DAFTAR KUANTITAS DAN HARGA

PEKERJAAN TAMBAH / KURANG (CCO) AMANDEMEN KONTRAK

PENINGKATAN JALAN BAAD - SINEGI DISTRIK ANIMHA KABUPATEN MERAUKE

SEMULA PEKERJAAN TAMBAH/KURANG (CCO)

NO URAIAN PEKERJAAN SAT. PEKERJAAN TAMBAH PEKERJAAN KURANG


PERKIRAAN HARGA SATUAN JUMLAH HARGA BOBOT
VOLUME (Rupiah) (Rupiah) (%)
VOLUME JLH. HARGA VOLUME

I DEVISI 1 UMUM
1 Mobilisasi Ls 1.00 125,750,000.00 125,750,000.00 1.07
2 Pengukuran Dan Pematokan Jalan M1 1,480.00 1,257.00 1,860,360.00 0.02 -

II DEVISI 2 PEKERJAAN TIMBUNAN TANAH DAN PASIR PADA BADAN DAN BAHU JALAN
1 Timbunan Pilihan Bahu Jalan M3 284.66 275,673.00 78,473,076.18 0.67 315.56 86,991,738.07
2 Penyiapan Badan Jalan M2 13,320.00 1,009.00 13,439,880.00 0.11 -
3 Urugan Pasir M3 37.00 408,681.00 15,121,197.00 0.13 37.00

III DEVISI 3 PEKERJAAN PERKERASAN BADAN JALAN


1 Pondasi Jalan Beton Bertulang 25/28 Cm
1.a Cor Beton Mutu Sedang fc' = 25 Mpa (K - 300) M3 121.36 3,898,287.00 473,096,110.32 4.03 85.84 334,628,956.08
1.b besi Tulangan Diameter 10 Kg 9,715.47 18,297.00 177,763,954.59 1.51 342.50
1.c besi Tulangan Diameter 8 Kg 6,074.67 18,055.00 109,678,166.85 0.93 2,734.30 49,367,858.72
1.d Bekisting Badan Jalan M2 43.69 283,743.00 12,396,731.67 0.11 252.31 71,591,196.33
2 LPA - Cor Badan Jalan Beton Bertulang Tebal 18 Cm
2.a Cor Beton Mutu Sedang fc' = 25 Mpa (K - 300) M3 1,465.49 3,898,287.00 5,712,900,615.63 48.62 0.29
2.b besi Tulangan Diameter 10 Kg 102,657.57 18,297.00 1,878,325,558.29 15.99 28,799.61
3 Dowel Tulangan Besi Diameter 16 Kg 67.26 18,478.00 1,242,830.28 0.01 372.61 6,885,124.54

IV DEVISI 4 PEKERJAAN LAPIS PERMUKAAN


1 Prime Coat (Lapis Pengikat) M2 8,880.00 20,804.00 184,739,520.00 1.57
2 HRS LATASTON (Tebal 4 Cm) M2 8,880.00 333,952.00 2,965,493,760.00 25.24

(A) JUMLAH 11,750,281,760.81 100.00 549,464,873.73


(B) PAJAK PERTAMBAHAN NILAI (PPN) = 10 % x (A) 1,175,028,176.08
(C) TOTAL HARGA (A) + (B) 12,925,309,936.89
(D) TOTAL HARGA DIBULATKAN 12,925,309,000.00

MENGETAHUI : MENYETUJUI : DIPERIKSA :


KEPALA DINAS PEKERJAAN UMUM PENATAAN PEJABAT PELAKSANA TEKNIS KEGIATN (PPTK) PENGAWAS LAPANGAN
RUANG DAN PERTANAHAN KABUPATEN MERAUKE PENINGKATAN JALAN BAAD - SINEGI PENINGKATAN JALAN BAAD - SINEGI

Ir. H.B.L.TOBING,MEng LEO PATRIA MOGOT,ST U S M A N ,A . Md


NIP. 19601216 199103 1 008 NIP. 19730628 200605 1 002 NIP. 19610110 200012 1 002
AFTAR KUANTITAS DAN HARGA
N TAMBAH / KURANG (CCO) AMANDEMEN KONTRAK

