Back Up Data
Back Up Data
PERHITUNGAN VOLUME PEMB. MCK UPT SDN 002 KUOK KEC. KUOK
PEK. BETON
Berat 1M Besi (B. D-) P L TC JM JUMLAH
D16 = 1.584 0.600 x 0.600 x 0.200 x 4.000 = 0.288 M3
D13 = 1.042
D10 = 0.620 PEK. PEMBESIAN
Ф 16 = 1.583 P : JS L : JS T. UTAMA JM Besi Type JUMLAH
Ф 15 = 1.388 4 + 4 = 8.000 x 1.52 = 12.160 + 12.160 x 4.000 x 0.892 = 43.371 KG
Ф 14 = 1.208
Ф 13 = 1.042
Ф 12 = 0.892
Ф 10 = 0.617
Ф8 = 0.395
Ф6 = 0.222
KOLOM 10x10 CM
Panjang (P) = 0.100 PEK. BEKISTING
Lebar (L) = 0.100 T (P+L)x2 JM JUMLAH
Tinggi (T) = 3.000 3.000 x 0.200 x 5.000 = 3.000 M2
Jumlah (JM) = 5.000
Jarak sengkang (JS) = 0.150
PEK. PEMBESIAN
Berat 1M Besi (B. D-) Sengkang P : JS Begel JM P. Begel Besi Type JUMLAH
D16 = 1.584 20.000 x 0.32 x 5.000 = 32.000 x 0.222 = 7.093 KG
D13 = 1.042
D10 = 0.620 Tulangan P JT JM P. Tul JUMLAH
Ф 16 = 1.583 3.000 x 4.000 x 5.000 = 60.000 x 0.617 = 37.000 KG
Ф 15 = 1.388
Ф 14 = 1.208 PEK. BETON
Ф 13 = 1.042 P L T JM JUMLAH
Ф 12 = 0.892 0.100 x 0.100 x 3.000 x 5.000 = 0.150 M3
Ф 10 = 0.617
Ф8 = 0.395
Ф6 = 0.222
BALOK 15x30 CM
PEK. BEKISTING
PJNG BNYK JMLH T T L P JUMLAH
SLOOF 1 = 1.300 4.00 5.20 0.300 + 0.300 + = 0.600 x 5.200 = 3.120 M2
SLOOF 2 = 0.00 PEK. BETON
SLOOF 3 = 0.00 P L T JUMLAH
SLOOF 4 = 0.00 5.200 x 0.200 x 0.300 = 0.312 M3
SLOOF 5 = 0.00
SLOOF 6 = 0.00 PEK. PEMBESIAN
SLOOF 7 = 0.00 Sengkang P JS Begel JUMLAH
SLOOF 8 = 0.00 5.200 : 0.150 = 34.6666667 x 0.92 x 0.395 = 12.598 KG
SLOOF 9 = 0.00
Panjang (P) = 5.200 Tulangan Atas P JT P + JT JUMLAH
5.200 3 15.600 0.892 = 13.910 KG
Lebar = 0.200
Tinggi = 0.300 Tengah P JT P + JT JUMLAH
5.200 2 10.400 0.892 = 9.273 KG
Jarak sengkang (JS) = 0.150
Berat 1M Besi (B. D-) Bawah P JT P + JT JUMLAH
D16 = 1.584 5.200 2 10.400 0.892 = 9.273 KG
D13 = 1.042
D10 = 0.620
Ф 16 = 1.583
Ф 15 = 1.388
Ф 14 = 1.208
Ф 13 = 1.042
Ф 12 = 0.892
Ф 10 = 0.617
Ф8 = 0.395
Ф6 = 0.222
BALOK 10x20 CM
PEK. BEKISTING
PJNG BNYK JMLH T T L P JUMLAH
SLOOF 1 = 2.900 2.00 5.80 0.200 + 0.200 + = 0.400 x 22.950 = 9.180 M2
SLOOF 2 = 1.400 1.00 1.40 PEK. BETON
SLOOF 3 = 1.350 1.00 1.35 P L T JUMLAH
SLOOF 4 = 2.900 4.00 11.60 22.950 x 0.100 x 0.200 = 0.459 M3
SLOOF 5 = 1.400 2.00 2.80
SLOOF 6 = 0.00 PEK. PEMBESIAN
SLOOF 7 = 0.00 Sengkang P JS Begel JUMLAH
SLOOF 8 = 0.00 22.950 : 0.150 = 153 x 0.52 x 0.222 = 17.636 KG
SLOOF 9 = 0.00
Panjang (P) = 22.950 Tulangan Atas P JT P + JT JUMLAH
