ANALISA HARGA SATUAN

1
JENIS PEKERJAAN : Pembangunan Kembali Jalan Beton/Rekonstruksi4 Jam Terpasang Pembesian 1 Lapis Wiremesh
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 2.500.000,00 2.500.000,00

JUMLAH HARGA I 2.500.000,00

B. BAHAN
1 Ctb m3 1,0300 974.853,31 1.004.098,90
2 Beton Rapid Setting 4 jam m3 1,0300 4.600.000,00 4.738.000,00
3 Wiremesh WM 8 m2 3,8000 81.569,66 309.964,72
4 Bekisting m2 0,7100 250.000,00 177.500,00
5 Baja Tulangan U24 kg 22,2253 14.511,50 322.522,44
6 Plastik Cor m2 3,8000 3.800,00 14.440,00
7 Curing Ltr 0,5351 41.500,00 22.204,57
8 Joint Sealent Kg 1,2533 35.800,00 44.869,33

JUMLAH HARGA II 6.633.599,96

C. PERALATAN ls 1,0000 4.500.000,00 4.500.000,00

JUMLAH HARGA III 4.500.000,00

D. JUMLAH HARGA TENAGA, BAHAN, DAN PERALATAN ( A + B + C ) 13.633.599,96


E. OVERHEAD + PROFIT 2.045.039,99
F. JUMLAH HARGA DENGAN OVERHEAD + PROFIT (D+E) 15.678.639,95
G. PPN 11% (F X 11%) 1.724.650,39
H. HARGA SATUAN PEKERJAAN (F+G) 17.403.290,34

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
2
JENIS PEKERJAAN : Pembangunan Kembali Jalan Beton/Rekonstruksi 4 Jam Terpasang Pembesian 2 Lapis Wiremesh
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 2.750.000,00 2.750.000,00

JUMLAH HARGA I 2.750.000,00

B. BAHAN
1 Ctb m3 1,0300 974.853,31 1.004.098,90
2 Beton Rapid Setting 4 jam m3 1,0300 4.600.000,00 4.738.000,00
3 Wiremesh WM 8 m2 7,6000 81.569,66 619.929,45
4 Bekisting m2 0,7100 250.000,00 177.500,00
5 Baja Tulangan U24 kg 22,2253 14.511,50 322.522,44
6 Plastik Cor m2 7,6000 3.800,00 28.880,00
7 Curing Ltr 0,5351 41.500,00 22.204,57
8 Joint Sealent Kg 1,2533 35.800,00 44.869,33

JUMLAH HARGA II 6.958.004,69

C. PERALATAN ls 1,0000 4.650.000,00 4.650.000,00

JUMLAH HARGA III 4.650.000,00

D. JUMLAH HARGA TENAGA, BAHAN, DAN PERALATAN ( A + B + C ) 14.358.004,69


E. OVERHEAD + PROFIT 2.153.700,70
F. JUMLAH HARGA DENGAN OVERHEAD + PROFIT (D+E) 16.511.705,39
G. PPN 11% (F X 11%) 1.816.287,59
H. HARGA SATUAN PEKERJAAN (F+G) 18.327.992,98

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
3
JENIS PEKERJAAN : Pembangunan Kembali Jalan Beton/Rekonstruksi 8 Jam Terpasang Pembesian 1 Lapis Wiremesh
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 2.500.000,00 2.500.000,00

JUMLAH HARGA I 2.500.000,00

B. BAHAN

1 Ctb m3 1,0300 974.853,31 1.004.098,90


2 Beton Rapid Setting 8 jam m3 1,0300 4.025.000,00 4.145.750,00
3 Wiremesh WM 8 m2 3,8000 81.569,66 309.964,72
4 Bekisting m2 0,7100 250.000,00 177.500,00
5 Baja Tulangan U25 kg 22,8506 14.511,50 331.596,35
6 Plastik Cor m2 3,8000 3.800,00 14.440,00
7 Curing Ltr 0,5351 41.500,00 22.204,57
8 Joint Sealent Kg 1,2533 35.800,00 44.869,33

JUMLAH HARGA II 6.050.423,87

C. PERALATAN ls 1,0000 4.500.000,00 4.500.000,00

JUMLAH HARGA III 4.500.000,00

D. JUMLAH HARGA TENAGA, BAHAN, DAN PERALATAN ( A + B + C ) 13.050.423,87


E. OVERHEAD + PROFIT 1.957.563,58
F. JUMLAH HARGA DENGAN OVERHEAD + PROFIT (D+E) 15.007.987,45
G. PPN 11% (F X 11%) 1.650.878,61
H. HARGA SATUAN PEKERJAAN (F+G) 16.658.866,06

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
4
JENIS PEKERJAAN : Pembangunan Kembali Jalan Beton/Rekonstruksi 8 Jam Terpasang Pembesian 2 Lapis Wiremesh
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 2.750.000,00 2.750.000,00

JUMLAH HARGA I 2.750.000,00

B. BAHAN
1 Ctb m3 1,0300 974.853,31 1.004.098,90
2 Beton Rapid Setting 8 jam m3 1,0300 4.025.000,00 4.145.750,00
3 Wiremesh WM 8 m2 7,6000 81.569,66 619.929,45
4 Bekisting m2 0,7100 250.000,00 177.500,00
5 Baja Tulangan U25 kg 22,2253 14.511,50 322.522,44
6 Plastik Cor m2 7,6000 3.800,00 28.880,00
7 Curing Ltr 0,5351 41.500,00 22.204,57
8 Joint Sealent Kg 1,2533 35.800,00 44.869,33

JUMLAH HARGA II 6.365.754,69

C. PERALATAN ls 1,0000 4.650.000,00 4.650.000,00

JUMLAH HARGA III 4.650.000,00

D. JUMLAH HARGA TENAGA, BAHAN, DAN PERALATAN ( A + B + C ) 13.765.754,69


E. OVERHEAD + PROFIT 2.064.863,20
F. JUMLAH HARGA DENGAN OVERHEAD + PROFIT (D+E) 15.830.617,89
G. PPN 11% (F X 11%) 1.741.367,96
H. HARGA SATUAN PEKERJAAN (F+G) 17.571.985,85

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
5
Peninggian Jalan Beton/Overlay 4 Jam Terpasang Pembesian 1
JENIS PEKERJAAN :
Lapis Wiremesh dengan Bongkar Perkerasan Eksisting

SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 2.500.000,00 2.500.000,00

JUMLAH HARGA I 2.500.000,00

B. BAHAN
1 Beton Rapid Setting 4 jam m3 1,0300 4.600.000,00 4.738.000,00
2 Wiremesh WM 8 m2 3,8000 81.569,66 309.964,72
3 Bekisting m2 0,7100 250.000,00 177.500,00
4 Baja Tulangan U24 kg 22,2253 14.511,50 322.522,44
5 Plastik Cor m2 3,8000 3.800,00 14.440,00
6 Curing Ltr 0,5351 41.500,00 22.204,57
7 Joint Sealent Kg 1,2533 35.800,00 44.869,33

JUMLAH HARGA II 5.629.501,06

C. PERALATAN ls 1,0000 1.950.000,00 1.950.000,00

JUMLAH HARGA III 1.950.000,00

D. JUMLAH HARGA TENAGA, BAHAN, DAN PERALATAN ( A + B + C ) 10.079.501,06


E. OVERHEAD + PROFIT 1.511.925,15
F. JUMLAH HARGA DENGAN OVERHEAD + PROFIT (D+E) 11.591.426,21
G. PPN 11% (F X 11%) 1.275.056,88
H. HARGA SATUAN PEKERJAAN (F+G) 12.866.483,09

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
6
Peninggian Jalan Beton/Overlay 4 Jam Terpasang Pembesian 1
JENIS PEKERJAAN :
Lapis Wiremesh Tanpa Bongkar Perkerasan Eksisting

SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 2.500.000,00 2.500.000,00

JUMLAH HARGA I 2.500.000,00

B. BAHAN
1 Beton Rapid Setting 4 jam m3 1,0300 4.600.000,00 4.738.000,00
2 Wiremesh WM 8 m2 3,8000 81.569,66 309.964,72
3 Bekisting m2 0,7100 250.000,00 177.500,00
4 Baja Tulangan U24 kg 22,8506 14.511,50 331.596,35
5 Plastik Cor m2 3,8000 3.800,00 14.440,00
6 Curing Ltr 0,5351 41.500,00 22.204,57
7 Joint Sealent Kg 1,2533 35.800,00 44.869,33

JUMLAH HARGA II 5.638.574,97

C. PERALATAN ls 1,0000 1.750.000,00 1.750.000,00

JUMLAH HARGA III 1.750.000,00

D. JUMLAH HARGA TENAGA, BAHAN, DAN PERALATAN ( A + B + C ) 9.888.574,97


E. OVERHEAD + PROFIT 1.483.286,24
F. JUMLAH HARGA DENGAN OVERHEAD + PROFIT (D+E) 11.371.861,21
G. PPN 11% (F X 11%) 1.250.904,73
H. HARGA SATUAN PEKERJAAN (F+G) 12.622.765,94

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
7
Peninggian Jalan Beton/Overlay 4 Jam Terpasang Pembesian 2
JENIS PEKERJAAN :
Lapis Wiremesh dengan Bongkar Perkerasan Eksisting

SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 2.750.000,00 2.750.000,00

JUMLAH HARGA I 2.750.000,00

B. BAHAN
1 Beton Rapid Setting 4 jam m3 1,0300 4.600.000,00 4.738.000,00
2 Wiremesh WM 8 m2 7,6000 81.569,66 619.929,45
3 Bekisting m2 0,7100 250.000,00 177.500,00
4 Baja Tulangan U24 kg 22,2253 14.511,50 322.522,44
5 Plastik Cor m2 7,6000 3.800,00 28.880,00
6 Curing Ltr 0,5351 41.500,00 22.204,57
7 Joint Sealent Kg 1,2533 35.800,00 44.869,33

JUMLAH HARGA II 5.953.905,79

C. PERALATAN ls 1,0000 1.950.000,00 1.950.000,00

JUMLAH HARGA III 1.950.000,00

D. JUMLAH HARGA TENAGA, BAHAN, DAN PERALATAN ( A + B + C ) 10.653.905,79


E. OVERHEAD + PROFIT 1.598.085,86
F. JUMLAH HARGA DENGAN OVERHEAD + PROFIT (D+E) 12.251.991,65
G. PPN 11% (F X 11%) 1.347.719,08
H. HARGA SATUAN PEKERJAAN (F+G) 13.599.710,73