PEKERJAAN TAMBAH/KURANG (CCO) MENJADI

PEKERJAAN KURANG KET


PERKIRAAN HARGA SATUAN JUMLAH HARGA BOBOT (%)
VOLUME (Rupiah) (Rupiah)
JLH. HARGA

1.00 125,750,000.00 125,750,000.00 1.07 TETAP


- 1,480.0 1,257.00 1,860,360.00 0.02 TETAP

600.22 275,673.00 165,464,814.25 1.41 BERTAMBAH


- 13,320.00 1,009.00 13,439,880.00 0.11 TETAP
15,121,197.00 - 408,681.00 - - DIHILANGKAN

207.20 3,898,287.00 807,725,066.40 6.87 BERTAMBAH


6,266,715.18 9,372.97 18,297.00 171,497,239.41 1.46 BERKURANG
8,808.97 18,055.00 159,046,025.57 1.35 BERTAMBAH
296.00 283,743.00 83,987,928.00 0.71 BERTAMBAH

1,130,503.23 1,465.20 3,898,287.00 5,711,770,112.40 48.61 BERKURANG


526,946,458.31 73,857.96 18,297.00 1,351,379,099.98 11.50 BERTAMBAH
439.87 18,478.00 8,127,954.82 0.07 BERTAMBAH

8,880.00 20,804.00 184,739,520.00 1.57 TETAP


8,880.00 333,952.00 2,965,493,760.00 25.24 TETAP

549,464,873.73 11,750,281,760.82 100.00


1,175,028,176.08
12,925,309,936.90
12,925,309,000.00

DIPERIKSA : DIBUAT :
KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
PT.MAKROTHUMIA EIRENE CONSULTANT PT. TUNAS JAYA IRJA

WAYAN DARYASA, ST HENRY KURNIAWAN


Team Leader Direktur
PEMERINTAH KABUPATEN MERAUKE
DINAS PEKERJAAN UMUM PENATAAN RUANG DAN PERTANAHAN
BIDANG BINA MARGA

KONTRAKTOR :PT. PEMBANGUNAN JAYA PAPUA RAYA


NO. KONTRAK : 03/KONTRAK/DAK - K1/DPUPRP - BM/V/2018
TGL MULAI KERJA : 23 MEI 2018
KONSULTAN : PT. MAKROTHUMIA EIRENE CONSULTANT

Kegiatan : -
Pekerjaan : PEMBANGUNAN SIRKUIT BALAP MOTOR
Lokasi : DISTRIK TANAH MIRING
Kabupaten : MERAUKE - PAPUA
T. Anggaran : 2019

DAFTAR KUANTITAS DAN HARGA


BOBOT
Jumlah
NILAI
No. Uraian Pekerjaan Satuan Volume
PEKERJAAN
Harga Satuan Harga Satuan %

I PEKERJAAN PERSIAPAN
A. PEKERJAAN PERSIAPAN UMUM 478,400,000.00 0.674
B. PEKERJAAN MOBILISASI DAN DEMOBILISASI 77,000,000.00 0.108

II PEKERJAAN PEMBENTUKAN LAHAN (CUT & FILL) 6,433,061,917.88 9.061

III PEKERJAAN STRUKTURAL


A. GEDUNG TRIBUN 2,657,426,718.86 3.743
B. GEDUNG SEKRETARIAT (TIDAK TERMASUK LINGKUP) 910,496,470.68 1.282
C. RUMAH JAGA 177,169,596.40 0.250
D. TOILET 209,937,048.46 0.296
E. BENGKEL (TIDAK TERMASUK LINGKUP) 231,436,877.32 0.326
F. POS JAGA (3 UNIT) 39,597,012.19 0.056
G. BANGUNAN GERBANG MASUK 86,246,855.83 0.121

IV PEKERJAAN ARSITEKTURAL
A. GEDUNG TRIBUN 2,967,712,846.00 4.180
B. GEDUNG SEKRETARIAT (TIDAK TERMASUK LINGKUP) 1,019,217,984.12 1.436
C. RUMAH JAGA 526,906,824.01 0.742
D. TOILET 357,025,666.62 0.503
E. BENGKEL (TIDAK TERMASUK LINGKUP) 423,373,185.13 0.596
F. POS JAGA (3 UNIT) 87,709,150.99 0.124
G. BANGUNAN GERBANG MASUK 52,037,207.65 0.073
H. LANDSCAPE 10,844,334,975.64 15.274

