RENCANA ANGGARAN BIAYA PEKERJAAN RENOVASI GEDUNG


BADAN CADANGAN LOGISTIK STRATEGIS
NAMA PEKERJAAN : PEMBANGUNAN KANTIN & MUSHOLA BARU
LOKASI : JL.KAMPUS LABSHCOOL CIBUBUR RT 003 RW 005 NO 720
: JATINANGOR - BEKASI
TAHUN ANGGARAN : 2022

HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp

I PEKERJAAN PERSIAPAN
1 Pengukuran & Bowplank Ls 1,00 7.150.000 7.150.000 0,437%
2 Air Kerja & Listrik ls 1,00 2.145.000 2.145.000 0,131%
Sub Total 9.295.000 0,569%
II PEKERJAAN STRUKTUR
A PEKERJAAN ANAH & PONDASI
1 Galian Tanah Pondasi Cakar Ayam m3 12,00 111.540 1.338.480 0,082%
1 Galian Tanah Pondasi Batu Kali m3 18,90 111.540 2.108.106 0,129%
1 Galian Tanah Septiktank m3 8,00 171.600 1.372.800 0,084%
2 Pek.Lantai Kerja m3 0,60 1.930.500 1.158.300 0,071%
3 Pondasi Cakar Ayam m3 3,00 8.294.000 24.882.000 1,522%
2 Anstamping m3 6,48 373.230 2.418.530 0,148%
3 Pas.Pondasi Batu Kali m3 11,34 1.215.500 13.783.770 0,843%
4 Pas.Sloof m3 3,24 8.294.000 26.872.560 1,644%
9 Urugan Kembali m3 16,56 64.350 1.065.636 0,065%
Sub Total 75.000.182 4,588%
B PEKERJAAN STRUKTUR LT.1
1 Balok 20x40 cm, K-225, tul. 8D13, 2D10, SK Ø8-100/200 + bekisting m3 1,20 8.294.000 9.952.800 0,609%
2 Balok 15x30 cm, K-225, tul. 4D13, 2D13, SK Ø8-100/200 + bekisting m3 2,34 8.294.000 19.407.960 1,187%
3 Kolom 25x35 cm, K-225, tul. 12.D13, SK Ø8-100/200 + bekisting m3 5,25 8.294.000 43.543.500 2,664%
4 Balok Lintel m3 0,95 8.294.000 7.837.830 0,479%
5 Plat (S1) dak elv. +4.00 t. 120 mm, K-225, tul. Ø8-200 double + bekisting m3 12,90 8.294.000 106.992.600 6,545%
6 Listplank Beton, K-225, tul.Ø12-150, Ø8-200 + bekisting m3 3,24 8.294.000 26.872.560 1,644%
RAP ADDWORK KANTIN Page 2 of 7

HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp

Sub Total 214.607.250 13,127%


C PEKERJAAN PEKERJAAN TANGGA DAN RAILLNG
1 Pek.Beton Tangga Ls 1,00 24.310.000 24.310.000 1,487%
2 Lantai Tangga fin. Homogenous tile 60x60 cm m2 19,48 602.745 11.741.473 0,718%
3 Step Nosing m1 37,00 207.350 7.671.950 0,469%
4 Finishing tangga sisi bawah dan samping fin. Plesteran s/d acian + cat m2 9,90 210.210 2.081.079 0,127%
5 Railling tangga m1 12,90 1.206.563 15.564.656 0,952%
6 Railling Balkon (Sesuai Gambar) m1 31,00 1.206.563 37.403.438 2,288%
98.772.595 6,042%
D PEKERJAAN STRUKTUR LT.2
1 Balok 20x40 cm, K-225, tul. 8D13, 2D10, SK Ø8-100/200 + bekisting m3 1,20 8.294.000 9.952.800 0,609%
2 Balok 15x30 cm, K-225, tul. 4D13, 2D13, SK Ø8-100/200 + bekisting m3 2,34 8.294.000 19.407.960 1,187%
3 Plat (S1) dak elv. +7.50 t. 120 mm, K-225, tul. Ø8-200 double + bekisting m3 5,25 8.294.000 43.543.500 2,664%
4 Kolom 25x35 cm, K-225, tul. 12.D13, SK Ø8-100/200 + bekisting m3 3,50 8.294.000 29.029.000 1,776%
5 Listplank Beton, K-225, tul.Ø12-150, Ø8-200 + bekisting (LT.2) m3 3,24 8.294.000 26.872.560 1,644%
6 Pek,Plester & Acian Listplank Beton m2 108,00 171.600 18.532.800 1,134%
7 Balok Lintel m3 0,95 8.294.000 7.837.830 0,479%
8 Waterprofing m2 127,00 271.700 34.505.900 2,111%
9 Ban-banan diatas Lstplank Beton di Finish plester acian m1 54,00 271.700 14.671.800 0,897%
Sub Total 204.354.150 12,500%
II PEKERJAAN ARSITEKTUR
A PEKERJAAN DINDING DAN FINISHING
1 Pasang Dinding Hebel
Lantai 1 m2 277,50 193.050 53.571.375 3,277%
Lantai 2 m2 201,60 193.050 38.918.880 2,381%
2 Pek,Plester & Acian
Lantai 1 m2 555,00 122.980 68.253.900 4,175%
Lantai 2 m2 403,20 122.980 49.585.536 3,033%
3 Pek,Openingan
Lantai 1 m2 84,00 64.350 5.405.400 0,331%
RAP ADDWORK KANTIN Page 3 of 7

HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp

Lantai 2 m2 79,00 64.350 5.083.650 0,311%


4 Pengecatan dinding exterior fin. Cat waterproof
Lantai 1 m2 277,50 74.360 20.634.900 1,262%
Lantai 2 m2 201,60 74.360 14.990.976 0,917%
7 Pengecatan dinding Interior Exs Vinilex
Lantai 1 m2 277,50 47.190 13.095.225 0,801%
Lantai 2 m2 201,60 47.190 9.513.504 0,582%
8 Kolom Facade fin. Plester + Acian m1 82,50 257.400 21.235.500 1,299%
9 Dinding Façade Batu Alam m2 24,50 873.730 21.406.385 1,309%
Sub Total 321.695.231 19,678%
B PEKERJAAN JENDELA DAN PINTU
1 Pintu (P.2) Tipe Pintu swing Kusen Aluminium set 8,00 6.006.000 48.048.000 2,939%
Spesifikasi :
- Kusen Aluminium fin. Powder coating warna Hitam.
- Daun pintu Kaca t. 5 mm + rangka Alumunium
- Aksesoris : Engsel kupu-kupu (1 set), Lever handle (1 set),
Lockcase (1 set).

2 Pintu (P3) Tipe Pintu swing + Kusen Aluminium set 2,00 2.574.000 5.148.000 0,315%
Spesifikasi :
- Kusen Aluminium fin. Powder coating warna Hitam.
- Daun pintu Double plywood t. 6 mm + rangka kayu
fin. Melamik (Flush Door).
- Aksesoris : Engsel kupu-kupu (1 set), Handle + lock (1 set),
window stopper (1 set), Lockcase (1 set).

3 Jendela (J. 8) Tipe Jendela Jungkit & Jendela Mati (tuga daun besar) set 7,00 13.942.500 97.597.500 5,970%
Spesifikasi :
- Kusen Aluminium fin. Powder coating warna Hitam.
- Daun aluminium fin. Powder coating + kaca clear t. 6 mm.
RAP ADDWORK KANTIN Page 4 of 7

HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp

- Aksesoris : Engsel kupu-kupu (2 set), Handle + lock (2 set)


window stopper (2 set).

6 Bouvenlight Mati (BV1) set 6,00 587.909 3.527.453 0,216%


Spesifikasi : -
- Kusen Aluminium fin. Powder coating warna Hitam.
- Daun aluminium fin. Powder coating + kaca clear t. 6 mm.

Sub Total 154.320.953 9,440%


C PEKERJAAN LANTAI
1 Lantai Granit LT.1 -
a. Lantai Utama m2 86,00 436.150 37.508.900 2,294%
b. Lantai Teras m2 30,60 436.150 13.346.190 0,816%
2 Plint Dinding HT ukuran 10x60 m1 104,50 87.230 9.115.535 0,558%
3 Pas.Keramik Dinding Toilet m2 45,00 436.150 19.626.750 1,201%
4 Pas.Keramik Lantai Toilet m2 17,85 393.250 7.019.513 0,429%
5 Lantai Granit LT.2 -
a. Lantai Utama m2 86,00 1.644.500 141.427.000 8,651%
b. Lantai Teras m2 34,00 1.644.500 55.913.000 3,420%
6 Plint Dinding HT ukuran 10x60 m1 104,50 164.450 17.185.025 1,051%
Sub Total 301.141.913 18,421%
D PEKERJAAN PLAFON DAN FINISHING
1 Plafon gypsum t. 9 mm rangka hollow 40x40 mm m2 215,00 138.138 29.699.670 1,817%
2 Pengecatan plafon gypsum m2 215,00 47.190 10.145.850 0,621%
3 List nad aluminium U 30x30 mm m1 24,00 25.740 617.760 0,038%
4 List Gibsum U 60mm m2 209,00 32.890 6.874.010 0,420%

Sub Total 47.337.290 2,896%


III. PEKERJAAN ELEKTRIKAL
-
RAP ADDWORK KANTIN Page 5 of 7

HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp

A Pekerjaan Panel - -
1 Penyambungan daya PLN 5500 VA unit 1,00 19.305.000 19.305.000 1,181%
2 MCB - Box 12 Group unit 1,00 2.022.020 2.022.020 0,124%

B Pekerjaan Kabel Feeder


Dari KWH ke :
1
MCB - Box 12 Group m' 50,00 223.795 11.189.750 0,684%

C Pekerjaan Grounding Elektrikal


1 Dari KWH ke : Pekerjaan Grounding m' 55,00 102.960 5.662.800 0,346%
2 Stikrood 5/8 btg 2,00 1.787.500 3.575.000 0,219%
3 BC 35mm m' 48,00 74.360 3.569.280 0,218%
4 Splitzent buah 2,00 929.500 1.859.000 0,114%
5 Cadweel titik 4,00 243.100 972.400 0,059%