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
8
Peninggian Jalan Beton/Overlay 4 Jam Terpasang Pembesian 2
JENIS PEKERJAAN :
Lapis Wiremesh Tanpa Bongkar Perkerasan Eksisting

SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 2.750.000,00 2.750.000,00

JUMLAH HARGA I 2.750.000,00

B. BAHAN
1 Beton Rapid Setting 4 jam m3 1,0300 4.600.000,00 4.738.000,00
2 Wiremesh WM 8 m2 7,6000 81.569,66 619.929,45
3 Bekisting m2 0,7100 250.000,00 177.500,00
4 Baja Tulangan U24 kg 22,2253 14.511,50 322.522,44
5 Plastik Cor m2 7,6000 3.800,00 28.880,00
6 Curing Ltr 0,5351 41.500,00 22.204,57
7 Joint Sealent Kg 1,2533 35.800,00 44.869,33

JUMLAH HARGA II 5.953.905,79

C. PERALATAN ls 1,0000 1.750.000,00 1.750.000,00

JUMLAH HARGA III 1.750.000,00

D. JUMLAH HARGA TENAGA, BAHAN, DAN PERALATAN ( A + B + C ) 10.453.905,79


E. OVERHEAD + PROFIT 1.568.085,86
F. JUMLAH HARGA DENGAN OVERHEAD + PROFIT (D+E) 12.021.991,65
G. PPN 11% (F X 11%) 1.322.419,08
H. HARGA SATUAN PEKERJAAN (F+G) 13.344.410,73

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
9
Peninggian Jalan Beton/Overlay 8 Jam Terpasang Pembesian 1
JENIS PEKERJAAN : Lapis Wiremesh dengan Bongkar Perkerasan Eksisting

SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 2.500.000,00 2.500.000,00

JUMLAH HARGA I 2.500.000,00

B. BAHAN
1 CTB m3 1,0300 974.853,31 1.004.098,90
2 Beton Rapid Setting 8 jam m3 1,0300 4.025.000,00 4.145.750,00
3 Wiremesh WM 8 m2 3,8000 81.569,66 309.964,72
4 Bekisting m2 0,7100 250.000,00 177.500,00
5 Baja Tulangan U24 kg 22,2253 14.511,50 322.522,44
6 Plastik Cor m2 3,8000 3.800,00 14.440,00
7 Curing Ltr 0,5351 41.500,00 22.204,57
8 Joint Sealent Kg 1,2533 35.800,00 44.869,33

JUMLAH HARGA II 6.041.349,96

C. PERALATAN ls 1,0000 1.950.000,00 1.950.000,00

JUMLAH HARGA III 1.950.000,00

D. JUMLAH HARGA TENAGA, BAHAN, DAN PERALATAN ( A + B + C ) 10.491.349,96


E. OVERHEAD + PROFIT 1.573.702,49
F. JUMLAH HARGA DENGAN OVERHEAD + PROFIT (D+E) 12.065.052,45
G. PPN 11% (F X 11%) 1.327.155,76
H. HARGA SATUAN PEKERJAAN (F+G) 13.392.208,21

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
10
Peninggian Jalan Beton/Overlay 8 Jam Terpasang Pembesian 1
JENIS PEKERJAAN : Lapis Wiremesh Tanpa Bongkar Perkerasan Eksisting

SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 2.500.000,00 2.500.000,00

JUMLAH HARGA I 2.500.000,00

B. BAHAN
1 CTB m3 1,0300 974.853,31 1.004.098,90
2 Beton Rapid Setting 8 jam m3 1,0300 4.025.000,00 4.145.750,00
3 Wiremesh WM 8 m2 3,8000 81.569,66 309.964,72
4 Bekisting m2 0,7100 250.000,00 177.500,00
5 Baja Tulangan U24 kg 22,2253 14.511,50 322.522,44
6 Plastik Cor m2 3,8000 3.800,00 14.440,00
7 Curing Ltr 0,5351 41.500,00 22.204,57
8 Joint Sealent Kg 1,2533 35.800,00 44.869,33

JUMLAH HARGA II 6.041.349,96

C. PERALATAN ls 1,0000 1.750.000,00 1.750.000,00

JUMLAH HARGA III 1.750.000,00

D. JUMLAH HARGA TENAGA, BAHAN, DAN PERALATAN ( A + B + C ) 10.291.349,96


E. OVERHEAD + PROFIT 1.543.702,49
F. JUMLAH HARGA DENGAN OVERHEAD + PROFIT (D+E) 11.835.052,45
G. PPN 11% (F X 11%) 1.301.855,76
H. HARGA SATUAN PEKERJAAN (F+G) 13.136.908,21

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
11
Peninggian Jalan Beton/Overlay 8 Jam Terpasang Pembesian 2
JENIS PEKERJAAN : Lapis Wiremesh dengan Bongkar Perkerasan Eksisting

SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 2.750.000,00 2.750.000,00

JUMLAH HARGA I 2.750.000,00

B. BAHAN
1 Beton Rapid Setting 8 jam m3 1,0300 4.025.000,00 4.145.750,00
2 Wiremesh WM 8 m2 3,8000 81.569,66 309.964,72
3 Bekisting m2 0,7100 250.000,00 177.500,00
4 Baja Tulangan U24 kg 3,8000 14.511,50 55.143,70
5 Plastik Cor m2 3,8000 3.800,00 14.440,00
6 Curing Ltr 0,5351 41.500,00 22.204,57
7 Joint Sealent Kg 1,2533 35.800,00 44.869,33

JUMLAH HARGA II 4.769.872,32

C. PERALATAN ls 1,0000 1.950.000,00 1.950.000,00

JUMLAH HARGA III 1.950.000,00

D. JUMLAH HARGA TENAGA, BAHAN, DAN PERALATAN ( A + B + C ) 9.469.872,32


E. OVERHEAD + PROFIT 1.420.480,84
F. JUMLAH HARGA DENGAN OVERHEAD + PROFIT (D+E) 10.890.353,16
G. PPN 11% (F X 11%) 1.197.938,84
H. HARGA SATUAN PEKERJAAN (F+G) 12.088.292,00

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
12
Peninggian Jalan Beton/Overlay 8 Jam Terpasang Pembesian 2
JENIS PEKERJAAN : Lapis Wiremesh Tanpa Bongkar Perkerasan Eksisting

SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 2.750.000,00 2.750.000,00

JUMLAH HARGA I 2.750.000,00

B. BAHAN
1 Beton Rapid Setting 8 jam m3 1,0300 4.025.000,00 4.145.750,00
2 Wiremesh WM 8 m2 7,6000 81.569,66 619.929,45
3 Bekisting m2 0,7100 250.000,00 177.500,00
4 Baja Tulangan U24 kg 1,0300 14.511,50 14.946,84
5 Plastik Cor m2 7,6000 3.800,00 28.880,00
6 Curing Ltr 0,5351 41.500,00 22.204,57
7 Joint Sealent Kg 1,2533 35.800,00 44.869,33

JUMLAH HARGA II 5.054.080,19

C. PERALATAN ls 1,0000 1.750.000,00 1.750.000,00

JUMLAH HARGA III 1.750.000,00

D. JUMLAH HARGA TENAGA, BAHAN, DAN PERALATAN ( A + B + C ) 9.554.080,19


E. OVERHEAD + PROFIT 1.433.112,02
F. JUMLAH HARGA DENGAN OVERHEAD + PROFIT (D+E) 10.987.192,21
G. PPN 11% (F X 11%) 1.208.591,14
H. HARGA SATUAN PEKERJAAN (F+G) 12.195.783,35

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
13
JENIS PEKERJAAN : Peninggian Jalan Beton/Overlay dengan Ketebalan Rendah (min. 5 cm) dengan Bongkar Perkerasan Eksisting
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 2.750.000,00 2.750.000,00

JUMLAH HARGA I 2.750.000,00

B. BAHAN
1 Beton Rapid Setting 8 jam m3 1,0300 4.025.000,00 4.145.750,00
2 Wiremesh WM 12 m2 6,3529 92.592,00 588.231,52
3 Bekisting m2 0,7100 250.000,00 177.500,00
4 Baja Tulangan U24 kg 9,7235 14.511,50 141.101,84
5 Plastik Cor m2 6,3529 3.800,00 24.141,17
6 Curing Ltr 0,5351 41.500,00 22.204,57
7 Joint Sealent Kg 1,2533 35.800,00 44.869,33

JUMLAH HARGA II 5.143.798,43

C. PERALATAN ls 1,0000 1.750.000,00 1.750.000,00

JUMLAH HARGA III 1.750.000,00

D. JUMLAH HARGA TENAGA, BAHAN, DAN PERALATAN ( A + B + C ) 9.643.798,43


E. OVERHEAD + PROFIT 1.446.569,76
F. JUMLAH HARGA DENGAN OVERHEAD + PROFIT (D+E) 11.090.368,19
G. PPN 11% (F X 11%) 1.219.940,50
H. HARGA SATUAN PEKERJAAN (F+G) 12.310.308,69

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
14
JENIS PEKERJAAN : Peninggian Jalan Beton/Overlay dengan Ketebalan Rendah (min. 5 cm) Tanpa Bongkar Perkerasan Eksisting
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 2.750.000,00 2.750.000,00

JUMLAH HARGA I 2.750.000,00

B. BAHAN
1 Beton Rapid Setting 4 jam m3 1,0040 4.600.000,00 4.618.400,00
2 Wiremesh WM 8 m2 6,3529 92.592,00 588.231,52
3 Bekisting m2 0,7100 250.000,00 177.500,00
4 Baja Tulangan U24 kg 9,7235 14.511,50 141.101,84
5 Plastik Cor m2 6,3529 3.800,00 24.141,17
6 Curing Ltr 0,5351 41.500,00 22.204,57
7 Joint Sealent Kg 1,2533 35.800,00 44.869,33

JUMLAH HARGA II 5.616.448,43

C. PERALATAN ls 1,0000 1.750.000,00 1.750.000,00

JUMLAH HARGA III 1.750.000,00

D. JUMLAH HARGA TENAGA, BAHAN, DAN PERALATAN ( A + B + C ) 10.116.448,43


E. OVERHEAD + PROFIT 1.517.467,26
F. JUMLAH HARGA DENGAN OVERHEAD + PROFIT (D+E) 11.633.915,69
G. PPN 11% (F X 11%) 1.279.730,72
H. HARGA SATUAN PEKERJAAN (F+G) 12.913.646,41