V PEKERJAAN LANSEKAP
A. PEKERJAAN HARDSCAPE 788,347,303.00 1.110

VI PEKERJAAN INFRASTRUKTUR
A. PEKERJAAN DRAINASE 1,937,944,871.80 2.730
B. PEKERJAAN JALAN 33,205,620,463.00 46.770
C. MARKA JALAN 5,656,194,000.00 7.967

VII PEKERJAAN ELEKTRIKAL


A. PENYAMBUNGAN, DISTRIBUSI DAN PEMBANGKITAN DAYA 778,615,000.00 1.097
B. PEKERJAAN INSTALASI PENERANGAN 378,980,000.00 0.534
C. PEKERJAAN PENANGKAL PETIR 61,560,000.00 0.087
D. PEKERJAAN SISTEM TELEPON 79,892,000.00 0.113
E. SISTEM TATA SUARA 98,493,000.00 0.139
F. SISTEM FIRE ALARM 59,820,000.00 0.084

VIII PEKERJAAN MEKANIKAL


A. PEKERJAAN PLUMBING AIR BERSIH 74,169,000.00 0.104
B. PEMIPAAN AIR BERSIH TOILET 8,697,000.00 0.012
C. PEMIPAAN AIR KOTOR DAN BUANGAN TOILET 102,746,000.00 0.145
D. PEMIPAAN AIR BERSIH KE AREA MOTOR CROSS 57,850,000.00 0.081
E. PEKERJAAN SISTEM TATA UDARA 60,320,000.00 0.085
F. BANGUNAN SEKERTARIAT 69,920,000.00 0.098

(A) JUMLAH 70,998,258,975.58 100.000


(B) PAJAK PERTAMBAHAN NILAI (PPN) = 10 % x (A) 7,099,825,897.56
(C) TOTAL HARGA (A) + (B) 78,098,084,873.14
(D) TOTAL HARGA DIBULATKAN 78,098,084,000.00
PEMERINTAH KABUPATEN MERAUKE
DINAS PEKERJAAN UMUM PENATAAN RUANG DAN PERTANAHAN
BIDANG BINA MARGA

KONTRAKTOR : : PT. PT. PEMBANGUNAN JAYA PAPUA RAYA


NO. KONTRAK : : 03/KONTRAK/DAK - K1/DPUPRP - BM/V/2018
TGL MULAI KERJA : : 23 MEI 2018
KONSULTAN : : PT. MAKROTHUMIA EIRENE CONSULTANT
:
Kegiatan : PEMBANGUNAN SIRKUIT BALAP MOTOR
Pekerjaan : INSFRASTRUKTUR
Lokasi : DISTRIK TANAH MIRING
Kabupaten : MERAUKE - PAPUA
T. Anggaran : 2019

DAFTAR KUANTITAS DAN HARGA INSFRASTRUKTUR


BOBOT
Jumlah NILAI
No. Uraian Pekerjaan Satuan Volume
PEKERJAAN
Harga Satuan Harga Satuan
%

VI PEKERJAAN INFRASTRUKTUR
A PEKERJAAN DRAINASE
A.1 SALURAN U-DITCH & GORONG-GORONG
1 U-ditch Tertutup uk. 50X70 Cm M 255.60 2,004,459.00 512,339,720.40 1.256
2 U-ditch Tertutup uk. 60X80 Cm M 14.00 2,351,899.00 32,926,586.00 0.081
3 Gorong-gorong 80 Cm M 86.00 1,059,563.00 91,122,418.00 0.223
4 Gorong-gorong 100 Cm M 371.60 1,407,924.00 523,184,558.40 1.282
5 Pipa PVC 4 inch M 57.80 78,000.00 4,508,400.00 0.011
6 Bak Kontrol (BK1) 100x100x125 Cm Bh 12.00 11,611,216.00 139,334,592.00 0.342
7 Bak Kontrol (BK2) 150 x150X175 Cm Bh 1.00 16,304,417.00 16,304,417.00 0.040
8 Saluran Batu Kali 100x120 cm M 32.00 6,748,740.00 215,959,680.00 0.529

