RENCANA JADWAL PELAKSANAAN

NAMA KEGIATAN : BIAYA REHABILITASI GEDUNG LINGKUP PUSKESMAS ALASA (DAK AFIRMASI TAHUN 2017)

TAHUN 2017 ( 120 HARI KALENDER )


HARGA BOBOT
NO JENIS PEKERJAAN BULAN I BULAN II BULAN III BULAN IV
( Rp ) % I II III IV I II III IV I II III IV I II III IV

1 PEK. PERSIAPAN 2,363,739.72 0.37% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%

2 PEK. BONGKARAN DAN SISIPAN 20,627,383.49 3.25% 0.20% 0.20% 0.20% 0.20% 0.20% 0.20% 0.20% 0.20% 0.20% 0.20% 0.20% 0.20% 0.20% 0.20% 0.20% 0.20%

3 PEK. TANAH / URUGAN 2,639,579.22 0.42% 0.08% 0.08% 0.08% 0.08% 0.08%

4 PEK. BETON, BATU, PLESTERAN 41,502,717.34 6.53% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59%

5 PEK. KERAMIK 49,597,531.32 7.81% 1.56% 1.56% 1.56% 1.56% 1.56%

6 PEK.  KAYU 8,557,912.40 1.35% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19%

7 PEK.  ATAP 81,953,286.27 12.90% 2.15% 2.15% 2.15% 2.15% 2.15% 2.15%

8 PEK.  PLAFOND 103,188,440.00 16.24% 2.32% 2.32% 2.32% 2.32% 2.32% 2.32% 2.32%

9 PEK.  DAUN PINTU KAMAR MANDI 8,000,000.00 1.26% 1.26%

10 PEK.  KUNCI DAN ASSESSORIS 45,959,904.55 7.23% 2.41% 2.41% 2.41%

11 PEK. PENGECATAN 102,000,879.80 16.06% 2.01% 2.01% 2.01% 2.01% 2.01% 2.01% 2.01% 2.01%

12 PEK. ELEKTRIKAL 42,178,035.00 6.64% 2.21% 2.21% 2.21%

13 PEK. SANITARI / PLUMBING 109,642,384.48 17.26% 2.47% 2.47% 2.47% 2.47% 2.47% 2.47% 2.47%

14 PEK. BESI PABRIKASI 17,056,801.45 2.68% 2.68%

TOTAL 635,268,595.04 100%

RENCANA KEMAJUAN PEKERJAAN / MINGGU 0.226% 0.309% 0.903% 1.096% 3.246% 4.807% 5.983% 11.517% 11.517% 13.929% 12.238% 14.923% 9.826% 7.019% 2.233% 0.226%

RENCANA KEMAJUAN PEKERJAAN KOMULATIF 0.226% 0.535% 1.439% 2.534% 5.780% 10.587% 16.571% 28.088% 39.605% 53.534% 65.772% 80.695% 90.521% 97.541% 99.774% 100.000%

DEVIASI

Lotu, …………………….2017
Dibuat oleh
CV. DEVERIAN CONSULTANT

BETLEHEM KARO KARO, ST


Team Leader
DINAS KESEHATAN
PEMERINTAH KABUPATEN NIAS UTARA

ENGINEERING ESTIMATE

: PEKERJAAN

BIAYA REHABILITASI GEDUNG LINGKUP PUSKESMAS


ALASA
) DAK AFIRMASI TAHUN 2017 (

: KONSULTAN PERENCANA

REHAB RUMAH DINAS TYPE 50 2 (DUA) UNIT


REKAPITULASI

Kegiatan :
PENGADAAN SARANA DAN PRASARANA PUSKESMAS
DINAS KESEHATAN KABUPATEN NIAS UTARA
SUMBER DANA : DAK
Pekerjaan :
BIAYA REHABILITASI GEDUNG LINGKUP PUSKESMAS ALASA (DAK AFIRMASI TAHUN 2017)

SUB.JUMLAH
NO. JENIS PEKERJAAN KETERANGAN
(Rp.)
1 2 3 4

1 A. PEK. PERSIAPAN 2,363,739.72


2 B.  PEK. BONGKARAN DAN SISIPAN 20,627,383.49
3 C.  PEK. TANAH / URUGAN 2,639,579.22
4 D. PEK. BETON, BATU, PLESTERAN 41,502,717.34
5 E. PEK. KERAMIK 49,597,531.32
6 F. PEK.  KAYU 8,557,912.40
7 G.  PEK.  ATAP 81,953,286.27
8 H. PEK.  PLAFOND 103,188,440.00
9 I. PEK.  DAUN PINTU KAMAR MANDI 8,000,000.00
10 J. PEK.  KUNCI DAN ASSESSORIS 45,959,904.55
11 K. PEK. PENGECATAN 102,000,879.80
12 L. PEK. ELEKTRIKAL 42,178,035.00
13 M. PEK. SANITARI / PLUMBING 109,642,384.48
14 N. PEK. BESI PABRIKASI 17,056,801.45

NILAI FISIK Rp. 635,268,595.04


IURAN JAMSOSTEK Rp. 1,204,545.45
PAJAK PERTAMBAHAN NILAI (PPN) 10 % Rp. 63,526,859.50
JUMLAH KESELURUHAN Rp. 700,000,000.00
PEMBULATAN Rp. 700,000,000.00

Terbilang : Tujuh Ratus Juta Rupiah

Lotu, …………………….2017
Dibuat oleh
CV. DEVERIAN CONSULTANT

BETLEHEM KARO KARO, ST SYAHRUL, ST


Team Leader Ahli Estimasi Biaya

Disetujui oleh Diperiksa oleh


PEJABAT PEMBUAT KOMITMEN ( PPK ) DIREKSI PEKERJAAN

YUNIMAN NAZARA WARISMAN ZENDRATO, ST


PENATA Tk. I PENATA
NIP. 19680604 198903 01 001 NIP. 19830621 201001 1 041

Diketahui oleh
KEPALA DINAS KESEHATAN
KABUPATEN NIAS UTARA
SELAKU PENGGUNA ANGGARAN

BERITANI GEA, S.Si,Apt


PEMBINA Tk.I
NIP. 19680713 200502 1001
RENCANA ANGGARAN BIAYA

Kegiatan :
PENGADAAN SARANA DAN PRASARANA PUSKESMAS
DINAS KESEHATAN KABUPATEN NIAS UTARA
SUMBER DANA : DAK
Pekerjaan :
BIAYA REHABILITASI GEDUNG LINGKUP PUSKESMAS ALASA (DAK AFIRMASI TAHUN 2017)

H. SATUAN JUMLAH HARGA


No. JENIS PEKERJAAN ANALISA VOLUME SATUAN
Rp. Rp.
1 2 3 4 5 6 7
A. PEK. PERSIAPAN
1 Pemasangan Bowplank dan pengukuran Ls 1.00 Ls 1,063,739.72 1,063,739.72
2 Foto dokumentasi & pelaporan Ls 1.00 Ls 800,000.00 800,000.00
3 Papan Pengenal Proyek Ls 1.00 Ls 500,000.00 500,000.00
Sub Jumlah A 2,363,739.72
B.  PEK. BONGKARAN DAN SISIPAN
1 Bongkaran Atap Gedung A Puskesmas + Atap Selasar Al.Tambahan 8 603.48 M2 6,435.00 3,883,393.80
2 Bongkaran Plafond Gedung A, Gedung B, Gedung C dan di Gedung D (R. Al.Tambahan 8 489.06 M2 6,435.00 3,147,101.10
Aula Terbuka)

3 Bongkaran Rangka Atap Teras Gedung A Al.Tambahan 9 54.96 M2 10,642.50 584,911.80


4 Bongkaran Rangka Plafond Gedung A, B, C dan D Al.Tambahan 9 489.06 M2 10,642.00 5,204,576.52
5 Bongkaran Lisplank Puskesmas Al. Tambahan 14 290.06 M' 2,970.00 861,478.20
6 Bongkaran keramik Lantai, dan keramik Dinding di Ruangan Al.Tambahan 5 25.55 M2 11,385.00 290,886.75
7 Bongkaran keramik Lantai uk. 20x20cm, dan keramik Dinding Al.Tambahan 5 39.76 M2 11,385.00 452,667.60
Uk.25x25cm di Kamar mandi
8 Bongkaran Dinding di Ruangan IGD Rehab Al.Tambahan 4 3.60 M2 212,850.00 766,260.00
9 Bongkaran Plesteran Dinding Jalur Instalasi Listrik Al.Tambahan 7 19.09 M2 5,321.00 101,577.89
10 Bongkaran Plesteran Jalur Dinding yang retak / patah di Lingkup Al.Tambahan 7 673.26 M2 5,321.00 3,582,416.46
Puskesmas
11 Bongkaran Kusen Pintu dan Kusen Jendela Al.Tambahan 10 1.05 M3 154,577.00 162,305.85
12 Bongkaran Daun Pintu dan Daun Jendela Al.Tambahan 11 26.59 M2 2,128.00 56,583.52
13 Bongkaran Septictank yang lama di R. Inap dan di buang Al.Tambahan 6 1.40 M3 1,095,160.00 1,533,224.00
Sub Jumlah B 20,627,383.49
C.  PEK. TANAH / URUGAN
1 Galian Tanah Pondasi selasar R. Inap dan Selasar Belakang Puskesmas A.2.3.1.1 8.50 M3 77,962.00 662,677.00
2 Pek. Pasir urug di bawah lantai selasar A.2.3.1.11 1.22 M3 335,921.00 409,823.62
3 Timbunan Sirtu  padat untuk peninggian lantai selasar belakang A.2.3.1.14 3.82 M3 410,230.00 1,567,078.60
puskesmas
Sub Jumlah C 2,639,579.22
D. PEK. BETON, BATU, PLESTERAN
1 Pengecoran beton mutu K-100 atau camp. 1 : 4 : 4.5 di Belakang Lantai A.4.1.1.4 3.15 M3 1,230,254.00 3,875,300.10
Luar Puskesamas dan selasar R. Inap dan Lantai cor Parit
2 Pasangan dinding bata merah camp 1 : 4, untuk menutup Ventilasi A.4.4.1.9 8.04 M2 238,790.00 1,919,871.60
atas Puskesmas dan Lubang Ventilasi R. IGD, Gudang Obat, R. Bersalin,
R. Poli KIA/KB , R. Poli Umum, R. Poli Gigi dan R. Laboratorium

