Anda di halaman 1dari 2

PEMERINTAH KABUPATEN BANDUNG

DINAS PERUMAHAN RAKYAT, KAWASAN PEMUKIMAN DAN PERTANAMAN

PENATAAN TAMAN PEMERINTAH

RENCANA ANGGARAN BIAYA


Rev A - 22/10/2019

No. Uraian Unit Volume Harga Satuan Total


( IDR ) ( IDR )

A. PEKERJAAN PERSIAPAN 22,089,200.00


1 Pembersihan lahan ( +/- 900 m2) ls 1.00 9,450,000.00 9,450,000.00
3 Pembuatan Kantor / Gudang (+/- 12 m2) ls 1.00 10,639,200.00 10,639,200.00
4 Dokumentasi ls 1.00 500,000.00 500,000.00
5 Shop Drawings & As Built Drawings ls 1.00 1,500,000.00 1,500,000.00

B. PEKERJAAN KONSTRUKSI LAHAN 265,375,786.90


B.1 Pekerjaan Tanah 9,859,705.90
1 Galian tanah m3 89.63 76,500.00 6,856,977.29
2 Buangan tanah bekas galian (+/- 1 km) m3 89.63 33,500.00 3,002,728.62

B.2 Sistem Saluran & Drainasi 154,685,700.00


Saluran Uditch 60x60 cm (termasuk Galian, Timbunan kembali ,
1 dan buang tanah sisa glian dan timbuna, Lantai kerja, Pasir
dipadatkan, pemadatan tanah dasar)
(a) - U-600 m' 169.00 915,300.00 154,685,700.00

B.3 Jalan, Parkir dan Pedestrian 89,851,101.00


1 Pedestrian / Trotoar pejalan kaki
Pasangan Paving Blok Hexagon K-400 t = 60 mm, urugan pasir di
(a) m2 177.000 220,400.00 39,010,800.00
padatkan
(C) - Pemadatan tanah dasar, CBR 5% m2 177.00 6,200.00 1,097,400.00
2 Kanstin (termasuk urugan pasir dipadatkan)
(a) - Kanstin tipe 1, 400x280x150 mm m' 328.77 151,300.00 49,742,901.00

B.4 Pekerjaan Lansekap 10,979,280.00


1 Rumput Gajah mini m2 280.80 39,100.00 10,979,280.00

C PEKERJAAN SIPIL & STRUKTUR 96,035,604.60


C.1 - Lapang Bola Terbuka
Slab Beton , t = 100 mm
- Beton Mutu K-225 m3 63.08 1,049,600.00 66,211,706.88
- Bekisting m2 12.23 93,500.00 1,143,093.60
C.2 - Taman skatebaord
Slab Beton , t = 100 mm
- Beton Mutu K-225 m3 26.55 1,049,600.00 27,867,814.14
- Bekisting m2 8.70 93,500.00 812,989.98

D PEKERJAAN ARSITEKTUR 189,735,149.45


D.1 - Lapang Bola Terbuka
1 Acian untuk lantai m2 630.83 30,500.00 19,240,254.00
2 Garis lantai untuk lapangan bola t=80 mm m1 170.82 5,700.00 973,674.00
3 Pagar Jaring (tinggi 4.12 m) m1 41.00 819,400.00 33,595,400.00
4 Gawang unit 2.00 4,526,000.00 9,052,000.00

D.2 - Taman skatebaord


1 Acian untuk lantai m2 265.51 30,500.00 8,098,021.45
2 Seluncuran Skateboard 1 unit 1.00 16,616,000.00 16,616,000.00
3 Seluncuran Skateboard 2 unit 2.00 420,900.00 841,800.00
4 Seluncuran Skateboard 3 unit 2.00 5,201,600.00 10,403,200.00
5 Cover Toren unit 2.00 30,381,500.00 60,763,000.00
6 Bangku beton unit 2.00 5,400,800.00 10,801,600.00
7 Pot Bata unit 2.00 5,119,000.00 10,238,000.00
8 Trotoar Segmen unit 1.00 9,112,200.00 9,112,200.00

E PEKERJAAN ELEKTRIKAL
E.1 Pekerjaan Armatur Lampu, Saklar & Stop Kontak
Luar Bangunan : Taman & Lapang
Lampu Taman LED Bulb 14 w, Tipe GL Pilar Daiko E27 bh 10.00 1,319,000.00 13,190,000.00
E.2 Perjaan Instalasi Final
Luar Bangunan : Taman & Lapang
NYM 3 x 2,5 mm2 + PVC Conduit dia.20 untuk Lampu ttk 10.00 402,000.00 4,020,000.00

Total 590,445,740.95
PPN 10 % 59,044,574.10
Grand Total 649,490,315.05

RAB-TAMANPEMKAB Page 1
Pembulatan 649,490,000.00

RAB-TAMANPEMKAB Page 2

Anda mungkin juga menyukai