A.2 SWALE (DRAINASE SISTEM KERING)


1 Swale Uk. (100x300)cm M 1,114.00 102,000.00 113,628,000.00 0.279
˗ (Dinding Tanah dipadatkan ditanami rumput)
2 Swale Uk. (50x300)cm M 340.30 95,000.00 32,328,500.00 0.079
˗ (Dinding Tanah dipadatkan ditanami rumput)
3 Swale Uk. (100x300)cm pinggir jalan utama M 454.00 102,000.00 46,308,000.00 0.114
˗ (Dinding Tanah dipadatkan ditanami rumput)

A.3 SUMUR RESAPAN


1 Sumur resapan 1,2 m kedalaman 8 m buis beton pasir, kerikil, injuk, geotextile M 12.00 17,500,000.00 210,000,000.00 0.515

B. PEKERJAAN JALAN
B.1 PEKERJAAN JALAN SIRKUIT
1 Pemadatan Tanah Asli/Urugan sub grade CBR 5% M2 15,955.00 10,965.00 174,946,575.00 0.429
2 Lay concrette tebal 5 cm M2 15,955.00 223,770.00 3,570,250,350.00 8.751
3 Lapisan beton Fc=30 mpa tebal 20 cm M2 15,955.00 1,082,064.00 17,264,331,120.00 42.315
4 Tack Coat, 0.4 ltr / m2 M2 15,955.00 22,586.00 360,359,630.00 0.883
5 AC/WC 4 cm M2 15,955.00 283,094.00 4,516,764,770.00 11.071

B.2 PEKERJAAN JALAN PIT LANE


1 Pemadatan Tanah Asli/Urugan sub grade CBR 5% M2 2,892.00 10,965.00 31,710,780.00 0.078
2 Lay concrette tebal 5 cm M2 2,892.00 223,770.00 647,142,840.00 1.586
3 Lapisan beton Fc=30 mpa tebal 20 cm M2 2,892.00 1,082,064.00 3,129,329,088.00 7.670
4 Tack Coat, 0.4 ltr / m2 M2 2,892.00 22,586.00 65,318,712.00 0.160
5 AC/WC 4 cm M2 2,892.00 283,094.00 818,707,848.00 2.007

B.3 PEKERJAAN JALAN MASUK KE PIT LANE


1 Pemadatan Tanah Asli/Urugan sub grade CBR 5% M2 1,400.00 10,965.00 15,351,000.00 0.038
2 Lay concrette tebal 15 cm M2 1,400.00 671,310.00 939,834,000.00 2.304

B.4 PEKERJAAN PARKIR MOBIL (TIDAK TERMASUK LINGKUP)


1 Pemadatan Tanah Asli/Urugan sub grade CBR 5% M2 1,907.00 10,965.00 20,910,255.00 0.051
2 Lay concrette tebal 15 cm M2 1,907.00 671,310.00 1,280,188,170.00 3.138

B.5 PEKERJAAN JALAN PERIMATER KELILING (HANYA SAMPAI PIT LANE)


1 Pemadatan Tanah Asli/Urugan sub grade CBR 5% M2 543.00 10,965.00 5,953,995.00 0.015
2 Lay concrette tebal 15 cm M2 543.00 671,310.00 364,521,330.00 0.893

C MARKA JALAN
C.1 DAERAH JALAN SIRKUIT
1 Marka garis lurus L= 15 cm M 4,541.00 89,300.00 405,511,300.00 0.994
2 Zebracross pada tikungan L= 200 cm M 750.00 617,000.00 462,750,000.00 1.134

C.2 DAERAH JALAN MASUK, JALAN PERIMETER, AREA PARKIR


1 Marka garis lurus L= 15 cm M 3,399.60 89,300.00 303,584,280.00 0.744
2 Marka garis putus putus L= 15 cm M 354.00 89,300.00 31,612,200.00 0.077
3 Tanda panah lurus M 95.00 617,000.00 58,615,000.00 0.144
4 Tanda panah belok M 8.00 617,000.00 4,936,000.00 0.012