3 Pasangan dinding bata merah camp 1 : 4, untuk rehab Puskesmas A.4.4.1.9 5.00 M2 238,790.00 1,193,950.00
4 Pasangan batu belah camp 1 : 4, untuk selasar belakang Puskesmas A.3.2.1.2 7.22 M3 1,204,238.00 8,694,598.36
dan Pas. Parit batu belah di Pondasi selasar R. Inap

5 Plesteran Dinding yang Direhab , Pondasi selasar , pasanga parit yang A.4.4.2.4 52.70 M2 77,761.00 4,098,004.70
terlihat serta Kanopi Puskesmas dan R. Inap
7 Plesteran Kembali Bongkaran Dinding Jalur Instalasi Listrik A.4.4.2.4 19.09 M2 77,761.00 1,484,457.49
8 Plesteran Jalur Dinding yang retak / patah Lingkup Puskesmas Al. Tambahan 12 673.26 M' 18,559.70 12,495,503.62
9 Acian Dinding yang Direhab , Pondasi selasar yang terlihat di R. Inap A.4.4.2.27 87.12 M2 43,504.00 3,790,068.48
dan atas teras Plat beton Puskesmas dan R. Inap
10 Acian Kembali Bongkaran Dinding Jalur Instalasi Listrik A.4.4.2.27 19.09 M2 43,504.00 830,491.36
11 Acian Jalur Dinding yang retak / patah lingkup Puskesmas Al. Tambahan 13 673.26 M' 4,350.00 2,928,681.00
12 Pek. Beton bertulang :
a. Balok Latei 13 x 15 cm, Sisip di Ruang IGD
Beton cor K-125 atau camp. 1 : 3 : 3.6 A.4.1.1.2 0.03 M3 1,365,198.00 40,955.94
Pembesian A.4.1.1.17 5.93 KG 16,618.80 98,549.48
Bekisting A.4.1.1.21 0.51 M2 102,520.00 52,285.20
Sub Jumlah D 41,502,717.34
E. PEK. KERAMIK
1 Pasangan keramik 20 x 25 pada dinding Kamar Mandi dan dinding Al.Tambahan 1 16.52 M2 267,475.00 4,418,687.00
Rehab Ruangan IGD
2 Pasangan keramik lantai dalam kamar mandi 20 x 20 A.4.4.3.36 23.24 M2 279,125.00 6,486,865.00
H. SATUAN JUMLAH HARGA
No. JENIS PEKERJAAN ANALISA VOLUME SATUAN
Rp. Rp.
1 2 3 4 5 6 7
3 Pasangan keramik 30 x 30 pada selasar Ruang Inap dan Keramik Al.Tambahan 2 55.84 M2 283,421.00 15,826,228.64
Lantai sisipan di lingkup Puskesmas
4 Pasangan keramik 40 x 40 pada Dinding, R. Bersalin, R. Poli KIA/KB , Al.Tambahan 3 115.66 M2 197,698.00 22,865,750.68
R. Poli Umum, R. Poli Gigi dan R. Laboratorium, Tinggi = 2,00 M'
Sub Jumlah E 49,597,531.32
H. SATUAN JUMLAH HARGA
No. JENIS PEKERJAAN ANALISA VOLUME SATUAN
Rp. Rp.
1 2 3 4 5 6 7
F. PEK.  KAYU
1 Menyediakan & mengerjakan kusen pintu, jendela dari kayu kelas I A.4.6.1.2 0.40 M3 8,711,948.00 3,484,779.20
(simalambuo) jenis keras diketam rapi
2 Menyediakan & mengerjakan daun pintu panel, Jendela dan daun A.4.6.1.5 6.80 M2 746,049.00 5,073,133.20
ventilasi dari kayu kelas I (simalambuo) jenis keras diketam rapi
Sub Jumlah F 8,557,912.40
G.  PEK.  ATAP
1 Pekerjaan Rangka +Penutup atap Genteng Metal t = 0.30 mm, Untuk Ditaksir 85.06 M2 225,000.00 19,138,500.00
Teras Selasar Gedung A (Puskemas)
2 Pekerjaan Penutup atap Genteng Metal t = 0.30 mm, untuk Gedung Al.03-3436-1994-33 518.40 M2 106,870.00 55,401,408.00
Puskesmas
3 Pekerjaan Penutup atap Genteng Metal t = 0.30 mm, untuk sisipan Ditaksir 10.00 Lbr 66,198.16 661,981.60
gedung Lingkup Puskesmas
4 Pekerjaan Listplank GRC 8 x 200 mm Gedung A, B, C dan D Ditaksir 334.78 M' 20,166.67 6,751,396.67
Sub Jumlah G 81,953,286.27
H. PEK.  PLAFOND
1 Pekerjaan Rangka + Plafond Gipsum Tbl= 9 mm Gedung A, B, C dan D Ditaksir 554.88 M2 133,000.00 73,799,040.00
2 Pekerjaan Rangka + Plafond PVC (Sunda Plafond) Tbl= 6 mm Sisi Luar Ditaksir 127.78 M2 230,000.00 29,389,400.00
selasar Puskesmas atas
Sub Jumlah H 103,188,440.00
I. PEK.  DAUN PINTU KAMAR MANDI
1 Menyediakan & memasang daun pintu Aluminium + accessories Ditaksir 8.00 Set 1,000,000.00 8,000,000.00
Sub Jumlah I 8,000,000.00
J. PEK.  KUNCI DAN ASSESSORIS
1 Engsel Uk. 4" (Pintu) Ditaksir 141.00 Bh 82,500.00 11,632,500.00
2 Engsel Uk. 3" (Jendela) Ditaksir 190.00 Bh 68,200.00 12,958,000.00
3 Grendel Pintu 12" (Pintu Ganda sisi Atas). Untuk P2 Ditaksir 11.00 Bh 67,500.00 742,500.00
4 Grendel Pintu 6" (Pintu Ganda sisi Bawah). Untuk P2 Ditaksir 11.00 Bh 33,750.00 371,250.00
5 Grendel Kodok (Jendela+ Ventilasi ). Ditaksir 95.00 Bh 23,700.00 2,251,500.00
6 Hak Angin Jendela Ditaksir 190.00 Bh 28,500.00 5,415,000.00
7 Kunci Tanam Biasa Ditaksir 36.00 Bh 200,400.00 7,214,400.00
8 Kaca Buram t= 5 mm untuk Daun Pintu Ditaksir 3.42 M2 267,201.32 913,828.51
9 Kaca Polos/bening t= 5 mm Jendela (60 x 134 cm) Ditaksir 5.63 M2 133,600.66 752,171.72
10 Kaca Buram t= 5 mm Jendela Ditaksir 12.34 M2 267,201.32 3,297,264.29
11 Kaca Buram t= 5 mm Ventilasi (V1)+(V3) Ditaksir 1.54 M2 267,201.32 411,490.03
Sub Jumlah J 45,959,904.55
K. PEK. PENGECATAN
1 Pengecatan dinding dan kolom Gedung A, B , C dan Pelataran Parkir A.4.7.1.10 2,547.89 M2 26,870.00 68,461,804.30
2 Pengecatan plafond Gedung A, B dan C A.4.7.1.10 710.71 M2 26,870.00 19,096,777.70
3 Pengecatan listplank A, B dan C A.4.7.1.5 60.36 M2 54,960.00 3,317,385.60
4 Pengecatan Plat beton Atas Teras depan (Aquaprooff) Al. Tambahan 15 34.40 M2 35,808.00 1,231,795.20
5 Pengecatan kusen, dan daun pintu, daun jendela yang diganti A.4.7.1.5 292.30 M2 26,870.00 7,854,101.00
6 Pengecatan Anti Maling Jendela, Pintu dan Ventilasi yang Lama A.4.7.1.5 37.10 M2 54,960.00 2,039,016.00
Sub Jumlah K 102,000,879.80
L. PEK. ELEKTRIKAL
1 Menyediakan & memasang lampu LED 12 Watt + Fitting Ditaksir 8.00 Set 114,150.00 913,200.00
2 Menyediakan & memasang lampu LED 16 Watt + Fitting Ditaksir 32.00 Set 126,750.00 4,056,000.00
3 Menyediakan & memasang lampu LED 20 Watt + Fitting Ditaksir 58.00 Set 178,200.00 10,335,600.00
4 Menyediakan & memasang saklar tanam tunggal Ditaksir 79.00 Set 37,965.00 2,999,235.00
5 Menyediakan & memasang stop kontak tanam Ditaksir 58.00 Set 33,000.00 1,914,000.00
6 Menyediakan & memasang kabel listrik NYM 2 x 2.5 mm Ditaksir 900.00 M' 8,000.00 7,200,000.00
7 Menyediakan & memasang pipa konduit listrik + persambungan Ditaksir 900.00 M' 6,000.00 5,400,000.00
antara cabang
8 Biaya pemasangan instalasi titik api Ditaksir 156.00 Ttk 60,000.00 9,360,000.00
Sub Jumlah L 42,178,035.00
M. PEK. SANITARI / PLUMBING
1 Menyediakan & memasang pipa dia.1/2" (air bersih) Besi Ditaksir 195.80 M' 33,800.00 6,618,040.00
2 Menyediakan & memasang Pipa pembuangan dari wastafel Pipa PVC Ditaksir 84.40 M' 32,500.00 2,743,000.00
dia.2"
3 Menyediakan & memasang Pipa pembuangan dari Plat beton Pipa PVC Ditaksir 22.60 M' 73,000.00 1,649,800.00
dia. 2" Gedung Puskesmas dan Parkir
4 Menyediakan & memasang closet jongkok Ditaksir 8.00 Set 285,574.00 2,284,592.00
5 Menyediakan & memasang pipa dia.3" (air kotor) kamar mandi PVC Ditaksir 26.40 M' 73,000.00 1,927,200.00
6 Menyediakan & memasang pipa dia.4" (air tinja) PVC Ditaksir 94.45 M' 89,500.00 8,453,275.00
7 Menyediakan & memasang kran air .1/2" (air bersih) besi Ditaksir 8.00 Bh 26,468.75 211,750.00
8 Menyediakan & memasang kran angsa .1/2" (air bersih) Ditaksir 8.00 Bh 100,500.00 804,000.00
9 Menyediakan & memasang kran duduk wastafel .1/2" (air bersih) Ditaksir 5.00 Bh 105,875.00 529,375.00
H. SATUAN JUMLAH HARGA
No. JENIS PEKERJAAN ANALISA VOLUME SATUAN
Rp. Rp.
1 2 3 4 5 6 7
10 Menyediakan & memasang Stop kran .1/2" (air bersih) Ditaksir 1.00 Bh 78,000.00 78,000.00
H. SATUAN JUMLAH HARGA
No. JENIS PEKERJAAN ANALISA VOLUME SATUAN
Rp. Rp.
1 2 3 4 5 6 7
11 Menyediakan & memasang wastafel keramik + sifon. Ditaksir 5.00 Bh 550,000.00 2,750,000.00
12 Menyediakan Bak air Fiberglas Ditaksir 8.00 Bh 608,781.25 4,870,250.00
13 Menyediakan & memasang floor drain Ditaksir 8.00 Set 85,000.00 680,000.00
14 Menyediakan & memasang talang tegak pipa PVC dia.3" Ditaksir 131.90 M' 73,000.00 9,628,700.00
15 Menyediakan & Memasang Klem pipa dia. 3" Ditaksir 75.00 Bh 25,500.00 1,912,500.00
16 Menyediakan & memasang talang datar Plat segi 4, Uk. 8 x 17 x 16 Ditaksir 232.26 M' 95,000.00 22,064,700.00
17 Menyediakan & memasang penggantung talang datar Ditaksir 332.00 Bh 25,000.00 8,300,000.00
18 Pekerjaan Water Tank
a. Galian tanah pondasi A.2.3.1.1 1.66 M3 77,962.00 129,416.92
b. Pasangan pondasi batu belah camp. 1:4 A.3.2.1.2 2.77 M3 1,204,238.00 3,335,739.26
c. Timbunan tanah kembali A.2.3.1.9 0.12 M3 56,925.00 6,831.00
d. Timbunan tanah di bawah lantai A.2.3.1.14.a 0.55 M3 310,497.00 170,773.35
e. Pasir Urug dibawah lantai A.2.3.1.11 0.04 M3 335,921.00 13,436.84
f. Watertank beton bertulang
- Beton cor K-175 atau camp. 1 : 2.3 : 3.1 A.4.1.1.5 1.03 M3 1,458,412.00 1,502,164.36
- Pembesian A.4.1.1.17 208.03 KG 16,618.80 3,457,208.96
- Bekisting A.4.1.1.21 16.84 M2 102,520.00 1,726,436.80
g. Plasteran bidang yang terlihat A.4.4.2.4 4.70 M2 77,761.00 365,476.70
h. Acian bidang yang terlihat A.4.4.2.27 14.78 M2 43,504.00 642,989.12
i. Pengecatan bidang yang terlihat A.4.7.1.10 14.78 M2 26,870.00 397,138.60
j. Pintu Besi Penutup Watertank Ditaksir 1.00 Set 250,000.00 250,000.00
19 Pekerjaan Septictank (3 Unit)
a. Galian tanah A.2.3.1.1 11.75 M3 77,962.00 916,053.50
b. Pengecoran beton mutu K-100 lantai atau camp. 1 : 4 : 4.5 A.4.1.1.4 0.98 M3 1,230,254.00 1,205,648.92
c. Pasangan dinding bata merah camp 1 : 3 A.4.4.1.20 27.98 M2 374,674.00 10,483,378.52
d. Plasteran dinding camp. 1 : 3 A.4.4.2.3 29.25 M2 80,663.00 2,359,392.75
e. Acian bidang yang terlihat A.4.4.2.27 29.25 M2 43,504.00 1,272,492.00
f. Beton bertulang t = 10 cm :
- Beton cor K-175 (plat penutup) atau camp. 1 : 2.3 : 3.1 A.4.1.1.5 1.00 M3 1,458,412.00 1,458,412.00
- Pembesian A.4.1.1.17 129.85 KG 16,618.80 2,157,951.18
- Bekisting A.4.1.1.24 8.71 M2 145,320.00 1,265,737.20
g. Menyediakan & memasang pipa besi hawa dia.2" Ditaksir 3.00 Bh 35,000.00 105,000.00
20 Pekerjaan Peresapan ( 3 Unit)
a Galian tanah A.2.3.1.1 3.00 M3 77,962.00 233,886.00
b Lapisan pasir A.2.3.1.11 0.80 M3 335,921.00 268,736.80
c. Lapisan kerikil A.2.3.1.14 0.45 M3 410,230.00 184,603.50
d. Lapisan ijuk Ditaksir 1.20 KG 35,000.00 42,000.00
e Timbunan tanah A.2.3.1.14.a 0.60 M3 310,497.00 186,298.20
Sub Jumlah M 109,642,384.48
N. PEK. BESI PABRIKASI
1 Pek. Pabrikasi Pintu Besi :
1.1 Pintu Besi (PB2) uk. 160 x 216 ( 2 Unit ) Sesuaikan dengan Kusen
a. Mendatangkan Harga Bahan 126.06 KG 15,953.46 2,011,093.17
b. Memotong dan Merakit A.4.2.1.3 126.06 KG 137.00 17,270.22
c. Pengelasan A.4.2.1.5 1,664.00 CM 1,375.00 2,288,000.00
d. Pengecatan A.4.7.1.5 8.78 M2 54,960.00 482,548.80
1.2 Pintu Besi (P1B2)uk. 140 x 216 (1 Unit ) Sesuaikan dengan Kusen
a. Mendatangkan Harga Bahan 57.62 KG 15,953.46 919,238.37
b. Memotong dan Merakit A.4.2.1.3 57.62 KG 137.00 7,893.94
c. Pengelasan A.4.2.1.5 832.00 CM 1,375.00 1,144,000.00
d. Pengecatan A.4.7.1.5 4.010 M2 54,960.00 220,389.60
1.3 Pintu Besi (PB1) uk. 80 x 216 (4 Unit ) Sesuaikan dengan Kusen
a. Mendatangkan Harga Bahan 126.05 KG 15,953.46 2,010,933.63
b. Memotong dan Merakit A.4.2.1.3 126.05 KG 137.00 17,268.85
c. Pengelasan A.4.2.1.5 1,664.00 CM 1,375.00 2,288,000.00
d. Pengecatan A.4.7.1.5 8.78 M2 54,960.00 482,548.80
H. SATUAN JUMLAH HARGA
No. JENIS PEKERJAAN ANALISA VOLUME SATUAN
Rp. Rp.
1 2 3 4 5 6 7
2 Pek. Pabrikasi Anti Maling Jendela :
2.1 Anti Maling Jendela Type JB 1 (58x132 cm) (3 Unit)
a. Mendatangkan Harga Bahan 38.98 KG 15,953.46 621,865.87
b. Memotong dan Merakit A.4.2.1.3 38.98 KG 137.00 5,340.26
c. Pengelasan A.4.2.1.5 192.00 CM 1,375.00 264,000.00
d. Pengecatan A.4.7.1.5 1.90 M2 54,960.00 104,424.00
2.2 Anti Maling Jendela Type JB 1 (60x132 cm) (6 Unit)
a. Mendatangkan Harga Bahan 78.62 KG 15,953.46 1,254,261.03
b. Memotong dan Merakit A.4.2.1.3 78.62 KG 137.00 10,770.94
c. Pengelasan A.4.2.1.5 384.00 CM 1,375.00 528,000.00
d. Pengecatan A.4.7.1.5 3.86 M2 54,960.00 212,145.60
2.3 Anti Maling Jendela Type J4B 1 (60x182 cm) (4 Unit)
a. Mendatangkan Harga Bahan 90.82 KG 15,953.46 1,448,893.24
b. Memotong dan Merakit A.4.2.1.3 90.82 KG 137.00 12,442.34
c. Pengelasan A.4.2.1.5 336.00 CM 1,375.00 462,000.00
d. Pengecatan A.4.7.1.5 4.43 M2 54,960.00 243,472.80
Sub Jumlah N 17,056,801.45
NILAI FISIK Rp. 635,268,595.04
IURAN JAMSOSTEK Rp. 1,204,545.45
PAJAK PERTAMBAHAN NILAI (PPN) 10 % Rp. 63,526,859.50
JUMLAH KESELURUHAN Rp. 700,000,000.00
PEMBULATAN Rp. 700,000,000.00

