6.00 50,455.00 302,730.00 0.01 - - - - - 0.00%
4. 4.67. Pas. Saklar Tunggal bh 2.00 82,100.00 164,200.00 0.01 - - - - - 0.00%
5. 4.68. Pas. Saklar Ganda bh 2.00 84,500.00 169,000.00 0.01 - - - - - 0.00%
6. 4.69. Pas. Lampu LED 18 Watt bh 14.00 102,000.00 1,428,000.00 0.04 - - - - - 0.00%

XI PEKERJAAN PENGGANTUNG / PENGUNCI JUMLAH XI 6,026,000.00 0.19 - - - 0.00%


1. 4.70. Pas. Engsel Pintu 4 bh 12.00 48,600.00 583,200.00 0.02 - - - - - 0.00%
2. 4.71. Pas. Engsel Jendela 3 (2bh/jendela) bh 20.00 77,950.00 1,559,000.00 0.05 - - - - - 0.00%
3. 4.72. Pas. Kait \/ Hak Angin (2bh/jendela) bh 20.00 60,200.00 1,204,000.00 0.04 - - - - - 0.00%
4. 4.73. Pas.Set Slot Pintu (1 bh/pintu) bh 2.00 248,600.00 497,200.00 0.02 - - - - - 0.00%
5. 4.74. Pas. Grendel Pintu bh 8.00 77,950.00 623,600.00 0.02 - - - - - 0.00%
6. 4.75. Pas. Slot Jendela Kunci Tanam (2bh/jendela) bh 20.00 77,950.00 1,559,000.00 0.05 - - - - - 0.00%

XII PEKERJAAN PENGECATAN JUMLAH XII 29,579,474.00 0.93 - - - 0.00%


1. 4.76. Pek. Cat Dinding Dalam berikut plamir m2 445.92 25,780.00 11,495,817.60 0.36 - - - - - 0.00%
2. 4.77. Pek. Cat Dinding Luar ( Cat Weathershield ) m2 209.60 31,450.00 6,591,920.00 0.21 - - - - - 0.00%
3. 4.78. Pek. Cat Plafond m2 226.89 25,780.00 5,849,224.20 0.18 - - - - - 0.00%
4. 4.79. Pek. Cat Kilat Pintu dan Jendela m2 59.19 71,980.00 4,260,496.20 0.13 - - - - - 0.00%
5. 4.80. Pek. Cat Kilat Listplank m2 19.20 71,980.00 1,382,016.00 0.04 - - - - - 0.00%

XIII PEKERJAAN LAIN - LAIN JUMLAH XIII 950,832.00 0.03 - - - 0.00%


1. 4.81. Pasang Reling Ramp Pipa dia 2 m1 3.72 255,600.00 950,832.00 0.03 - - - - - 0.00%

C RENOVASI GEDUNG C ( 1 RUANG GURU + 1 RKB)


I PEKERJAAN PERSIAPAN JUMLAH I 6,428,755.00 0.20 - - - 0.00%
1. 5.1. Pek. Pemasangan Bowplank m1 70.00 69,663.00 4,876,410.00 0.15 - - - - - 0.00%
2. 5.2. Bongkar bangunan lama ( Dinding ) m3 34.20 24,450.00 836,190.00 0.03 - - - - - 0.00%
3. 5.3. Bongkar bangunan lama ( Beton ) m3 3.19 224,500.00 716,155.00 0.02 - - - - - 0.00%

II PEKERJAAN TANAH JUMLAH II 25,275,130.76 0.79 - - - 0.00%


1. 5.4. Pek. Galian Tanah Pondasi m3 95.06 99,770.00 9,484,136.20 0.30 - - - - - 0.00%
2. 5.5. Pek. Urugan Kembali bekas Galian m3 23.76 46,800.00 1,111,968.00 0.03 - - - - - 0.00%
3. 5.6. Pek. Urugan Pasir Bawah Pondasi m3 6.32 383,108.00 2,421,242.56 0.08 - - - - - 0.00%
4. 5.7. Pek. Urugan Sirtu Dipadatkan m3 29.70 412,720.00 12,257,784.00 0.38 - - - - - 0.00%

III PEKERJAAN PONDASI JUMLAH III 49,093,726.29 1.54 - - - 0.00%


1. 5.8. Pek. Pas. Pondasi Batu Kosong Batu Kali/ Aanstampeng m3 11.58 732,943.00 8,487,479.94 0.27 - - - - - 0.00%
2. 5.9. Pembesian Overstage Pondasi kg 72.81 22,075.00 1,607,280.75 0.05 - - - - - 0.00%
3. 5.10. Pek. Pas. Pondasi Batu Kali 1 Pc 3 Ps m3 26.40 1,301,064.00 34,348,089.60 1.08 - - - - - 0.00%
4. 5.11. Pondasi Rolag m2 24.66 188,600.00 4,650,876.00 0.15 - - - - - 0.00%

IV PEKERJAAN BETON JUMLAH IV 93,879,904.57 2.94 - - - 0.00%


1. 5.12. Pek. Beton Sloof Ruangan Fc 21,7 MPa m2 2.25 1,517,097.00 3,413,468.25 0.11 - - - - - 0.00%
5.13. Pembesian kg 329.25 22,075.00 7,268,193.75 0.23 - - - - - 0.00%
5.14. Bekisting sloof m2 30.00 145,957.00 4,378,710.00 0.14 - - - - - 0.00%
2. 5.15. Pek. Beton Sloof Teras Fc 21,7 Mpa m3 0.72 1,517,097.00 1,092,309.84 0.03 - - - - - 0.00%
5.16. Pembesian kg 99.04 22,075.00 2,186,308.00 0.07 - - - - - 0.00%
5.17. Bekisting sloof m2 8.80 145,957.00 1,284,421.60 0.04 - - - - - 0.00%

Page 8 SMTKN PELITA SEMBAB MANOKWARI


KONTRAK AWAL PROGRES MINGGUAN
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )
a b c d e f=dxe g h i=h/dxg j k=j/dxg l=h+j m=i+k n=m/g
3. 5.18. Pek. Beton Kolom Utama Fc 21,7 MPa m3 3.71 1,517,097.00 5,628,429.87 0.18 - - - - - 0.00%
5.19. Pembesian kg 582.91 22,075.00 12,867,738.25 0.40 - - - - - 0.00%
5.20. Bekisting Kolom m2 66.78 203,834.00 13,612,034.52 0.43 - - - - - 0.00%
4. 5.21. Pek. Beton Kolom Teras Fc 21,7 MPa m3 0.79 1,517,097.00 1,198,506.63 0.04 - - - - - 0.00%
5.22. Pembesian kg 121.29 22,075.00 2,677,476.75 0.08 - - - - - 0.00%
5.23. Bekisting Kolom m2 15.96 203,834.00 3,253,190.64 0.10 - - - - - 0.00%
5. 5.24. Pek. Beton Kolom Praktis Fc 21,7 MPa m3 0.76 1,517,097.00 1,152,993.72 0.04 - - - - - 0.00%
5.25. Pembesian kg 171.63 22,075.00 3,788,732.25 0.12 - - - - - 0.00%
5.26. Bekisting Kolom m2 12.24 203,834.00 2,494,928.16 0.08 - - - - - 0.00%
6. 5.27. Pek. Beton Balok Latei Fc 21,7 MPa m3 0.41 1,517,097.00 622,009.77 0.02 - - - - - 0.00%
5.28. Pembesian kg 93.10 22,075.00 2,055,182.50 0.06 - - - - - 0.00%
5.29. Bekisting Balok m2 6.90 205,278.00 1,416,418.20 0.04 - - - - - 0.00%
7. 5.30. Pek. Beton Ring Balok (RB ) Fc 21,7 MPa m3 3.15 1,517,097.00 4,778,855.55 0.15 - - - - - 0.00%
5.31. Pembesian kg 457.56 22,075.00 10,100,637.00 0.32 - - - - - 0.00%
5.32. Bekisting Balok m2 41.94 205,278.00 8,609,359.32 0.27 - - - - - 0.00%

