Jul-22 Aug-22 PERIODE REALISASI BIAYA (Rp)

NO PEKERJAAN NILAI PEK (Rp) BOBOT


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 BULAN MINGGU MINGGUAN KOMULATIF

1 Pembersihan & Perataan 12.640.000 2,0% 2,0% 1 11.376.000 11.376.000


2 Pemasangan Bouwplank 18.960.000 3,0% 3,0% 2 17.867.904 29.243.904
Jul-22
3 Galian tanah footplat 20.224.000 3,2% 2,07% 0,07% 1,07% 3 26.666.608 55.910.512
4 Galiantanah dingin penahan tanah 15.168.000 2,4% 0,20% 2,20% 4 37.357.362 93.267.874
5 Dinding penahan tanah batu kali 53.088.000 8,4% 2,80% 2,80% 2,80% 5 38.740.968 132.008.842
6 Galian tanah sloof 7.584.000 1,2% 0,60% 0,60% 6 38.663.390 170.672.232
7 Dinding penahan tanah beton 66.044.000 10,5% 3,48% 3,48% 3,48% Aug-22 7 38.473.632 209.145.864
8 Pondasi footplat 62.568.000 9,9% 1,20% 5,20% 3,50% 8 39.168.516 248.314.380
9 Sloof pondasi footplat 41.712.000 6,6% 4,30% 2,30% 9 42.551.296 290.865.676
10 Kolom 79.948.000 12,7% 6,92% 1,52% 4,22% Sep-22 10 38.312.472 329.178.148
11 Sloof DPT batu kali 42.976.000 6,8% 2,40% 4,40%
12 Pasangan dinding bata 65.728.000 10,4% 4,47% 5,77% 0,17%
13 Kolom praktis 48.032.000 7,6% 5,30% 2,30%
14 Balok & plat lantai 97.328.000 15,4% 5,85% 4,85% 2,85% 1,85%
TOTAL 632.000.000 100,0%
MINGGUAN 2,00% 3,20% 4,87% 6,95% 7,35% 7,48% 7,60% 7,90% 8,77% 8,07% 7,09% 6,82% 6,52% 5,85% 4,85% 2,85% 1,85%
RENCANA PRESTASI
KOMULATIF 2,00% 5,20% 10,07% 17,02% 24,37% 31,85% 39,45% 47,35% 56,12% 64,19% 71,28% 78,10% 84,62% 90,47% 95,32% 98,17% 100,0%
MINGGUAN 1,88% 2,95% 4,40% 6,15% 6,37% 6,34% 6,30% 6,40% 6,93% 6,23%
REALISASI PRESTASI
KOMULATIF 1,88% 4,83% 9,23% 15,38% 21,75% 28,09% 34,39% 40,79% 47,72% 53,95%
MINGGUAN 1,8% 2,83% 4,22% 5,91% 6,13% 6,12% 6,09% 6,20% 6,73% 6,06%
ACWP
KOMULATIF 1,8% 4,63% 8,85% 14,76% 20,89% 27,01% 33,09% 39,29% 46,02% 52,09%

REKAP
NILAI
BCWS Rp 405.680.800,00
BCWP Rp 340.964.000,00
ACWP Rp 329.178.148,00
Waktu Laporan (minggu) 10

EVALUASI BIAYA
NILAI
Anggaran Total Rp 632.000.000,00
Sisa Anggaran Rp 291.036.000,00
CPI16(Indeks Kinerja Biaya) 1,04
ETC(Perkiraan Biaya Tersisa) Rp 280.975.972,48
EAC (Perkiraan Biaya Akhir Proyek) Rp 610.154.120,48
Keuntungan Rp 21.845.879,52

EVALUASI BIAYA
NILAI
Waktu Rencana (minggu) 17
Sisa Waktu (minggu) 7,00
SPI16(Indeks Kinerja waktu) 0,84
ETS(Perkiraan Waktu Tersisa) 8,33
EAS (Perkiraan Biaya Akhir Proyek) 18,33
KETERLAMBATAN -1,33
NO ITEM YANG DI CRASH KAN KODE DURASI NORMAL (Minggu) DURASI CRASH (Minggu) COST NORMAL (Rp) COST CRASH (Rp) Di (minggu) COST SLOPE (Rp) PENAMBAHAN BIAYA
1 KOLOM I 3 2 79.948.000 70.000.000 1 9948000 9948000
2 SLOOF DPT BATU KALI J 2 1 42.976.000 40.000.000 1 2976000 2976000
3 PASANGAN DINTING BATA K 3 2 65.728.000 60.000.000 1 5728000 5728000
4 KOLOM PRAKTIS L 2 1 48.032.000 40.000.000 1 8032000 8032000
5 BALOK & PLAT LANTAI M 4 3 97.328.000 90.000.000 1 7328000 7328000
334.012.000 300.000.000 1 34012000

RAB AKHIR KEUNTUNGAN AKHIR

NO ITEM RAB AWAL (RP) TAMBAHAN BIAYA RAB AKHIR NO ITEM NILAI

A BIAYA LANGSUNG Rp 632.000.000 Rp 34.012.000 Rp 666.012.000 A KEUNTUNGAN


Perkiraan Efisiensi berdasarkan EAC Rp 21.845.880
TOTAL I Rp 21.845.880
B TAMBAHAN BIAYA
1 Crash Program Pekerjaan Arsitektur Rp 34.012.000
TOTAL II Rp 34.012.000
TOTAL (I-II) -Rp 12.166.120