Terbilang : Tujuh Ratus Juta Rupiah

Lotu, …………………….2017
Dibuat oleh
CV. DEVERIAN CONSULTANT

BETLEHEM KARO KARO, ST SYAHRUL, ST


Team Leader Ahli Estimasi Biaya
DAFTAR ANALISA HARGA SATUAN PEKERJAAN (SNI)

Kegiatan :
PENGADAAN SARANA DAN PRASARANA PUSKESMAS
DINAS KESEHATAN KABUPATEN NIAS UTARA
SUMBER DANA : DAK
Pekerjaan :

BIAYA REHABILITASI GEDUNG LINGKUP PUSKESMAS ALASA (DAK AFIRMASI TAHUN 2017)

ANALISA PEKERJAAN TANAH (A.2.3.1)

A.2.3.1.1
Menggali 1 m3 tanah biasa sedalam 1 meter
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Pekerja OH 0.750 Rp 99,000.00 Rp 74,250.00
Tenaga kerja
Mandor OH 0.025 Rp 148,500.00 Rp 3,712.50
Jumlah Harga / Satuan Pekerjaan Rp 77,962.50
Dibulatkan Rp 77,962.00

A.2.3.1.9
Mengurug kembali 1 m3 galian dihitung dari 1/3 kali dari indeks pekerjaan galian
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Pekerja OH 0.500 Rp 99,000.00 Rp 49,500.00
Tenaga kerja
Mandor OH 0.050 Rp 148,500.00 Rp 7,425.00
Jumlah Harga / Satuan Pekerjaan Rp 56,925.00
Dibulatkan Rp 56,925.00

