SUMMARY PROGRESS REPORT

PROJECT : PEMBANGUNAN RUMAH GENSET 300 KVA - PORT


PERIODE : AGUSTUS
WEEK : WEEKLY - 01
DATE : 02 AGUSTUS - 08 AUGUST 2021

PLAN PROGRESS ACTUAL PROGRESS


WEIGHT
DEVIASI
NO ITEM PEKERJAAN FACTOR
PREVIOUS THIS PERIOD CUMM. PREVIOUS THIS PERIOD CUMM. (%)
(%)
(%) (%) (%) (%) (%) (%)

A PEKERJAAN PERSIAPAN 9.45% 0.00% 3.78% 3.78% 0.00% 3.78% 3.78% 0.00%
B PEKERJAAN PONDASI BATU KALI 4.09% 0.00% 0.00% 0.00% 0.00% 0.25% 0.25% 0.25%
C PEKERJAAN SLAB, SLOOF, KOLOM DAN RING BALOK 5.41% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
D PEKERJAAN DINDING 10.76% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
E PEKERJAAN ATAP DAN KAWAT HARMONIKA 36.40% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
F PEKERJAAN ELEKTRIKAL 0.0195 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
G PEKERJAAN LAIN-LAIN 0.1944 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
H Internal IN Inspection & Remedy work 5.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
I Owner Inspection & Remedy work 5.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
J HAND OVER 2.50% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

TOTAL 100.00% 0.0000% 3.7817% 3.7817% 0.0000% 4.0286% 4.0286% 0.2469%

KALTENG, 08 AGUSTUS 2021


Diajukan oleh : Disetujui oleh :
PT. BINTANG GLOBAL SERVICE PT. MULTI TAMBANGJAYA UTAMA
DETAIL PROGRESS REPORT
PROJECT : PEMBANGUNAN RUMAH GENSET 300 KVA - PORT
PERIODE : AGUSTUS
WEEK : WEEKLY - 01
DATE : 02 AGUSTUS - 08 AUGUST 2021

PLAN PROGRESS ACTUAL PROGRESS

NO DESCRIPTION SATUAN QUANTITY BOBOT DEVIASI


(%) (%)
PREVIOUS THIS PERIOD CUMM. PREVIOUS THIS PERIOD CUMM.
(%) (%) (%) (%) (%) (%)