V PEKERJAAN DINDING JUMLAH V 101,003,546.80 3.16 - - - 0.00%


1. 5.33. Pas. Dinding 1/4 Batubata 1:4 m2 174.01 188,623.00 32,822,288.23 1.03 - - - - - 0.00%
2. 5.34. Pas. Dinding 1/4 Batubata 1:2 m2 32.15 200,987.00 6,461,732.05 0.20 - - - - - 0.00%
3. 5.35. Pek. Plesteran Dinding 1:4 m2 353.02 86,645.00 30,587,417.90 0.96 - - - - - 0.00%
4. 5.36. Pek. Plesteran Dinding 1:2 m2 64.30 92,841.00 5,969,676.30 0.19 - - - - - 0.00%
5. 5.37. Pek. Acian Dinding m2 412.32 51,046.00 21,047,286.72 0.66 - - - - - 0.00%
6. 5.38. Pek. Acian Kolom Utama m2 33.60 51,046.00 1,715,145.60 0.05 - - - - - 0.00%
7. 5.39. Pek. Pasang Logo PUPR Steinless Steel bh 2.00 1,200,000.00 2,400,000.00 0.08 - - - - - 0.00%

VI PEKERJAAN PINTU DAN JENDELA JUMLAH VI 32,635,949.60 1.02 - - - 0.00%


1. 5.40. Pek. Kusen Kayu Besi ( P 1 ) Kayu Besi 5/10 m3 0.08 12,884,500.00 1,030,760.00 0.03 - - - - - 0.00%
2. 5.41. Pek. Kusen Kayu Besi ( J 1 ) Kayu Besi 5/10 m3 0.45 12,884,500.00 5,798,025.00 0.18 - - - - - 0.00%
3. 5.42. Pek. Kusen Kayu Besi ( J 2 ) Kayu Besi 5/10 m3 0.05 12,884,500.00 644,225.00 0.02 - - - - - 0.00%
4. 5.43. Pek. Jalusi Kayu Besi ( P 1 ) m2 0.92 1,012,600.00 931,592.00 0.03 - - - - - 0.00%
5. 5.44. Pek. Jalusi Kayu Besi ( J 1 ) m2 6.05 1,012,600.00 6,126,230.00 0.19 - - - - - 0.00%
6. 5.45. Pek. Jalusi Kayu Besi ( J 2 ) m2 1.51 1,012,600.00 1,529,026.00 0.05 - - - - - 0.00%
7. 5.46. Pek. Jalusi Kayu Besi ( J 3 ) m2 2.16 1,012,600.00 2,187,216.00 0.07 - - - - - 0.00%
8. 5.47. Pek. Daun Pintu Kayu ( P 1) m2 5.60 846,340.00 4,739,504.00 0.15 - - - - - 0.00%
9. 5.48. Pek. Daun Jendela Kayu Besi (J1 ) m2 8.64 760,850.00 6,573,744.00 0.21 - - - - - 0.00%
10. 5.49. Pek. Kaca Bening tb 5 mm Ex.Asahimas m2 12.57 244,680.00 3,075,627.60 0.10 - - - - - 0.00%

VII PEKERJAAN RANGKA ATAP JUMLAH VII 94,796,525.00 2.97 - - - 0.00%


1. 5.50. Pas. Kuda-kuda Ky. Besi 5/10. 3/10 m3 0.88 11,222,500.00 9,875,800.00 0.31 - - - - - 0.00%
2. 5.51. Pas.Gording Ky. Besi 5/10 m3 1.69 12,460,500.00 21,058,245.00 0.66 - - - - - 0.00%
3. 5.52. Pas. Kaso + Reng (Matoa) m2 246.00 122,450.00 30,122,700.00 0.94 - - - - - 0.00%
4. 5.53. Pasang lisplank Kayu Matoa uk.2x3x20 cm m1 64.60 99,800.00 6,447,080.00 0.20 - - - - - 0.00%
5. 5.54. Pasang Genteng Metal Tb. 4 mm Berglazur m2 246.00 102,450.00 25,202,700.00 0.79 - - - - - 0.00%
6. 5.55. Pasang Bubungan Metal Tb. 4 mm Berglazur m1 20.00 104,500.00 2,090,000.00 0.07 - - - - - 0.00%

VIII PEKERJAAN PLAFOND JUMLAH VIII 50,769,324.68 1.59 - - - 0.00%


1. 5.56. Pek. Rangka Plafond Ky Matoa 5/5 m2 226.88 146,884.00 33,325,041.92 1.04 - - - - - 0.00%
2. 5.57. Pek. Penutup Plafond Dalam Tripleks 4 mm m2 138.95 59,384.00 8,251,406.80 0.26 - - - - - 0.00%
3. 5.58. Pek. Penutup Plafond Luar Tripleks 4 mm m' 87.94 59,384.00 5,222,228.96 0.16 - - - - - 0.00%
4. 5.59. Pek. List Plafond m' 133.02 29,850.00 3,970,647.00 0.12 - - - - - 0.00%

IX PEKERJAAN LANTAI / KERAMIK JUMLAH IX 86,987,725.30 2.72 - - - 0.00%


1. 5.60. Pek. Urugan Pasir bawah lantai m3 17.49 383,108.00 6,700,558.92 0.21 - - - - - 0.00%
2. 5.61. Pek. Rabat Beton Lantai Fc 21,7 MPa m3 22.54 1,517,097.00 34,195,366.38 1.07 - - - - - 0.00%

Page 9 SMTKN PELITA SEMBAB MANOKWARI


KONTRAK AWAL PROGRES MINGGUAN
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )
a b c d e f=dxe g h i=h/dxg j k=j/dxg l=h+j m=i+k n=m/g
3. 5.62. Pek. Lantai Keramik 40x40 cm m2 178.00 238,660.00 42,481,480.00 1.33 - - - - - 0.00%
4. 5.63. Pas. Plin Keramik 10cm x 40cm m2 98.00 36,840.00 3,610,320.00 0.11 - - - - - 0.00%

X PEKERJAAN INSTALASI LISTRIK JUMLAH X 9,049,930.00 0.28 - - - 0.00%


1. 5.64. Pas. MCB + Box Sekring bh 1.00 350,000.00 350,000.00 0.01 - - - - - 0.00%
2. 5.65. Pek. Instalasi Lampu dan Stop Kontak ttk 20.00 331,800.00 6,636,000.00 0.21 - - - - - 0.00%
3. 5.66. Pas.Stop Kontak bh 6.00 50,455.00 302,730.00 0.01 - - - - - 0.00%
4. 5.67. Pas. Saklar Tunggal bh 2.00 82,100.00 164,200.00 0.01 - - - - - 0.00%
5. 5.68. Pas. Saklar Ganda bh 2.00 84,500.00 169,000.00 0.01 - - - - - 0.00%
6. 5.69. Pas. Lampu LED 18 Watt bh 14.00 102,000.00 1,428,000.00 0.04 - - - - - 0.00%

