REKAPITULASI ENGINEER ESTIMATE

(REKAP EE)
PEKERJAAN PEMELIHARAAN KIRMIR DAN JALAN LINGKUNGAN BALAI

DINAS KETAHANAN PANGAN DAN PERTERNAKAN

PROVINSI JAWA BARAT

JUMLAH
NO URAIAN PEKERJAAN HARGA
(Rp.)

A PEKERJAAN PERSIAPAN 41.926.774,84


B PEKERJAAN KIRMIR 55.483.299,08
C PEKERJAAN JALAN LINGKUNGAN 72.950.554,88
D PEKERJAAN LAIN-LAIN 8.200.000,00
SUB TOTAL Rp. 178.560.628,80
PPn 10% Rp. 17.856.062,88
JUMLAH TOTAL Rp. 196.416.691,67
DIBULATKAN Rp. 196.416.000,00

Terbilang : SERATUS SEMBILAN PULUH ENAM JUTA EMPAT RATUS ENAM BELAS RIBU RUPIAH

BANDUNG, 2020
KONSULTAN PERENCANA
CV.CIPTA DESAIN SELARAS

AGUNG SAMOLO
DIREKTUR
ENGINEER ESTIMATE
(EE)
PEKERJAAN PEMELIHARAAN KIRMIR DAN JALAN LINGKUNGAN BALAI
DINAS KETAHANAN PANGAN DAN PERTERNAKAN
PROVINSI JAWA BARAT
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
(Rp.) (Rp.)

A PEKERJAAN PERSIAPAN
A.1 Administrasi dan dokumentasi ls 1,00 350.000,00 350.000,00
A.2 Papan nama proyek ls 1,00 500.000,00 500.000,00
A.3 Pengukuran dan Bouwplank m1 59,93 113.500,62 6.801.524,84
A.4 Mobilisasi dan demobilisasi (Bahan dan Alat) ls 1,00 3.500.000,00 3.500.000,00
A.5 Cut and Fill m3 310,00 99.275,00 30.775.250,00
JUMLAH PEKERJAAN PERSIAPAN 41.926.774,84
B PEKERJAAN KIRMIR
B.1 Pek. Galian Tanah Keras m3 43,12 117.295,20 5.057.769,02
B.2 Pek. Urugan Pasir 5cm m3 1,38 325.666,00 449.419,08
B.3 Pek. Aanstamping 15 cm m3 3,99 576.084,30 2.298.576,36
B.4 Pek. Pas. Kirmir 1:3 m3 25,42 1.050.387,80 26.700.857,88
B.5 Pek. Pondasi Footplate
- Cor beton K-250 m3 1,83 1.555.752,07 2.847.026,29
- Besi kg 274,50 18.700,00 5.133.150,00
- Bekisting m2 3,48 194.025,70 674.627,36
B.6 Pek. Sloof 20/20
- Cor beton K-250 m3 1,59 1.555.752,07 2.473.645,79
- Besi kg 238,50 18.700,00 4.459.950,00
- Bekisting m2 3,02 194.025,70 586.151,64
B.7 Pek. Urugan Tanah kembali m3 10,44 28.939,24 302.125,67
B.8 Pek. Pondasi rucuk bambu dan pemancangan ls 1,00 3.000.000,00 3.000.000,00
B.9 Pek. Pipa Suling ls 1,00 1.500.000,00 1.500.000,00
JUMLAH PEKERJAAN KIRMIR 55.483.299,08
C PEKERJAAN JALAN LINGKUNGAN
C.1 Pek. Urugan Sirtu dipadatkan m3 13,40 349.415,00 4.682.161,00
C.2 Pek. Lantai Kerja m3 6,70 1.261.962,68 8.455.149,96
C.3 Pek. Rigid Beton Jalan
- Cor beton K-250, tbl. 10 cm m3 13,40 1.555.752,07 20.847.077,72
- Wiremesh M8 Kg 1.742,00 18.700,00 32.575.400,00
- Bekisting m2 10,21 194.025,70 1.981.390,45
- Cutting dan aspal silent m1 24,00 27.000,00 648.000,00
- Plastik Cor m2 134,09 20.000,00 2.681.800,00
C.4 Pek. Grill Besi m1 2,50 431.830,30 1.079.575,75
JUMLAH PEKERJAAN JALAN LINGKUNGAN 72.950.554,88
D PEKERJAAN LAIN-LAIN
D.1 Pembersihan dan pembuangan bekas pekerjaan ls 1,00 8.200.000,00 8.200.000,00
JUMLAH PEKERJAAN LAIN-LAIN 8.200.000,00
ANALISIS HARGA SATUAN PEKERJAAN (AHSP)
BIDANG CIPTA KARYA
BERDASARKAN PERWAL BANDUNG ASB 2019

