HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp

I PEKERJAAN RENOVASI
A PEKERJAAN PERSIAPAN & BONGKARAN LT.2
1 Pengukuran & Bowplank Ls 1,00 7.150.000 7.150.000 0,297%
2 Pekerjaan Bongkar Atap m2 266,00 17.160 4.564.560 0,190%
3 Air Kerja & Listrik ls 1,00 28.600 28.600 0,001%
Sub Total 11.743.160 0,488%
B PEKERJAAN STRUKTUR LT.1
1 Balok 20x50 cm, K-225, tul. 8D13, 2D10, SK Ø8-100/200 + bekisting m3 6,00 8.294.000 49.764.000 2,068%
2 Balok 15x30 cm, K-225, tul. 4D13, 2D13, SK Ø8-100/200 + bekisting m3 3,98 8.294.000 33.030.855 1,373%
3 Plat (S1) dak elv. +4.00 t. 120 mm, K-225, tul. Ø8-200 double + bekisting m3 35,40 8.294.000 293.607.600 12,201%
4 Listplank Beton, K-225, tul.Ø12-150, Ø8-200 + bekisting m3 0,96 8.294.000 7.962.240 0,331%
Sub Total 384.364.695 15,972%
C PEKERJAAN PEKERJAAN TANGGA DAN RAILLNG
1 Pek.Beton Tangga Ls 1,00 24.310.000 24.310.000 1,010%
2 Lantai Tangga fin. Homogenous tile 60x60 cm m2 19,48 602.745 11.741.473 0,488%
3 Step Nosing m1 37,00 207.350 7.671.950 0,319%
4 Finishing tangga sisi bawah dan samping fin. Plesteran s/d acian + cat m2 9,90 210.210 2.081.079 0,086%
5 Railling tangga m1 12,90 1.206.563 15.564.656 0,647%
61.369.158 2,550%
D PEKERJAAN STRUKTUR LT.2
1 Balok 20x50 cm, K-225, tul. 8D13, 2D10, SK Ø8-100/200 + bekisting m3 6,00 8.294.000 49.764.000 2,068%
2 Balok 15x30 cm, K-225, tul. 4D13, 2D13, SK Ø8-100/200 + bekisting m3 4,25 8.294.000 35.270.235 1,466%
3 Plat (S1) dak elv. +7.50 t. 120 mm, K-225, tul. Ø8-200 double + bekisting (Talang) m3 9,96 8.294.000 82.608.240 3,433%
ADDWORK GEDUNG A Page 2 of 7

HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp

4 Kolom 25x35 cm, K-225, tul. 12.D13, SK Ø8-100/200 + bekisting m3 6,30 8.294.000 52.252.200 2,171%
5 Listplank Beton, K-225, tul.Ø12-150, Ø8-200 + bekisting (LT.2) m3 3,98 8.294.000 33.043.296 1,373%
6 Pek,Plester & Acian Listplank Beton m2 83,00 171.600 14.242.800 0,592%
7 Pengecatan Listplank Beton exterior fin. Cat waterproof m2 83,00 74.360 6.171.880 0,256%
8 Balok Lintel m2 1,87 8.294.000 15.489.045 0,644%
9 Tangga Beon + bekisting (sesuai design) Unit 1,00 35.750.000 35.750.000 1,486%
10 Finishing Kolom (Plester + Acian) m1 72,00 271.700 19.562.400 0,813%
Sub Total 344.154.096 14,301%
II PEKERJAAN ARSITEKTUR LT.2
A PEKERJAAN DINDING DAN FINISHING
1 Pasang Dinding Hebel m2 348,80 193.050 67.335.840 2,798%
2 Pek,Plester & Acian m2 697,60 122.980 85.790.848 3,565%
3 Pek,Openingan m1 236,00 122.980 29.023.280 1,206%
4 Pengecatan dinding exterior fin. Cat waterproof m2 253,75 74.360 18.868.850 0,784%
5 Pemasangan Wallpaper m2 420,00 143.000 60.060.000 2,496%
6 Dinding Partisi Gibsum 2 lapis m2 75,00 271.700 20.377.500 0,847%
7 Pengecatan dinding Interior Exs Vinilex m2 150,00 47.190 7.078.500 0,294%
8 Kolom Facade fin. Acian + cat waterproof m1 24,00 257.400 6.177.600 0,257%
9 Dinding Façade Batu Alam m2 24,50 873.730 21.406.385 0,890%
Sub Total 316.118.803 13,136%
B PEKERJAAN JENDELA DAN PINTU
1 Pintu (P.1) Tipe Doble Pintu swing + Kusen Aluminium set 2,00 9.295.000 18.590.000 0,773%
Spesifikasi :
- Kusen Aluminium fin. Powder coating warna coklat.
- Daun pintu Double plywood t. 5 mm + rangka kayu solid
(Solid Engineering Door) fin. Melamik.
- Jendela kaca t. 6 mm rangka aluminium fin. Powder coating warna
coklat.
- Aksesoris : Engsel kupu-kupu (2 set), Handle + lock (2 set)
ADDWORK GEDUNG A Page 3 of 7

HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp

2 Pintu (P.2) Tipe Pintu swing Kusen Aluminium set 7,00 6.006.000 42.042.000 1,747%
Spesifikasi :
- Kusen Aluminium fin. Powder coating warna coklat.
- Daun pintu Kaca t. 5 mm + rangka Alumunium
- Aksesoris : Engsel kupu-kupu (1 set), Lever handle (1 set),
Lockcase (1 set).