A PEKERJAAN PERSIAPAN 9.4542% 0.0000% 3.7817% 3.7817% 0.0000% 3.7817% 3.7817% 0.0000%
1 Mobilisasi/Demobilisasi LS 1.0 2.8363% 0.0000% 2.8363% 2.8363% 0.0000% 2.8363% 2.8363% 0.0000%
2 Safety (APD, MCU & Dok. HIRA-JSEA) LS 1.0 0.9454% 0.0000% 0.9454% 0.9454% 0.0000% 0.9454% 0.9454% 0.0000%
3 Staking Out, Bouwplank & Pembersihan Lokasi M2 34.6 5.6725% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
B PEKERJAAN PONDASI BATU KALI 4.0882% 0.0000% 0.0000% 0.0000% 0.0000% 0.2469% 0.2469% 0.2469%
1 Pekerjaan Galian Pondasi M3 14.3 0.6132% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan Pondasi Batu Kali M3 7.7 0.6132% 0.0000% 0.0000% 0.0000% 0.0000% 0.2469% 0.2469% 0.2469%
3 Pekerjaan Pasir Pasang T=50 mm M3 1.2 0.8176% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Lantai Kerja T=50 mm M3 1.2 1.0221% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
5 Pekerjaan Urugan Tanah Dipadatkan M3 14.3 1.0221% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
C PEKERJAAN SLAB, SLOOF, KOLOM DAN RING BALOK 5.4082% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
1 Pekerjaan Slab T=150 mm, K-225, Tul. Ø12-150 2 Lapis Finish Aci Kasar M3 2.1 0.5408% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan Sloof 150x150, K-175, Tul. 4Ø8 Sengkang Ø6-150 M3 1.1 0.8112% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pekerjaan Kolom 150x150, K-175 dan Penebalan, Tul. 4Ø8 Sengkang Ø6-150 M3 1.3 1.3520% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Ringbalk 150x150, K-175, Tul. 4Ø8 Sengkang Ø6-150 M3 1.1 1.6224% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
5 Pekerjaan Slab Selasar T=60 mm 1pc:2ps:3kr M3 1.0 1.0816% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
D PEKERJAAN DINDING 10.7562% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
1 Pekerjaan Dinding Batako M2 64.7 5.3781% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan Plester Dinding + Aci M2 129.3 2.1512% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pengecatan Dinding Dalam Ex. Avitex Interior include dinding luar Fuel Tank M2 79.1 1.6134% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pengecatan Dinding Luar Ex. Avitex Exterior include dinding luar Fuel Tank M2 79.1 1.6134% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
E PEKERJAAN ATAP DAN KAWAT HARMONIKA 36.4003% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
1 Pekerjaan Atap Ex. Soka Jempol T=0.22mm M2 107.9 9.1001% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan Nok Spandek M1 11.3 3.6400% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pekerjaan Sopi-sopi Ex. Soka Jempol T=0.22mm M2 11.0 3.6400% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Rangka Atap Baja Ringan Ex. TASO Include Kolom M2 107.9 14.5601% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
5 Pekerjaan Kawat Harmonika M2 13.4 5.4600% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
F PEKERJAAN ELEKTRIKAL 1.9517% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
1 Pekerjaan Pemasangan Lampu Essential 18 W Ex. Philips + Fitting Bh 3.0 0.0976% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan Pemasangan Double Switch 16A Ex. Lokal Bh 1.0 0.1952% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pekerjaan Pemasangan Stop Kontak 16A, 220V Ex. Lokal Bh 1.0 0.1952% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Instalasi Lampu dengan cable NYA 2x1.5 mm2 dalam pipa conduit 20mm2 Ttk 3.0 0.2927% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
5 Pekerjaan Instalasi stop kontak dengan 2x1.5 mm2 dalam pipa conduit 20mm2 Ttk 1.0 0.2927% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
6 Pekerjaan Instalasi Double Switch dengan 2x1.5 mm2 dalam pipa conduit 20mm2 Ttk 1.0 0.3903% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
7 Pentanahan Bangunan Standard PUIL Ls 1.0 0.3903% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
8 Pekerjaan Pemasangan Box MCB 8 Group Ex. Hager Out Bow Set 1.0 0.0976% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
G PEKERJAAN LAIN-LAIN 19.4413% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
1 Pekerjaan Pembongkaran Rumah Genset Existing M2 34.6 4.8603% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
2 Pekerjaan Demarkasi Lantai Ex. Epodur M2 34.6 0.9721% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
3 Pekerjaan Box Kontrol Uk. 40x 40 cm Include Tutup Plat T=3 mm Bh 2.0 1.9441% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
4 Pekerjaan Saluran Oli Uk. 10x10 cm M1 8.2 1.9441% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
5 Pekerjaan Sparing Pipa AW 4" M1 4.5 0.9721% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
6 Pekerjaan Tranch Kabel M1 5.9 0.9721% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
7 Pekerjaan Pembuatan Pintu Besi Plat Baja Tebal 2 mm, Rangka Baja Siku L50.50.5 Include Kusen CNP100.50.5.7,5 M2 10.0 0.9721% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
8 Pekerjaan Bobok Lantai Rumah Pompa Existing M2 8.6 1.9441% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
9 Cerobong Asap (Muffler) Pipa Besi Hitam 4" Bh 2.0 1.9441% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
10 Pekerjaan Cerobong : Tangga Inspeksi Pipa Galvanis 2" Bh 2.0 0.9721% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
11 Pekerjaan Cerobong : Tempat Berdiri Material Siku 40.40.3 + Plat Besi=3mm Ls 2.0 0.9721% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
12 Pekerjaan Cerobong : Titik Sampling Uk. 3" Ls 2.0 0.9721% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
H Internal IN Inspection & Remedy work Ls 1.0 5.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
I Owner Inspection & Remedy work Ls 1.0 5.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%
Re-owner inspection
J HAND OVER Ls 1.0 2.5000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000% 0.0000%

TOTAL 100% 0.0000% 3.7817% 3.7817% 0.0000% 4.0286% 4.0286% 0.2469%

KALTENG, 08 AGUSTUS 2021


Diajukan oleh : Disetujui oleh :
PT. BINTANG GLOBAL SERVICE PT. MULTI TAMBANGJAYA UTAMA
S-CURVE
PEMBANGUNAN RUMAH GENSET 300 KVA- PORT
PROJECT : PEMBANGUNAN RUMAH GENSET 300 KVA - PORT
PERIOD : AGUSTUS
WEEK : WEEKLY - 01
DATE : 02 AGUSTUS - 08 AUGUST 2021
1 2 3
MONTH AUG 2021 SEP 2021 OCT 2021
BOBOT WEEK W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13
NO DESCRIPTION (%) Percentage