C.3 MATERIAL PENDUKUNG


1 Lapisan Kerikil T= 10 Cm M2 5,580.00 253,259.00 1,413,185,220.00 3.464
2 Ban Bekas Bh 18,600.00 160,000.00 2,976,000,000.00 7.294

JUMLAH 40,799,759,334.80 100.0


JADWAL PELAKSANAAN PEKERJAAN KURVA "S"
Paket Pekerjaan : PEMBANGUNAN SIRKUIT BALAP MOTOR
Lokasi : DISTRIK TANAH MIRING, KABUPATEN MERAUKE
Tahun : 2019
WAKTU PELAKSANAAN 210 HARI KALENDER
Bobot %
BULAN DESEMBER JANUARI FEBRUARI MARET APRIL MEI JUNI BULAN VIII
MINGGU KE : 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
No. URAIAN KET
2 9 16 23
Renc Real
TANGGAL S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D
8 15 22 29 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr

I PEKERJAAN PERSIAPAN 100


A PEKERJAAN PERSIAPAN UMUM 0.67 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
B PEKERJAAN MOBILISASI DAN DEMOBILISASI 0.11 0.04 0.04 0.04

II PEKERJAAN PEMBENTUKAN LAHAN (CUT & FILL) 9.06 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65
90
III PEKERJAAN STRUKTURAL
A GEDUNG TRIBUN 3.74 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22
B GEDUNG SEKRETARIAT (TIDAK TERMASUK LINGKUP) 1.28 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10
C RUMAH JAGA 0.25 0.04 0.04 0.04 0.04 0.04 0.04
80
D TOILET 0.30 0.07 0.07 0.07 0.07
E BENGKEL (TIDAK TERMASUK LINGKUP) 0.33 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
F POS JAGA (3 UNIT) 0.06 0.02 0.02 0.02
G BANGUNAN GERBANG MASUK 0.12 0.03 0.03 0.03 0.03 0.03
70
IV PEKERJAAN ARSITEKTURAL
A GEDUNG TRIBUN 4.18 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42
B GEDUNG SEKRETARIAT (TIDAK TERMASUK LINGKUP) 1.44 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18
C RUMAH JAGA 0.74 0.25 0.25 0.25
D TOILET 0.50 0.25 0.25 60
E BENGKEL (TIDAK TERMASUK LINGKUP) 0.60 0.15 0.15 0.15 0.15
F POS JAGA (3 UNIT) 0.12 0.06 0.06
G BANGUNAN GERBANG MASUK 0.07 0.07
H LANDSCAPE 15.27 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09
50
V PEKERJAAN LANSEKAP
A PEKERJAAN HARDSCAPE 1.11 0.28 0.28 0.28 0.28

VI PEKERJAAN INFRASTRUKTUR
40
A PEKERJAAN DRAINASE 2.73 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19
B. PEKERJAAN JALAN 46.77 1.23 1.23 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46
C MARKA JALAN 7.97 1.99 1.99 1.99 1.19 0.80

VII PEKERJAAN ELEKTRIKAL 30


A PENYAMBUNGAN, DISTRIBUSI DAN PEMBANGKITAN DAYA 1.10 0.27 0.27 0.27 0.27
B PEKERJAAN INSTALASI PENERANGAN 0.53 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06
C PEKERJAAN PENANGKAL PETIR 0.09 0.09
D PEKERJAAN SISTEM TELEPON 0.11 0.03 0.03 0.03 0.03
SISTEM TATA SUARA 20
E. 0.14 0.03 0.03 0.03 0.03
F SISTEM FIRE ALARM 0.08 0.02 0.02 0.02 0.02 0.02

VIII PEKERJAAN MEKANIKAL


A PEKERJAAN PLUMBING AIR BERSIH 0.10 0.02 0.02 0.02 0.02 0.02 0.02 10
B PEMIPAAN AIR BERSIH TOILET 0.01 0.01 0.01
C PEMIPAAN AIR KOTOR DAN BUANGAN TOILET 0.14 0.04 0.04 0.04 0.04
D PEMIPAAN AIR BERSIH KE AREA MOTOR CROSS 0.08 0.02 0.02 0.02 0.02 0.02
E PEKERJAAN SISTEM TATA UDARA 0.08 0.04 0.04
F BANGUNAN SEKERTARIAT 0.10 0.02 0.02 0.02 0.02 0

