II PEKERJAAN STRUKTURAL
Main Struktur
Lantai 1 (Elevasi ±0.00) 2.87 - 1.97 1.97 68.59
Lantai 2 (Elevasi +4.50) 3.00 - 0.86 0.86 28.78
VI PEKERJAAN PLUMBING
Lantai 1 (Elevasi ±0.00) 0.16 - -
Lantai 2 (Elevasi +4.50) 0.16 - -
PROGRESS TIME SCHEDULE 8.24 % TINGKAT PENYELESAIAN SAMPAI MINGGU INI : 12.99 %
PROGRESS REALISASI PEKERJAAN 12.99 % TINGKAT PENYELESAIAN SAMPAI MINGGU LALU : - %
============ ========
PEKERJAAN MENDAHULUI / TERLAMBAT 4.75 % TINGKAT KEMAJUAN PEKERJAAN PER MINGGU : 12.99
MENGETAHUI :
PEJABAT PELAKSANA TEKNIS KEGIATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KAB. BALANGAN
AKHMAD NOVIE, ST
NIP. 19781101 200604 1 008