XI PEKERJAAN PENGGANTUNG / PENGUNCI JUMLAH XI 6,026,000.00 0.19 - - - 0.00%


1. 5.70. Pas. Engsel Pintu 4 (4bh/pintu) bh 12.00 48,600.00 583,200.00 0.02 - - - - - 0.00%
2. 5.71. Pas. Engsel Jendela 3 (2bh/jendela) bh 20.00 77,950.00 1,559,000.00 0.05 - - - - - 0.00%
3. 5.72. Pas. Kait / Hak Angin (2bh/jendela) bh 20.00 60,200.00 1,204,000.00 0.04 - - - - - 0.00%
4. 5.73. Pas.Set Slot Pintu (1 bh/pintu) bh 2.00 248,600.00 497,200.00 0.02 - - - - - 0.00%
5. 5.74. Pas. Grendel Pintu bh 8.00 77,950.00 623,600.00 0.02 - - - - - 0.00%
6. 5.75. Pas. Slot Jendela Kunci Tanam (2bh/jendela) bh 20.00 77,950.00 1,559,000.00 0.05 - - - - - 0.00%

XII PEKERJAAN PENGECATAN JUMLAH XII 29,579,474.00 0.93 - - - 0.00%


1. 5.76. Pek. Cat Dinding Dalam berikut plamir m2 445.92 25,780.00 11,495,817.60 0.36 - - - - - 0.00%
2. 5.77. Pek. Cat Dinding Luar ( Cat Weathershield ) m2 209.60 31,450.00 6,591,920.00 0.21 - - - - - 0.00%
3. 5.78. Pek. Cat Plafond m2 226.89 25,780.00 5,849,224.20 0.18 - - - - - 0.00%
4. 5.79. Pek. Cat Kilat Pintu dan Jendela m2 59.19 71,980.00 4,260,496.20 0.13 - - - - - 0.00%
5. 5.80. Pek. Cat Kilat Listplank m2 19.20 71,980.00 1,382,016.00 0.04 - - - - - 0.00%

XIII PEKERJAAN LAIN - LAIN JUMLAH XIII 950,832.00 0.03 - - - 0.00%


1. 5.81. Pasang Reling Ramp Pipa dia 2 m1 3.72 255,600.00 950,832.00 0.03 - - - - - 0.00%

D RENOVASI KM/WC
I PEKERJAAN PERSIAPAN JUMLAH I 3,552,813.00 0.11 - 0.06 0.06 50.00%
1. 6.1. Pek. Pemasangan Bowplank m1 51.00 69,663.00 3,552,813.00 0.11 - - 25.50 0.06 25.50 0.06 50.00%

II PEKERJAAN TANAH JUMLAH II 23,764,494.42 0.74 - - - 0.00%


1. 6.2. Pek. Galian Tanah Pondasi m3 60.61 99,770.00 6,047,059.70 0.19 - - - - - 0.00%
2. 6.3. Pek. Urugan Kembali bekas Galian m3 15.15 46,800.00 709,020.00 0.02 - - - - - 0.00%
3. 6.4. Pek. Urugan Pasir Bawah Pondasi m3 7.24 383,108.00 2,773,701.92 0.09 - - - - - 0.00%
4. 6.5. Pek. Urugan Sirtu Dipadatkan m3 34.49 412,720.00 14,234,712.80 0.45 - - - - - 0.00%

III PEKERJAAN PONDASI JUMLAH III 50,761,434.15 1.59 - - - 0.00%


1. 6.6. Pek. Pas. Pondasi Batu Kosong Batu Kali / Aanstampeng m3 14.47 732,943.00 10,605,685.21 0.33 - - - - - 0.00%
2. 6.7. Pek. Pas. Pondasi Batu Kali 1 Pc 4 Ps m3 27.99 1,239,106.00 34,682,576.94 1.09 - - - - - 0.00%
3. 6.8. Pas. Pondasi Rolag Batu Tela 1 Pc 4 Ps m2 29.02 188,600.00 5,473,172.00 0.17 - - - - - 0.00%

IV PEKERJAAN BETON JUMLAH IV 102,990,719.52 3.22 - - - 0.00%


1. 6.9. Beton Sloof Ruangan (SL 15/20) Fc 21,7 Mpa m3 2.17 1,517,097.00 3,292,100.49 0.10 - - - - - 0.00%
6.10. Pembesian kg 1,430.48 22,075.00 31,577,846.00 0.99 - - - - - 0.00%
6.11. Bekisting sloof m2 28.94 145,957.00 4,223,995.58 0.13 - - - - - 0.00%
2. 6.12. Beton Kolom Utama (K1 25/20) Fc 21,7 Mpa m3 1.16 1,517,097.00 1,759,832.52 0.06 - - - - - 0.00%
6.13. Pembesian kg 246.37 22,075.00 5,438,617.75 0.17 - - - - - 0.00%
6.14. Bekisting sloof m2 20.79 145,957.00 3,034,446.03 0.09 - - - - - 0.00%
3. 6.15. Beton Kolom (K2 20/20) Fc 21,7 Mpa m3 0.46 1,517,097.00 697,864.62 0.02 - - - - - 0.00%
6.16. Pembesian kg 89.87 22,075.00 1,983,880.25 0.06 - - - - - 0.00%
6.17. Bekisting Kolom m2 9.24 203,834.00 1,883,426.16 0.06 - - - - - 0.00%

Page 10 SMTKN PELITA SEMBAB MANOKWARI


KONTRAK AWAL PROGRES MINGGUAN
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )
a b c d e f=dxe g h i=h/dxg j k=j/dxg l=h+j m=i+k n=m/g
4. 6.18. Beton Kolom (K3 15/15) Fc 21,7 Mpa m2 1.66 1,517,097.00 2,518,381.02 0.08 - - - - - 0.00%
6.19. Pembesian kg 539.33 22,075.00 11,905,709.75 0.37 - - - - - 0.00%
6.20. Bekisting Kolom m2 44.16 203,834.00 9,001,309.44 0.28 - - - - - 0.00%
5. 6.21. Beton Ring Balok (RB 15/20) Fc 21,7 Mpa m3 2.55 1,517,097.00 3,868,597.35 0.12 - - - - - 0.00%
6.22. Pembesian kg 671.40 22,075.00 14,821,155.00 0.46 - - - - - 0.00%
6.23. Bekisting Balok m2 34.02 205,278.00 6,983,557.56 0.22 - - - - - 0.00%

V PEKERJAAN DINDING JUMLAH V 68,155,430.14 2.13 - - - 0.00%


1. 6.24. Pas. Dinding 1/4 Batu Tela 1:4 m2 86.00 188,623.00 16,221,578.00 0.51 - - - - - 0.00%
2. 6.25. Pas. Dinding 1/4 Batu Tela 1:2 m2 58.40 200,987.00 11,737,640.80 0.37 - - - - - 0.00%
3. 6.26. Pek. Plesteran Dinding 1:4 m2 159.32 86,645.00 13,804,281.40 0.43 - - - - - 0.00%
4. 6.27. Pek. Plesteran Dinding 1:2 m2 116.80 92,841.00 10,843,828.80 0.34 - - - - - 0.00%
5. 6.28. Pek. Acian Dinding m2 304.59 51,046.00 15,548,101.14 0.49 - - - - - 0.00%