A.2.3.1.11
Mengurug 1 m3 pasir urug
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Bahan Pasir urug m 3
1.200 Rp 253,946.80 Rp 304,736.16
Pekerja OH 0.300 Rp 99,000.00 Rp 29,700.00
Tenaga kerja
Mandor OH 0.010 Rp 148,500.00 Rp 1,485.00
Jumlah Harga / Satuan Pekerjaan Rp 335,921.16
Dibulatkan Rp 335,921.00

A.2.3.1.14.a
Mengurug 1 m3 Tanah timbunan untuk peninggian lantai bangunan
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Bahan Bukho m 3
1.200 Rp 235,029.00 Rp 282,034.80
Pekerja OH 0.250 Rp 99,000.00 Rp 24,750.00
Tenaga kerja
Mandor OH 0.025 Rp 148,500.00 Rp 3,712.50
Jumlah Harga / Satuan Pekerjaan Rp 310,497.30
Dibulatkan Rp 310,497.00

A.2.3.1.14.b
Mengurug 1 m3 Tanah timbunan (Upah dibayarkan)
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Pekerja OH 0.250 Rp 99,000.00 Rp 24,750.00
Tenaga kerja
Mandor OH 0.025 Rp 148,500.00 Rp 3,712.50
Jumlah Harga / Satuan Pekerjaan Rp 28,462.50
Dibulatkan Rp 28,462.00

Page 10 of 35
A.2.3.1.14
Mengurug 1 m3 sirtu padat untuk peninggian lantai bangunan
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Bahan Sirtu m 3
1.200 Rp 318,139.80 Rp 381,767.76
Pekerja OH 0.250 Rp 99,000.00 Rp 24,750.00
Tenaga kerja
Mandor OH 0.025 Rp 148,500.00 Rp 3,712.50
Jumlah Harga / Satuan Pekerjaan Rp 410,230.26
Dibulatkan Rp 410,230.00

Page 11 of 35
ANALISA PEKERJAAN BETON (A.4.1.1)

A.4.1.1.4
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Semen kg 230.000 Rp 2,149.06 Rp 494,283.80
Bahan Pasir beton kg 893.000 Rp 287.54 Rp 256,769.27
Krikil sungai disaring Uk. 0,5 - 2 cm kg 1,027.000 Rp 312.58 Rp 321,021.03
Pekerja OH 1.200 Rp 99,000.00 Rp 118,800.00
Tukang batu OH 0.200 Rp 137,500.00 Rp 27,500.00
Tenaga kerja
Kepala tukang OH 0.020 Rp 148,500.00 Rp 2,970.00
Mandor OH 0.060 Rp 148,500.00 Rp 8,910.00
Jumlah Harga / Satuan Pekerjaan Rp 1,230,254.09
Dibulatkan Rp 1,230,254.00

A.4.1.1.2
Membuat 1 m3 beton mutu f’c = 9,8 MPa (K 125), slump (12 2) cm, w/c = 0,78
±

Harga Satuan Bahan / Jumlah


Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Semen kg 276.000 Rp 2,149.06 Rp 593,140.56
Bahan Pasir beton kg 828.000 Rp 287.54 Rp 238,079.45
Krikil sungai disaring Uk. 0,5 - 2 cm kg 1,012.000 Rp 312.58 Rp 316,332.31
Pekerja OH 1.650 Rp 99,000.00 Rp 163,350.00
Tukang batu OH 0.275 Rp 137,500.00 Rp 37,812.50
Tenaga kerja
Kepala tukang OH 0.028 Rp 148,500.00 Rp 4,158.00
Mandor OH 0.083 Rp 148,500.00 Rp 12,325.50
Jumlah Harga / Satuan Pekerjaan Rp 1,365,198.32
Dibulatkan Rp 1,365,198.00

A.4.1.1.5
Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), slump (12 2) cm, w/c = 0,66
±

Harga Satuan Bahan / Jumlah


Kebutuhan Indeks Upah (Rp.) (Rp.)
Satuan
Semen kg 326.000 Rp 2,149.06 Rp 700,593.56
Bahan Pasir beton kg 760.000 Rp 287.54 Rp 218,527.03
Krikil sungai disaring Uk. 0,5 - 2 cm kg 1,029.000 Rp 312.58 Rp 321,646.19
Pekerja OH 1.650 Rp 99,000.00 Rp 163,350.00
Tukang batu OH 0.275 Rp 137,500.00 Rp 37,812.50
Tenaga kerja
Kepala tukang OH 0.028 Rp 148,500.00 Rp 4,158.00
Mandor OH 0.083 Rp 148,500.00 Rp 12,325.50
Jumlah Harga / Satuan Pekerjaan Rp 1,458,412.79
Dibulatkan Rp 1,458,412.00

A.4.1.1.17
Pembesian 10 kg dengan besi polos atau besi ulir
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Besi beton (polos/ulir) kg 10.500 Rp 13,699.56 Rp 143,845.38
Bahan
Kawat beton kg 0.150 Rp 27,698.16 Rp 4,154.72
Pekerja OH 0.070 Rp 99,000.00 Rp 6,930.00
Tukang besi OH 0.070 Rp 137,500.00 Rp 9,625.00
Tenaga kerja
Kepala tukang OH 0.007 Rp 148,500.00 Rp 1,039.50
Mandor OH 0.004 Rp 148,500.00 Rp 594.00
Jumlah Harga / Satuan Pekerjaan Rp 166,188.60
Dibulatkan Rp 166,188.00

A.4.1.1.20
Page 12 of 35
Memasang 1 m2 bekisting untuk pondasi ( 2 x Pakai )
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Kayu Sembarang m3 ### Rp 2,307,580.00 Rp 92,303.20
Bahan
Paku biasa Uk. 1" s/d 4" kg ### Rp 20,823.16 Rp 6,246.95
Pekerja OH ### Rp 99,000.00 Rp 51,480.00
Tukang kayu OH ### Rp 137,500.00 Rp 35,750.00
Tenaga kerja
Kepala tukang OH ### Rp 148,500.00 Rp 3,861.00
Mandor OH ### Rp 148,500.00 Rp 3,861.00
Jumlah Harga / Satuan Pekerjaan Rp 193,502.15
2 X Pakai Rp 96,751.07
Dibulatkan Rp 96,751.00

Page 13 of 35
A.4.1.1.21
Memasang 1 m2 bekisting untuk sloof ( 2 x Pakai )
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Kayu Sembarang m 3
### Rp 2,307,580.00 Rp 103,841.10
Bahan
Paku biasa Uk. 1" s/d 4" kg ### Rp 20,823.16 Rp 6,246.95
Pekerja OH ### Rp 99,000.00 Rp 51,480.00
Tukang kayu OH ### Rp 137,500.00 Rp 35,750.00
Tenaga kerja
Kepala tukang OH ### Rp 148,500.00 Rp 3,861.00
Mandor OH ### Rp 148,500.00 Rp 3,861.00
Jumlah Harga / Satuan Pekerjaan Rp 205,040.05
2 X Pakai Rp 102,520.02
Dibulatkan Rp 102,520.00

A.4.1.1.22
Memasang 1 m2 bekisting untuk kolom ( 2 x Pakai )
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Papan Kayu sembarang m3
### Rp 2,307,580.00 Rp 92,303.20
Paku biasa Uk. 1" s/d 4" kg ### Rp 20,823.16 Rp 8,329.26
Bahan
Balok kayu sembarang m3 ### Rp 2,307,580.00 Rp 34,613.70
Kayu sokong Batang 2.000 Rp 5,813.24 Rp 11,626.49
Pekerja OH ### Rp 99,000.00 Rp 65,340.00
Tukang kayu OH ### Rp 137,500.00 Rp 45,375.00
Tenaga kerja
Kepala tukang OH ### Rp 148,500.00 Rp 4,900.50
Mandor OH ### Rp 148,500.00 Rp 4,900.50
Jumlah Harga / Satuan Pekerjaan Rp 267,388.65
2 X Pakai Rp 133,694.33
Dibulatkan Rp 133,694.00

A.4.1.1.23
Memasang 1 m2 bekisting untuk balok ( 2 x Pakai )
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Papan Kayu sembarang m3 ### Rp 2,307,580.00 Rp 92,303.20
Paku biasa Uk. 1" s/d 4" kg ### Rp 20,823.16 Rp 8,329.26
Bahan
Balok kayu sembarang m3 ### Rp 2,307,580.00 Rp 41,536.44
Kayu sokong Batang 2.000 Rp 5,813.24 Rp 11,626.49
Pekerja OH ### Rp 99,000.00 Rp 65,340.00
Tukang kayu OH ### Rp 137,500.00 Rp 45,375.00
Tenaga kerja
Kepala tukang OH ### Rp 148,500.00 Rp 4,900.50
Mandor OH ### Rp 148,500.00 Rp 4,900.50
Jumlah Harga / Satuan Pekerjaan Rp 274,311.39
2 X Pakai Rp 137,155.70
Dibulatkan Rp 137,155.00

A.4.1.1.24
Memasang 1 m2 bekisting untuk lantai ( 2 x Pakai )
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Kayu Sembarang m3 ### Rp 2,307,580.00 Rp 92,303.20
Paku biasa Uk. 1" s/d 4" kg ### Rp 20,823.16 Rp 8,329.26
Bahan
Balok kayu sembarang m3 ### Rp 2,307,580.00 Rp 34,613.70
Kayu sokong 6.000 Rp 5,813.24 Rp 34,879.46
Pekerja OH ### Rp 99,000.00 Rp 65,340.00
Tukang kayu OH ### Rp 137,500.00 Rp 45,375.00
Tenaga kerja
Kepala tukang OH ### Rp 148,500.00 Rp 4,900.50
Mandor OH ### Rp 148,500.00 Rp 4,900.50
Page 14 of 35
Jumlah Harga / Satuan Pekerjaan Rp 290,641.63
2 X Pakai Rp 145,320.81
Dibulatkan Rp 145,320.00

Catt : Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Bukling factor pasir = 20 %