22.950 2 45.900 0.617 = 28.305 KG
Lebar = 0.100
Tinggi = 0.200 Tengah P JT P + JT JUMLAH
22.950 2 45.900 = 0.000 KG
Jarak sengkang (JS) = 0.150
Berat 1M Besi (B. D-) Bawah P JT P + JT JUMLAH
D16 = 1.584 22.950 2 45.900 0.617 = 28.305 KG
D13 = 1.042
D10 = 0.620
Ф 16 = 1.583
Ф 15 = 1.388
Ф 14 = 1.208
Ф 13 = 1.042
Ф 12 = 0.892
Ф 10 = 0.617
Ф8 = 0.395
Ф6 = 0.222
6.161 KG
Pekerjaan Bata
P T Banyak JUMLAH
A = 2.90 x 2.80 x 2.00 = 16.240 -( 3.420 - 6.080 - 1.600 - )= 5.140 M2
B = 1.40 x 2.80 x 1.00 = 3.920 -( - - - )= 3.920 M2
C = 1.35 x 2.80 x 1.00 = 3.780 -( - - - )= 3.780 M2
D = 2.85 x 2.80 x 4.00 = 31.920 -( - - - )= 31.920 M2
E = 1.40 x 2.70 x 2.00 = 7.560 -( - - - )= 7.560 M2
F = 1.30 x 2.70 x 4.00 = 14.040 -( - - - )= 14.040 M2
G = 1.50 x 1.00 x 1.00 = 1.500 -( - - - )= 1.500 M2
H = 1.50 x 1.00 x 1.00 = 1.500 -( - - - )= 1.500 M2
I = 1.30 x 1.00 x 1.00 = 1.300 -( - - - )= 1.300 M2
TOTAL = 70.660 M2
TOTAL = 11.002 M2
P1
KUSEN
KUSEN KUSEN JUMLAH
Panjang (P) = 4.800 4.800 x 0.050 x 0.120 x 2.000 = 0.058 M3
Lebar (L) = 0.050
Tinggi (T) = 0.120
Pengecetan Bidang 1 = 0.220 0.220 x 4.800 x 2.000 = 2.112 M2
Pengecetan Bidang 2 = 0.340
JUMLAH = 2.000
PINTU 80x205Cm PINTU 80x205Cm JUMLAH
Tinggi (T) = 1.850 1.850 x 0.800 x 2.000 = 2.960 M2
Lebar (L) = 0.800
Jumlah Bidang = 2.000 1.850 x 0.800 x 2.000 x 2.000 5.920 M2
JUMLAH = 2.000
V2
KUSEN KUSEN JUMLAH
Panjang (P) = 2.000 2.000 x 0.050 x 0.120 x 8.000 = 0.096 M3
Lebar (L) = 0.050
Tinggi (T) = 0.120
Pengecetan Bidang 1 = 0.220 0.220 x 2.100 x 8.000 = 3.696 M2
Pengecetan Bidang 2 = 0.340 = 0.000 M2
JUMLAH = 8.000
Kaca Kaca JUMLAH
Tinggi (T) = 0.200 0.200 x 0.420 x 16.000 = 1.344 M2
Lebar (L) = 0.420
Jumlah Bidang = 0.200 x 0.420 x 16.000 x 0.000 0.000 M2
JUMLAH = 16.000
P2
KUSEN
KUSEN KUSEN JUMLAH
Panjang (P) = 4.600 4.600 x 0.050 x 0.120 x 4.000 = 0.110 M3
Lebar (L) = 0.050
Tinggi (T) = 0.120
Pengecetan Bidang 1 = 0.220 0.220 x 4.800 x 4.000 = 4.224 M2
Pengecetan Bidang 2 = 0.340
JUMLAH = 4.000
PINTU 60x205Cm PINTU 60x205Cm JUMLAH
Tinggi (T) = 1.800 1.800 x 0.600 x 4.000 = 4.320 M2
Lebar (L) = 0.600
Jumlah Bidang = 2.000 1.800 x 0.600 x 4.000 x 2.000 8.640 M2
JUMLAH = 4.000
Pekerjaan Penimbunan Lantai
Dalam Ruangan
Arah X x Arah Y x Arah Z x Jumlah
Dalam Ruang 1 = 2.87 x 1.370 x 0.120 x 2.000 = 0.944 M3
Dalam Ruang 2 = 1.37 x 1.370 x 0.120 x 4.000 = 0.901 M3