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
15
JENIS PEKERJAAN : Peninggian Jalan Beton/Overlay dengan Ketebalan Rendah (± 12 cm) dengan Bongkar Perkerasan Eksisting
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 2.750.000,00 2.750.000,00

JUMLAH HARGA I 2.750.000,00

B. BAHAN
1 Beton Rapid Setting 8 jam m3 0,7750 4.025.000,00 3.119.375,00
2 Wiremesh WM 8 m2 6,3529 92.592,00 588.231,52
3 Bekisting m2 0,7100 250.000,00 177.500,00
4 Baja Tulangan U24 kg 9,7235 14.511,50 141.101,84
5 Plastik Cor m2 6,3529 3.800,00 24.141,17
6 Curing Ltr 0,5351 41.500,00 22.204,57
7 Joint Sealent Kg 1,2533 35.800,00 44.869,33

JUMLAH HARGA II 4.117.423,43

C. PERALATAN ls 1,0000 1.750.000,00 1.750.000,00

JUMLAH HARGA III 1.750.000,00

D. JUMLAH HARGA TENAGA, BAHAN, DAN PERALATAN ( A + B + C ) 8.617.423,43


E. OVERHEAD + PROFIT 1.292.613,51
F. JUMLAH HARGA DENGAN OVERHEAD + PROFIT (D+E) 9.910.036,94
G. PPN 11% (F X 11%) 1.090.104,06
H. HARGA SATUAN PEKERJAAN (F+G) 11.000.141,00

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
16
JENIS PEKERJAAN : Peninggian Jalan Beton/Overlay dengan Ketebalan Rendah (± 12 cm) Tanpa Bongkar Perkerasan Eksisting
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 2.750.000,00 2.750.000,00

JUMLAH HARGA I 2.750.000,00

B. BAHAN
1 Beton Rapid Setting 4 jam m3 0,9300 4.600.000,00 4.278.000,00
2 Wiremesh WM 8 m2 6,3529 92.592,00 588.231,52
3 Bekisting m2 0,7100 250.000,00 177.500,00
4 Baja Tulangan U24 kg 9,7235 14.511,50 141.101,84
5 Plastik Cor m2 6,3529 3.800,00 24.141,17
6 Curing Ltr 0,5351 41.500,00 22.204,57
7 Joint Sealent Kg 1,2533 35.800,00 44.869,33

JUMLAH HARGA II 5.276.048,43

C. PERALATAN ls 1,0000 1.750.000,00 1.750.000,00

JUMLAH HARGA III 1.750.000,00

D. JUMLAH HARGA TENAGA, BAHAN, DAN PERALATAN ( A + B + C ) 9.776.048,43


E. OVERHEAD + PROFIT 1.466.407,26
F. JUMLAH HARGA DENGAN OVERHEAD + PROFIT (D+E) 11.242.455,69
G. PPN 11% (F X 11%) 1.236.670,12
H. HARGA SATUAN PEKERJAAN (F+G) 12.479.125,81

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
17
JENIS PEKERJAAN : Perbaikan Beton dengan Peninggian Grill Underpass dengan perbaikan slab
SATUAN PEMBAYARAN : M'

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 2.750.000,00 2.750.000,00

JUMLAH HARGA I 2.750.000,00

B. BAHAN
1 Beton Rapid Setting 4 jam m3 0,5890 4.600.000,00 2.709.400,00
2 Wiremesh WM 8 m2 8,3333 75.006,00 625.050,00
3 Bekisting m2 0,7100 250.000,00 177.500,00
4 Baja Tulangan U24 kg 22,2253 14.511,50 322.522,44
5 Plastik Cor m2 8,3333 3.800,00 31.666,66
6 Curing Ltr 0,5394 41.500,00 22.385,10
7 Joint Sealent Kg 1,2533 35.800,00 44.869,33

JUMLAH HARGA II 3.933.393,53

C. PERALATAN ls 1,0000 3.500.000,00 3.500.000,00

JUMLAH HARGA III 3.500.000,00

D. JUMLAH HARGA TENAGA, BAHAN, DAN PERALATAN ( A + B + C ) 10.183.393,53


E. OVERHEAD + PROFIT 1.527.509,02
F. JUMLAH HARGA DENGAN OVERHEAD + PROFIT (D+E) 11.710.902,55
G. PPN 11% (F X 11%) 1.288.199,28
H. HARGA SATUAN PEKERJAAN (F+G) 12.999.101,83

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
18
JENIS PEKERJAAN : Perbaikan Beton dengan Peninggian Grill Underpass tanpa perbaikan slab
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 2.950.000,00 2.950.000,00

JUMLAH HARGA I 2.950.000,00

B. BAHAN
1 Beton Rapid Setting 4 jam m3 0,5890 4.600.000,00 2.709.400,00
2 Wiremesh WM 8 m2 8,3333 75.006,00 625.050,00
3 Bekisting m2 0,7100 250.000,00 177.500,00
4 Baja Tulangan U24 kg 22,2253 14.511,50 322.522,44
5 Plastik Cor m2 8,3333 3.800,00 31.666,66
6 Curing Ltr 0,5351 41.500,00 22.204,57
7 Joint Sealent Kg 1,2533 35.800,00 44.869,33

JUMLAH HARGA II 3.933.213,00

C. PERALATAN ls 1,0000 3.500.000,00 3.500.000,00

JUMLAH HARGA III 3.500.000,00

D. JUMLAH HARGA TENAGA, BAHAN, DAN PERALATAN ( A + B + C ) 10.383.213,00


E. OVERHEAD + PROFIT 1.557.481,95
F. JUMLAH HARGA DENGAN OVERHEAD + PROFIT (D+E) 11.940.694,95
G. PPN 11% (F X 11%) 1.313.476,44
H. HARGA SATUAN PEKERJAAN (F+G) 13.254.171,39

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
19
JENIS PEKERJAAN : Pekerjaan Lapis Bawah dengan CTB
SATUAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 165.000,00 165.000,00

JUMLAH HARGA I 165.000,00

B. BAHAN
1 Semen Kg 121,7700 1.280,00 155.865,60
2 Agregat Kasar M3 1,2433 273.000,00 339.420,90

JUMLAH HARGA II 495.286,50

C. PERALATAN ls 1,0000 314.566,82 314.566,81

JUMLAH HARGA III 314.566,81

D. JUMLAH HARGA TENAGA, BAHAN, DAN PERALATAN ( A + B + C ) 974.853,31


E. OVERHEAD + PROFIT 146.227,99
F. JUMLAH HARGA DENGAN OVERHEAD + PROFIT (D+E) 1.121.081,30
G. PPN 11% (F X 11%) 123.318,94
H. HARGA SATUAN PEKERJAAN (F+G) 1.244.400,24

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
1
JENIS PEKERJAAN : Jalan Beton FS 45 Tebal 25 cm (Konvensional 28 Hari)
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 210.000,00 210.000,00

JUMLAH HARGA I 210.000,00

B. BAHAN
1 Readymix FS. 45 m3 1,0600 1.265.000,00 1.340.900,00
2 Bekisting Pelat m2 0,4275 218.500,00 93.408,75
3 Baja Tulangan U24 kg 16,9333 15.617,50 264.456,33
4 Olie / Gemuk Liter 0,4550 11.000,00 5.005,00
5 Plastik Bening m2 3,9000 3.800,00 14.820,00
6 Curing Ltr 0,6090 41.000,00 24.969,00
7 Joint Sealent Kg 1,2533 36.000,00 45.120,00

JUMLAH HARGA II 1.788.679,08

C. PERALATAN ls 1,0000 300.000,00 300.000,00

JUMLAH HARGA III 300.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.298.679,08
E. OVERHEAD DAN PROFIT 344.801,86
F. TOTAL DENGAN OVERHEAD (D+E) 2.643.480,94
G. PPN 11% (F X 11%) 290.782,90
H. HARGA SATUAN PEKERJAAN (F+G) 2.934.263,84

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
2
JENIS PEKERJAAN : Jalan Beton FS 45 Tebal 25 cm (Konvensional 28 Hari) Pembesian 1 Lapis wiremesh
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 230.000,00 230.000,00

JUMLAH HARGA I 230.000,00

B. BAHAN
1 Readymix FS. 45 m3 1,0600 1.265.000,00 1.340.900,00
2 Wiremesh WM 8 m2 3,8000 87.000,00 330.600,00
3 Bekisting Pelat m2 0,4275 218.500,00 93.408,75
4 Baja Tulangan U24 kg 16,9333 15.617,50 264.456,33
5 Olie / Gemuk Liter 0,4550 11.000,00 5.005,00
6 Plastik Bening m2 3,9000 3.800,00 14.820,00
7 Curing Ltr 0,6090 41.000,00 24.969,00
8 Joint Sealent Kg 1,2533 36.000,00 45.120,00

JUMLAH HARGA II 2.119.279,08

C. PERALATAN ls 1,0000 400.000,00 400.000,00

JUMLAH HARGA III 400.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.749.279,08
E. OVERHEAD DAN PROFIT 412.391,86
F. TOTAL DENGAN OVERHEAD (D+E) 3.161.670,94
G. PPN 11% (F X 11%) 347.783,80
H. HARGA SATUAN PEKERJAAN (F+G) 3.509.454,74

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
3
JENIS PEKERJAAN : Jalan Beton FS 45 Tebal 20 cm (Konvensional 28 Hari)
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 250.000,00 250.000,00

JUMLAH HARGA I 250.000,00

B. BAHAN
1 Readymix FS. 45 m3 1,0600 1.265.000,00 1.340.900,00
2 Bekisting Pelat m2 0,4560 218.500,00 99.636,00
3 Baja Tulangan U24 kg 16,9887 15.617,50 265.321,08
4 Olie / Gemuk Liter 0,4550 11.000,00 5.005,00
5 Plastik Bening m2 3,9000 3.800,00 14.820,00
6 Curing Ltr 0,6090 41.000,00 24.969,00
7 Joint Sealent Kg 1,2533 36.000,00 45.120,00