Page 15 of 35
ANALISA PEKERJAAN PONDASI (A.3.2.1)

A.3.2.1.9
Memasang 1 m3 batu kosong (aanstamping)
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)

Batu belah uk. 10 -15 cm m 3


1.200 Rp 310,549.80 Rp 372,659.76
Bahan
Pasir urug m3 0.432 Rp 253,946.80 Rp 109,705.02
Pekerja OH 0.780 Rp 99,000.00 Rp 77,220.00
Tukang batu OH 0.390 Rp 137,500.00 Rp 53,625.00
Tenaga kerja
Kepala tukang OH 0.039 Rp 148,500.00 Rp 5,791.50
Mandor OH 0.039 Rp 148,500.00 Rp 5,791.50
Jumlah Harga / Satuan Pekerjaan Rp 624,792.78
Dibulatkan Rp 624,792.00

A.3.2.1.2
Memasang 1 m3 pondasi batu belah, campuran 1 PC : 4 PP
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Batu belah uk. 10 -15 cm m3
1.200 Rp 310,549.80 Rp 372,659.76
Bahan Semen kg 163.000 Rp 2,149.06 Rp 350,296.78
Pasir Pasang m3 0.520 Rp 398,812.30 Rp 207,382.40
Pekerja OH 1.500 Rp 99,000.00 Rp 148,500.00
Tukang batu OH 0.750 Rp 137,500.00 Rp 103,125.00
Tenaga kerja
Kepala tukang OH 0.075 Rp 148,500.00 Rp 11,137.50
Mandor OH 0.075 Rp 148,500.00 Rp 11,137.50
Jumlah Harga / Satuan Pekerjaan Rp 1,204,238.94
Dibulatkan Rp 1,204,238.00

ANALISA PEKERJAAN BESI DAN ALUMINIUM (A.4.2.1)

A.4.2.1.3
Mengerjakan 100 kg besi profil memotong dan perakitan
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Tenaga Kerja Tukang besi OH 0.100 Rp 137,500.00 Rp 13,750.00
Jumlah Harga / Satuan Pekerjaan Rp 13,750.00
Jumlah Harga / Kg Rp 137.50
Dibulatkan Rp 137.00

A.4.2.1.5
Mengerjakan 10 cm pengelasan dengan las listrik
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Bahan Kawat las listrik kg 0.400 Rp 27,500.00 Rp 11,000.00
Tenaga Kerja Tukang besi OH 0.020 Rp 137,500.00 Rp 2,750.00
Jumlah Harga / Satuan Pekerjaan Rp 13,750.00
Jumlah Harga / Cm Rp 1,375.00
Dibulatkan Rp 1,375.00

ANALISA PEKERJAAN DINDING (A.4.4.1)

A.4.4.1.20
Memasang 1 m2 dinding HB 10, campuran spesi 1 PC : 3 PP (Bata merah)
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)

Page 16 of 35
Bata Merah Buah 70.000 Rp 2,139.50 Rp 149,765.00
Bahan Portland Cement kg 15.160 Rp 2,149.06 Rp 32,579.75
Pasir Pasang m3 0.364 Rp 398,812.30 Rp 145,167.68
Pekerja OH 0.300 Rp 99,000.00 Rp 29,700.00
Tukang batu OH 0.100 Rp 137,500.00 Rp 13,750.00
Tenaga kerja
Kepala tukang OH 0.010 Rp 148,500.00 Rp 1,485.00
Mandor OH 0.015 Rp 148,500.00 Rp 2,227.50
Jumlah Harga / Satuan Pekerjaan Rp 374,674.93
Dibulatkan Rp 374,674.00

Page 17 of 35
A.4.4.1.9
Memasang 1 m2 dinding bata merah tebal 1/2 bata, campuran spesi 1 PC : 4 PP
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Bata Merah Buah 70.000 Rp 2,139.50 Rp 149,765.00
Bahan Portland Cement kg 11.500 Rp 2,149.06 Rp 24,714.19
Pasir Pasang m3 0.043 Rp 398,812.30 Rp 17,148.93
Pekerja OH 0.300 Rp 99,000.00 Rp 29,700.00
Tukang batu OH 0.100 Rp 137,500.00 Rp 13,750.00
Tenaga kerja
Kepala tukang OH 0.010 Rp 148,500.00 Rp 1,485.00
Mandor OH 0.015 Rp 148,500.00 Rp 2,227.50
Jumlah Harga / Satuan Pekerjaan Rp 238,790.62
Dibulatkan Rp 238,790.00

ANALISA PEKERJAAN PLESTERAN (A.4.4.2)

A.4.4.2.27
Memasang 1 m2 acian
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Bahan Semen kg 3.250 Rp 2,149.06 Rp 6,984.45
Pekerja OH 0.200 Rp 99,000.00 Rp 19,800.00
Tukang batu OH 0.100 Rp 137,500.00 Rp 13,750.00
Tenaga kerja
Kepala tukang OH 0.010 Rp 148,500.00 Rp 1,485.00
Mandor OH 0.010 Rp 148,500.00 Rp 1,485.00
Jumlah Harga / Satuan Pekerjaan Rp 43,504.45
Dibulatkan Rp 43,504.00

A.4.4.2.3
Memasang 1 m2 plesteran 1 PC : 3 PP, tebal 15 mm
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)

Portland Cement kg 7.776 Rp 2,149.06 Rp 16,711.09


Bahan
Pasir Pasang m3 0.023 Rp 398,812.30 Rp 9,172.68
Pekerja OH 0.300 Rp 99,000.00 Rp 29,700.00
Tukang batu OH 0.150 Rp 137,500.00 Rp 20,625.00
Tenaga kerja
Kepala tukang OH 0.015 Rp 148,500.00 Rp 2,227.50
Mandor OH 0.015 Rp 148,500.00 Rp 2,227.50
Jumlah Harga / Satuan Pekerjaan Rp 80,663.77
Dibulatkan Rp 80,663.00

A.4.4.2.4
Memasang 1 m2 plesteran 1 PC : 4 PP, tebal 15 mm
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)

Semen kg 6.240 Rp 2,149.06 Rp 13,410.13


Bahan
Pasir Pasang m3 0.024 Rp 398,812.30 Rp 9,571.50
Pekerja OH 0.300 Rp 99,000.00 Rp 29,700.00
Tukang batu OH 0.150 Rp 137,500.00 Rp 20,625.00
Tenaga kerja
Kepala tukang OH 0.015 Rp 148,500.00 Rp 2,227.50
Mandor OH 0.015 Rp 148,500.00 Rp 2,227.50
Jumlah Harga / Satuan Pekerjaan Rp 77,761.63
Dibulatkan Rp 77,761.00

ANALISA PEKERJAAN PENUTUP LANTAI DAN DINDING (A.4.4.3)

A.4.4.3.36
Memasang 1 m2 lantai keramik ukuran (20 x 20) cm
Page 18 of 35
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Keramik Buah 26.500 Rp 3,857.93 Rp 102,235.05
Portland Cement kg 10.400 Rp 2,149.06 Rp 22,350.22
Bahan
Pasir Pasang m3 0.045 Rp 398,812.30 Rp 17,946.55
Semen warna kg 1.620 Rp 5,415.70 Rp 8,773.43
Pekerja OH 0.700 Rp 99,000.00 Rp 69,300.00
Tukang batu OH 0.350 Rp 137,500.00 Rp 48,125.00
Tenaga kerja
Kepala tukang OH 0.035 Rp 148,500.00 Rp 5,197.50
Mandor OH 0.035 Rp 148,500.00 Rp 5,197.50
Jumlah Harga / Satuan Pekerjaan Rp 279,125.26
Dibulatkan Rp 279,125.00

Page 19 of 35
Al.Tambahan 1
Memasang 1 m2 dinding keramik ukuran (20 x 25) cm
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Keramik Buah 21.500 Rp 4,616.16 Rp 99,247.40
Portland Cement kg 10.400 Rp 2,149.06 Rp 22,350.22
Bahan
Pasir Pasang m3 0.045 Rp 398,812.30 Rp 17,946.55
Semen warna kg 1.620 Rp 5,415.70 Rp 8,773.43
Pekerja OH 0.620 Rp 99,000.00 Rp 61,380.00
Tukang batu OH 0.350 Rp 137,500.00 Rp 48,125.00
Tenaga kerja
Kepala tukang OH 0.035 Rp 148,500.00 Rp 5,197.50
Mandor OH 0.030 Rp 148,500.00 Rp 4,455.00
Jumlah Harga / Satuan Pekerjaan Rp 267,475.11
Dibulatkan Rp 267,475.00

Al.Tambahan 2
Memasang 1 m2 lantai keramik ukuran (30 x 30) cm
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Keramik Buah 11.870 Rp 9,101.99 Rp 108,040.68
Portland Cement kg 10.000 Rp 2,149.06 Rp 21,490.60
Bahan
Pasir Pasang m3 0.045 Rp 398,812.30 Rp 17,946.55
Semen warna kg 1.500 Rp 5,415.70 Rp 8,123.55
Pekerja OH 0.700 Rp 99,000.00 Rp 69,300.00
Tukang batu OH 0.350 Rp 137,500.00 Rp 48,125.00
Tenaga kerja
Kepala tukang OH 0.035 Rp 148,500.00 Rp 5,197.50
Mandor OH 0.035 Rp 148,500.00 Rp 5,197.50
Jumlah Harga / Satuan Pekerjaan Rp 283,421.38
Dibulatkan Rp 283,421.00

Al.Tambahan 3
Memasang 1 m2 lantai keramik ukuran (40 x 40) cm
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)

keramik Buah 6.630 Rp 16,091.71 Rp 106,688.01


Portland Cement kg 9.800 Rp 2,149.06 Rp 21,060.79
Bahan
Pasir Pasang m3 0.045 Rp 398,812.30 Rp 17,946.55
Semen warna kg 1.300 Rp 5,415.70 Rp 7,040.41
Pekerja OH 0.250 Rp 99,000.00 Rp 24,750.00
Tukang batu OH 0.120 Rp 137,500.00 Rp 16,500.00
Tenaga kerja
Kepala tukang OH 0.012 Rp 148,500.00 Rp 1,782.00
Mandor OH 0.013 Rp 148,500.00 Rp 1,930.50
Jumlah Harga / Satuan Pekerjaan Rp 197,698.26
Dibulatkan Rp 197,698.00

