PEMBERI TUGAS KONSULTAN PENGAWAS NAMA PAKET KEGIATAN KONTRAKTOR

FORM
PEKERJAAN PERBAIKAN
STRUKTUR OFFICE BIU 2 SITE
0 BATU KAJANG
PT. UNITED TRACTORS, TBK PT. KINAYA ASIA ARSITEKTURA PT. YASA PRIMA KONSRUKSI

SUMMARY PROGRESS
PERIODE MINGGU :MINGGU KE - 1 (Satu) S/D MINGGU LALU MINGGU INI S/D MINGGU INI
TANGGAL :17-Jul-23 s/d 23-Jul-23 (%) (%) (%)

NO KONTRAK :SPK/316-P/9972/XII/2022 RENCANA 0,00% 8,22% 8,22%


NO KONTRAK ADDENDUM I :- REALISASI 0,00% 7,77% 7,77%
TANGGAL KONTRAK :16 DESEMBER 2022 DEVIASI 0,00% -0,45% -0,45%
TANGGAL KONTRAK ADDENDUM I :-
WAKTU PELAKSANAAN :120 HARI KALENDER (4 BULAN)

S/D MINGGU LALU MINGGU INI S/D MINGGU INI


NO. URAIAN PEKERJAAN BOBOT (%)
BOBOT (%) BOBOT (%) BOBOT (%)

A PEKERJAAN PERSIAPAN 31,443% 0,00% 6,23% 6,23%


B PEKERJAAN BONGKARAN
I.0 - BONGKAR AREA OFFICE BIU 2 7,903% 0,00% 1,11% 1,11%
II.0 - BONGKAR AREA OFFICE BIU 2 MEP 0,759% 0,00% 0,43% 0,43%
C PEKERJAAN REBUILD OFFICE BIU 2
I.0 - PEKERJAAN CIVIL DAN FINISHING 52,062% 0,00% 0,00% 0,00%
II.0 - PEKERJAAN MEP 7,833% 0,00% 0,00% 0,00%

JUMLAH TOTAL 100,00% 0,00% 7,77% 7,77%

URAIAN BOBOT (%)


REALISASI PROGRESS SAMPAI DENGAN MINGGU LALU 0,00% KETERANGAN :
REALISASI PROGRESS MINGGU INI 7,77% WAKTU PELAKSANAAN = 120 HARI
REALISASI PROGRESS SAMPAI DENGAN MINGGU INI 7,77% WAKTU YANG TERPAKAI = 7 HARI
RENCANA PROGRESS MENURUT TIME SCHEDULE 8,22% SISA WAKTU = 113 HARI
DEVIASI -0,45%

Batu Kajang, 24 Juli 2023

Disetujui oleh : Diperiksa oleh : Diajukan oleh :


Konsultan Pengawas Kontraktor Pelaksana
PT. UNITED TRACTORS PT. KINAYA ASIA ARSITEKTURA PT. YASA PRIMA KONSRUKSI

Mikhael Adi K Kurniawan NB


Spv Sipil Spv / Team Leader