I PEKERJAAN RENOVASI PINTU GERBANG


1 Bongkaran Dinding Pagar M2 110,40 32.890 3.631.056 0,770%
2 Bongkar Pintu Gerbang Ls 1,00 715.000 715.000 0,152%
3 Bongkar Gapura Ls 1,00 1.430.000 1.430.000 0,303%
Sub Total 5.776.056 1,225%
II PEK.POS BARU
A Pekerjaan Struktur
1 Galian Tanah Pondasi Sloof & Cakar Ayam m3 12,50 111.540 1.394.250 0,296%
2 Pek.Lantai Kerja m3 0,65 1.930.500 1.254.825 0,266%
3 Pondasi Cakar Ayam 8 Titik m3 0,63 8.294.000 5.225.220 1,108%
4 Pas.Sloof m3 1,17 8.294.000 9.703.980 2,058%
5 Pas.Kolom Uk.15 x 30cm m3 2,52 8.294.000 20.900.880 4,432%
6 Pas.Dinding Hebel m2 96,20 193.050 18.571.410 3,938%
7 Plester + Acian m2 192,40 122.980 23.661.352 5,017%
8 Finishing Kolom m1 28,00 307.450 8.608.600 1,825%
9 Urugan Kembali m3 10,70 64.350 688.545 0,146%
10 Pek.Balok Uk.15 x 30cm m3 1,17 8.294.000 9.703.980 2,058%
11 Pas.Kolom Praktis Uk.10 x 15cm m3 0,27 8.294.000 2.239.380 0,475%
12 Pek.Listplank Beton m3 1,08 8.294.000 8.957.520 1,899%
13 Cor Dak beton m3 4,32 8.294.000 35.830.080 7,597%
14 Finishing Listplank Beton m2 18,00 164.450 2.960.100 0,628%
Sub Total 149.700.122 31,741%
B Pekerjaan Lantai & Plafon
RAP POS BARU GERBANG Page 2 of 4

HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
(%)
Rp.
Rp

1 Pek.Lantai Kerja T.5cm m3 1,50 1.930.500 2.895.750 0,614%


2 Pas.Granit Uk.60 x 60cm m2 36,00 436.150 15.701.400 3,329%
3 Pas.Keramik Dinding m2 21,00 436.150 9.159.150 1,942%
4 Pas.Plafond Gibsum m2 36,00 138.138 4.972.968 1,054%
5 Pas.List Plafon m' 54,00 22.880 1.235.520 0,262%
Sub Total 33.964.788 7,202%
C Pekerjaan Kusen & Jendela
1 Pintu (P.2) Tipe Pintu swing Kusen Aluminium set 2,00 3.432.000 6.864.000 1,455%
2 Pintu (P.3) Tipe Pintu swing (PVC) set 2,00 1.986.270 3.972.540 0,842%
3 Jendela (J.4) Tipe Jendela Jungkit set 1,00 2.334.904 2.334.904 0,495%
4 Jendela (J. 5) Tipe Jendela Siku Kaca Mati set 1,00 6.006.000 6.006.000 1,273%
5 Bouven (BV.1) set 1,00 587.909 587.909 0,125%
Sub Total 19.765.353 4,191%
C Pekerjaan Finishing
1 Pengecatan dinding exterior fin. Cat waterproof m2 96,20 74.360 7.153.432 1,517%
2 Pengecatan dinding Interior m2 96,20 47.190 4.539.678 0,963%
3 Pengecatan Plafon m2 36,00 47.190 1.698.840 0,360%
4 Pengecatan List Plafon m2 54,00 47.190 2.548.260 0,540%
5 Pengecatan Listplank Beton m2 18,00 74.360 1.338.480 0,284%
Sub Total 17.278.690 3,664%
III PEK.PINTU REMOT OTOMATIS
1 Pintu Besi Minimalis (sleding Uk.3 x 6meter) m2 18,00 1.787.500 32.175.000 6,822%
2 Pintu Besi Minimalis (swing) uk.1m x 3meter) m2 3,00 1.787.500 5.362.500 1,137%
3 Automatic Sliding Door Telescopic Mesin Pintu Otomatis Unit 1,00 54.340.000 54.340.000 11,522%
Sub Total 91.877.500 19,481%
IV PEKERJAAN SANITASI & SANITAIR -
A1 Peralatan Utama - -
1 Pas.Jetwasher Set 1,00 1.787.500 1.787.500 0,379%
2 Pas.Kloset Duduk Set 1,00 5.005.000 5.005.000 1,061%
3 Pas.Floordrain Set 1,00 178.750 178.750 0,038%
RAP POS BARU GERBANG Page 3 of 4

HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
(%)
Rp.
Rp

4 Pas.Wastafel Set 1,00 3.932.500 3.932.500 0,834%


5 Pas.Krant Set 3,00 107.250 321.750 0,068%
A2 Instalasi Pemipaan
1 Pipa Φ 1 " m' 14,00 44.187 618.618 0,131%
2 Pipa Φ 3/4" m' 32,00 27.885 892.320 0,189%
3 Pipa Φ 1/2" m' 36,00 25.454 916.344 0,194%
4 Fiting-fiting, klem, support dan gantungan serta finishing lot 1,00 1.430.000 1.430.000 0,303%
5 Gate Valve Φ 1 " bh 1,00 691.405 691.405 0,147%
6 Check Valve Φ 1 " bh 1,00 687.544 687.544 0,146%
Sub Total 16.461.731 3,490%
B PEKERJAAN PLUMBING AIR KOTOR, AIR BEKAS DAN AIR HUJAN

B1 Peralatan Utama
1 Septic Tank, Kap : 3 M3 unit 1,00 10.725.000 10.725.000 2,274%
2 Sumur Resapan unit 1,00 2.726.035 2.726.035 0,578%
3 Bak Kontrol ( 300 x 300 x 400 mm ) unit 1,00 1.822.106 1.822.106 0,386%

B2 Instalasi Pemipaan Air Kotor


1 Pipa Φ 3" m' 10,00 128.700 1.287.000 0,273%
2 Pipa Φ 4" m' 12,00 148.763 1.785.155 0,379%
3 Fiting-fiting, klem, support dan gantungan serta finishing lot 1,00 715.000 715.000 0,152%
4 Clean Out Φ 4" bh 4,00 109.252 437.008 0,093%

B3 Instalasi Pemipaan Air Bekas


1 Pipa Φ 3" m' 28,00 128.700 3.603.600 0,764%
2 Fiting-fiting, klem, support dan gantungan serta finishing lot 1,00 715.000 715.000 0,152%
3 Floor Drain Φ 3" bh 2,00 145.574 291.148 0,062%

B4 Instalasi Pemipaan Air Hujan


1 Pipa Φ 4" m' 16,00 148.763 2.380.206 0,505%
RAP POS BARU GERBANG Page 4 of 4

HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
(%)
Rp.
Rp

2 Fiting-fiting, klem, support dan gantungan serta finishing lot 1,00 715.000 715.000 0,152%
3 Roof Drain Φ 4" lot 2,00 145.574 291.148 0,062%
Sub Total 27.493.406 5,829%
V PEKERJAAN PAGAR DEPAN
1 Galian Tanah Pondasi Batu Kali m3 3,85 111.540 429.429 0,091%
2 Pas.Anstamping m3 1,10 373.230 410.553 0,087%
3 Pas.Pondasi Batukali m3 3,85 1.215.500 4.679.675 0,992%
4 Pek.Lantai Kerja m3 0,65 1.930.500 1.254.825 0,266%
5 Pondasi Cakar Ayam m3 0,63 8.294.000 5.225.220 1,108%
6 Pas.Sloof m1 0,50 8.294.000 4.105.530 0,870%
7 Pas.Kolom Uk.40 x 40cm m3 1,80 8.294.000 14.929.200 3,165%
8 Pas.Dinding Hebel m2 33,00 193.050 6.370.650 1,351%
9 Plester + Acian m2 66,00 122.980 8.116.680 1,721%
10 Finishing Kolom m1 20,00 307.450 6.149.000 1,304%
11 Urugan Kembali m3 2,73 64.350 175.354 0,037%
12 Pek.Balok Uk.15 x 30cm m3 0,50 8.294.000 4.105.530 0,870%
13 Ban - banan Pagar m1 132,00 45.760 6.040.320 1,281%
14 Pas.Dindng Batu Andesit m2 45,00 679.250 30.566.250 6,481%
15 Pot Bunga + Ornamen lot 1,00 14.300.000 14.300.000 3,032%
16 Pengecatan Dnding Pagar Bagian dalam m2 33,00 74.360 2.453.880 0,520%
Sub Total 109.312.096 23,178%