BANGUNAN WAREHOUSE UNIT , WAREHOUSE PART DAN FASILITAS PENUNJANG, CANDI - SEMARANG
ASTRA MOTOR - REGION SEMARANG
PT. ASTRA INTERNATIONAL Tbk - HONDA SALES OPERATION PERIODE : 13 JUNI 2022 S/D 19 JUNI 2022 PROGRESS NO URAIAN PEKERJAAN WEIGHT SISA BOBOT LAST MONTH THIS MONTH UP TO THIS MONTH PROGRRES S/D Performance Performance Performance (%) From (%) From (%) From (%) 12 JUNI 2022 (%) (%) (%)
REKAPITULASI TOTAL PEKERJAAN SIPIL, ARSITEKTUR DAN MEP
I PERSIAPAN 1,67% 100,00% 1,67% 0,00% 0,00% 100,00% 1,67% 0,00%
II PEMATANGAN LAHAN 3,29% 100,00% 3,29% 0,00% 0,00% 100,00% 3,29% 0,00% III BANGUNAN WAREHOUSE UNIT - PEKERJAAN STRUKTUR 28,10% 95,00% 26,70% 0,05% 0,01% 95,05% 26,71% 1,39% - PEKERJAAN ARSITEKTUR 4,88% 80,49% 3,93% 1,05% 0,05% 81,54% 3,98% 0,90% IV BANGUNAN WAREHOUSE PART - PEKERJAAN STRUKTUR 22,08% 97,34% 21,49% 0,39% 0,09% 97,73% 21,58% 0,50% - PEKERJAAN ARSITEKTUR 6,03% 48,02% 2,89% 0,84% 0,05% 48,86% 2,94% 3,08% V BANGUNAN BALAI BENGONG - PEKERJAAN STRUKTUR 1,34% 99,69% 1,34% 0,28% 0,00% 99,97% 1,34% 0,00% - PEKERJAAN ARSITEKTUR 1,68% 88,49% 1,48% 2,60% 0,04% 91,08% 1,53% 0,15% VI BANGUNAN POWERHOUSE DAN GROUNDTANK - PEKERJAAN STRUKTUR 0,84% 100,00% 0,84% 0,00% 0,00% 100,00% 0,84% 0,00% - PEKERJAAN ARSITEKTUR 0,41% 80,28% 0,33% 1,40% 0,01% 81,68% 0,33% 0,07% VII BANGUNAN PARKIRAN MOTOR - PEKERJAAN STRUKTUR 0,60% 89,52% 0,53% 10,41% 0,06% 99,92% 0,60% 0,00% VIII PEKERJAAN LUAR 18,41% 94,93% 17,48% 0,04% 0,01% 94,98% 17,49% 0,92% IX PEKERJAAN MEP - PEKERJAAN SERTIFIKASI DAN PERIJINAN 0,29% 36,91% 0,11% 0,00% 0,00% 36,91% 0,11% 0,18% - PEKERJAAN PLUMBING 1,35% 71,76% 0,97% 3,57% 0,05% 75,34% 1,02% 0,33% - PEKERJAAN PEMADAM KEBAKARAN 3,00% 73,72% 2,21% 2,74% 0,08% 76,46% 2,29% 0,71% - PEKERJAAN TATA UDARA 0,16% 79,03% 0,13% 4,22% 0,01% 83,25% 0,13% 0,03% - PEKERJAAN ELEKTRIKAL DAN ELEKTRONIK 5,89% 69,00% 4,06% 6,55% 0,39% 75,55% 4,45% 1,44%