ANALISA PEKERJAAN PLAFOND (A.4.5.1)

A.4.5.1.1
Memasang 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 6 mm
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)

Tripleks Lembar 0.375 Rp 130,823.16 Rp 49,058.69


Bahan
Paku tripleks kg 0.030 Rp 20,823.16 Rp 624.69
Pekerja OH 0.100 Rp 99,000.00 Rp 9,900.00
Tukang kayu OH 0.100 Rp 137,500.00 Rp 13,750.00
Tenaga kerja
Kepala tukang OH 0.010 Rp 148,500.00 Rp 1,485.00
Mandor OH 0.005 Rp 148,500.00 Rp 742.50
Jumlah Harga / Satuan Pekerjaan Rp 75,560.88
Dibulatkan Rp 75,560.00

ANALISA PEKERJAAN ATAP (A.4.5.2)


Page 20 of 35
Al.03-3436-1994-33
1m² Pasang Atap Genteng Metal
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Genteng Metal lbr 1.020 Rp 66,198.16 Rp 67,522.12
Bahan Paku Kg 0.200 Rp 20,823.16 Rp 4,164.63
Pekerja Oh 0.200 Rp 99,000.00 Rp 19,800.00
Tukang kayu Oh 0.100 Rp 137,500.00 Rp 13,750.00
Kepala tukang Oh 0.010 Rp 148,500.00 Rp 1,485.00
Tenaga Mandor Oh 0.001 Rp 148,500.00 Rp 148.50
Jumlah Harga / Satuan Pekerjaan Rp 106,870.26
Dibulatkan Rp 106,870.00

Page 21 of 35
ANALISA PEKERJAAN KAYU (A.4.6.1)

A.4.6.1.2
Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Kelas I (simalambuo)
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)

Broti kayu m3 1.200 Rp 4,410,642.50 Rp 5,292,771.00


Bahan Paku biasa Uk. 1" s/d 4" kg 1.250 Rp 20,823.16 Rp 26,028.95
Lem kayu kg 1.000 Rp 12,298.16 Rp 12,298.16
Pekerja OH 6.000 Rp 99,000.00 Rp 594,000.00
Tukang kayu OH 18.000 Rp 137,500.00 Rp 2,475,000.00
Tenaga kerja
Kepala tukang OH 1.800 Rp 148,500.00 Rp 267,300.00
Mandor OH 0.300 Rp 148,500.00 Rp 44,550.00
Jumlah Harga / Satuan Pekerjaan Rp 8,711,948.11
Dibulatkan Rp 8,711,948.00

A.4.6.1.13
Memasang 1 m3 konstruksi kuda-kuda / rangka atas, kayu kelas I (simalambuo)
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)

Broti kayu m 3
1.100 Rp 4,410,642.50 Rp 4,851,706.75
Bahan
Paku biasa Uk. 1" s/d 4" kg 5.600 Rp 20,823.16 Rp 116,609.70
Pekerja OH 4.000 Rp 99,000.00 Rp 396,000.00
Tukang kayu OH 12.000 Rp 137,500.00 Rp 1,650,000.00
Tenaga kerja
Kepala tukang OH 1.200 Rp 148,500.00 Rp 178,200.00
Mandor OH 0.200 Rp 148,500.00 Rp 29,700.00
Jumlah Harga / Satuan Pekerjaan Rp 7,222,216.45
Dibulatkan Rp 7,222,216.00

A.4.6.1.20
Memasang 1 m2 rangka langit-langit (60 x 80) cm, kayu Kelas I (simalambuo)
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)

Kaso-kaso (5 x 7) cm m3 0.016 Rp 4,410,642.50 Rp 71,893.47


Bahan
Paku biasa Uk. 1" s/d 4" kg 0.250 Rp 20,823.16 Rp 5,205.79
Pekerja OH 0.200 Rp 99,000.00 Rp 19,800.00
Tukang kayu OH 0.300 Rp 137,500.00 Rp 41,250.00
Tenaga kerja
Kepala tukang OH 0.030 Rp 148,500.00 Rp 4,455.00
Mandor OH 0.010 Rp 148,500.00 Rp 1,485.00
Jumlah Harga / Satuan Pekerjaan Rp 144,089.26
Dibulatkan Rp 144,089.00

A.4.6.1.21
Memasang 1 m1 lisplank ukuran (3 x 20) cm, kayu Kelas I (simalambuo)
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)

Broti kayu m3 0.011 Rp 4,410,642.50 Rp 47,634.94


Bahan
Paku biasa Uk. 1" s/d 4" kg 0.100 Rp 20,823.16 Rp 2,082.32
Pekerja OH 0.100 Rp 99,000.00 Rp 9,900.00
Tukang kayu OH 0.200 Rp 137,500.00 Rp 27,500.00
Tenaga kerja
Kepala tukang OH 0.020 Rp 148,500.00 Rp 2,970.00
Mandor OH 0.005 Rp 148,500.00 Rp 742.50
Jumlah Harga / Satuan Pekerjaan Rp 90,829.76
Dibulatkan Rp 90,829.00

A.4.6.1.7
Membuat dan memasang 1 m2 pintu dan jendela jalusi, kayu Kelas I (simalambuo)
Page 22 of 35
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)

Papan kayu m 3
0.064 Rp 4,410,642.50 Rp 282,281.12
Bahan
Lem kayu kg 0.500 Rp 12,298.16 Rp 6,149.08
Pekerja OH 1.000 Rp 99,000.00 Rp 99,000.00
Tukang kayu OH 3.000 Rp 137,500.00 Rp 412,500.00
Tenaga kerja
Kepala tukang OH 0.300 Rp 148,500.00 Rp 44,550.00
Mandor OH 0.050 Rp 148,500.00 Rp 7,425.00
Jumlah Harga / Satuan Pekerjaan Rp 851,905.20
Dibulatkan Rp 851,905.00

Page 23 of 35
A.4.6.1.10
Memasang 1 m2 jalusi kusen, kayu Kelas I (simalambuo)
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Papan kayu m 3
0.060 Rp 4,410,642.50 Rp 264,638.55
Bahan
Paku biasa Uk. 1" s/d 4" kg 0.150 Rp 20,823.16 Rp 3,123.47
Pekerja OH 0.670 Rp 99,000.00 Rp 66,330.00
Tukang kayu OH 2.000 Rp 137,500.00 Rp 275,000.00
Tenaga kerja
Kepala tukang OH 0.200 Rp 148,500.00 Rp 29,700.00
Mandor OH 0.335 Rp 148,500.00 Rp 49,747.50
Jumlah Harga / Satuan Pekerjaan Rp 688,539.52
Dibulatkan Rp 688,539.00

A.4.6.1.5
Membuat dan memasang 1 m2 daun pintu dan jendela panel, kayu Kelas I (simalambuo)
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)

Papan kayu m3 0.040 Rp 4,410,642.50 Rp 176,425.70


Bahan
Lem kayu kg 0.500 Rp 12,298.16 Rp 6,149.08
Pekerja OH 1.000 Rp 99,000.00 Rp 99,000.00
Tukang kayu OH 3.000 Rp 137,500.00 Rp 412,500.00
Tenaga kerja
Kepala tukang OH 0.300 Rp 148,500.00 Rp 44,550.00
Mandor OH 0.050 Rp 148,500.00 Rp 7,425.00
Jumlah Harga / Satuan Pekerjaan Rp 746,049.78
Dibulatkan Rp 746,049.00

A.4.6.1.15
Memasang 1 m3 konstruksi gordeng, kayu kelas I (simalambuo)
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)

Balok kayu m3 1.100 Rp 4,410,642.50 Rp 4,851,706.75


Bahan
Paku biasa Uk. 1" s/d 4" kg 3.000 Rp 20,823.16 Rp 62,469.48
Pekerja OH 2.400 Rp 99,000.00 Rp 237,600.00
Tukang kayu OH 7.200 Rp 137,500.00 Rp 990,000.00
Tenaga kerja
Kepala tukang OH 0.720 Rp 148,500.00 Rp 106,920.00
Mandor OH 0.120 Rp 148,500.00 Rp 17,820.00
Jumlah Harga / Satuan Pekerjaan Rp 6,266,516.23
Dibulatkan Rp 6,266,516.00

ANALISA PEKERJAAN CAT (A.4.7.1)

A.4.7.1.10
1 m² Pengecatan Tembok Baru ( 1 Lapis Cat Dasar, 2 Lapis Cat Penutup )
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Cat Dasar Tembok Kg 0.100 Rp 41,448.16 Rp 4,144.82
Bahan
Cat Tembok Kg 0.260 Rp 41,448.16 Rp 10,776.52
Pekerja Oh 0.020 Rp 99,000.00 Rp 1,980.00
Tukang Cat Oh 0.063 Rp 137,500.00 Rp 8,662.50
Tenaga
Kepala tukang Oh 0.006 Rp 148,500.00 Rp 935.55
Mandor Oh 0.003 Rp 148,500.00 Rp 371.25
Jumlah Harga / Satuan Pekerjaan Rp 26,870.64
Dibulatkan Rp 26,870.00

A.4.7.1.16
1 m² Pengecatan Permukaan Baja dengan Cat Meni
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Page 24 of 35
Bahan Cat Meni Kg 0.100 Rp 30,448.16 Rp 3,044.82
Pekerja Oh 0.020 Rp 99,000.00 Rp 1,980.00
Tukang Cat Oh 0.200 Rp 137,500.00 Rp 27,500.00
Tenaga
Kepala tukang Oh 0.020 Rp 148,500.00 Rp 2,970.00
Mandor Oh 0.010 Rp 148,500.00 Rp 1,485.00
Jumlah Harga / Satuan Pekerjaan Rp 36,979.82
Dibulatkan Rp 36,979.00