JUMLAH HARGA II 1.795.771,08

C. PERALATAN ls 1,0000 320.000,00 320.000,00

JUMLAH HARGA III 320.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.365.771,08
E. OVERHEAD DAN PROFIT 354.865,66
F. TOTAL DENGAN OVERHEAD (D+E) 2.720.636,74
G. PPN 11% (F X 11%) 299.270,04
H. HARGA SATUAN PEKERJAAN (F+G) 3.019.906,78

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
4
JENIS PEKERJAAN : Jalan Beton FS 45 Tebal 20 cm (Konvensional 28 Hari) Pembesian 1 Lapis wiremesh
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 250.000,00 250.000,00

JUMLAH HARGA I 250.000,00

B. BAHAN
1 Readymix FS. 45 m3 1,0600 1.265.000,00 1.340.900,00
2 Wiremesh WM 8 m2 3,8000 87.000,00 330.600,00
3 Bekisting Pelat m2 0,4560 218.500,00 99.636,00
4 Baja Tulangan U24 kg 16,9887 15.617,50 265.321,08
5 Olie / Gemuk Liter 0,4550 11.000,00 5.005,00
6 Plastik Bening m2 3,9000 3.800,00 14.820,00
7 Curing Ltr 0,6090 41.000,00 24.969,00
8 Joint Sealent Kg 1,2533 36.000,00 45.120,00

JUMLAH HARGA II 2.126.371,08

C. PERALATAN ls 1,0000 400.000,00 400.000,00

JUMLAH HARGA III 400.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.776.371,08
E. OVERHEAD DAN PROFIT 416.455,66
F. TOTAL DENGAN OVERHEAD (D+E) 3.192.826,74
G. PPN 11% (F X 11%) 351.210,94
H. HARGA SATUAN PEKERJAAN (F+G) 3.544.037,68

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
5
JENIS PEKERJAAN : Jalan Beton FS 45 Tebal 15 cm (Konvensional 28 Hari)
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 300.000,00 300.000,00

JUMLAH HARGA I 300.000,00

B. BAHAN
1 Readymix K.350 m3 1,0600 1.127.000,00 1.194.620,00
2 Bekisting Pelat m2 0,4275 218.500,00 93.408,75
3 Baja Tulangan U24 kg 16,9333 15.617,50 264.456,33
4 Olie / Gemuk Liter 0,4550 11.000,00 5.005,00
5 Plastik Bening m2 3,9000 3.800,00 14.820,00
6 Curing Ltr 0,6090 41.000,00 24.969,00
7 Joint Sealent Kg 1,2533 36.000,00 45.120,00

JUMLAH HARGA II 1.642.399,08

C. PERALATAN ls 1,0000 320.000,00 320.000,00

JUMLAH HARGA III 320.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.262.399,08
E. OVERHEAD DAN PROFIT 339.359,86
F. TOTAL DENGAN OVERHEAD (D+E) 2.601.758,94
G. PPN 11% (F X 11%) 286.193,48
H. HARGA SATUAN PEKERJAAN (F+G) 2.887.952,42

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
6
JENIS PEKERJAAN : Jalan Beton FS 45 Tebal 15 cm (Konvensional 28 Hari) Pembesian 1 Lapis wiremesh
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 380.000,00 380.000,00

JUMLAH HARGA I 380.000,00

B. BAHAN
1 Readymix K.350 m3 1,0600 1.265.000,00 1.340.900,00
2 Wiremesh WM 8 m2 3,8000 87.000,00 330.600,00
3 Bekisting Pelat m2 0,4275 218.500,00 93.408,75
4 Baja Tulangan U24 kg 16,9333 15.617,50 264.456,33
5 Olie / Gemuk Liter 0,4550 11.000,00 5.005,00
6 Plastik Bening m2 3,9000 3.800,00 14.820,00
7 Curing Ltr 0,6090 41.000,00 24.969,00
8 Joint Sealent Kg 1,2533 36.000,00 45.120,00

JUMLAH HARGA II 2.119.279,08

C. PERALATAN ls 1,0000 628.000,00 628.000,00

JUMLAH HARGA III 628.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 3.127.279,08
E. OVERHEAD DAN PROFIT 469.091,86
F. TOTAL DENGAN OVERHEAD (D+E) 3.596.370,94
G. PPN 11% (F X 11%) 395.600,80
H. HARGA SATUAN PEKERJAAN (F+G) 3.991.971,74

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
7
JENIS PEKERJAAN : Jalan Beton K-350 Tebal 25 cm (Konvensional 28 Hari)
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 250.000,00 250.000,00

JUMLAH HARGA I 250.000,00

B. BAHAN
1 Readymix K.350 m3 1,0600 1.127.000,00 1.194.620,00
2 Bekisting Pelat m2 0,3420 218.500,00 74.727,00
3 Baja Tulangan U24 kg 18,1213 15.617,50 283.009,15
4 Olie / Gemuk Liter 0,4550 11.000,00 5.005,00
5 Plastik Bening m2 3,9000 3.800,00 14.820,00
6 Curing Ltr 0,6090 41.000,00 24.969,00
7 Joint Sealent Kg 1,2533 36.000,00 45.120,00

JUMLAH HARGA II 1.642.270,15

C. PERALATAN ls 1,0000 300.000,00 300.000,00

JUMLAH HARGA III 300.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.192.270,15
E. OVERHEAD DAN PROFIT 328.840,52
F. TOTAL DENGAN OVERHEAD (D+E) 2.521.110,67
G. PPN 11% (F X 11%) 277.322,17
H. HARGA SATUAN PEKERJAAN (F+G) 2.798.432,84

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
8
JENIS PEKERJAAN : Jalan Beton K-350 Tebal 20 cm (Konvensional 28 Hari)
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 270.000,00 270.000,00

JUMLAH HARGA I 270.000,00

B. BAHAN
1 Readymix K.350 m3 1,0600 1.127.000,00 1.194.620,00
2 Bekisting Pelat m2 0,3420 218.500,00 74.727,00
3 Baja Tulangan U24 kg 18,1213 15.617,50 283.009,15
4 Olie / Gemuk Liter 0,4550 11.000,00 5.005,00
5 Plastik Bening m2 3,9000 3.800,00 14.820,00
6 Curing Ltr 0,6090 41.000,00 24.969,00
7 Joint Sealent Kg 1,2533 36.000,00 45.120,00

JUMLAH HARGA II 1.642.270,15

C. PERALATAN ls 1,0000 320.000,00 320.000,00

JUMLAH HARGA III 320.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.232.270,15
E. OVERHEAD DAN PROFIT 334.840,52
F. TOTAL DENGAN OVERHEAD (D+E) 2.567.110,67
G. PPN 11% (F X 11%) 282.382,17
H. HARGA SATUAN PEKERJAAN (F+G) 2.849.492,84

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
9
JENIS PEKERJAAN : Jalan Beton K-350 Tebal 15 cm (Konvensional 28 Hari)
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 300.000,00 300.000,00

JUMLAH HARGA I 300.000,00

B. BAHAN
1 Readymix K.350 m3 1,0600 1.127.000,00 1.194.620,00
2 Bekisting Pelat m2 0,3420 218.500,00 74.727,00
3 Baja Tulangan U24 kg 18,1213 15.617,50 283.009,15
4 Olie / Gemuk Liter 0,4550 11.000,00 5.005,00
5 Plastik Bening m2 3,9000 3.800,00 14.820,00
6 Curing Ltr 0,6090 41.000,00 24.969,00
7 Joint Sealent Kg 1,2533 36.000,00 45.120,00

JUMLAH HARGA II 1.642.270,15

C. PERALATAN ls 1,0000 320.000,00 320.000,00

JUMLAH HARGA III 320.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.262.270,15
E. OVERHEAD DAN PROFIT 339.340,52
F. TOTAL DENGAN OVERHEAD (D+E) 2.601.610,67
G. PPN 11% (F X 11%) 286.177,17
H. HARGA SATUAN PEKERJAAN (F+G) 2.887.787,84

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
10
JENIS PEKERJAAN : Jalan Beton K-250 Tebal 12 cm (Konvensional 28 Hari)
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 310.000,00 310.000,00

JUMLAH HARGA I 310.000,00

B. BAHAN
1 Readymix K.250 m3 1,0600 1.081.000,00 1.145.860,00
2 Bekisting Pelat m2 0,2052 218.500,00 44.836,20
3 Baja Tulangan U24 kg 9,0048 15.617,50 140.632,16
4 Olie / Gemuk Liter 0,4550 11.000,00 5.005,00
5 Plastik Bening m2 6,5534 3.800,00 24.902,92
6 Curing Ltr 0,6090 41.000,00 24.969,00
7 Joint Sealent Kg 1,2533 36.000,00 45.120,00

JUMLAH HARGA II 1.431.325,28

C. PERALATAN ls 1,0000 220.000,00 220.000,00

JUMLAH HARGA III 220.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.961.325,28
E. OVERHEAD DAN PROFIT 294.198,79
F. TOTAL DENGAN OVERHEAD (D+E) 2.255.524,07
G. PPN 11% (F X 11%) 248.107,64
H. HARGA SATUAN PEKERJAAN (F+G) 2.503.631,71

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
11
JENIS PEKERJAAN : Jalan Beton FS 45 Tebal 25 cm (Fast Track 3 Hari)
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 250.000,00 250.000,00

JUMLAH HARGA I 250.000,00

B. BAHAN
1 Readymix FS. 45 (Fast Track 3 Hari) m3 1,0600 1.667.500,00 1.767.550,00
2 Bekisting Pelat m2 0,4275 218.500,00 93.408,75
3 Baja Tulangan U24 kg 16,9333 15.617,50 264.456,33
4 Olie / Gemuk Liter 0,4550 11.000,00 5.005,00
5 Plastik Bening m2 3,9000 3.800,00 14.820,00
6 Curing Ltr 0,6090 41.000,00 24.969,00
7 Joint Sealent Kg 1,2533 36.000,00 45.120,00

JUMLAH HARGA II 2.215.329,08

C. PERALATAN ls 1,0000 230.000,00 230.000,00

JUMLAH HARGA III 230.000,00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.695.329,08


E. OVERHEAD DAN PROFIT 404.299,36
F. TOTAL DENGAN OVERHEAD (D+E) 3.099.628,44
G. PPN 11% (F X 11%) 340.959,12
H. HARGA SATUAN PEKERJAAN (F+G) 3.440.587,56