DATE 02-Agus - 09-Agus - 16-Agus - 23-Agus - 30-Agus - 06-Sept - 13-Sept - 20-Sept - 27-Sept - 04-Okt - 11-Okt - 18-Okt - 25-Okt -
08-Agus 15-Agus 22-Agus 29-Agus 05-Sept 12-Sept 19-Sept 26-Sept 03-Okt 10-Okt 17-Okt 24-Okt 31-Okt

A PEKERJAAN PERSIAPAN 9.45% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
1 Mobilisasi/Demobilisasi 2.84% 0.0284 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 100%
97.500%
2 Safety (APD, MCU & Dok. HIRA-JSEA) 0.95% 0.0095 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
3 Staking Out, Bouwplank & Pembersihan Lokasi 5.67% 0.0000 0.0567 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
B PEKERJAAN PONDASI BATU KALI 4.09% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
1 Pekerjaan Galian Pondasi 0.61% 0.0000 0.0000 0.0061 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
2 Pekerjaan Pondasi Batu Kali 0.61% 0.0000 0.0000 0.0061 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
3 Pekerjaan Pasir Pasang T=50 mm 0.82% 0.0000 0.0000 0.0082 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.000087.500% 0.0000 0.0000
4 Pekerjaan Lantai Kerja T=50 mm 1.02% 0.0000 0.0000 0.0102 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
5 Pekerjaan Urugan Tanah Dipadatkan 1.02% 0.0000 0.0000 0.0102 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
C PEKERJAAN SLAB, SLOOF, KOLOM DAN RING BALOK 5.41% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
1 Pekerjaan Slab T=150 mm, K-225, Tul. Ø12-150 2 Lapis Finish Aci Kasar 0.54% 0.0000 0.0000 0.0000 0.0054 0.0000 0.0000 0.0000 0.0000 0.0000 79.723%
0.0000 0.0000 0.0000 0.0000
80%
2 Pekerjaan Sloof 150x150, K-175, Tul. 4Ø8 Sengkang Ø6-150 0.81% 0.0000 0.0000 0.0000 0.0081 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
3 Pekerjaan Kolom 150x150, K-175 dan Penebalan, Tul. 4Ø8 Sengkang Ø6-150 1.35% 0.0000 0.0000 0.0000 0.0135 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
4 Pekerjaan Ringbalk 150x150, K-175, Tul. 4Ø8 Sengkang Ø6-150 1.62% 0.0000 0.0000 0.0000 0.0162 0.0000 0.0000 0.0000 0.0000 0.0000
72.919%
0.0000 0.0000 0.0000 0.0000
5 Pekerjaan Slab Selasar T=60 mm 1pc:2ps:3kr 1.08% 0.0000 0.0000 0.0000 0.0108 0.0000 0.0000 0.0000 0.0000
71.065%
0.0000 0.0000 0.0000 0.0000 0.0000
D PEKERJAAN DINDING 10.76% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
1 Pekerjaan Dinding Batako 5.38% 0.0000 0.0000 0.0000 0.0000 0.0538 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
2 Pekerjaan Plester Dinding + Aci 2.15% 0.0000 0.0000 0.0000 0.0000 0.0215 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
3 Pengecatan Dinding Dalam Ex. Avitex Interior include dinding luar Fuel Tank 1.61% 0.0000 0.0000 0.0000 0.0000 0.0161 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
4 Pengecatan Dinding Luar Ex. Avitex Exterior include dinding luar Fuel Tank 1.61% 0.0000 0.0000 0.0000 0.0000 0.0161 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
E PEKERJAAN ATAP DAN KAWAT HARMONIKA 36.40% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
60%
1 Pekerjaan Atap Ex. Soka Jempol T=0.22mm 9.10% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0910 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
2 Pekerjaan Nok Spandek 3.64% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0364 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
3 Pekerjaan Sopi-sopi Ex. Soka Jempol T=0.22mm 3.64% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0364 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
4 Pekerjaan Rangka Atap Baja Ringan Ex. TASO Include Kolom 14.56% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.1456 0.0000 0.0000 0.0000 0.0000 0.0000
50.947%
5 Pekerjaan Kawat Harmonika 5.46% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0546 0.0000 0.0000 0.0000 0.0000 0.0000
F PEKERJAAN ELEKTRIKAL 1.95% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
47.307%
1 Pekerjaan Pemasangan Lampu Essential 18 W Ex. Philips + Fitting 0.10% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0010 0.0000 0.0000 0.0000 0.0000 0.0000
2 Pekerjaan Pemasangan Double Switch 16A Ex. Lokal 0.20% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0020 0.0000 0.0000 0.0000 0.0000
3 Pekerjaan Pemasangan Stop Kontak 16A, 220V Ex. Lokal 0.20% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0020 0.0000 0.0000 0.0000 0.0000
4 Pekerjaan Instalasi Lampu dengan cable NYA 2x1.5 mm2 dalam pipa conduit 20mm2 0.29% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0029 0.0000 0.0000 0.0000 0.0000
5 Pekerjaan Instalasi stop kontak dengan 2x1.5 mm2 dalam pipa conduit 20mm2 0.29% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0029 0.0000 0.0000 0.0000 0.0000 40%