Bobot (%) 100 0.06 0.06 0.67 0.89 1.08 2.32 2.32 3.55 3.45 3.49 3.49 3.49 3.49 3.49 3.49 4.58 4.28 4.66 4.66 4.70 4.59 4.53 4.53 4.61 4.96 4.99 4.88 4.69 3.06 0.98
Rencana
Kumulatif (%) - 0.06 0.12 0.79 1.68 2.76 5.08 7.39 10.94 14.39 17.88 21.37 24.86 28.35 31.84 35.33 39.92 44.19 48.85 53.51 58.21 62.80 67.33 71.86 76.47 81.43 86.41 91.30 95.99 99.05 100
KEMAJUAN
PEKERJAAN Bobot (%) - #REF!
Realisasi
Kumulatif (%) - - #REF!
Deviasi Bobot (%) - 0.059 #REF!

KONTRAKTOR PELAKSANA
PT. BANGUN PERSADA PAPUA RAYA

JONI PASULE
Direktur
PEMERINTAH KABUPATEN MERAUKE
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
BIDANG CIPTA KARYA

PEKERJAAN : PEMBANGUNAN SIRKUIT BALAP MOTOR PEKERJAAN : PENGAWASAN PEMBANGUNAN SIRKUIT BALAP MOTOR
KONTRAKTOR : PT. PEMBANGUNAN JAYA PAPUA RAYA KONSULTAN : PT. MAKROTHUMIA EIRENE CONSULTANT
NO. KONTRAK : 03/KONTRAK/DAK - K1/DPUPRP - BM/V/2018 NO. KONTRAK : 10/KONTRAK/DAU-PENG.DAK.1/DPUPRP - BM/V/2018
TGL MULAI KERJA : 02 DESEMBER 2019 TANGGAL KONTRAK : 2 DESEMBER 2019
LOKASI : DISTRIK TANAH MIRING SUMBER DANA : APBD
KABUPATEN : MERAUKE - PAPUA TAHUN ANGGARAN : 2019 - 2020

LAPORAN MINGGU KE - 1
PERIODE 2 DESEMBER S/D 8 DESEMBER
TAHUN 2019
PEKERJAAN : INSFRASTRUKTUR

BOBOT REALISASI KEMAJUAN FISIK


NILAI MINGGU LALU MINGGU INI S/D MINGGU INI PRESTASI
No. Uraian Pekerjaan Satuan Volume PROGRES
PEKERJAAN BOBOT BOBOT BOBOT
VOLUME VOLUME VOLUME
% % % % %

VI PEKERJAAN INFRASTRUKTUR
A PEKERJAAN DRAINASE
A.1 SALURAN U-DITCH & GORONG-GORONG
1 U-ditch Tertutup uk. 50X70 Cm M 255.60 1.2557 - - - - - - -
2 U-ditch Tertutup uk. 60X80 Cm M 14.00 0.0807 - - - - - - -
3 Gorong-gorong 80 Cm M 86.00 0.2233 - - - - - - -
4 Gorong-gorong 100 Cm M 371.60 1.2823 - - - - - - -
5 Pipa PVC 4 inch M 57.80 0.0111 - - - - - - -
6 Bak Kontrol (BK1) 100x100x125 Cm Bh 12.00 0.3415 - - - - - - -
7 Bak Kontrol (BK2) 150 x150X175 Cm Bh 1.00 0.0400 - - - - - - -
8 Saluran Batu Kali 100x120 cm M 32.00 0.5293 - - - - - - -

A.2 SWALE (DRAINASE SISTEM KERING)


1 Swale Uk. (100x300)cm M 1,114.00 0.2785 - - - - - - -
˗ (Dinding Tanah dipadatkan ditanami rumput)
2 Swale Uk. (50x300)cm M 340.30 0.0792 - - - - - - -
˗ (Dinding Tanah dipadatkan ditanami rumput)
3 Swale Uk. (100x300)cm pinggir jalan utama M 454.00 0.1135 - - - - - - -
˗ (Dinding Tanah dipadatkan ditanami rumput)