VI PEKERJAAN PINTU DAN JENDELA JUMLAH VI 17,286,492.40 0.54 - - - 0.00%


1. 6.29. Pek. Kusen Pintu Kayu Kelas I m3 0.28 12,884,500.00 3,607,660.00 0.11 - - - - - 0.00%
2. 6.30. Pek. Jalusi Kayu Kelas I m2 2.16 1,012,600.00 2,187,216.00 0.07 - - - - - 0.00%
3. 6.31. Pek. Daun Pintu Kayu ( P 1) m2 5.04 846,340.00 4,265,553.60 0.13 - - - - - 0.00%
4. 6.32. Pek. Daun Pintu Kayu ( P 2) m2 8.22 846,340.00 6,956,914.80 0.22 - - - - - 0.00%
5. 6.33. Pek. Kaca Cermin tb 5 mm ex. Asahimas m2 1.10 244,680.00 269,148.00 0.01 - - - - - 0.00%

VII PEKERJAAN RANGKA ATAP JUMLAH VII 32,463,740.00 1.02 - - - 0.00%


1. 6.34. Kuda-kuda Kayu Kelas I m3 0.56 11,222,500.00 6,284,600.00 0.20 - - - - - 0.00%
2. 6.35. Pas. Gording Kayu Kelas 1 m3 0.44 12,460,500.00 5,482,620.00 0.17 - - - - - 0.00%
3. 6.36. Pas. Kaso + Reng Ky. Matoa m2 72.20 122,450.00 8,840,890.00 0.28 - - - - - 0.00%
4. 6.37. Pasang lisplank, 2x2/25 cm m1 36.30 99,800.00 3,622,740.00 0.11 - - - - - 0.00%
5. 6.38. Pasang Genteng Metal Roof Berglazur Tbl. 4mm m2 72.20 102,450.00 7,396,890.00 0.23 - - - - - 0.00%
6. 6.39. Pasang Bubungan Metal Roof Berglazur Tbl. 4mm m1 8.00 104,500.00 836,000.00 0.03 - - - - - 0.00%

VIII PEKERJAAN PLAFOND JUMLAH VIII 29,210,075.70 0.91 - - - 0.00%


1. 6.40. Pek. Rangka Plafond Kayu Kelas II m2 119.40 146,884.00 17,537,949.60 0.55 - - - - - 0.00%
2. 6.41. Pek. Penutup Plafond Multipleks t=4mm m2 119.40 59,384.00 7,090,449.60 0.22 - - - - - 0.00%
3. 6.42. Pek. List Plafond m1 153.49 29,850.00 4,581,676.50 0.14 - - - - - 0.00%

IX PEKERJAAN LANTAI / KERAMIK JUMLAH IX 57,251,942.46 1.79 - - - 0.00%


1. 6.43. Pek. Urugan Pasir bawah lantai m3 4.27 383,108.00 1,635,871.16 0.05 - - - - - 0.00%
2. 6.44. Pek. Rabat Beton Lantai Fc 21,7 MPa m3 5.98 1,517,097.00 9,072,240.06 0.28 - - - - - 0.00%
3. 6.45. Pek. Lantai Keramik m2 50.16 298,664.00 14,980,986.24 0.47 - - - - - 0.00%
4. 6.46. Pek. Keramik Dinding m2 93.70 336,850.00 31,562,845.00 0.99 - - - - - 0.00%

X PEKERJAAN INSTALASI LISTRIK JUMLAH X 5,652,415.00 0.18 - - - 0.00%


1. 6.47. Pas. MCB + Box Sekring bh 1.00 350,000.00 350,000.00 0.01 - - - - - 0.00%
2. 6.48. Pek. Instalasi Lampu dan Stop Kontak ttk 11.00 331,800.00 3,649,800.00 0.11 - - - - - 0.00%
3. 6.49. Pas.Stop Kontak bh 5.00 50,455.00 252,275.00 0.01 - - - - - 0.00%
4. 6.50. Pas. Saklar Tunggal bh 1.00 82,100.00 82,100.00 0.00 - - - - - 0.00%
5. 6.51. Pas. Lampu SL 18 Watt bh 11.00 119,840.00 1,318,240.00 0.04 - - - - - 0.00%

XI PEKERJAAN PENGGANTUNG / PENGUNCI JUMLAH XI 4,354,650.00 0.14 - - - 0.00%


1. 6.52. Pas. Engsel Pintu 4 (4bh/pintu) bh 36.00 48,600.00 1,749,600.00 0.05 - - - - - 0.00%
2. 6.53. Pas. 1 Set Pintu Kunci (1 bh/pintu) bh 9.00 211,500.00 1,903,500.00 0.06 - - - - - 0.00%
3. 6.54. Pas. Grendel Pintu bh 9.00 77,950.00 701,550.00 0.02 - - - - - 0.00%

Page 11 SMTKN PELITA SEMBAB MANOKWARI


KONTRAK AWAL PROGRES MINGGUAN
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )
a b c d e f=dxe g h i=h/dxg j k=j/dxg l=h+j m=i+k n=m/g
XII PEKERJAAN PENGECATAN JUMLAH XII 18,204,830.60 0.57 - - - 0.00%
1. 6.55. Pek. Cat Dinding Dalam berikut plamir m2 361.77 25,780.00 9,326,430.60 0.29 - - - - - 0.00%
2. 6.56. Pek. Cat Dinding Luar ( Cat Weathershield ) m2 103.98 31,450.00 3,270,171.00 0.10 - - - - - 0.00%
3. 6.57. Pek. Cat Plafond m2 119.40 25,780.00 3,078,132.00 0.10 - - - - - 0.00%
4. 6.58. Pek. Cat Kilap Atap, Kusen Pintu, Lisplank, Jendela, Daun Pintu Cat Natural Grey m2 35.15 71,980.00 2,530,097.00 0.08 - - - - - 0.00%

