PEKERJAAN TANAH
GALIAN GROUNDTANK
P= 20.000 PJNG LBR TNG JUMLAH
L= 12.000 20.000 12.000 3.500 840 M3
T= 3.500
PASIR URUG GROUND TANK
P= 17.000 PJNG LBR TNG JUMLAH
L= 9.000 17.000 9.000 0.200 30.6 M3
T= 0.200
BECK'UP DATA
P JT P + JT B.D13 JUMLAH
92.400 2 184.800 1.042 192.562 KG
P JT P + JT B.D13 JUMLAH
92.400 2 184.800 1.042 192.562 KG
598.556
1648.416
2246.972
2836.486
P JT P + JT JM B.D13 JUMLAH
4.100 2 8.200 10.000 82.000 1.042 85.444 KG
P JT P + JT JM B.D13 JUMLAH
4.100 2 8.200 10.000 82.000 1.042 85.444 KG
273.296
664.774
938.070
P JT P + JT JM B.D13 JUMLAH
4.100 2 8.200 5.000 41.000 0.000 KG
P JT P + JT JM B.D13 JUMLAH
4.100 2 8.200 5.000 41.000 0.000 KG
136.648
246.943
383.591
4902.818
1122.495
PEKERJAAN BALOK 1
PEK. BEKISTING
Panjang (P) = 88.000 P T J. bekisting JUMLAH
Lebar (L) = 0.250 88.000 0.250 2.000 44.000 M2
Tinggi (T) = 0.500
PEK. BETON
Jarak sengkang (JS) = 0.150 P L T JUMLAH
88.000 0.250 0.500 11.000 M3
Berat 1M Besi (B. D-)
D16 = 1.584 PEK. PEMBESIAN
D13 = 1.042 Sengkang P : JS Keliling Begel B.D10 JUMLAH
D10 = 0.620 588.667 1.44 0.620 525.562 M2
D8 = 0.395
D6 = 0.221 Tulangan Atas P JT P + JT B.D16 JUMLAH
92.400 3 277.200 1.584 439.085 KG
P JT P + JT B.D13 JUMLAH
92.400 2 184.800 1.042 192.562 KG
P JT P + JT B.D13 JUMLAH
92.400 0.000 1.042 0.000 KG
525.562
1263.293
1788.854
2836.486
17,055.77
PEKERJAAN PILECEP
PEK. PAS. BATA SEKELILING PILECEP
Panjang (P) = 0.600 P T JM JUMLAH
Lebar (L) = 0.600 2.4 0.200 6.000 2.880 M2
Tinggi (T) = 0.200
Jumlah (JM) = 6.000 PEK. PENGECORAN
Jarak sengkang (JS) = 0.150 P L T JM JUMLAH
0.600 0.600 0.200 6.000 0.432 M3
Berat 1M Besi (B. D-)
D16 = 1.584 PEK. PEMBESIAN
D13 = 1.042 P : JS P : JS Keliling Begel (P : JS) +(P : JS) JM B.D13 JUMLAH
D10 = 0.620 4 4 1.59 8.000 6.000 1.042 79.525 KG
D8 = 0.395
D6 = 0.221