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
12
JENIS PEKERJAAN : Jalan Beton FS 45 Tebal 25 cm (Fast Track 3 Hari) Pembesian 1 Lapis wiremesh
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 380.000,00 380.000,00

JUMLAH HARGA I 380.000,00

B. BAHAN
1 Readymix FS. 45 (Fast Track 3 Hari) m3 1,0600 1.667.500,00 1.767.550,00
2 Wiremesh WM 8 m2 3,8000 15.617,50 59.346,50
3 Bekisting Pelat m2 0,4275 11.000,00 4.702,50
4 Baja Tulangan U24 kg 16,9333 3.800,00 64.346,66
5 Olie / Gemuk Liter 0,4550 41.000,00 18.655,00
6 Plastik Bening m2 3,9000 36.000,00 140.400,00
7 Curing Ltr 0,6090 41.000,00 24.969,00
8 Joint Sealent Kg 1,2533 36.000,00 45.120,00

JUMLAH HARGA II 2.125.089,66

C. PERALATAN ls 1,0000 630.000,00 630.000,00

JUMLAH HARGA III 630.000,00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 3.135.089,66


E. OVERHEAD DAN PROFIT 470.263,44
F. TOTAL DENGAN OVERHEAD (D+E) 3.605.353,10
G. PPN 11% (F X 11%) 396.588,84
H. HARGA SATUAN PEKERJAAN (F+G) 4.001.941,94

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
13
JENIS PEKERJAAN : Jalan Beton FS 45 Tebal 20 cm (Fast Track 3 Hari)
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 270.000,00 270.000,00

JUMLAH HARGA I 270.000,00

B. BAHAN
1 Readymix FS. 45 (Fast Track 3 Hari) m3 1,0600 1.667.500,00 1.767.550,00
2 Bekisting Pelat m2 0,3420 218.500,00 74.727,00
3 Baja Tulangan U24 kg 18,1213 15.617,50 283.009,15
4 Olie / Gemuk Liter 0,4550 11.000,00 5.005,00
5 Plastik Bening m2 4,9000 3.800,00 18.620,00
6 Curing Ltr 0,6090 41.000,00 24.969,00
7 Joint Sealent Kg 1,2533 36.000,00 45.120,00

JUMLAH HARGA II 2.219.000,15

C. PERALATAN ls 1,0000 210.000,00 210.000,00

JUMLAH HARGA III 210.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.699.000,15
E. OVERHEAD DAN PROFIT 404.850,02
F. TOTAL DENGAN OVERHEAD (D+E) 3.103.850,17
G. PPN 11% (F X 11%) 341.423,51
H. HARGA SATUAN PEKERJAAN (F+G) 3.445.273,68

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
14
JENIS PEKERJAAN : Jalan Beton FS 45 Tebal 20 cm (Fast Track 3 Hari) Pembesian 1 Lapis wiremesh
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 400.000,00 400.000,00

JUMLAH HARGA I 400.000,00

B. BAHAN
1 Readymix FS. 45 (Fast Track 3 Hari) m3 1,0600 1.667.500,00 1.767.550,00
2 Bekisting Pelat m2 0,3420 15.617,50 5.341,18
3 Baja Tulangan U24 kg 18,1213 11.000,00 199.334,12
4 Olie / Gemuk Liter 0,4550 3.800,00 1.729,00
5 Plastik Bening m2 4,9000 41.000,00 200.900,00
6 Curing Ltr 0,6090 36.000,00 21.924,00
7 Joint Sealent Kg 1,2533 36.000,00 45.120,00

JUMLAH HARGA II 2.241.898,30

C. PERALATAN ls 1,0000 510.000,00 510.000,00

JUMLAH HARGA III 510.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 3.151.898,30
E. OVERHEAD DAN PROFIT 472.784,74
F. TOTAL DENGAN OVERHEAD (D+E) 3.624.683,04
G. PPN 11% (F X 11%) 398.715,13
H. HARGA SATUAN PEKERJAAN (F+G) 4.023.398,17

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
15
JENIS PEKERJAAN : Jalan Beton FS 45 Tebal 15 cm (Fast Track 3 Hari)
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 420.000,00 420.000,00

JUMLAH HARGA I 420.000,00

B. BAHAN
1 Readymix FS. 45 (Fast Track 3 Hari) m3 1,0600 1.667.500,00 1.767.550,00
2 Bekisting Pelat m2 0,4275 218.500,00 93.408,75
3 Baja Tulangan U24 kg 16,9333 15.617,50 264.456,33
4 Olie / Gemuk Liter 0,4550 11.000,00 5.005,00
5 Plastik Bening m2 3,9000 3.800,00 14.820,00
6 Curing Ltr 0,6090 41.000,00 24.969,00
7 Joint Sealent Kg 1,2533 36.000,00 45.120,00

JUMLAH HARGA II 2.215.329,08

C. PERALATAN ls 1,0000 510.000,00 510.000,00

JUMLAH HARGA III 510.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 3.145.329,08
E. OVERHEAD DAN PROFIT 471.799,36
F. TOTAL DENGAN OVERHEAD (D+E) 3.617.128,44
G. PPN 11% (F X 11%) 397.884,12
H. HARGA SATUAN PEKERJAAN (F+G) 4.015.012,56

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
16
JENIS PEKERJAAN : Jalan Beton FS 45 Tebal 15 cm (Fast Track 3 Hari) Pembesian 1 Lapis wiremesh
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 470.000,00 470.000,00

JUMLAH HARGA I 470.000,00

B. BAHAN
1 Readymix FS. 45 (Fast Track 3 Hari) m3 1,0600 1.667.500,00 1.767.550,00
2 Bekisting Pelat m2 0,4275 15.617,50 6.676,48
3 Baja Tulangan U24 kg 16,9333 11.000,00 186.266,66
4 Olie / Gemuk Liter 0,4550 3.800,00 1.729,00
5 Plastik Bening m2 3,9000 41.000,00 159.900,00
6 Curing Ltr 0,6090 36.000,00 21.924,00
7 Joint Sealent Kg 1,2533 - -

JUMLAH HARGA II 2.144.046,14

C. PERALATAN ls 1,0000 510.000,00 510.000,00

JUMLAH HARGA III 510.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 3.124.046,14
E. OVERHEAD DAN PROFIT 468.606,92
F. TOTAL DENGAN OVERHEAD (D+E) 3.592.653,06
G. PPN 11% (F X 11%) 395.191,83
H. HARGA SATUAN PEKERJAAN (F+G) 3.987.844,89

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
17
JENIS PEKERJAAN : Jalan Beton K-350 Tebal 25 cm (Fast Track 3 Hari)
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 250.000,00 250.000,00

JUMLAH HARGA I 250.000,00

B. BAHAN
1 Readymix K.350 (Fast Track 3 Hari) m3 1,0600 1.552.500,00 1.645.650,00
2 Bekisting Pelat m2 0,3420 218.500,00 74.727,00
3 Baja Tulangan U24 kg 18,1213 15.617,50 283.009,15
4 Olie / Gemuk Liter 0,4550 11.000,00 5.005,00
5 Plastik Bening m2 4,9000 3.800,00 18.620,00
6 Curing Ltr 0,6090 41.000,00 24.969,00
7 Joint Sealent Kg 1,2533 36.000,00 45.120,00

JUMLAH HARGA II 2.097.100,15

C. PERALATAN ls 1,0000 210.000,00 210.000,00

JUMLAH HARGA III 210.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.557.100,15
E. OVERHEAD DAN PROFIT 383.565,02
F. TOTAL DENGAN OVERHEAD (D+E) 2.940.665,17
G. PPN 11% (F X 11%) 323.473,16
H. HARGA SATUAN PEKERJAAN (F+G) 3.264.138,33

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
18
JENIS PEKERJAAN : Jalan Beton K-350 Tebal 20 cm (Fast Track 3 Hari)
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 270.000,00 270.000,00

JUMLAH HARGA I 270.000,00

B. BAHAN
1 Readymix K.350 (Fast Track 3 Hari) m3 1,0600 1.552.500,00 1.645.650,00
2 Bekisting Pelat m2 0,3420 218.500,00 74.727,00
3 Baja Tulangan U24 kg 18,1213 15.617,50 283.009,15
4 Olie / Gemuk Liter 0,4550 11.000,00 5.005,00
5 Plastik Bening m2 4,9000 3.800,00 18.620,00
6 Curing Ltr 0,6090 41.000,00 24.969,00
7 Joint Sealent Kg 1,2533 36.000,00 45.120,00

JUMLAH HARGA II 2.097.100,15

C. PERALATAN ls 1,0000 210.000,00 210.000,00

JUMLAH HARGA III 210.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.577.100,15
E. OVERHEAD DAN PROFIT 386.565,02
F. TOTAL DENGAN OVERHEAD (D+E) 2.963.665,17
G. PPN 11% (F X 11%) 326.003,16
H. HARGA SATUAN PEKERJAAN (F+G) 3.289.668,33

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
19
JENIS PEKERJAAN : Jalan Beton K-350 Tebal 15 cm (Fast Track 3 Hari)
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 290.000,00 290.000,00

JUMLAH HARGA I 290.000,00

B. BAHAN
1 Readymix K.350 (Fast Track 3 Hari) m3 1,0600 1.552.500,00 1.645.650,00
2 Bekisting Pelat m2 0,3420 218.500,00 74.727,00
3 Baja Tulangan U24 kg 18,1213 15.617,50 283.009,15
4 Olie / Gemuk Liter 0,4550 11.000,00 5.005,00
5 Plastik Bening m2 4,9000 3.800,00 18.620,00
6 Curing Ltr 0,6090 41.000,00 24.969,00
7 Joint Sealent Kg 1,2533 36.000,00 45.120,00

JUMLAH HARGA II 2.097.100,15

C. PERALATAN ls 1,0000 230.000,00 230.000,00

JUMLAH HARGA III 230.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.617.100,15
E. OVERHEAD DAN PROFIT 392.565,02
F. TOTAL DENGAN OVERHEAD (D+E) 3.009.665,17
G. PPN 11% (F X 11%) 331.063,16
H. HARGA SATUAN PEKERJAAN (F+G) 3.340.728,33

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
20
JENIS PEKERJAAN : Beton K-B0/Lantai Kerja
SATUAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 150.000,00 150.000,00

