BANGUNAN WAREHOUSE UNIT , WAREHOUSE PART DAN FASILITAS PENUNJANG, CANDI - SEMARANG

ASTRA MOTOR - REGION SEMARANG


PT. ASTRA INTERNATIONAL Tbk - HONDA SALES OPERATION
PERIODE : 13 JUNI 2022 S/D 19 JUNI 2022
PROGRESS
NO URAIAN PEKERJAAN WEIGHT SISA BOBOT
LAST MONTH THIS MONTH UP TO THIS MONTH
PROGRRES S/D
Performance Performance Performance
(%) From (%) From (%) From (%) 12 JUNI 2022
(%) (%) (%)

REKAPITULASI TOTAL PEKERJAAN SIPIL, ARSITEKTUR DAN MEP

I PERSIAPAN 1,67% 100,00% 1,67% 0,00% 0,00% 100,00% 1,67% 0,00%


II PEMATANGAN LAHAN 3,29% 100,00% 3,29% 0,00% 0,00% 100,00% 3,29% 0,00%
III BANGUNAN WAREHOUSE UNIT
- PEKERJAAN STRUKTUR 28,10% 95,00% 26,70% 0,05% 0,01% 95,05% 26,71% 1,39%
- PEKERJAAN ARSITEKTUR 4,88% 80,49% 3,93% 1,05% 0,05% 81,54% 3,98% 0,90%
IV BANGUNAN WAREHOUSE PART
- PEKERJAAN STRUKTUR 22,08% 97,34% 21,49% 0,39% 0,09% 97,73% 21,58% 0,50%
- PEKERJAAN ARSITEKTUR 6,03% 48,02% 2,89% 0,84% 0,05% 48,86% 2,94% 3,08%
V BANGUNAN BALAI BENGONG
- PEKERJAAN STRUKTUR 1,34% 99,69% 1,34% 0,28% 0,00% 99,97% 1,34% 0,00%
- PEKERJAAN ARSITEKTUR 1,68% 88,49% 1,48% 2,60% 0,04% 91,08% 1,53% 0,15%
VI BANGUNAN POWERHOUSE DAN GROUNDTANK
- PEKERJAAN STRUKTUR 0,84% 100,00% 0,84% 0,00% 0,00% 100,00% 0,84% 0,00%
- PEKERJAAN ARSITEKTUR 0,41% 80,28% 0,33% 1,40% 0,01% 81,68% 0,33% 0,07%
VII BANGUNAN PARKIRAN MOTOR
- PEKERJAAN STRUKTUR 0,60% 89,52% 0,53% 10,41% 0,06% 99,92% 0,60% 0,00%
VIII PEKERJAAN LUAR 18,41% 94,93% 17,48% 0,04% 0,01% 94,98% 17,49% 0,92%
IX PEKERJAAN MEP
- PEKERJAAN SERTIFIKASI DAN PERIJINAN 0,29% 36,91% 0,11% 0,00% 0,00% 36,91% 0,11% 0,18%
- PEKERJAAN PLUMBING 1,35% 71,76% 0,97% 3,57% 0,05% 75,34% 1,02% 0,33%
- PEKERJAAN PEMADAM KEBAKARAN 3,00% 73,72% 2,21% 2,74% 0,08% 76,46% 2,29% 0,71%
- PEKERJAAN TATA UDARA 0,16% 79,03% 0,13% 4,22% 0,01% 83,25% 0,13% 0,03%
- PEKERJAAN ELEKTRIKAL DAN ELEKTRONIK 5,89% 69,00% 4,06% 6,55% 0,39% 75,55% 4,45% 1,44%

100,00% 89,44% 0,85% 90,29% 9,71%