BADAN STANDAR NASIONAL UNTUK BANGUNAN GEDUNG

1 M3 Beton Semen Pasir Bt. Pecah Air W/C Slump


Mutu Beton Kg Kg Kg Liter
fc' = 7.4 Mpa K.100 247 869 999 215 0.87 12 ± 2
fc' = 9.8 Mpa K. 125 276 828 1012 215 0.87 12 ± 2
fc' = 12.2 Mpa K. 150 299 799 1017 215 0.72 12 ± 2
fc' = 14.5 Mpa K. 175 326 760 1029 215 0.66 12 ± 2
fc' = 16.9 Mpa K. 200 352 731 1031 215 0.61 12 ± 2
fc' = 19.3 Mpa K. 225 371 698 1047 215 0.58 12 ± 2
fc' = 21.7 Mpa K. 250 384 692 1039 215 0.56 12 ± 2
fc' = 24 Mpa K. 275 406 684 1026 215 0.53 12 ± 2
fc' = 26.4 Mpa K.300 413 681 1021 215 0.52 12 ± 2
fc' = 28.8 Mpa K. 325 439 670 1006 215 0.49 12 ± 2
fc' = 31.2 Mpa K. 350 448 667 1000 215 0.48 12 ± 2

ANALISA BINA MARGA


K. 500 578 538 992 0.38
K. 400 478 622 992 0.45
K. 350 456 637 992 0.45
K.300 456 631 992 0.45
K. 250 410 670 992 0.50
K. 175 318 622 1207 0.57
K. 125 302 633 1207 0.57
CAMPURAN CARA MANUAL
Menggunakan Truck Mixer K. 125 Input Data Mix Design
Produksi (M3) K. 250 Semen
4 1640 2680 3968 Pasir
32.8 2.73 4.20 Batu Pecah
Proporsi Campuran
1536 2768 4156 Perbandingan Volume
30.7 2.82 4.40 Volume
(m3)
0.59 0.0326
0.75 0.0310
Catatan : Jangan dirubah tulisan warna merah
CAMPURAN DENGAN TRUCK MIXER
Standar Cipta Karya K. 250 Input Data Mix Design
Semen
Pasir
Batu Pecah
Proporsi Campuran
Perbandingan Volume
Volume
(m3)
Semen
Pasir
Batu Pecah
Catatan : Jangan dirubah tulisan warna merah

Standar Bina Marga CAMPURAN DENGAN TRUCK MIXER (


K. 250 Input Data Mix Design
Semen
Pasir
Batu Pecah
Proporsi Campuran
INPUT Perbandingan Volume
Volume
(m3)
Semen
Pasir
Batu Pecah

CAMPURAN DENGAN TRUCK MIXER (

K. 250 Input Data Mix Design


Semen
Pasir
Batu Pecah
Proporsi Campuran
Perbandingan Volume
Volume
(m3)
Semen

Pasir
Batu Pecah
Perbandingan Semen Pasir Bt. Pecah

Volume 1 2 3

50 175.9 202.23

0.06 0.05
Semen Berat Isi (kg/m3) Ukuran Tong Pasir (M)
1 Zak (50 kg) Pasir Bt. Pecah Tinggi Lebar Panjang
50 1,400 1,350 0.2 0.4 0.79
0.2 0.4 0.67
0.2 0.4 0.60
0.2 0.4 0.52
0.2 0.4 0.46
0.2 0.4 0.42
0.2 0.4 0.40
0.2 0.4 0.38
0.2 0.4 0.37
0.2 0.4 0.34
0.2 0.4 0.33

RA MANUAL
Input Data Mix Design Semen Berat Isi ( Unit Weight)
302.00 50 1400 1350 1 x Campur =
828.00 1 M3
1,012.00 137.09 167.55
Proporsi Campuran Semen Pasir Bt. Pecah
Perbandingan Volume 1 3 4
1 x Campur Ukuran Tong (m)
0.166 Tinggi Lebar Panjang
Pasir 0.18 0.42 0.43
Kerikil 0.18 0.42 0.41
tulisan warna merah
GAN TRUCK MIXER
Input Data Mix Design Semen Berat Isi ( Unit Weight)
384.00 50 1400 1350
692.00
1,039.00 90.10 135.29
Proporsi Campuran
Perbandingan Volume
Ukuran Bucket (m3)
4 0.7
(Zak) 30.72
(M3) 1.98 2.82
(M3) 3.08 4.40
tulisan warna merah

NGAN TRUCK MIXER ( A ) Catatan :


Input Data Mix Design Semen Berat Isi ( Unit Weight) Tabel A : Input Volume Beton
410.00 50 1300 1400 Tabel B : Input Jumlah Zak Semen
670.00
992.00 81.71 120.98
Proporsi Campuran
Perbandingan Volume
Ukuran Bucket (m3)
1 0.7
(Zak) 8.20
(M3) 0.52 0.74
(M3) 0.71 1.01
Bucket
NGAN TRUCK MIXER ( B ) CAMPURAN CARA MANUAL

Input Data Mix Design Semen Berat Isi ( Unit Weight) K. 250 Input Data Mix Design
410.00 50 1300 1400 Semen
670.00 Pasir
992.00 81.71 120.98 Batu Pecah
Proporsi Campuran Proporsi Campuran
Perbandingan Volume Perbandingan Volume
Ukuran Bucket (m3) Volume
1.000 0.7 (m3)
(Zak) 8.20 0.0314

(kg) - ( M3 ) 670.00 0.515 0.74 0.0288


(kg) - ( M3 ) 992.00 0.709 1.01 Satu kali mencampur
Kg M3 Bucket PC.200
Ukuran Tong Bt. Pecah (m)
Tinggi Lebar Panjang
0.2 0.4 0.62
0.2 0.4 0.57
0.2 0.4 0.52
0.2 0.4 0.49
0.2 0.4 0.45
0.2 0.4 0.44
0.2 0.4 0.42
0.2 0.4 0.39
0.2 0.4 0.38
0.2 0.4 0.35
0.2 0.4 0.34

0.166 M3
6.04 x Campur
el A : Input Volume Beton
el B : Input Jumlah Zak Semen

RA MANUAL

Input Data Mix Design Semen Berat Isi ( Unit Weight)


410.00 50 1300 1400
670.00
992.00 81.71 120.98
Proporsi Campuran Semen Pasir Bt. Pecah
Perbandingan Volume 1 2 3
Ukuran Tong (m)
Tinggi Lebar Panjang
Pasir 0.20 0.40 0.39

Kerikil 0.20 0.40 0.36


Satu kali mencampur 0.122 M3