XIII PEKERJAAN SANITASI JUMLAH XIII 55,721,013.44 1.74 - - - 0.00%


1. 6.59. Pas. Closed Duduk bh 1.00 2,798,500.00 2,798,500.00 0.09 - - - - - 0.00%
2. 6.60. Pas. Closed Jongkok bh 6.00 886,500.00 5,319,000.00 0.17 - - - - - 0.00%
3. 6.61. Pas. 1 Set Wastafel bh 5.00 2,188,500.00 10,942,500.00 0.34 - - - - - 0.00%
4. 6.62. Pas. 1 Urinoir bh 3.00 2,998,600.00 8,995,800.00 0.28 - - - - - 0.00%
5. 6.63. Pas. Kran Air 3/4 AW bh 7.00 98,400.00 688,800.00 0.02 - - - - - 0.00%
6. 6.64. Pas. Pipa PVC 1/2 AW m1 22.00 26,500.00 583,000.00 0.02 - - - - - 0.00%
7. 6.65. Pas. Pipa PVC 3/4 AW m1 20.00 27,000.00 540,000.00 0.02 - - - - - 0.00%
8. 6.66. Pas. Pipa PVC 3 AW m1 56.00 116,820.00 6,541,920.00 0.20 - - - - - 0.00%
9. 6.67. Pas. Pipa PVC 4 AW m1 30.00 173,220.00 5,196,600.00 0.16 - - - - - 0.00%
10. 6.68. Pas. Floor drain bh 9.00 122,500.00 1,102,500.00 0.03 - - - - - 0.00%
11. Pek. Septic Tank dan Resapan
a. 6.69. Septic Tank - Galian Tanah m3 6.75 99,770.00 673,447.50 0.02 - - - - - 0.00%
b. 6.70. Septic Tank - Pas. Dinding 1/2 Batu Tela 1:4 m2 19.95 188,623.00 3,763,028.85 0.12 - - - - - 0.00%
c. 6.71. Septic Tank - Pek. Plesteran Dinding 1:4 m2 19.95 86,645.00 1,728,567.75 0.05 - - - - - 0.00%
d. 6.72. Septic Tank - Pek. Acian Dinding m2 21.90 51,046.00 1,117,907.40 0.03 - - - - - 0.00%
e. 6.73. Septic Tank - Cor beton Plat Penutup, Beton Fc 21,7 Mpa m3 0.52 1,517,097.00 788,890.44 0.02 - - - - - 0.00%
f. 6.74. Septic Tank - Pembesian kg 54.59 22,075.00 1,205,074.25 0.04 - - - - - 0.00%
g. 6.75. Septic Tank - Bekesting m2 0.45 145,957.00 65,680.65 0.00 - - - - - 0.00%
h. 6.76. Septic Tank - Urugan Pasir Resapan m3 0.75 383,108.00 287,331.00 0.01 - - - - - 0.00%
i. 6.77. Septic Tank - Urugan Kerikil Resapan m3 0.49 412,720.00 202,232.80 0.01 - - - - - 0.00%
j. 6.78. Septic Tank - Urugan Ijuk Resapan kg 10.00 112,800.00 1,128,000.00 0.04 - - - - - 0.00%
k. 6.79. Septic Tank - Urugan Sirtu Resapan m3 0.49 412,720.00 202,232.80 0.01 - - - - - 0.00%
12. 6.80. Pompa Air Sumersible bh 1.00 1,850,000.00 1,850,000.00 0.06 - - - - - 0.00%

E PEKERJAAN LANDSCAPE
I SALURAN SEKOLAH JUMLAH I 129,380,004.53 4.05 - - - 0.00%
1. 7.1. Galian tanah m3 77.58 99,770.00 7,740,156.60 0.24 - - - - - 0.00%
2. 7.2. Lantai kerja Fc 14,50 Mpa t=5cm m3 3.87 1,423,580.00 5,509,254.60 0.17 - - - - - 0.00%
3. 7.3. Urug Pasir Bawah Pondasi t= 5cm m3 3.87 383,108.00 1,482,627.96 0.05 - - - - - 0.00%
4. 7.4. Pasangan Bata 1:4 m2 310.32 188,623.00 58,533,489.36 1.83 - - - - - 0.00%
5. 7.5. Plesteran 1:4 m2 310.32 86,645.00 26,887,676.40 0.84 - - - - - 0.00%
6. 7.6. Acian m2 310.32 51,046.00 15,840,594.72 0.50 - - - - - 0.00%
7. 7.7. Plat Beton Penutup Saluran Didepan Pintu Fc 21,7 Mpa m3 0.79 1,517,097.00 1,198,506.63 0.04 - - - - - 0.00%
7.8. Pembesian kg 83.74 22,075.00 1,848,560.50 0.06 - - - - - 0.00%
7.9. Bekisting m2 19.92 205,278.00 4,089,137.76 0.13 - - - - - 0.00%
8. 7.10. Pemasangan bak kontrol pasangan bata bh 5.00 1,250,000.00 6,250,000.00 0.20 - - - - - 0.00%

II POT TAMAN DEPAN KELAS JUMLAH II 19,838,795.67 0.62 - - - 0.00%


1. 8.1. Galian Tanah m3 2.41 99,770.00 240,445.70 0.01 - - - - - 0.00%
2. 8.2. Tanah Pilihan m3 4.48 74,680.00 334,566.40 0.01 - - - - - 0.00%
3. 8.3. Balok 12/15 Mutu Fc 21,7 Mpa m3 1.51 1,517,097.00 2,290,816.47 0.07 - - - - - 0.00%
4. 8.4. Pembesian kg 189.78 22,075.00 4,189,393.50 0.13 - - - - - 0.00%
5. 8.5. Cor Beton Mutu Fc 14,50 Mpa m3 0.84 1,423,580.00 1,195,807.20 0.04 - - - - - 0.00%
6. 8.6. Pas. Dinding 1/2 Batubata 1:2 m2 33.60 200,987.00 6,753,163.20 0.21 - - - - - 0.00%
7. 8.7. Pek. Plesteran Dinding 1:2 m2 33.60 92,841.00 3,119,457.60 0.10 - - - - - 0.00%
8. 8.8. Pek. Acian Dinding m2 33.60 51,046.00 1,715,145.60 0.05 - - - - - 0.00%

Page 12 SMTKN PELITA SEMBAB MANOKWARI


KONTRAK AWAL PROGRES MINGGUAN
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )
a b c d e f=dxe g h i=h/dxg j k=j/dxg l=h+j m=i+k n=m/g
III LAPANGAN JUMLAH III 95,078,269.80 2.98 - - - 0.00%
1. 9.1. Galian Tanah m3 72.90 99,770.00 7,273,233.00 0.23 - - - - - 0.00%
2. 9.2. Urugan Pasir m3 48.60 383,108.00 18,619,048.80 0.58 - - - - - 0.00%
3. 9.3. Rabat Beton Fc 14,50 Mpa m3 48.60 1,423,580.00 69,185,988.00 2.17 - - - - - 0.00%

IV TIANG BENDERA JUMLAH IV 6,602,659.77 0.21 - - - 0.00%


1. 10.1. Galian Pondasi m3 0.48 99,770.00 47,889.60 0.00 - - - - - 0.00%
2. 10.2. Lantai Kerja t=5cm fc 14,50 Mpa m3 0.03 1,423,580.00 42,707.40 0.00 - - - - - 0.00%
3. 10.3. Beton Pondasi Tiang Bendera fc 21,7 Mpa (FP 80.80.25) m3 0.19 1,517,097.00 288,248.43 0.01 - - - - - 0.00%
4. 10.4. Kolom 25 x 25 Fc 21,7 Mpa m3 0.19 1,517,097.00 288,248.43 0.01 - - - - - 0.00%
5. 10.5. Dumpal Pas 1/2 bata m2 0.17 188,623.00 32,065.91 0.00 - - - - - 0.00%
6. 10.6. Tiang Bendera Besi 4, 3 & 2 tb 5mm H= 8,65m + Angkur + 2 Tangkai 1m terpasang bh 1.00 5,500,000.00 5,500,000.00 0.17 - - - - - 0.00%
7. 10.7. Besi Pengikat Tali + Tali Tampar 6mm bh 1.00 68,500.00 68,500.00 0.00 - - - - - 0.00%
8. 10.8. Roll Roda Kerekan bh 1.00 145,000.00 145,000.00 0.00 - - - - - 0.00%
9. 10.9. Bendera Indonesia Uk. 120x180 cm bh 1.00 190,000.00 190,000.00 0.01 - - - - - 0.00%