3 Pintu (P3) Tipe Pintu swing + Kusen Aluminium set 7,00 2.574.000 18.018.000 0,749%
Spesifikasi :
- Kusen Aluminium fin. Powder coating warna coklat.
- Daun pintu Double plywood t. 6 mm + rangka kayu
fin. Melamik (Flush Door).
- Aksesoris : Engsel kupu-kupu (1 set), Handle + lock (1 set),
window stopper (1 set), Lockcase (1 set).

4 Jendela (J. 8) Tipe Jendela Jungkit & Jendela Mati (tuga daun besar) set 3,00 13.942.500 41.827.500 1,738%
Spesifikasi :
- Kusen dan rangka aluminium ex. Alexindo
- Kusen Aluminium fin. Powder coating warna coklat.
- Daun aluminium fin. Powder coating + kaca clear t. 6 mm.
- Aksesoris : Engsel kupu-kupu (2 set), Handle + lock (2 set)
window stopper (2 set).

5 Jendela (J. 2) Tipe Jendela Jungkit set 9,00 4.576.000 41.184.000 1,711%
Spesifikasi :
- Kusen Aluminium fin. Powder coating warna coklat.
- Daun aluminium fin. Powder coating + kaca clear t. 6 mm.
- Aksesoris : Engsel kupu-kupu (2 set), Handle + lock (2 set)
window stopper (1 set).
ADDWORK GEDUNG A Page 4 of 7

HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp

6 Bouvenlight Mati (BV1) set 6,00 587.909 3.527.453 0,147%


Spesifikasi : -
- Kusen Aluminium fin. Powder coating warna coklat.
- Daun aluminium fin. Powder coating + kaca clear t. 6 mm.

Sub Total 165.188.953 6,864%


C PEKERJAAN LANTAI LT.2
1 Lantai Marmer -
a. Lantai Utama m2 295,00 1.644.500 485.127.500 20,160%
b. Lantai Tangga m2 34,00 1.644.500 55.913.000 2,323%
2 Plint Dinding HT ukuran 10x60 m1 147,00 164.450 24.174.150 1,005%
3 Pas.Keramik Dinding Toilet m2 135,00 436.150 58.880.250 2,447%
4 Pas.Keramik Lantai Toilet m2 17,85 393.250 7.019.513 0,292%

Sub Total 631.114.413 26,226%


D PEKERJAAN PLAFON DAN FINISHING
1 Plafon gypsum t. 9 mm rangka hollow 40x40 mm m2 295,00 138.138 40.750.710 1,693%
2 Pengecatan plafon gypsum m2 295,00 47.190 13.921.050 0,578%
3 List nad aluminium U 30x30 mm m1 24,00 25.740 617.760 0,026%
4 List Gibsum U 60mm m2 213,00 32.890 7.005.570 0,291%

Sub Total 62.295.090 2,589%


E PEKERJAAN ATAP
1 Pas.Rangka Atap Baja Ringan m2 354,00 235.950 83.526.300 3,471%
2 Pas.Atap Genteng Keramik Kanmuri m1 354,00 370.370 131.110.980 5,448%
3 Pas. Nok atap m1 45,00 401.830 18.082.350 0,751%
4 Pas.Lisplank Woodplank m1 79,00 64.350 5.083.650 0,211%
5 Pengecatan Nok atap m1 45,00 32.890 1.480.050 0,062%
6 Pengecatan Lisplank (cat minyak) m1 79,00 37.752 2.982.408 0,124%
Sub Total 242.265.738 10,067%
ADDWORK GEDUNG A Page 5 of 7

HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp

III. PEKERJAAN ELEKTRIKAL


-
A Pekerjaan Panel - -
1 Penyambungan daya PLN 2200 VA unit 1,00 0,000%
2 MCB - Box 12 Group unit 1,00 2.022.020 2.022.020 0,084%

B Pekerjaan Kabel Feeder


Dari KWH ke :
1 MCB - Box 12 Group m' 42,00 223.795 9.399.390 0,391%

C Pekerjaan Grounding Elektrikal


1 Dari KWH ke : Pekerjaan Grounding m' 47,00 102.960 4.839.120 0,201%
2 Stikrood 5/8 btg 2,00 1.787.500 3.575.000 0,149%
3 BC 35mm m' 48,00 74.360 3.569.280 0,148%
4 Splitzent buah 2,00 929.500 1.859.000 0,077%
5 Cadweel titik 4,00 243.100 972.400 0,040%