JUMLAH HARGA I 150.000,00

B. BAHAN
1 Readymix K.BO M3 1,0200 968.000,00 987.360,00

JUMLAH HARGA II 987.360,00

C. PERALATAN ls 1,0000 10.000,00 10.000,00

JUMLAH HARGA III 10.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.147.360,00
E. OVERHEAD DAN PROFIT 172.104,00
F. TOTAL DENGAN OVERHEAD (D+E) 1.319.464,00
G. PPN 10% (F X 10%) 145.141,04
H. HARGA SATUAN PEKERJAAN (F+G) 1.464.605,04

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
21
JENIS PEKERJAAN : Bongkaran secara Manual Termasuk Buangan
SATUAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 440.000,00 440.000,00

JUMLAH HARGA I 440.000,00

B. BAHAN

JUMLAH HARGA II -

C. PERALATAN ls 1,0000 20.000,00 20.000,00

JUMLAH HARGA III 20.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 460.000,00
E. OVERHEAD DAN PROFIT 69.000,00
F. TOTAL DENGAN OVERHEAD (D+E) 529.000,00
G. PPN 11% (F X 11%) 58.190,00
H. HARGA SATUAN PEKERJAAN (F+G) 587.190,00

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
22
JENIS PEKERJAAN : Bongkaran dengan Alat Termasuk Buangan
SATUAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 75.000,00 75.000,00

JUMLAH HARGA I 75.000,00

B. BAHAN

JUMLAH HARGA II -

C. PERALATAN ls 1,0000 235.000,00 235.000,00

JUMLAH HARGA III 235.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 310.000,00
E. OVERHEAD DAN PROFIT 46.500,00
F. TOTAL DENGAN OVERHEAD (D+E) 356.500,00
G. PPN 11% (F X 11%) 39.215,00
H. HARGA SATUAN PEKERJAAN (F+G) 395.715,00

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
23
JENIS PEKERJAAN : Galian secara Manual Termasuk Buangan
SATUAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 75.000,00 75.000,00

JUMLAH HARGA I 75.000,00

B. BAHAN

JUMLAH HARGA II -

C. PERALATAN ls 1,0000 50.000,00 50.000,00

JUMLAH HARGA III 50.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 125.000,00
E. OVERHEAD DAN PROFIT 18.750,00
F. TOTAL DENGAN OVERHEAD (D+E) 143.750,00
G. PPN 11% (F X 11%) 15.812,50
H. HARGA SATUAN PEKERJAAN (F+G) 159.562,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
24
JENIS PEKERJAAN : Galian dengan Alat Termasuk Buangan
SATUAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 118.852,55 118.852,55

JUMLAH HARGA I 118.852,55

B. BAHAN

JUMLAH HARGA II -

C. PERALATAN ls 1,0000 154.000,00 154.000,00

JUMLAH HARGA III 154.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 272.852,55
E. OVERHEAD DAN PROFIT 40.927,88
F. TOTAL DENGAN OVERHEAD (D+E) 313.780,43
G. PPN 11% (F X 11%) 34.515,84
H. HARGA SATUAN PEKERJAAN (F+G) 348.296,27

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
25
JENIS PEKERJAAN : Penyiapan Badan Jalan
SATUAN : m²

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 7.000,00 7.000,00

JUMLAH HARGA I 7.000,00

B. BAHAN

JUMLAH HARGA II -

C. PERALATAN ls 1,0000 11.000,00 11.000,00

JUMLAH HARGA III 11.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 18.000,00
E. OVERHEAD DAN PROFIT 2.700,00
F. TOTAL DENGAN OVERHEAD (D+E) 20.700,00
G. PPN 11% (F X 11%) 2.277,00
H. HARGA SATUAN PEKERJAAN (F+G) 22.977,00

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
26
JENIS PEKERJAAN : Peninggian Duiker ukuran 80/100 cm
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 340.000,00 340.000,00

JUMLAH HARGA I 340.000,00

B. BAHAN
1 Readymix K.250 m3 1,0600 1.081.000,00 1.145.860,00
2 Bekisting m2 0,9550 258.000,00 246.390,00
3 Baja Tulangan U24 kg 108,7200 15.617,50 1.697.934,60
4 Olie / Gemuk Liter 0,4550 11.000,00 5.005,00
5 Curing m2 0,9700 41.000,00 39.770,00

JUMLAH HARGA II 3.134.959,60

C. PERALATAN ls 1,0000 29.992,90 29.992,90

JUMLAH HARGA III 29.992,90


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 3.504.952,50
E. OVERHEAD DAN PROFIT 525.742,87
F. TOTAL DENGAN OVERHEAD (D+E) 4.030.695,37
G. PPN 11% (F X 11%) 443.376,49
H. HARGA SATUAN PEKERJAAN (F+G) 4.474.071,86

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
27
JENIS PEKERJAAN : Peninggian Duiker ukuran 100/120 cm
SATUAN PEMBAYARAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 340.000,00 340.000,00

JUMLAH HARGA I 340.000,00

B. BAHAN
1 Readymix K.250 m3 1,0600 1.081.000,00 1.145.860,00
2 Bekisting m2 0,0947 258.000,00 24.419,70
3 Baja Tulangan U24 kg 160,2100 15.617,50 2.502.079,67
4 Olie / Gemuk Liter 0,4550 11.000,00 5.005,00
5 Curing m2 0,9700 41.000,00 39.770,00

JUMLAH HARGA II 3.717.134,37

C. PERALATAN ls 1,0000 29.992,90 29.992,90

JUMLAH HARGA III 29.992,90


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 4.087.127,27
E. OVERHEAD DAN PROFIT 613.069,09
F. TOTAL DENGAN OVERHEAD (D+E) 4.700.196,36
G. PPN 11% (F X 11%) 517.021,59
H. HARGA SATUAN PEKERJAAN (F+G) 5.217.217,95

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
28
JENIS PEKERJAAN : Timbunan Agregat Kelas A Padat
SATUAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 150.000,00 150.000,00

JUMLAH HARGA TENAGA 150.000,00

B. BAHAN
1 Agregat A M3 1,2200 215.000,00 262.300,00

JUMLAH HARGA BAHAN 262.300,00

C. PERALATAN ls 1,0000 60.000,00 60.000,00

JUMLAH HARGA PERALATAN 60.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 472.300,00
E. OVERHEAD DAN PROFIT 70.845,00
F. TOTAL DENGAN OVERHEAD (D+E) 543.145,00
G. PPN 11% (F X 11%) 59.745,95
H. HARGA SATUAN PEKERJAAN (F+G) 602.890,95

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
29
JENIS PEKERJAAN : Timbunan Agregat Kelas B Padat
SATUAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 150.000,00 150.000,00

JUMLAH HARGA I 150.000,00

B. BAHAN
1 Agregat B M3 1,2200 210.000,00 256.200,00

JUMLAH HARGA II 256.200,00

C. PERALATAN ls 1,0000 60.000,00 60.000,00

JUMLAH HARGA III 60.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 466.200,00
E. OVERHEAD DAN PROFIT 69.930,00
F. TOTAL DENGAN OVERHEAD (D+E) 536.130,00
G. PPN 11% (F X 11%) 58.974,30
H. HARGA SATUAN PEKERJAAN (F+G) 595.104,30

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
30
JENIS PEKERJAAN : Timbunan Limestone Padat
SATUAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 150.000,00 150.000,00

JUMLAH HARGA I 150.000,00

B. BAHAN
1 Limestone M3 1,2200 205.000,00 250.100,00

JUMLAH HARGA II 250.100,00

C. PERALATAN ls 1,0000 60.000,00 60.000,00

JUMLAH HARGA III 60.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 460.100,00
E. OVERHEAD DAN PROFIT 69.015,00
F. TOTAL DENGAN OVERHEAD (D+E) 529.115,00
G. PPN 11% (F X 11%) 58.202,65
H. HARGA SATUAN PEKERJAAN (F+G) 587.317,65

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
31
JENIS PEKERJAAN : Cerucuk Dolken
SATUAN : batang

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 5.000,00 5.000,00

JUMLAH HARGA I 5.000,00

B. BAHAN
1 Cerucuk kayu diameter 10 – 20 cm Btg 1,0000 33.800,00 33.800,00

JUMLAH HARGA II 33.800,00

C. PERALATAN ls 1,0000 2.331,50 2.331,50

JUMLAH HARGA III 2.331,50


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 41.131,50
E. OVERHEAD DAN PROFIT 6.169,72
F. TOTAL DENGAN OVERHEAD (D+E) 47.301,22
G. PPN 11% (F X 11%) 5.203,13
H. HARGA SATUAN PEKERJAAN (F+G) 52.504,35

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
32
JENIS PEKERJAAN : Lapis Pondasi Bawah Mortar Busa tebal 100 cm UCS 800 KPa
SATUAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 55.000,00 55.000,00

JUMLAH HARGA I 55.000,00

B. BAHAN
1 Pondasi Bawah Mortar Busa tebal 100 cm UCS 800 KPa m3 1,0600 1.600.000,00 1.696.000,00

JUMLAH HARGA II 1.696.000,00

C. PERALATAN ls 1,0000 60.000,00 60.000,00

JUMLAH HARGA III 60.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.811.000,00
E. OVERHEAD DAN PROFIT 271.650,00
F. TOTAL DENGAN OVERHEAD (D+E) 2.082.650,00
G. PPN 11% (F X 11%) 229.091,50
H. HARGA SATUAN PEKERJAAN (F+G) 2.311.741,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama

ANALISA HARGA SATUAN


33
JENIS PEKERJAAN : Lapis Pondasi Bawah Mortar Busa tebal 80 cm UCS 2000 KPa
SATUAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 55.000,00 55.000,00

JUMLAH HARGA I 55.000,00

B. BAHAN
1 Pondasi Bawah Mortar Busa tebal 80 cm UCS 2000 KPa m3 1,0400 1.600.000,00 1.664.000,00

JUMLAH HARGA II 1.664.000,00

C. PERALATAN ls 1,0000 60.000,00 60.000,00

JUMLAH HARGA III 60.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.779.000,00
E. OVERHEAD DAN PROFIT 266.850,00
F. TOTAL DENGAN OVERHEAD (D+E) 2.045.850,00
G. PPN 11% (F X 11%) 225.043,50
H. HARGA SATUAN PEKERJAAN (F+G) 2.270.893,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
34
JENIS PEKERJAAN : Lapis Pondasi Bawah Mortar Busa tebal 60 cm UCS 2000 KPa
SATUAN : M3