Page 25 of 35
A.4.7.1.5
1 m² Mengecatan Bidang Kayu Baru ( 1 Lapis Cat Dasar, 2 Lapis Cat Penutup )
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Cat Meni Kg 0.200 Rp 30,448.16 Rp 6,089.63
Bahan
Cat Minyak Kg 0.350 Rp 75,823.16 Rp 26,538.11
Pekerja Oh 0.070 Rp 99,000.00 Rp 6,930.00
Tukang Cat Oh 0.105 Rp 137,500.00 Rp 14,437.50
Tenaga
Kepala tukang Oh 0.004 Rp 148,500.00 Rp 594.00
Mandor Oh 0.003 Rp 148,500.00 Rp 371.25
Jumlah Harga / Satuan Pekerjaan Rp 54,960.49
Dibulatkan Rp 54,960.00

ANALISA PEKERJAAN TAMBAHAN

Al.Tambahan 4
1 m³ Membongkar Dinding 1/2 batu ( Batako / Batu Lega )
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Pekerja Oh 2.000 Rp 99,000.00 Rp 198,000.00
Tenaga
Mandor Oh 0.100 Rp 148,500.00 Rp 14,850.00
Jumlah Harga / Satuan Pekerjaan Rp 212,850.00
Dibulatkan Rp 212,850.00

Al.Tambahan 5
1 m² Membongkar Lantai
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Pekerja Oh 0.100 Rp 99,000.00 Rp 9,900.00
Tenaga
Mandor Oh 0.010 Rp 148,500.00 Rp 1,485.00
Jumlah Harga / Satuan Pekerjaan Rp 11,385.00
Dibulatkan Rp 11,385.00

Al.Tambahan 6
1 m³ Membongkar beton bertulang
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Pekerja Oh 8.000 Rp 99,000.00 Rp 792,000.00
Tukang Oh 1.600 Rp 137,500.00 Rp 220,000.00
Tenaga
Kepala tukang Oh 0.160 Rp 148,500.00 Rp 23,760.00
Mandor Oh 0.400 Rp 148,500.00 Rp 59,400.00
Jumlah Harga / Satuan Pekerjaan Rp 1,095,160.00
Dibulatkan Rp 1,095,160.00

Al.Tambahan 7
1 m² Membongkar Plesteran
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Pekerja Oh 0.050 Rp 99,000.00 Rp 4,950.00
Tenaga
Mandor Oh 0.0025 Rp 148,500.00 Rp 371.25
Jumlah Harga / Satuan Pekerjaan Rp 5,321.25
Dibulatkan Rp 5,321.00

Al.Tambahan 8
1 m² Membongkar Atap Seng dan Plafond
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Pekerja Oh 0.050 Rp 99,000.00 Rp 4,950.00
Tenaga
Mandor Oh 0.010 Rp 148,500.00 Rp 1,485.00
Jumlah Harga / Satuan Pekerjaan Rp 6,435.00
Page 26 of 35
Dibulatkan Rp 6,435.00

Al.Tambahan 9
1 m² Membongkar Rangka Atap dan Rangka Plafond
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Pekerja Oh 0.100 Rp 99,000.00 Rp 9,900.00
Tenaga
Mandor Oh 0.005 Rp 148,500.00 Rp 742.50
Jumlah Harga / Satuan Pekerjaan Rp 10,642.50
Dibulatkan Rp 10,642.00

Page 27 of 35
Al.Tambahan 10
1 m³ Membongkar Kusen Pintu dan Jendela
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Tukang Oh 1.000 Rp 137,500.00 Rp 137,500.00
Tenaga Kepala tukang Oh 0.100 Rp 148,500.00 Rp 14,850.00
Mandor Oh 0.015 Rp 148,500.00 Rp 2,227.50
Jumlah Harga / Satuan Pekerjaan Rp 154,577.50
Dibulatkan Rp 154,577.00

Al.Tambahan 11
1 m² Membongkar Daun Pintu dan Jendela
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Pekerja Oh 0.020 Rp 99,000.00 Rp 1,980.00
Tenaga
Mandor Oh 0.001 Rp 148,500.00 Rp 148.50
Jumlah Harga / Satuan Pekerjaan Rp 2,128.50
Dibulatkan Rp 2,128.00

Al. Tambahan 12
Memasang 1 m2 plesteran 1 PC : 4 PP, tebal 15 mm (Sisipan dinding Retak / Patah)
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Semen Kg 6.240 Rp 2,149.06 Rp 13,410.13
Pasir Pasang M3 0.024 Rp 398,812.30 Rp 9,571.50
Bahan
Kawat Nyamuk Logam / Aluminium M2 1.000 Rp 48,268.16 Rp 48,268.16
Paku beton Putih Uk. 1" Ktk 1.400 Rp 42,548.16 Rp 59,567.42
Pekerja OH 0.300 Rp 99,000.00 Rp 29,700.00
Tukang batu OH 0.150 Rp 137,500.00 Rp 20,625.00
Tenaga kerja
Kepala tukang OH 0.015 Rp 148,500.00 Rp 2,227.50
Mandor OH 0.015 Rp 148,500.00 Rp 2,227.50
Jumlah Harga / Satuan Pekerjaan Rp 185,597.21
Dibulatkan Rp 185,597.00

Al. Tambahan 13
Memasang 1 m' acian
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Bahan Semen kg 0.325 Rp 2,149.06 Rp 698.44
Pekerja OH 0.020 Rp 99,000.00 Rp 1,980.00
Tukang batu OH 0.010 Rp 137,500.00 Rp 1,375.00
Tenaga kerja
Kepala tukang OH 0.001 Rp 148,500.00 Rp 148.50
Mandor OH 0.001 Rp 148,500.00 Rp 148.50
Jumlah Harga / Satuan Pekerjaan Rp 4,350.44
Dibulatkan Rp 4,350.00

Al. Tambahan 14
1 m' Membongkar Listplank
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Tenaga kerja Pekerja OH 0.030 Rp 99,000.00 Rp 2,970.00
Jumlah Harga / Satuan Pekerjaan Rp 2,970.00
Dibulatkan Rp 2,970.00

Al. Tambahan 15
1 m² Pengecatan Tembok ( 1 Lapis Cat Dasar, 2 Lapis Cat Penutup Pelapis anti bocor )
Harga Satuan Bahan / Jumlah
Kebutuhan Satuan Indeks
Upah (Rp.) (Rp.)
Cat Dasar Tembok Kg 0.100 Rp 41,448.16 Rp 4,144.82
Bahan
Cat Pelapis anti bocor (Aquaprooff) Kg 0.260 Rp 75,823.16 Rp 19,714.02
Page 28 of 35
Pekerja Oh 0.020 Rp 99,000.00 Rp 1,980.00
Tukang Cat Oh 0.063 Rp 137,500.00 Rp 8,662.50
Tenaga
Kepala tukang Oh 0.006 Rp 148,500.00 Rp 935.55
Mandor Oh 0.003 Rp 148,500.00 Rp 371.25
Jumlah Harga / Satuan Pekerjaan Rp 35,808.14
Dibulatkan Rp 35,808.00

Lotu, …………………….2017
Dibuat oleh
CV. DEVERIAN CONSULTANT

BETLEHEM KARO KARO, ST SYAHRUL, ST


Team Leader Ahli Estimasi Biaya

Page 29 of 35
DAFTAR HARGA BAHAN SAMPAI DILOKASI

Kegiatan :
PENGADAAN SARANA DAN PRASARANA PUSKESMAS
DINAS KESEHATAN KABUPATEN NIAS UTARA
SUMBER DANA : DAK
Pekerjaan :

BIAYA REHABILITASI GEDUNG LINGKUP PUSKESMAS ALASA (DAK AFIRMASI TAHUN 2017)

Harga / Satuan
Satuan Volume
No. Uraian
volume (Rp.)
1 Pasir pasangan M3 398,812.30
2 Pasir beton M3 402,549.80
3 Pasir urug M3 253,946.80
4 Krikil disaring Uk. 0,5 - 2 cm M3 421,984.80
5 Krikil tidak disaring M3 351,719.80
6 Batu belah uk. 10 - 15 cm M3 310,549.80
7 Batu utuh uk. 15 - 20 cm M3 290,309.80
8 Tanah timbunan setempat M3 203,634.00
9 Bukho M3 235,029.00
10 Sirtu M3 318,139.80
11 Kayu kelas I (Simalambuo) M3 4,410,642.50
12 Kayu Sembarang M3 2,307,580.00
13 Seng gel. bjls 0.20 mm pjng 6 kk; 11 b Lbr 52,448.16
14 Sement Porland Berat 50 Kg Zak 107,453.00
15 Semen putih 40 Kg Zak 216,628.00
16 Besi beton Kg 13,699.56
17 Kawat beton Kg 27,698.16
18 Batu Bata dari Tanah 5 Cm x 10 Cm x 20 Bh 2,139.50
Cm
19 Batako / Batu Lega Bh 7,014.65
20 Paku biasa Uk. 1" s/d 4" Kg 20,823.16
21 Paku beton Putih Uk. 1" Ktk 42,548.16
22 Triplex t = 6 mm Lbr 130,823.16
23 Lat plafond Btg 6,798.16
24 Cat tembok Kg 41,448.16
25 Keramik 20 x 25 Ktk 92,323.16
26 Keramik 20 x 20 Ktk 96,448.16
27 Keramik 30 x 30 Ktk 101,123.16
28 Keramik 40 x 40 Ktk 100,573.16
29 Rabung Atap Metal, t = 0.30 mm Lbr 62,073.16
30 Cat Meni Kg 30,448.16
31 Cat Kayu/Besi (Platone) Kg 75,823.16
32 Cat Pelapis anti bocor (Aquaprooff) Kg 75,823.16
33 Minyak silinder Ltr 41,034.56
34 Lem kayu Kg 12,298.16
35 Atap Genteng Metal, t = 0.30 mm Lbr 66,198.16
36 Kaca t = 5 mm (100 x 100 ) Lbr 133,600.66
37 Kawat Listrik Kg 27,500.00
38 Solar Ltr 5,665.00
39 Minyak Pelumas Ltr 42,985.80
40 Besi Hollow Kg 15,953.46
41 Paving Blok Bh 2,665.46
42 Kawat Nyamuk Logam / Aluminium M2 48,268.16

