HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp
I PEKERJAAN PERSIAPAN
1 Pengukuran & Bowplank Ls 1,00 7.150.000 7.150.000 0,437%
2 Air Kerja & Listrik ls 1,00 2.145.000 2.145.000 0,131%
Sub Total 9.295.000 0,569%
II PEKERJAAN STRUKTUR
A PEKERJAAN ANAH & PONDASI
1 Galian Tanah Pondasi Cakar Ayam m3 12,00 111.540 1.338.480 0,082%
1 Galian Tanah Pondasi Batu Kali m3 18,90 111.540 2.108.106 0,129%
1 Galian Tanah Septiktank m3 8,00 171.600 1.372.800 0,084%
2 Pek.Lantai Kerja m3 0,60 1.930.500 1.158.300 0,071%
3 Pondasi Cakar Ayam m3 3,00 8.294.000 24.882.000 1,522%
2 Anstamping m3 6,48 373.230 2.418.530 0,148%
3 Pas.Pondasi Batu Kali m3 11,34 1.215.500 13.783.770 0,843%
4 Pas.Sloof m3 3,24 8.294.000 26.872.560 1,644%
9 Urugan Kembali m3 16,56 64.350 1.065.636 0,065%
Sub Total 75.000.182 4,588%
B PEKERJAAN STRUKTUR LT.1
1 Balok 20x40 cm, K-225, tul. 8D13, 2D10, SK Ø8-100/200 + bekisting m3 1,20 8.294.000 9.952.800 0,609%
2 Balok 15x30 cm, K-225, tul. 4D13, 2D13, SK Ø8-100/200 + bekisting m3 2,34 8.294.000 19.407.960 1,187%
3 Kolom 25x35 cm, K-225, tul. 12.D13, SK Ø8-100/200 + bekisting m3 5,25 8.294.000 43.543.500 2,664%
4 Balok Lintel m3 0,95 8.294.000 7.837.830 0,479%
5 Plat (S1) dak elv. +4.00 t. 120 mm, K-225, tul. Ø8-200 double + bekisting m3 12,90 8.294.000 106.992.600 6,545%
6 Listplank Beton, K-225, tul.Ø12-150, Ø8-200 + bekisting m3 3,24 8.294.000 26.872.560 1,644%
RAP ADDWORK KANTIN Page 2 of 7
HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp
HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp
2 Pintu (P3) Tipe Pintu swing + Kusen Aluminium set 2,00 2.574.000 5.148.000 0,315%
Spesifikasi :
- Kusen Aluminium fin. Powder coating warna Hitam.
- Daun pintu Double plywood t. 6 mm + rangka kayu
fin. Melamik (Flush Door).
- Aksesoris : Engsel kupu-kupu (1 set), Handle + lock (1 set),
window stopper (1 set), Lockcase (1 set).
3 Jendela (J. 8) Tipe Jendela Jungkit & Jendela Mati (tuga daun besar) set 7,00 13.942.500 97.597.500 5,970%
Spesifikasi :
- Kusen Aluminium fin. Powder coating warna Hitam.
- Daun aluminium fin. Powder coating + kaca clear t. 6 mm.
RAP ADDWORK KANTIN Page 4 of 7
HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp
HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp
A Pekerjaan Panel - -
1 Penyambungan daya PLN 5500 VA unit 1,00 19.305.000 19.305.000 1,181%
2 MCB - Box 12 Group unit 1,00 2.022.020 2.022.020 0,124%
HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp
HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp
1.634.818.907 100,000%