D Pekerjaan Instalasi, Fixtures dan Armatures


1 Instalasi Penerangan titik 33,00 243.100 8.022.300 0,333%
2 Instalasi Exhaust Fan titik 3,00 243.100 729.300 0,030%
3 Instalasi Saklar Single titik 11,00 243.100 2.674.100 0,111%
4 Instalasi Saklar Double titik 6,00 243.100 1.458.600 0,061%
5 Instalasi Stop Kontak 1Ph, 10A, 200Va titik 22,00 243.100 5.348.200 0,222%
6 Instalasi Stop Kontak AC 1Ph, 16A, 1000Va titik 6,00 243.100 1.458.600 0,061%
7 Lampu Downlight PL-C 14 Watt bh 4,00 171.600 686.400 0,029%
8 Lampu Baret 14 Watt bh 13,00 345.345 4.489.485 0,187%
9 Lampu TL 40 Watt bh 16,00 307.450 4.919.200 0,204%
10 Exhaust Fan 25 w bh 3,00 929.500 2.788.500 0,116%
11 Saklar Single bh 11,00 78.650 865.150 0,036%
12 Saklar Double bh 6,00 78.650 471.900 0,020%
ADDWORK GEDUNG A Page 6 of 7

HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp

13 Stop Kontak Dinding 1Ph, 10A, 200Va bh 22,00 78.650 1.730.300 0,072%
14 Stop Kontak AC 1Ph, 16A, 1000Va bh 6,00 121.550 729.300 0,030%
Sub Total 62.607.545 2,602%
-
IV. PEKERJAAN MEKANIKAL PLUMBING -
-
A PEKERJAAN PLUMBING AIR BERSIH -
-
A1 Peralatan Utama - -
2 Pas.Jetwasher Set 3,00 1.787.500 5.362.500 0,223%
3 Pas.Kloset Duduk Set 3,00 5.005.000 15.015.000 0,624%
4 Pas.Floordrain Set 3,00 178.750 536.250 0,022%
5 Pas.Wastafel Set 3,00 3.932.500 11.797.500 0,490%
6 Pas.Krant Set 6,00 107.250 643.500 0,027%
7 Urinair Set 6,00 3.575.000 21.450.000 0,891%
5 Pas. Meja Wastafel Set 2,00 21.450.000 42.900.000 1,783%
A2 Instalasi Pemipaan
1 Pipa Φ 1 " m' 14,00 44.187 618.618 0,026%
2 Pipa Φ 3/4" m' 32,00 27.885 892.320 0,037%
3 Pipa Φ 1/2" m' 36,00 25.454 916.344 0,038%
4 Fiting-fiting, klem, support dan gantungan serta finishing lot 1,00 1.430.000 1.430.000 0,059%
5 Gate Valve Φ 1 " bh 1,00 691.405 691.405 0,029%
6 Check Valve Φ 1 " bh 1,00 687.544 687.544 0,029%

B PEKERJAAN PLUMBING AIR KOTOR, AIR BEKAS DAN AIR HUJAN

B2 Instalasi Pemipaan Air Kotor


1 Pipa Φ 3" m' 30,00 128.700 3.861.000 0,160%
2 Pipa Φ 4" m' 30,00 148.763 4.462.887 0,185%
3 Fiting-fiting, klem, support dan gantungan serta finishing lot 1,00 715.000 715.000 0,030%
ADDWORK GEDUNG A Page 7 of 7

HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp

4 Clean Out Φ 4" bh 4,00 109.252 437.008 0,018%

B3 Instalasi Pemipaan Air Bekas


1 Pipa Φ 3" m' 28,00 128.700 3.603.600 0,150%
2 Pipa Φ 2" m' 2,00 59.774 119.548 0,005%
3 Pipa Φ 1 1/2" m' 2,00 52.481 104.962 0,004%
4 Fiting-fiting, klem, support dan gantungan serta finishing lot 1,00 715.000 715.000 0,030%
5 Floor Drain Φ 4" bh 10,00 225.797 2.257.970 0,094%
6 Floor Drain Φ 3" bh 2,00 145.574 291.148 0,012%

B4 Instalasi Pemipaan Air Hujan


1 Pipa Φ 4" m' 16,00 148.763 2.380.206 0,099%
2 Pipa Φ 3" m' 18,00 128.700 2.316.600 0,096%
3 Fiting-fiting, klem, support dan gantungan serta finishing lot 1,00 715.000 715.000 0,030%
4 Roof Drain Φ 3" lot 2,00 145.574 291.148 0,012%
Sub Total 125.212.058 5,203%

2.406.433.708 100,000%