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 55.000,00 55.000,00

JUMLAH HARGA I 55.000,00

B. BAHAN
1 Pondasi Bawah Mortar Busa tebal 60 cm UCS 2000 KPa m3 1,0200 1.600.000,00 1.632.000,00

JUMLAH HARGA II 1.632.000,00

C. PERALATAN ls 1,0000 60.000,00 60.000,00

JUMLAH HARGA III 60.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.747.000,00
E. OVERHEAD DAN PROFIT 262.050,00
F. TOTAL DENGAN OVERHEAD (D+E) 2.009.050,00
G. PPN 11% (F X 11%) 220.995,50
H. HARGA SATUAN PEKERJAAN (F+G) 2.230.045,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama

ANALISA HARGA SATUAN


35
JENIS PEKERJAAN : Geotekstil Woven Terpasang
SATUAN : m²

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 5.000,00 5.000,00

JUMLAH HARGA I 5.000,00

B. BAHAN
1 Geotekstil Woven m² 1,0200 160.000,00 163.200,00

JUMLAH HARGA II 163.200,00

C. PERALATAN ls 1,0000 4.000,00 4.000,00

JUMLAH HARGA III 4.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 172.200,00
E. OVERHEAD DAN PROFIT 25.830,00
F. TOTAL DENGAN OVERHEAD (D+E) 198.030,00
G. PPN 11% (F X 11%) 21.783,30
H. HARGA SATUAN PEKERJAAN (F+G) 219.813,30

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
36
JENIS PEKERJAAN : Geotekstil Non Woven Terpasang
SATUAN : m²

Kuantitas / Harga Satuan Dasar Jumlah Harga


No. Uraian Satuan
Koefisien (Rp) (Rp.)

A. TENAGA ls 1,0000 5.000,00 5.000,00

JUMLAH HARGA I 5.000,00

B. BAHAN
1 Geotekstil NON Woven m² - 140.000,00 140.000,00

JUMLAH HARGA II 140.000,00

C. PERALATAN ls 1,0000 4.000,00 4.000,00

JUMLAH HARGA III 4.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 149.000,00
E. OVERHEAD DAN PROFIT 22.350,00
F. TOTAL DENGAN OVERHEAD (D+E) 171.350,00
G. PPN 11% (F X 11%) 18.848,50
H. HARGA SATUAN PEKERJAAN (F+G) 190.198,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
1
JENIS PEKERJAAN : Concrete Barrier Type Jersey Barrier ukuran 40 x 60 x 100 cm
SATUAN : unit

No. Uraian Satuan Kuantitas/ Harga Satuan Jumlah Harga


Koefisien Dasar (Rp.) (Rp.)

A. TENAGA KERJA ls 1,0000 15.000,00 15.000,00

JUMLAH HARGA I 15.000,00

B. BAHAN - BAHAN -

1 Concrete Barrier Type Jersey Barrier m' 1,00 770.000,00 770.000,00


ukuran 40 x 60 x 100 cm

JUMLAH HARGA II 770.000,00

C. PERALATAN ls 1,0000 300.000,00 300.000,00

JUMLAH HARGA III 300.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.085.000,00
E. OVERHEAD DAN PROFIT 108.500,00
F. TOTAL DENGAN OVERHEAD (D+E) 1.193.500,00
G. PPN 11% (F X 11%) 131.285,00
H. HARGA SATUAN PEKERJAAN (F+G) 1.324.785,00

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
2
JENIS PEKERJAAN : Concrete Barrier Type Jersey Barrier ukuran 50 x 80 x 100 cm
SATUAN : m1

No. Uraian Satuan Kuantitas/ Harga Satuan Jumlah Harga


Koefisien Dasar (Rp.) (Rp.)

A. TENAGA KERJA ls 1,0000 13.247,40 13.247,40

JUMLAH HARGA I 13.247,40

B. BAHAN - BAHAN

1 Concrete Barrier Type Jersey Barrier m' 1,00 1.200.000,00 1.200.000,00


ukuran 50 x 80 x 100 cm

JUMLAH HARGA II 1.200.000,00

C. PERALATAN ls 1,0000 63.041,03 63.041,03

JUMLAH HARGA III 63.041,03


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.276.288,43
E. OVERHEAD DAN PROFIT 191.443,26
F. TOTAL DENGAN OVERHEAD (D+E) 1.467.731,69
G. PPN 11% (F X 11%) 161.450,48
H. HARGA SATUAN PEKERJAAN (F+G) 1.629.182,17

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
3
JENIS PEKERJAAN : Saluran U-Ditch Ukuran 300 x 400 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 230.000,00 230.000,00

JUMLAH HARGA I 230.000,00

B. BAHAN
1 U-ditch 300 x 400 m' 1,0000 249.166,67 249.166,66
2 Lantai Kerja (BO) m3 0,0200 968.000,00 19.360,00
3 Pasir Urug m3 0,0200 310.000,00 6.200,00
4 Urugan m3 0,0560 11.000,00 616,00

JUMLAH HARGA II 275.342,66

C. PERALATAN ls 1,0000 65.000,00 65.000,00

JUMLAH HARGA III 65.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 570.342,66
E. OVERHEAD DAN PROFIT 85.551,39
F. TOTAL DENGAN OVERHEAD (D+E) 655.894,05
G. PPN 11% (F X 11%) 72.148,34
H. HARGA SATUAN PEKERJAAN (F+G) 728.042,39

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
4
JENIS PEKERJAAN : Saluran U-ditch Ukuran 300 x 300 mm terpasang
SATUAN : m1

No. Uraian Satuan Kuantitas/ Harga Satuan Jumlah Harga


Koefisien Dasar (Rp.) (Rp.)

A. TENAGA ls 1,0000 220.000,00 220.000,00

JUMLAH HARGA I 220.000,00

B. BAHAN
1 U-ditch 300 x 300 m' 1,0000 221.666,67 221.666,66
2 Lantai Kerja (BO) m3 0,0200 968.000,00 19.360,00
3 Pasir Urug m3 0,0200 310.000,00 6.200,00
4 Urugan m3 0,0520 11.000,00 572,00

JUMLAH HARGA II 247.798,66

C. PERALATAN ls 1,0000 50.000,00 50.000,00

JUMLAH HARGA III 50.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 517.798,66
E. OVERHEAD DAN PROFIT 77.669,79
F. TOTAL DENGAN OVERHEAD (D+E) 595.468,45
G. PPN 11% (F X 11%) 65.501,52
H. HARGA SATUAN PEKERJAAN (F+G) 660.969,97

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
5
JENIS PEKERJAAN : Saluran U-ditch Ukuran 400 x 300 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 250.000,00 250.000,00

JUMLAH HARGA I 250.000,00

B. BAHAN
1 U-ditch 400 x 300 m' 1,0000 249.166,67 249.166,66
2 Lantai Kerja (BO) m3 0,0025 968.000,00 2.420,00
3 Pasir Urug m3 0,0025 310.000,00 775,00
4 Urugan m3 0,0502 11.000,00 552,20

JUMLAH HARGA II 252.913,86

C. PERALATAN ls 1,0000 65.000,00 65.000,00

JUMLAH HARGA III 65.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 567.913,86
E. OVERHEAD DAN PROFIT 85.187,07
F. TOTAL DENGAN OVERHEAD (D+E) 653.100,93
G. PPN 11% (F X 11%) 71.841,10
H. HARGA SATUAN PEKERJAAN (F+G) 724.942,03

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
6
JENIS PEKERJAAN : Saluran U-ditch Ukuran 400 x 400 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 275.000,00 275.000,00

JUMLAH HARGA I 275.000,00

B. BAHAN
1 U-ditch 400 x 400 m' 1,0000 330.000,00 330.000,00
2 Lantai Kerja (BO) m3 0,0025 968.000,00 2.420,00
3 Pasir Urug m3 0,0025 310.000,00 775,00
4 Urugan m3 0,0402 11.000,00 442,20

JUMLAH HARGA II 333.637,20

C. PERALATAN ls 1,0000 87.600,00 87.599,99

JUMLAH HARGA III 87.599,99


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 696.237,19
E. OVERHEAD DAN PROFIT 104.435,57
F. TOTAL DENGAN OVERHEAD (D+E) 800.672,76
G. PPN 11% (F X 11%) 88.074,00
H. HARGA SATUAN PEKERJAAN (F+G) 888.746,76

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
7
JENIS PEKERJAAN : Saluran U-ditch Ukuran 400 x 600 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 220.000,00 220.000,00

JUMLAH HARGA I 220.000,00

B. BAHAN
1 U-ditch 400 x 600 m' 1,0000 436.666,67 436.666,66
2 Lantai Kerja (BO) m3 0,0025 968.000,00 2.420,00
3 Pasir Urug m3 0,0025 310.000,00 775,00
4 Urugan m3 0,0025 11.000,00 27,50

JUMLAH HARGA II 439.889,16

C. PERALATAN ls 1,0000 97.406,66 97.406,66

JUMLAH HARGA III 97.406,66


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 757.295,82
E. OVERHEAD DAN PROFIT 113.594,37
F. TOTAL DENGAN OVERHEAD (D+E) 870.890,19
G. PPN 11% (F X 11%) 95.797,92
H. HARGA SATUAN PEKERJAAN (F+G) 966.688,11

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
8
JENIS PEKERJAAN : Saluran U-ditch Ukuran 500 x 500 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 245.000,00 245.000,00

JUMLAH HARGA I 245.000,00

B. BAHAN
1 Saluran U ditch Ukuran 500 x 500 mm terpasang m' 1,0000 495.833,33 495.833,33
2 Lantai Kerja (BO) m3 0,0300 968.000,00 29.040,00
3 Pasir Urug m3 0,0300 310.000,00 9.300,00
4 Urugan m3 0,0300 11.000,00 330,00

JUMLAH HARGA II 534.503,33

C. PERALATAN ls 1,0000 98.008,34 98.008,33

JUMLAH HARGA III 98.008,33


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 877.511,66
E. OVERHEAD DAN PROFIT 131.626,74
F. TOTAL DENGAN OVERHEAD (D+E) 1.009.138,40
G. PPN 11% (F X 11%) 111.005,22
H. HARGA SATUAN PEKERJAAN (F+G) 1.120.143,62