6 Pekerjaan Instalasi Double Switch dengan 2x1.5 mm2 dalam pipa conduit 20mm2 0.39% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0039 0.0000 0.0000 0.0000 0.0000
7 Pentanahan Bangunan Standard PUIL 0.39% 0.0000 0.0000 0.0000 0.0000 0.0000
34.567% 0.0000 0.0000 0.0000 0.0039 0.0000 0.0000 0.0000 0.0000
8 Pekerjaan Pemasangan Box MCB 8 Group Ex. Hager Out Bow 0.10% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0010 0.0000 0.0000 0.0000 0.0000
G PEKERJAAN LAIN-LAIN 19.44% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
1 Pekerjaan Pembongkaran Rumah Genset Existing 4.86% 0.0000 0.0000 0.0000 0.0000 0.0486 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
2 Pekerjaan Demarkasi Lantai Ex. Epodur 0.97% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0097 0.0000 0.0000 0.0000
3 Pekerjaan Box Kontrol Uk. 40x 40 cm Include Tutup Plat T=3 mm 1.94% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0194 0.0000 0.0000 0.0000
4 Pekerjaan Saluran Oli Uk. 10x10 cm 1.94% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0194 0.0000 0.0000 0.0000
5 Pekerjaan Sparing Pipa AW 4" 0.97% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0097 0.0000 0.0000 0.0000
6 Pekerjaan Tranch Kabel 0.97% 0.0000 0.0000 0.0000 0.0000
18.951% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0097 0.0000 0.0000 0.0000
20%

7 Pekerjaan Pembuatan Pintu Besi Plat Baja Tebal 2 mm, Rangka Baja Siku L50.50.5 Include Kusen CNP100.50.5.7,5 0.97% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0097 0.0000 0.0000

8 Pekerjaan Bobok Lantai Rumah Pompa Existing 1.94% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0194 0.0000 0.0000
13.542%
9 Cerobong Asap (Muffler) Pipa Besi Hitam 4" 1.94% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0194 0.0000 0.0000
10 Pekerjaan Cerobong : Tangga Inspeksi Pipa Galvanis 2" 0.97% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0097 0.0000 0.0000
9.454%
11 Pekerjaan Cerobong : Tempat Berdiri Material Siku 40.40.3 + Plat Besi=3mm 0.97% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0097 0.0000 0.0000
12 Pekerjaan Cerobong : Titik Sampling Uk. 3" 0.97% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0097 0.0000 0.0000
H Internal IN Inspection & Remedy work 5.00% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0500 0.0000
3.782%
I Owner Inspection & Remedy work 5.00% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0500 0.0000
Re-owner inspection 4.029%
0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
0.000%
J HAND OVER 2.50% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0250 0%
0.000%

LEGEND : 100.00%
PLANNING 0.000% 3.782% 5.673% 4.088% 5.408% 15.617% 12.740% 3.640% 20.118% 1.854% 6.804% 7.777% 10.000% 2.500%
ACCUMULATION PLANNING 0.000% 3.782% 9.454% 13.542% 18.951% 34.567% 47.307% 50.947% 71.065% 72.919% 79.723% 87.500% 97.500% 100.000%
ACTUAL 0.000% 4.029%
ACCUMULATION ACTUAL 0.000% 4.029%
DEVIATION ( + AHEAD / - DELAY ) 0.247%

KALTENG, 08 AGUSTUS 2021


Diajukan oleh : Disetujui oleh :
PT. BINTANG GLOBAL SERVICE PT. MULTI TAMBANGJAYA UTAMA
DOKUMENTASI PROYEK

PROJECT : PEMBANGUNAN RUMAH GENSET 300 KVA - PORT


PERIODE : AGUSTUS
WEEK : WEEKLY - 01

DATE : 02 AGUSTUS - 08 AUGUST 2021

NO AREA KERJA DATE DOKUMENTASI DESCRIPTION

- ON SITE - MATERIAL BATU SPLIT 1 RATE (4 M3)


1 PORT 6-Aug-21
- ON SITE - MATERIAL BATU GUNUNG 1 RATE (6 M3)

2 PORT 7-Aug-21
- ON SITE - MATERIAL BATU GUNUNG 1 RATE (6 M3)