Uraian Pekerjaan Koefisien Satuan Harga Jumlah


Pasang 1 m' bouwplank M1
Pekerja 0,1000 Oh 133.583,22 13.358,32
Tukang 0,0100 Oh 166.985,64 1.669,86
Kepala Tukang 0,0100 Oh 200.435,65 2.004,36
Mandor 0,0100 Oh 234.017,88 2.340,18
Kaso 5/7 cm 0,0130 m3 3.589.667,00 46.665,67
Papan 3/20 0,0070 m3 5.082.000,00 35.574,00
Paku 5 cm dan 7 cm 0,0200 Kg 23.500,00 470,00
Waterpass 0,0040 Sewa-Hari 275.000,00 1.100,00
Total 103.182,38
Overhead 10% 10.318,24
Total Seluruh 113.500,62
1 M3 Galian Tanah Kedalaman 1 M M3
Pekerja 0,8500 O.H 101.000,00 85.850,00
Mandor 0,0250 O.H 176.000,00 4.400,00
Total 90.250,00
Overhead 10% 9.025,00
Total Seluruh 99.275,00
1 M3 Galian Tanah Keras Kedalaman 1 M M3
Pekerja 1,0000 O.H 101.000,00 101.000,00
Mandor 0,0320 O.H 176.000,00 5.632,00
Total 106.632,00
Overhead 10% 10.663,20
Total Seluruh 117.295,20
1 M3 Pasangan Pondasi Batu Belah, 1 Pc. : 3 M3
Pp.
Batu Belah 15/20 Cm 1,2000 M3 240.000,00 288.000,00
Semen Portland 4,0400 Zak 68.700,00 277.548,00
Pasir Pasang 0,4850 M3 245.000,00 118.825,00
Pekerja 1,5000 O.H 101.000,00 151.500,00
Tukang Batu 0,7500 O.H 126.000,00 94.500,00
Kepala Tukang Batu 0,0750 O.H 151.000,00 11.325,00
Mandor 0,0750 O.H 176.000,00 13.200,00
Total 954.898,00
Overhead 10% 95.489,80
Total Seluruh 1.050.387,80
1 M3 Urugan Tanah Kembali M3
Pekerja 0,2500 O.H 101.000,00 25.250,00
Mandor 0,0084 O.H 126.000,00 1.058,40
Total 26.308,40
Overhead 10% 2.630,84
Total Seluruh 28.939,24
1 m³ beton mutu, f’c = 7,4 MPa (K100), slump M3
(12±2) cm, w/c = 0,87
Pekerja 1,3230 OH 101.000,00 133.623,00
Tukang 0,1890 OH 126.000,00 23.814,00
Kepala Tukang 0,0190 OH 151.000,00 2.869,00
Mandor 0,1320 OH 176.000,00 23.232,00
Semen (PC) 6,1750 kg 68.700,00 424.222,50
Pasir Beton 0,4943 M3 245.000,00 121.103,50
Koral Beton 0,7697 M3 184.000,00 141.624,80
Air 215,0000 Liter 50,00 10.750,00
Molen 1,7500 Sewa-Hari 152.000,00 266.000,00
Total 1.147.238,80
Overhead 10% 114.723,88
Total Seluruh 1.261.962,68
1 M3 Beton Mutu FC = 21,7 Mpa (K 250) M3
Semen Portland 9,6800 Zak 68.700,00 665.016,00
Pasir Beton 0,5943 M3 245.000,00 145.603,50
Koral Beton 0,8697 M3 184.000,00 160.024,80
Air 215,0000 Liter 50,00 10.750,00
Molen 1,7500 Sewa-Hari 121.594,15 212.789,76
Pekerja 1,6500 O.H 101.000,00 166.650,00
Tukang Batu 0,2750 O.H 126.000,00 34.650,00
Kepala Tukang Batu 0,0280 O.H 151.000,00 4.228,00
Mandor 0,0830 O.H 176.000,00 14.608,00
Total 1.414.320,06
Overhead 10% 141.432,01
Total Seluruh 1.555.752,07
1 Kg Besi Kg
Pekerja 0,0200 Oh 101.000,00 2.020,00
Tukang 0,0050 Oh 126.000,00 630,00
Mandor 0,0050 Oh 176.000,00 880,00
Wiremesh 1,1000 Kg 11.200,00 12.320,00
Kawat Beton 0,0200 Kg 24.500,00 490,00
Alat Bantu 1,0000 Ls 660,00 660,00
Total 17.000,00
Overhead 10% 1.700,00
Total Seluruh 18.700,00