D Pekerjaan Instalasi, Fixtures dan Armatures


1 Instalasi Penerangan titik 25,00 243.100 6.077.500 0,372%
2 Instalasi Exhaust Fan titik 3,00 243.100 729.300 0,045%
3 Instalasi Saklar Single titik 11,00 243.100 2.674.100 0,164%
4 Instalasi Saklar Double titik 6,00 243.100 1.458.600 0,089%
5 Instalasi Stop Kontak 1Ph, 10A, 200Va titik 18,00 243.100 4.375.800 0,268%
6 Instalasi Stop Kontak AC 1Ph, 16A, 1000Va titik 6,00 243.100 1.458.600 0,089%
7 Lampu Downlight PL-C 14 Watt bh 4,00 171.600 686.400 0,042%
8 Lampu Baret 14 Watt bh 13,00 345.345 4.489.485 0,275%
9 Lampu TL 40 Watt bh 16,00 307.450 4.919.200 0,301%
10 Exhaust Fan 25 w bh 3,00 929.500 2.788.500 0,171%
11 Saklar Single bh 11,00 78.650 865.150 0,053%
12 Saklar Double bh 6,00 78.650 471.900 0,029%
13 Stop Kontak Dinding 1Ph, 10A, 200Va bh 18,00 78.650 1.415.700 0,087%
14 Stop Kontak AC 1Ph, 16A, 1000Va bh 6,00 121.550 729.300 0,045%
RAP ADDWORK KANTIN Page 6 of 7

HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp

Sub Total 81.294.785 4,973%


-
IV. PEKERJAAN MEKANIKAL PLUMBING -
-
A PEKERJAAN PLUMBING AIR BERSIH -
-
A1 Peralatan Utama - -
1 Pek.Septiktank Unit 1,00 1.787.500 1.787.500 0,109%
2 Pas.Jetwasher Set 3,00 1.787.500 5.362.500 0,328%
3 Pas.Kloset Duduk Set 3,00 5.005.000 15.015.000 0,918%
4 Pas.Floordrain Set 3,00 178.750 536.250 0,033%
5 Pas.Wastafel Set 3,00 3.932.500 11.797.500 0,722%
6 Pas.Krant Set 6,00 107.250 643.500 0,039%
7 Urinair Set 6,00 3.575.000 21.450.000 1,312%
5 Pas. Meja Wastafel Set 2,00 21.450.000 42.900.000 2,624%
A2 Instalasi Pemipaan
1 Pipa Φ 1 " m' 14,00 44.187 618.618 0,038%
2 Pipa Φ 3/4" m' 32,00 27.885 892.320 0,055%
3 Pipa Φ 1/2" m' 36,00 25.454 916.344 0,056%
4 Fiting-fiting, klem, support dan gantungan serta finishing lot 1,00 1.430.000 1.430.000 0,087%
5 Gate Valve Φ 1 " bh 1,00 691.405 691.405 0,042%
6 Check Valve Φ 1 " bh 1,00 687.544 687.544 0,042%

B PEKERJAAN PLUMBING AIR KOTOR, AIR BEKAS DAN AIR HUJAN

B1 Instalasi Pemipaan Air Kotor


1 Pipa Φ 3" m' 30,00 128.700 3.861.000 0,236%
2 Pipa Φ 4" m' 30,00 148.763 4.462.887 0,273%
3 Fiting-fiting, klem, support dan gantungan serta finishing lot 1,00 715.000 715.000 0,044%
4 Clean Out Φ 4" bh 4,00 109.252 437.008 0,027%
RAP ADDWORK KANTIN Page 7 of 7

HARGA
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN SAT VOLUME SATUAN
Rp. (%)
Rp

B2 Instalasi Pemipaan Air Bekas


1 Pipa Φ 3" m' 28,00 128.700 3.603.600 0,220%
2 Pipa Φ 2" m' 2,00 59.774 119.548 0,007%
3 Pipa Φ 1 1/2" m' 2,00 52.481 104.962 0,006%
4 Fiting-fiting, klem, support dan gantungan serta finishing lot 1,00 715.000 715.000 0,044%
5 Floor Drain Φ 4" bh 10,00 225.797 2.257.970 0,138%
6 Floor Drain Φ 3" bh 2,00 145.574 291.148 0,018%

B3 Instalasi Pemipaan Air Hujan


1 Pipa Φ 4" m' 16,00 148.763 2.380.206 0,146%
2 Pipa Φ 3" m' 18,00 128.700 2.316.600 0,142%
3 Fiting-fiting, klem, support dan gantungan serta finishing lot 1,00 715.000 715.000 0,044%
4 Roof Drain Φ 3" lot 2,00 145.574 291.148 0,018%
Sub Total 126.999.558 7,768%

1.634.818.907 100,000%