V WASTAFEL+PENYANGGA JUMLAH V 6,727,123.76 0.21 - - - 0.00%


1. 11.1. Beton Bertulang fc 21,7 Mpa m3 0.08 1,517,097.00 121,367.76 0.00 - - - - - 0.00%
2. 11.2. Pek. Cat Dinding Weathershield m2 1.28 31,450.00 40,256.00 0.00 - - - - - 0.00%
3. 11.3. Pas. Wastafel Unit 3.00 2,188,500.00 6,565,500.00 0.21 - - - - - 0.00%

VI TEMPAT SAMPAH DEPAN KELAS JUMLAH VI 5,600,000.00 0.18 - - - 0.00%


1. 12.1. Tempat Sampah Depan Kelas Unit 7.00 800,000.00 5,600,000.00 0.18 - - - - - 0.00%

VII RABAT AKSES JALAN JUMLAH VII 95,385,307.00 2.99 - - - 0.00%


1. 13.1. Galian Tanah m3 47.10 99,770.00 4,699,167.00 0.15 - - - - - 0.00%
2. 13.2. Urugan Pasir m3 25.40 383,108.00 9,730,943.20 0.30 - - - - - 0.00%
3. 13.3. Rabat Fc 21,7 Mpa m3 47.10 1,517,097.00 71,455,268.70 2.24 - - - - - 0.00%
4. 13.4. Plastik Cor m2 504.30 9,200.00 4,639,560.00 0.15 - - - - - 0.00%
5. 13.5. Bekesting Rabat Beton m2 33.30 145,957.00 4,860,368.10 0.15 - - - - - 0.00%

F PEKERJAAN GAPURA
I PEKERJAAN TANAH JUMLAH I 342,876.66 0.01 - - - 0.00%
1. 14.1. Galian Tanah m3 2.61 99,770.00 260,399.70 0.01 - - - - - 0.00%
2. 14.2. Urugan kembali m3 0.78 46,800.00 36,504.00 0.00 - - - - - 0.00%
3. 14.3. Urug Pasir Bawah Pondasi t= 5cm m3 0.12 383,108.00 45,972.96 0.00 - - - - - 0.00%

II PEKERJAAN PONDASI JUMLAH II 2,008,590.00 0.06 - - - 0.00%


1. 14.4. Pas. Pondasi Rolag Batu Tela 1:4 m2 10.65 188,600.00 2,008,590.00 0.06 - - - - - 0.00%

III PEKERJAAN STRUKTUR BETON JUMLAH III 14,191,597.39 0.44 - - - 0.00%


1. 14.5. Rabat Lantai Kerja Fc 14,50 Mpa m3 0.12 1,423,580.00 170,829.60 0.01 - - - - - 0.00%
2. 14.6. Plat Beton 120 x 120 x 20 cm Fc 21,70 Mpa m3 0.58 1,517,097.00 879,916.26 0.03 - - - - - 0.00%
14.7. Pembesian kg 41.20 22,075.00 909,490.00 0.03 - - - - - 0.00%
3. 14.8. Plat Beton 70 x 70 x 20 cm,Fc 21,70 Mpa m3 0.20 1,517,097.00 303,419.40 0.01 - - - - - 0.00%
14.9. Pembesian kg 12.43 22,075.00 274,392.25 0.01 - - - - - 0.00%
4. 14.10. Sloof 15 x 20,Fc 21,70 Mpa m3 0.33 1,517,097.00 500,642.01 0.02 - - - - - 0.00%
14.11. Pembesian kg 48.43 22,075.00 1,069,092.25 0.03 - - - - - 0.00%
14.12. Bekisting Sloof m2 4.40 145,957.00 642,210.80 0.02 - - - - - 0.00%
5. 14.13. Kolom (12/ 15) Fc 21,70 Mpa m3 0.41 1,517,097.00 622,009.77 0.02 - - - - - 0.00%
14.14. Pembesian kg 124.99 22,075.00 2,759,154.25 0.09 - - - - - 0.00%
14.15. Bekisting Kolom m2 4.75 203,834.00 968,211.50 0.03 - - - - - 0.00%
6. 14.16. Pek. Beton Kolom ( 20/20) Fc 21,70 Mpa m3 0.14 1,517,097.00 212,393.58 0.01 - - - - - 0.00%
14.17. Pembesian kg 17.98 22,075.00 396,908.50 0.01 - - - - - 0.00%
14.18. Bekisting Kolom m2 2.88 203,834.00 587,041.92 0.02 - - - - - 0.00%

Page 13 SMTKN PELITA SEMBAB MANOKWARI


KONTRAK AWAL PROGRES MINGGUAN
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )
a b c d e f=dxe g h i=h/dxg j k=j/dxg l=h+j m=i+k n=m/g
7. 14.19. Balok 12 x 15 Fc 21,70 Mpa m3 0.35 1,517,097.00 530,983.95 0.02 - - - - - 0.00%
14.20. Pembesian kg 68.20 22,075.00 1,505,515.00 0.05 - - - - - 0.00%
14.21. Bekisting Balok m2 5.88 205,278.00 1,207,034.64 0.04 - - - - - 0.00%
8. 14.22. Cor Beton m3 0.43 1,517,097.00 652,351.71 0.02 - - - - - 0.00%

IV PEKERJAAN PASANGAN & PLESTERAN JUMLAH IV 8,799,980.21 0.28 - - - 0.00%


1. 14.23. Pasangan Batu Tela 1 Pc 4 Psr m2 11.60 188,623.00 2,188,026.80 0.07 - - - - - 0.00%
2. 14.24. Plesteran 1 Pc 4 Psr m2 23.21 86,645.00 2,011,030.45 0.06 - - - - - 0.00%
3. 14.25. Plesteran 1 Pc 3 Psr Timbul m2 1.30 88,420.00 114,946.00 0.00 - - - - - 0.00%
4. 14.26. Acian m2 24.51 51,046.00 1,251,137.46 0.04 - - - - - 0.00%
5. 14.27. Cat Dinding Baru m2 24.51 31,450.00 770,839.50 0.02 - - - - - 0.00%
6. 14.28. Beton Precast Mahkota Pilar Uk.120 x 60 bh 2.00 282,000.00 564,000.00 0.02 - - - - - 0.00%
7. 14.29. Beton Precast Casing Kolom Uk. 70 x 70 x 180 bh 2.00 600,000.00 1,200,000.00 0.04 - - - - - 0.00%
8. 14.30. GRC Motif Papua bh 2.00 350,000.00 700,000.00 0.02 - - - - - 0.00%

G PEKERJAAN DINDING PAPAN NAMA (SIGN PAGE)


I PEKERJAAN TANAH JUMLAH I 380,884.00 0.01 - - - 0.00%
1. 15.1. Galian tanah pondasi m3 3.18 99,770.00 317,268.60 0.01 - - - - - 0.00%
2. 15.2. Urugan kembali m3 0.95 46,800.00 44,460.00 0.00 - - - - - 0.00%
3. 15.3. Urugan Pasir Pondasi m3 0.05 383,108.00 19,155.40 0.00 - - - - - 0.00%