1 m2 Bekisting balok beton biasa dengan Multipleks (tanpa perancah) dengan 2x pemakaian m2
Pekerja 0,3600 OH 101.000,00 36.360,00
Tukang 0,3600 OH 126.000,00 45.360,00
Kepala Tukang 0,0360 OH 151.000,00 5.436,00
Mandor 0,0360 OH 176.000,00 6.336,00
Multipleks 0,2030 lbr 185.000,00 37.555,00
kaso 5/7 cm 0,0230 m3 1.615.000,00 37.145,00
Paku 5 cm dan 7 cm 0,3200 Kg 23.500,00 7.520,00
Minyak Bekisting 0,2500 Ltr 2.700,00 675,00
Total 176.387,00
Overhead 10% 17.638,70
Total Seluruh 194.025,70
1 M3 Urugan Pasir M3
Pasir Urug 1,2000 M3 220.000,00 264.000,00
Pekerja 0,3000 O.H 101.000,00 30.300,00
Mandor 0,0100 O.H 176.000,00 1.760,00
Total 296.060,00
Overhead 10% 29.606,00
Total Seluruh 325.666,00
1 M3 Pasangan Batu Kosong / Aanstamping M3
Batu Belah 15/20 Cm 1,2000 M3 240.000,00 288.000,00
Pasir Urug 0,4320 M3 220.000,00 95.040,00
Pekerja 0,7800 O.H 101.000,00 78.780,00
Tukang Batu 0,3900 O.H 126.000,00 49.140,00
Kepala Tukang Batu 0,0390 O.H 151.000,00 5.889,00
Mandor 0,0390 O.H 176.000,00 6.864,00
Total 523.713,00
Overhead 10% 52.371,30
Total Seluruh 576.084,30
1 M3 Urugan Sirtu M3
Sirtu (Tersaring) 1,2000 M3 240.000,00 288.000,00
Pekerja 0,2500 O.H 101.000,00 25.250,00
Mandor 0,0250 O.H 176.000,00 4.400,00
Total 317.650,00
Overhead 10% 31.765,00
Total Seluruh 349.415,00
1 M Pasang Grill Besi UNP M
Besi UNP 6,0000 M 64.166,67 385.000,00
Pekerja 0,0200 O.H 101.000,00 2.020,00
Tukang 0,0300 O.H 126.000,00 3.780,00
Kepala Tukang 0,0030 O.H 151.000,00 453,00
Mandor 0,0075 O.H 176.000,00 1.320,00
Total 392.573,00
Overhead 10% 39.257,30
Total Seluruh 431.830,30
1 M1 Gorong-gorong Pipa Beton 100 cm M1
Pekerja 0,2000 Oh 133.583,22 26.716,64
Mandor 0,0400 Oh 234.017,88 9.360,72
Buis Beton 100 cm 2,0000 Buah 300.000,00 600.000,00
Urugan Porus 0,1220 M3 92.600,00 11.297,20
Mat. Pilihan 0,2277 M3 95.071,00 21.647,67
Semen 18,3192 Kg 1.500,00 27.478,80
Tamper 0,4779 jam 91.334,09 43.648,56
Alat Bantu 1,0000 Ls 1.320,00 1.320,00
Total 741.469,59
Overhead 10% 74.146,96
Total Seluruh 815.616,55
DAFTAR HARGA SATUAN BAHAN
TAHUN ANGGARAN : 2020

Harga Satuan
No. Jenis Bahan Bangunan Sat.
( Rp. )
1 Batu Belah 15/20 Cm M3 240.000,00
2 Semen Portland Zak 68.700,00
3 Pasir Urug M3 220.000,00
4 Pasir Pasang M3 245.000,00
5 Pasir Beton M3 245.000,00
6 Koral Beton M3 184.000,00
7 Air Liter 50,00
8 Molen Sewa-Hari 152.000,00
9 Wiremesh Kg 11.200,00
10 Kawat Beton Kg 24.500,00
11 Multipleks lbr 185.000,00
12 kaso 5/7 cm m3 1.615.000,00
13 Paku 5 cm dan 7 cm Kg 23.500,00
14 Minyak Bekisting Ltr 2.700,00
15 Sirtu (Tersaring) m3 240.000,00
16 UNP m 64.166,67
DAFTAR HARGA SATUAN UPAH
TAHUN ANGGARAN : 2020
Harga Satuan
No. Jenis Pekerjaan Sat.
( Rp. )
1 2 3 4
1 Pekerja Oh 101.000,00
2 Tukang Oh 126.000,00
3 Kepala Tukang Oh 151.000,00
4 Mandor Oh 176.000,00