= = - M3
= = - M3
= - M3
= - M3
Jumlah = 1.845 M3
Perhitungan Atap
PEK. PEMASANGAN
PANJANG TINGGI BANYAK JUMLAH
A = 7.730 x 2.890 x 1.000 = 22.340 -( - - - )= 22.340 M2
B = 5.300 x 2.890 x 1.000 = 15.317 -( - - - )= 15.317 M2
C = x x = 0.000 -( - - )= 0.000 M2
D = x x = 0.000 -( - - - )= 0.000 M2
E = x x = 0.000 -( - - - )= 0.000 M2
F = x x = 0.000 -( - - - )= 0.000 M2
G = x x = 0.000 -( - - - )= 0.000 M2
H = x x = 0.000 -( - - - )= 0.000 M2
I = x x = 0.000 -( - - - )= 0.000 M2
TOTAL = 37.657 M2
TOTAL = 8.560 M1
Perhitungan Perabung Atap
PEK. PEMASANGAN
P Jumlah JUMLAH
A = 5.300 x 1.000 5.300 M1
B = x 0.000 M1
C = x 0.000 M1
D = x 0.000 M1
E = x 0.000 M1
F = x 0.000 M1
G = x 0.000 M1
H = x 0.000 M1
I = x 0.000 M1
0.000 M1
0.000 M1
0.000 M1
TOTAL = 5.300 M1
TOTAL = 20.920 M1
VENTILASI SINGAP
KUSEN KUSEN JUMLAH
Panjang (P) = 0.120 0.120 x 0.050 x 6.420 x 2.000 = 0.077 M3
Lebar (L) = 0.050
Tinggi (T) = 6.420
Pengecetan Bidang = 1.000 1.000 x 0.220 x 2.000 = 0.440 M2
Pengecetan Bidang = 0.000 x 0.220 x 2.000 = 0.000 M2
JUMLAH = 2.000
VENTILASI VENTILASI JUMLAH
Panjang (P) = 1.200 1.200 x 0.080 x 2.000 x = 0.025 M2
Tinggi (T) = 0.080
Jumlah Bidang = 1.000 1.200 x 0.080 x 2.000 x 1.000 0.192 M2
JUMLAH = 2.000
PLAFOND
Pek. Plafond
JUMLAH
2.87 x 1.37 3.93 M2
2.87 x 1.37 3.93 M2
1.37 x 1.37 1.88 M2
1.37 x 1.37 1.88 M2
1.37 x 1.37 1.88 M2
1.37 x 1.37 1.88 M2
x - M2
x - M2
x - M2
x - M2
x - M2
x - M2
TOTAL = 15.37 M2
Pek. Plafond
P L Banyak JUMLAH
1.80 x 0.20 x 4.00 1.44 M2
2.04 x 2.47 x 2.00 10.08 M2
2.04 x 2.46 x 1.00 5.02 M2
x - M2
x - M2
x - M2
x - M2
x - M2
- M2
- M2
- M2
- M2
TOTAL = 16.54 M2
Pek. Plafond
P L Banyak JUMLAH
Zona 1 7.41 x 0.90 x 1.00 6.67 M2
Zona 2 5.14 x 0.90 x 1.00 4.63 M2
Zona 3 1.81 x 0.87 x 2.00 3.15 M2
Zona 4 1.81 x 0.87 x 1.00 1.57 M2
Zona 5 x x - M2
Zona 6 x x - M2
Zona 7 x x - M2
Zona 8 x x - M2
Zona 9 x x - M2
Zona 10 x x - M2
Zona 11 x x - M2
Zona 12 x x - M2
Zona 13 - M2
Zona 14 - M2
Zona 15 x - M2
TOTAL = 16.02 M2
TOTAL = 0.203 M3
PEK. BETON
PANJANG TINGGI LEBAR JUMLAH
Saluran = 0.700 x 0.050 X 5.800 x 1.000 = 0.203 -( - - )= 0.203 M3
Saluran = -( - - )= 0.000 M3
-( - - )= 0.000 M3
-( - - )= 0.000 M3
TOTAL = 0.203 M3
TOTAL = 4.800 M2
MUHAMMAD DAMSIR, S.Sos RAHMAD HIDAYAT Ir. INDRA UTAMA GILANG RAMADHAN. AS
NIP.19810204 200801 1 011 NIP. 19780821 200801 1 007 DIREKTUR DIREKTUR