II PEKERJAAN PONDASI JUMLAH II 6,697,186.00 0.21 - - - 0.00%


1. 15.4. Pas. Pondasi Rolag Batu Tela 1:4 m2 35.51 188,600.00 6,697,186.00 0.21 - - - - - 0.00%

III PEKERJAAN STRUKTUR BETON JUMLAH III 14,594,149.08 0.46 - - - 0.00%


1. 15.5. Pek. Beton Lantai Kerja ( foot plat ) Fc 14,5 Mpa m3 0.10 1,423,580.00 142,358.00 0.00 - - - - - 0.00%
2. 15.6. Pek. Beton Foot Plat (70x70x20) Fc21,70 Mpa m3 0.39 1,517,097.00 591,667.83 0.02 - - - - - 0.00%
15.7. Pembesian Footplat kg 59.23 22,075.00 1,307,502.25 0.04 - - - - - 0.00%
3. 15.8. Sloof 15 X 20 Fc21,70 Mpa m3 0.30 1,517,097.00 455,129.10 0.01 - - - - - 0.00%
15.9. Pembesian Sloof kg 54.87 22,075.00 1,211,255.25 0.04 - - - - - 0.00%
15.10. Bekisting Sloof m2 4.04 145,957.00 589,666.28 0.02 - - - - - 0.00%
4. 15.11. Pek. Beton Kolom Utama (K1 20/20) Fc21,70 Mpa m3 0.38 1,517,097.00 576,496.86 0.02 - - - - - 0.00%
15.12. Pembesian Kolom kg 47.96 22,075.00 1,058,717.00 0.03 - - - - - 0.00%
15.13. Bekesting Kolom m2 5.76 203,834.00 1,174,083.84 0.04 - - - - - 0.00%
5. 15.14. Pek. Beton Ring Balok (RB 15/15) Fc 21,70 Mpa m3 0.73 1,517,097.00 1,107,480.81 0.03 - - - - - 0.00%
15.15. Pembesian Ring Balok kg 176.30 22,075.00 3,891,822.50 0.12 - - - - - 0.00%
15.16. Bekisting Ring Balok m2 12.12 205,278.00 2,487,969.36 0.08 - - - - - 0.00%

IV PEKERJAAN PASANGAN & PLESTERAN JUMLAH IV 13,762,903.31 0.43 - - - 0.00%


1. 15.17. Pasangan Batu Tela 1 Pc 4 Psr m2 16.60 188,623.00 3,131,141.80 0.10 - - - - - 0.00%
2. 15.18. Plesteran 1 Pc 4 Psr m2 36.43 86,645.00 3,156,477.35 0.10 - - - - - 0.00%
3. 15.19. Acian m2 33.21 51,046.00 1,695,237.66 0.05 - - - - - 0.00%
4. 15.20. Cat Dinding Baru Setara Dulux m2 46.17 31,450.00 1,452,046.50 0.05 - - - - - 0.00%
5. 15.21. Beton Precast Casing Kolom Uk. 70 x 70 x 180 cm Terpasang bh 4.00 600,000.00 2,400,000.00 0.08 - - - - - 0.00%
6. 15.22. Beton Precast Motif Papua Barat Uk. 20 x 46 cm Terpasang bh 4.00 282,000.00 1,128,000.00 0.04 - - - - - 0.00%
7. 15.23. Tulisan Steinlis Papan Nama Komplit bh 1.00 800,000.00 800,000.00 0.03 - - - - - 0.00%

H PEKERJAAN PAGAR
I PEKERJAAN TANAH JUMLAH I 3,647,592.64 0.11 - - - 0.00%
1. 16.1. Galian tanah pondasi m3 29.76 99,770.00 2,969,155.20 0.09 - - - - - 0.00%
2. 16.2. Urugan kembali m3 8.93 46,800.00 417,924.00 0.01 - - - - - 0.00%
3. 16.3. Urugan Pasir Pondasi m3 0.68 383,108.00 260,513.44 0.01 - - - - - 0.00%

Page 14 SMTKN PELITA SEMBAB MANOKWARI


KONTRAK AWAL PROGRES MINGGUAN
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )
a b c d e f=dxe g h i=h/dxg j k=j/dxg l=h+j m=i+k n=m/g
II PEKERJAAN PONDASI JUMLAH II 58,797,936.00 1.84 - - - 0.00%
1. 16.4. Pas. Pondasi Rolag Batu Tela 1:4 m2 311.76 188,600.00 58,797,936.00 1.84 - - - - - 0.00%

III PEKERJAAN STRUKTUR BETON JUMLAH III 72,267,142.62 2.26 - - - 0.00%


1. 16.5. Pek. Beton Lantai Kerja ( foot plat ) Fc 14,5 Mpa m3 0.69 1,423,580.00 982,270.20 0.03 - - - - - 0.00%
2. 16.6. Pek. Beton Foot Plat (70x70x20) Fc21,70 Mpa m3 2.74 1,517,097.00 4,156,845.78 0.13 - - - - - 0.00%
16.7. Pembesian Foot Plat kg 414.62 22,075.00 9,152,736.50 0.29 - - - - - 0.00%
3. 16.8. Sloof 15 X 20 Fc21,70 Mpa m3 2.84 1,517,097.00 4,308,555.48 0.13 - - - - - 0.00%
16.9. Pembesian Sloof kg 519.48 22,075.00 11,467,521.00 0.36 - - - - - 0.00%
16.10. Bekisting Sloof m2 37.80 145,957.00 5,517,174.60 0.17 - - - - - 0.00%
4. 16.11. Pek. Beton Kolom Utama (K1 20/20) Fc21,70 Mpa m3 2.68 1,517,097.00 4,065,819.96 0.13 - - - - - 0.00%
16.12. Pembesian Kolom kg 335.73 22,075.00 7,411,239.75 0.23 - - - - - 0.00%
16.13. Bekisting Kolom m2 40.32 203,834.00 8,218,586.88 0.26 - - - - - 0.00%
5. 16.14. Pek. Beton Ring Balok (RB 12/15) Fc 21,70 Mpa m3 1.36 1,517,097.00 2,063,251.92 0.06 - - - - - 0.00%
16.15. Pembesian Ring Balok kg 412.39 22,075.00 9,103,509.25 0.28 - - - - - 0.00%
16.16. Bekisting Ring Balok m2 28.35 205,278.00 5,819,631.30 0.18 - - - - - 0.00%

IV PEKERJAAN PASANGAN & PLESTERAN JUMLAH IV 81,153,450.05 2.54 - - - 0.00%


1. 16.17. Pasangan Batu Tela 1 Pc 4 Psr m2 95.85 188,623.00 18,079,514.55 0.57 - - - - - 0.00%
2. 16.18. Pek. Plesteran Dinding 1:4 m2 191.70 86,645.00 16,609,846.50 0.52 - - - - - 0.00%
3. 16.19. Acian m2 191.70 51,046.00 9,785,518.20 0.31 - - - - - 0.00%
4. 16.20. Pek. Cat Dinding Weathershield m2 191.70 31,450.00 6,028,965.00 0.19 - - - - - 0.00%
5. 16.21. List Beton Tbl. 10 Cm Fc 14,50 Mpa m3 1.51 1,423,580.00 2,149,605.80 0.07 - - - - - 0.00%
6. 16.22. Kolom Beton Precast Uk. 70 x 180 cm unit 30.00 600,000.00 18,000,000.00 0.56 - - - - - 0.00%
7. 16.23. GRC Motif Papua unit 30.00 350,000.00 10,500,000.00 0.33 - - - - - 0.00%