A.3 SUMUR RESAPAN


1 Sumur resapan 1,2 m kedalaman 8 m buis beton pasir, kerikil, injuk, geotextile M 12.00 0.5147 - - - - - - -

B. PEKERJAAN JALAN
B.1 PEKERJAAN JALAN SIRKUIT
1 Pemadatan Tanah Asli/Urugan sub grade CBR 5% M2 15,955.00 0.4288 - - - - - - -
2 Lay concrette tebal 5 cm M2 15,955.00 8.7507 - - - - - - -
3 Lapisan beton Fc=30 mpa tebal 20 cm M2 15,955.00 42.3148 - - - - - - -
4 Tack Coat, 0.4 ltr / m2 M2 15,955.00 0.8832 - - - - - - -
5 AC/WC 4 cm M2 15,955.00 11.0706 - - - - - - -

B.2 PEKERJAAN JALAN PIT LANE


1 Pemadatan Tanah Asli/Urugan sub grade CBR 5% M2 2,892.00 0.0777 - - - - - - -
2 Lay concrette tebal 5 cm M2 2,892.00 1.5861 - - - - - - -
3 Lapisan beton Fc=30 mpa tebal 20 cm M2 2,892.00 7.6700 - - - - - - -
4 Tack Coat, 0.4 ltr / m2 M2 2,892.00 0.1601 - - - - - - -
5 AC/WC 4 cm M2 2,892.00 2.0066 - - - - - - -

B.3 PEKERJAAN JALAN MASUK KE PIT LANE


1 Pemadatan Tanah Asli/Urugan sub grade CBR 5% M2 1,400.00 0.0376 - - - - - - -
2 Lay concrette tebal 15 cm M2 1,400.00 2.3035 - - - - - - -

B.4 PEKERJAAN PARKIR MOBIL (TIDAK TERMASUK LINGKUP)


1 Pemadatan Tanah Asli/Urugan sub grade CBR 5% M2 1,907.00 0.0513 - - - - - - -
2 Lay concrette tebal 15 cm M2 1,907.00 3.1377 - - - - - - -

B.5 PEKERJAAN JALAN PERIMATER KELILING (HANYA SAMPAI PIT LANE)


1 Pemadatan Tanah Asli/Urugan sub grade CBR 5% M2 543.00 0.0146 - - - - - - -
2 Lay concrette tebal 15 cm M2 543.00 0.8934 - - - - - - -

C MARKA JALAN
C.1 DAERAH JALAN SIRKUIT
1 Marka garis lurus L= 15 cm M 4,541.00 0.9939 - - - - - - -
2 Zebracross pada tikungan L= 200 cm M 750.00 1.1342 - - - - - - -

C.2 DAERAH JALAN MASUK, JALAN PERIMETER, AREA PARKIR


1 Marka garis lurus L= 15 cm M 3,399.60 0.7441 - - - - - - -
2 Marka garis putus putus L= 15 cm M 354.00 0.0775 - - - - - - -
3 Tanda panah lurus M 95.00 0.1437 - - - - - - -
4 Tanda panah belok M 8.00 0.0121

C.3 MATERIAL PENDUKUNG


1 Lapisan Kerikil T= 10 Cm M2 5,580.00 3.4637 - - - - - - -
2 Ban Bekas Bh 18,600.00 7.2942 - - - - - - -

JUMLAH 100.0 0.000 0.000 0.000

RENCANA = 0.059 %
REALISASI = 0.000 %
DEVIASI = -0.059 %

MENGETAHUI: DISETUJUI OLEH : DIPERIKSA OLEH DIBUAT OLEH


PEJABAT PELAKSANA TEKNIS KEGIATAN (PPTK) DIREKSI TEKNIS LAPANGAN KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
PEMBANGUNAN SIRKUIT BALAP MOTOR PEMBANGUNAN SIRKUIT BALAP MOTOR PT. MAKROTHUMIA EIRENE CONSULTANT PT. BANGUN PERSADA PAPUA RAYA

LEO PATRIA MOGOT,ST U S M A N ,A . Md WAYAN DARYASA, ST. YANI SALEA BATU, ST.
NIP. 19730628 200605 1 002 NIP. 19610110 200012 1 002 Team Leader Sita Manager