Lotu, …………………….2017
Dibuat oleh
CV. DEVERIAN CONSULTANT

BETLEHEM KARO KARO, ST


Team Leader
DAFTAR HARGA BAHAN SAMPAI DILOKASI

Kegiatan :
PENGADAAN SARANA DAN PRASARANA PUSKESMAS
DINAS KESEHATAN KABUPATEN NIAS UTARA
SUMBER DANA : DAK
Pekerjaan :

LITASI GEDUNG LINGKUP PUSKESMAS ALASA (DAK AFIRMASI TAHUN 2017)

Keterangan

1 zak = 50 kg
1 zak = 40 kg

Lotu, …………………….2017
Dibuat oleh
CV. DEVERIAN CONSULTANT

SYAHRUL, ST
Ahli Estimasi Biaya
DAFTAR HARGA UPAH TENAGA KERJA

Kegiatan :
PENGADAAN SARANA DAN PRASARANA PUSKESMAS
DINAS KESEHATAN KABUPATEN NIAS UTARA
SUMBER DANA : DAK
Pekerjaan :

BIAYA REHABILITASI GEDUNG LINGKUP PUSKESMAS ALASA (DAK AFIRMASI TAHUN 2017)

Orang/hari
No. Uraian Keterangan
(Rp.)
1 Pekerja 99,000.00
2Tukang 137,500.00
3 Kepala tukang 148,500.00
4Mandor 148,500.00

Lotu, …………………….2017
Dibuat oleh
CV. DEVERIAN CONSULTANT

BETLEHEM KARO KARO, ST SYAHRUL, ST


Team Leader Ahli Estimasi Biaya
ANALISA HARGA SATUAN BAHAN/MATERIAL DAN UPAH DI LOKASI PEKERJAAN
BIAYA ANGKUT DENGAN TRUK

DATAR BUKIT
TOTAL BIAYA
PAJAK MINERAL

SATUAN
HARGA DASAR BIAYA / ONGKOS HARGA SAMPAI DILOKASI
KEUNTUNGAN ( 4 BUKAN LOGAM KETERANGAN
NO. JENIS MATERIAL QUARRY / HARGA
x 10 % ) Rp. DAN BEBATUAN
BONGKAR MUAT BAIK BAIK PEKERJAAN
SUMBER BAHAN
TOKO (Rp.) TRUK (Rp.) ( 4+5+6+8+10+12+14+34 )
( 4 X 20 % ) RP.
JARAK ONGKOS JARAK ONGKOS ANGKUT TRUK

Km Rp. Km Rp. Rp.


1 2 3 4 5 6 15 16 17 22 23 34 35 36
1 Pasir pasangan M3 204,125.00 20,412.50 40,825.00 79,685.00 - - 9.20 53,764.80 133,449.80 398,812.30 Alasa Talumuzoi
2 Pasir beton M3 207,000.00 20,700.00 41,400.00 79,685.00 - - 9.20 53,764.80 133,449.80 402,549.80 Alasa Talumuzoi
3 Pasir urug M3 92,690.00 9,269.00 18,538.00 79,685.00 - - 9.20 53,764.80 133,449.80 253,946.80 Alasa Talumuzoi
4 Krikil disaring Uk. 0,5 - 2 cm M3 221,950.00 22,195.00 44,390.00 79,685.00 - - 9.20 53,764.80 133,449.80 421,984.80 Alasa Talumuzoi
5 Krikil tidak disaring M3 167,900.00 16,790.00 33,580.00 79,685.00 - - 9.20 53,764.80 133,449.80 351,719.80 Alasa Talumuzoi
6 Batu belah uk. 10 - 15 cm M3 161,000.00 16,100.00 79,685.00 - - 9.20 53,764.80 133,449.80 310,549.80 Alasa Talumuzoi
7 Batu utuh uk. 15 - 20 cm M3 142,600.00 14,260.00 79,685.00 - - 9.20 53,764.80 133,449.80 290,309.80 Alasa Talumuzoi
8 Tanah timbunan setempat M3 90,850.00 9,085.00 18,170.00 79,685.00 - - 1.00 5,844.00 85,529.00 203,634.00 Alasa
9 Bukho M3 115,000.00 11,500.00 23,000.00 79,685.00 - - 1.00 5,844.00 85,529.00 235,029.00 Alasa
10 Sirtu M3 167,900.00 16,790.00 79,685.00 - - 9.20 53,764.80 133,449.80 318,139.80 Alasa Talumuzoi
11 Kayu kelas I (Simalambuo) M3 3,947,375.00 394,737.50 59,764.00 - - 2.00 8,766.00 68,530.00 4,410,642.50 Alasa
12 Kayu Sembarang M3 2,035,500.00 203,550.00 59,764.00 - - 2.00 8,766.00 68,530.00 2,307,580.00 Alasa
13 Seng gel. bjls 0.20 mm pjng 6 kk; 11 b Lbr 47,500.00 4,750.00 58.86 - - 35.00 139.30 198.16 52,448.16 G.sitoli
14 Sement Porland Berat 50 Kg Zak 88,000.00 8,800.00 2,988.00 - - 35.00 7,665.00 10,653.00 107,453.00 G.sitoli
15 Semen putih 40 Kg Zak 187,250.00 18,725.00 2,988.00 - - 35.00 7,665.00 10,653.00 216,628.00 G.sitoli
16 Besi beton Kg 12,274.00 1,227.40 58.86 - - 35.00 139.30 198.16 13,699.56 G.sitoli
17 Kawat beton Kg 25,000.00 2,500.00 58.86 - - 35.00 139.30 198.16 27,698.16 G.sitoli
18 Batu Bata dari Tanah 5 Cm x 10 Cm x 20 Cm Bh 1,500.00 150.00 239.00 - - 30.00 250.50 489.50 2,139.50 G.sitoli
19 Batako / Batu Lega Bh 5,894.00 589.40 239.00 - - 35.00 292.25 531.25 7,014.65 G.sitoli
20 Paku biasa Uk. 1" s/d 4" Kg 18,750.00 1,875.00 58.86 - - 35.00 139.30 198.16 20,823.16 G.sitoli
21 Paku beton Putih Uk. 1" Ktk 38,500.00 3,850.00 58.86 - - 35.00 139.30 198.16 42,548.16 G.sitoli
22 Triplex t = 6 mm Lbr 118,750.00 11,875.00 58.86 - - 35.00 139.30 198.16 130,823.16 G.sitoli
23 Lat plafond Btg 6,000.00 600.00 58.86 - - 35.00 139.30 198.16 6,798.16 G.sitoli
24 Cat tembok Kg 37,500.00 3,750.00 58.86 - - 35.00 139.30 198.16 41,448.16 G.sitoli
25 Keramik 20 x 25 Ktk 83,750.00 8,375.00 58.86 - - 35.00 139.30 198.16 92,323.16 G.sitoli
26 Keramik 20 x 20 Ktk 87,500.00 8,750.00 58.86 - - 35.00 139.30 198.16 96,448.16 G.sitoli
27 Keramik 30 x 30 Ktk 91,750.00 9,175.00 58.86 - - 35.00 139.30 198.16 101,123.16 G.sitoli
28 Keramik 40 x 40 Ktk 91,250.00 9,125.00 58.86 - - 35.00 139.30 198.16 100,573.16 G.sitoli
29 Rabung Atap Metal, t = 0.30 mm Lbr 56,250.00 5,625.00 58.86 - - 35.00 139.30 198.16 62,073.16 G.sitoli
30 Cat Meni Kg 27,500.00 2,750.00 58.86 - - 35.00 139.30 198.16 30,448.16 G.sitoli
31 Cat Kayu/Besi (Platone) Kg 68,750.00 6,875.00 58.86 - - 35.00 139.30 198.16 75,823.16 G.sitoli
32 Cat Pelapis anti bocor (Aquaprooff) Kg 68,750.00 6,875.00 58.86 - - 35.00 139.30 198.16 75,823.16 G.sitoli
33 Minyak silinder Ltr 37,124.00 3,712.40 58.86 - - 35.00 139.30 198.16 41,034.56 G.sitoli
34 Lem kayu Kg 11,000.00 1,100.00 58.86 - - 35.00 139.30 198.16 12,298.16 G.sitoli
35 Atap Genteng Metal, t = 0.30 mm Lbr 60,000.00 6,000.00 58.86 - - 35.00 139.30 198.16 66,198.16 G.sitoli
36 Kaca t = 5 mm (100 x 100 ) Lbr 121,275.00 12,127.50 58.86 - - 35.00 139.30 198.16 133,600.66 G.sitoli
37 Kawat Listrik Kg 25,000.00 2,500.00 - - - - - - 27,500.00 G.sitoli
38 Solar Ltr 5,150.00 515.00 - - - - - - 5,665.00 G.sitoli
39 Minyak Pelumas Ltr 39,078.00 3,907.80 - - - - - - 42,985.80 G.sitoli
40 Besi Hollow Kg 14,323.00 1,432.30 58.86 - - 35.00 139.30 198.16 15,953.46 G.sitoli
41 Paving Blok Bh 2,243.00 224.30 58.86 - - 35.00 139.30 198.16 2,665.46 G.sitoli
42 Kawat Nyamuk Logam / Aluminium M2 43,700.00 4,370.00 58.86 - - 35.00 139.30 198.16 48,268.16 G.sitoli

Lotu, …………………….2017
Dibuat oleh
CV. DEVERIAN CONSULTANT

BETLEHEM KARO KARO, ST SYAHRUL, ST


Team Leader Ahli Estimasi Biaya
Orang/hari
Harga Dasar Keuntungan (10
No. Uraian Keterangan
Upah % x 3) (Rp.) (
1 2 3 4 3 +54 ) 6
1 Pekerja 90,000.00 9,000.00 99,000.00
2T u k a n g 125,000.00 12,500.00 137,500.00
3 Kepala tukang 135,000.00 13,500.00 148,500.00
4M a n d o r 135,000.00 13,500.00 148,500.00

Lotu, …………………….2017
Dibuat oleh
CV. DEVERIAN CONSULTANT

BETLEHEM KARO KARO, ST SYAHRUL, ST


Team Leader Ahli Estimasi Biaya