I PEKERJAAN MENARA AIR


I PEKERJAAN PERSIAPAN JUMLAH I 1,114,608.00 0.03 - - - 0.00%
1. 17.1. Pek. Pemasangan Bowplank m1 16.00 69,663.00 1,114,608.00 0.03 - - - - - 0.00%

II PEKERJAAN TANAH JUMLAH II 361,984.80 0.01 - - - 0.00%


1. 17.2. Pek. Galian Tanah Pondasi m3 2.56 99,770.00 255,411.20 0.01 - - - - - 0.00%
2. 17.3. Pek. Urugan Kembali bekas Galian m3 0.64 46,800.00 29,952.00 0.00 - - - - - 0.00%
3. 17.4. Pek. Urugan Pasir Bawah Pondasi m3 0.20 383,108.00 76,621.60 0.00 - - - - - 0.00%

III PEKERJAAN PONDASI JUMLAH III 242,940.00 0.01 - - - 0.00%


1. 17.5. Pas. Pondasi Rolag Batu Tela 1 Pc 2 Ps m2 1.20 202,450.00 242,940.00 0.01 - - - - - 0.00%

IV PEKERJAAN BETON JUMLAH IV 25,100,530.89 0.79 - - - 0.00%


1. 17.6. Beton Lantai Kerja (foot plat) Fc 14,5 Mpa m3 0.13 1,423,580.00 185,065.40 0.01 - - - - - 0.00%
2. 17.7. Beton Foot Plat 80 x 80 Fc 21,7 Mpa kg 0.61 1,517,097.00 925,429.17 0.03 - - - - - 0.00%
17.8. Pembesian Foot plate m3 144.40 22,075.00 3,187,630.00 0.10 - - - - - 0.00%
17.9. Bekisting Footplate m3 6.40 143,344.00 917,401.60 0.03 - - - - - 0.00%
3. 17.10. Beton Sloof (20/30) Fc 21,7 MPa m3 0.32 1,517,097.00 485,471.04 0.02 - - - - - 0.00%
17.11. Pembesian sloof kg 54.48 22,075.00 1,202,646.00 0.04 - - - - - 0.00%
17.12. Bekisting Sloof m2 3.20 145,957.00 467,062.40 0.01 - - - - - 0.00%
4. 17.13. Beton Kolom Utama (K1 25/20) Fc 21,7 Mpa (SL1) m3 1.19 1,517,097.00 1,805,345.43 0.06 - - - - - 0.00%
17.14. Pembesian Kolom Utama kg 142.41 22,075.00 3,143,700.75 0.10 - - - - - 0.00%
17.15. Bekisting Kolom Utama m2 14.28 203,834.00 2,910,749.52 0.09 - - - - - 0.00%
5. 17.16. Beton Kolom Praktis (K2 15/15) Fc 21,70 Mpa m3 0.06 1,517,097.00 91,025.82 0.00 - - - - - 0.00%
17.17. Pembesian Kolom kg 11.33 22,075.00 250,109.75 0.01 - - - - - 0.00%
17.18. Bekisting Kolom m2 0.84 203,834.00 171,220.56 0.01 - - - - - 0.00%
6. 17.19. Beton Ring Balok (15/15) Fc 21,7 Mpa m2 0.18 1,517,097.00 273,077.46 0.01 - - - - - 0.00%
17.20. Pembesian Ring Balok 1 kg 33.27 22,075.00 734,435.25 0.02 - - - - - 0.00%
17.21. Bekisting Ring Balok 1 m2 2.40 205,278.00 492,667.20 0.02 - - - - - 0.00%

Page 15 SMTKN PELITA SEMBAB MANOKWARI


KONTRAK AWAL PROGRES MINGGUAN
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )
a b c d e f=dxe g h i=h/dxg j k=j/dxg l=h+j m=i+k n=m/g
7. 17.22. Beton Ring Balok (20/20) Fc 21,7 Mpa m3 0.64 1,517,097.00 970,942.08 0.03 - - - - - 0.00%
17.23. Pembesian Ring Balok 2 kg 77.39 22,075.00 1,708,384.25 0.05 - - - - - 0.00%
17.24. Bekisting Ring Balok 2 m2 4.80 205,278.00 985,334.40 0.03 - - - - - 0.00%
8. 17.25. Beton Plat Lantai Fc 21,7 Mpa m3 0.48 1,517,097.00 728,206.56 0.02 - - - - - 0.00%
17.26. Pembesian plat kg 148.43 22,075.00 3,276,592.25 0.10 - - - - - 0.00%
17.27. Bekisting plat m2 0.77 244,200.00 188,034.00 0.01 - - - - - 0.00%

V PEKERJAAN DINDING JUMLAH V 5,354,235.43 0.17 - - - 0.00%


1. 17.28. Pas. Tela 1:4 m2 4.07 188,623.00 767,695.61 0.02 - - - - - 0.00%
2. 17.29. Pek. Plesteran Dinding 1:4 m2 8.14 86,645.00 705,290.30 0.02 - - - - - 0.00%
3. 17.30. Pek Acian Dinding m2 16.28 51,046.00 831,028.88 0.03 - - - - - 0.00%
4. 17.31. Pek Acian Kolom Utama m2 16.64 51,046.00 849,405.44 0.03 - - - - - 0.00%
5. 17.32. Pek. Acian Balok m2 17.60 51,046.00 898,409.60 0.03 - - - - - 0.00%
6. 17.33. Pek. Pengecatan m2 50.52 25,780.00 1,302,405.60 0.04 - - - - - 0.00%

VI PEKERJAAN TANDON JUMLAH VI 4,432,489.00 0.14 - - - 0.00%


1. 17.34. Tandon 1100L bh 1.00 3,225,000.00 3,225,000.00 0.10 - - - - - 0.00%
2. 17.35. Pekerjaan Acian m3 21.50 51,046.00 1,097,489.00 0.03 - - - - - 0.00%
3. 17.36. Saklar Otomatis Tandon bh 1.00 110,000.00 110,000.00 0.00 - - - - - 0.00%

TOTAL REAL COST 3,194,678,513.37 100.00 - 0.07 0.07 0.07%

Manokwari, 03 Juli 2022


Mengetahui : Diperiksa Oleh : Dibuat Oleh :
KOORDINATOR DIREKSI TEKNIS PENYEDIA JASA KONSULTAN MANAJEMEN KONSTRUKSI PENYEDIA JASA KONSTRUKSI
SATKER PELAKSANAAN PRASARANA PERMUKIMAN CV. SIARA KONSULTAN - PT. INDO PAPUA CONSUTANT, KSO. PT. KEMER TIRI EMAS
PROVINSI PAPUA BARAT

MARIANE EMILIA N.T.,ST.,MT. MAKALEBU SAMMA, ST. JHON EDYSON P. S., ST.
NIP. 19881108 202012 2004 Team Leader Project Manager

Page 16 SMTKN PELITA SEMBAB MANOKWARI