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
9
JENIS PEKERJAAN : Saluran U-ditch Ukuran 600 x 600 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 350.000,00 350.000,00

JUMLAH HARGA I 350.000,00

B. BAHAN
1 U-ditch 600 x 600 m' 1,0000 523.333,33 523.333,33
2 Lantai Kerja (BO) m3 0,0350 968.000,00 33.880,00
3 Pasir Urug m3 0,0350 310.000,00 10.850,00
4 Urugan m3 0,0350 11.000,00 385,00

JUMLAH HARGA II 568.448,33

C. PERALATAN ls 1,0000 145.000,00 145.000,00

JUMLAH HARGA III 145.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.063.448,33
E. OVERHEAD DAN PROFIT 159.517,24
F. TOTAL DENGAN OVERHEAD (D+E) 1.222.965,57
G. PPN 11% (F X 11%) 134.526,21
H. HARGA SATUAN PEKERJAAN (F+G) 1.357.491,78

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
10
JENIS PEKERJAAN : Saluran U-ditch Ukuran 600 x 800 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 360.000,00 360.000,00

JUMLAH HARGA I 360.000,00

B. BAHAN
1 Saluran U ditch Ukuran 600 x 800 mm terpasang m' 1,0000 697.500,00 697.500,00
2 Lantai Kerja (BO) m3 0,0350 968.000,00 33.880,00
3 Pasir Urug m3 0,0350 310.000,00 10.850,00
4 Urugan m3 0,0350 11.000,00 385,00

JUMLAH HARGA II 742.615,00

C. PERALATAN ls 1,0000 145.000,00 145.000,00

JUMLAH HARGA III 145.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.247.615,00
E. OVERHEAD DAN PROFIT 187.142,25
F. TOTAL DENGAN OVERHEAD (D+E) 1.434.757,25
G. PPN 11% (F X 11%) 157.823,29
H. HARGA SATUAN PEKERJAAN (F+G) 1.592.580,54

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
11
JENIS PEKERJAAN : Saluran U-ditch Ukuran 800 x 800 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 450.000,00 450.000,00

JUMLAH HARGA I 450.000,00

B. BAHAN
1 U-ditch 800 x 800 m' 1,0000 832.500,00 832.500,00
2 Lantai Kerja (BO) m3 0,0450 968.000,00 43.560,00
3 Pasir Urug m3 0,0450 310.000,00 13.950,00
4 Urugan m3 0,0450 11.000,00 495,00

JUMLAH HARGA II 890.505,00

C. PERALATAN ls 1,0000 235.000,00 235.000,00

JUMLAH HARGA III 235.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.575.505,00
E. OVERHEAD DAN PROFIT 236.325,75
F. TOTAL DENGAN OVERHEAD (D+E) 1.811.830,75
G. PPN 11% (F X 11%) 199.301,38
H. HARGA SATUAN PEKERJAAN (F+G) 2.011.132,13

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
12
JENIS PEKERJAAN : Saluran U-ditch Ukuran 800 x 1000 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 470.000,00 470.000,00

JUMLAH HARGA I 470.000,00

B. BAHAN
1 Saluran U ditch Ukuran 800 x 1000 mm terpasang m' 1,0000 965.000,00 965.000,00
2 Lantai Kerja (BO) m3 0,0450 968.000,00 43.560,00
3 Pasir Urug m3 0,0450 310.000,00 13.950,00
4 Urugan m3 0,0450 11.000,00 495,00

JUMLAH HARGA II 1.023.005,00

C. PERALATAN ls 1,0000 255.000,00 255.000,00

JUMLAH HARGA III 255.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.748.005,00
E. OVERHEAD DAN PROFIT 262.200,75
F. TOTAL DENGAN OVERHEAD (D+E) 2.010.205,75
G. PPN 11% (F X 11%) 221.122,63
H. HARGA SATUAN PEKERJAAN (F+G) 2.231.328,38

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
13
JENIS PEKERJAAN : Saluran U-ditch Ukuran 1000 x 1000 mm terpasang
SATUAN : M'

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 480.000,00 480.000,00

JUMLAH HARGA I 480.000,00

B. BAHAN
1 U-ditch 1000 x 1000 m' 1,0000 1.083.333,33 1.083.333,33
2 Lantai Kerja (BO) m3 0,0550 968.000,00 53.240,00
3 Pasir Urug m3 0,0550 310.000,00 17.050,00
4 Urugan m3 0,0550 11.000,00 605,00

JUMLAH HARGA II 1.154.228,33

C. PERALATAN ls 1,0000 255.000,00 255.000,00

JUMLAH HARGA III 255.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.889.228,33
E. OVERHEAD DAN PROFIT 283.384,24
F. TOTAL DENGAN OVERHEAD (D+E) 2.172.612,57
G. PPN 11% (F X 11%) 238.987,38
H. HARGA SATUAN PEKERJAAN (F+G) 2.411.599,95

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
14
JENIS PEKERJAAN : Saluran U-ditch Ukuran 1000 x 1200 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 580.000,00 580.000,00

JUMLAH HARGA I 580.000,00

B. BAHAN
1 Saluran U ditch Ukuran 1000 x 1200 mm terpasangm' 1,0000 1.650.000,00 1.650.000,00
2 Lantai Kerja (BO) m3 0,0550 968.000,00 53.240,00
3 Pasir Urug m3 0,0550 310.000,00 17.050,00
4 Urugan m3 0,1755 11.000,00 1.930,50

JUMLAH HARGA II 1.722.220,50

C. PERALATAN ls 1,0000 255.000,00 255.000,00

JUMLAH HARGA III 255.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.557.220,50
E. OVERHEAD DAN PROFIT 383.583,07
F. TOTAL DENGAN OVERHEAD (D+E) 2.940.803,57
G. PPN 11% (F X 11%) 323.488,39
H. HARGA SATUAN PEKERJAAN (F+G) 3.264.291,96

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
15
JENIS PEKERJAAN : Saluran U-ditch Ukuran 1200 x 1200 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 600.000,00 600.000,00

JUMLAH HARGA I 600.000,00

B. BAHAN
1 U-ditch 1200 x 1200 m' 1,0000 2.100.000,00 2.100.000,00
2 Lantai Kerja (BO) m3 0,0650 968.000,00 62.920,00
3 Pasir Urug m3 0,0650 310.000,00 20.150,00
4 Urugan m3 0,2695 11.000,00 2.964,50

JUMLAH HARGA II 2.186.034,50

C. PERALATAN ls 1,0000 354.508,34 354.508,33

JUMLAH HARGA III 354.508,33


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 3.140.542,83
E. OVERHEAD DAN PROFIT 471.081,42
F. TOTAL DENGAN OVERHEAD (D+E) 3.611.624,25
G. PPN 11% (F X 11%) 397.278,66
H. HARGA SATUAN PEKERJAAN (F+G) 4.008.902,91

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
16
JENIS PEKERJAAN : Saluran U-ditch Ukuran 1200 x 1400 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 700.000,00 700.000,00

JUMLAH HARGA I 700.000,00

B. BAHAN
1 U-ditch 1200 x 1400 m' 1,0000 2.623.266,67 2.623.266,66
2 Lantai Kerja (BO) m3 0,0650 968.000,00 62.920,00
3 Pasir Urug m3 0,0650 310.000,00 20.150,00
4 Urugan m3 0,2695 11.000,00 2.964,50

JUMLAH HARGA II 2.709.301,16

C. PERALATAN ls 1,0000 354.508,34 354.508,33

JUMLAH HARGA III 354.508,33


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 3.763.809,49
E. OVERHEAD DAN PROFIT 564.571,42
F. TOTAL DENGAN OVERHEAD (D+E) 4.328.380,91
G. PPN 11% (F X 11%) 476.121,90
H. HARGA SATUAN PEKERJAAN (F+G) 4.804.502,81

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
17
JENIS PEKERJAAN : Saluran U-ditch Ukuran 1400 x 1400 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 900.000,00 900.000,00

JUMLAH HARGA I 900.000,00

B. BAHAN
1 U-ditch 1400 x 1400 m' 1,0000 3.333.333,33 3.333.333,33
2 Lantai Kerja (BO) m3 0,0750 968.000,00 72.600,00
3 Pasir Urug m3 0,0750 310.000,00 23.250,00
4 Urugan m3 0,2725 11.000,00 2.997,50

JUMLAH HARGA II 3.432.180,83

C. PERALATAN ls 1,0000 900.000,00 900.000,00

JUMLAH HARGA III 900.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 5.232.180,83
E. OVERHEAD DAN PROFIT 784.827,12
F. TOTAL DENGAN OVERHEAD (D+E) 6.017.007,95
G. PPN 11% (F X 11%) 661.870,87
H. HARGA SATUAN PEKERJAAN (F+G) 6.678.878,82

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
18
JENIS PEKERJAAN : Saluran U-ditch Ukuran 1500 x 1500 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 1.000.000,00 1.000.000,00

JUMLAH HARGA I 1.000.000,00

B. BAHAN
1 U-ditch 1500 x 1500 m' 1,0000 3.750.000,00 3.750.000,00
2 Lantai Kerja (BO) m3 0,0800 968.000,00 77.440,00
3 Pasir Urug m3 0,0800 310.000,00 24.800,00
4 Urugan m3 0,0800 11.000,00 880,00

JUMLAH HARGA II 3.853.120,00

C. PERALATAN ls 1,0000 1.000.000,00 1.000.000,00

JUMLAH HARGA III 1.000.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 5.853.120,00
E. OVERHEAD DAN PROFIT 877.968,00
F. TOTAL DENGAN OVERHEAD (D+E) 6.731.088,00
G. PPN 11% (F X 11%) 740.419,68
H. HARGA SATUAN PEKERJAAN (F+G) 7.471.507,68

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
19
JENIS PEKERJAAN : Saluran U-ditch Ukuran 2000 x 2000 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 1.300.000,00 1.300.000,00

JUMLAH HARGA I 1.300.000,00

B. BAHAN
1 U-ditch 2000 x 2000 m' 1,0000 5.666.666,67 5.666.666,66
2 Lantai Kerja (BO) m3 0,1050 968.000,00 101.640,00
3 Pasir Urug m3 0,1050 310.000,00 32.550,00
4 Urugan m3 0,1050 11.000,00 1.155,00

JUMLAH HARGA II 5.802.011,66

C. PERALATAN ls 1,0000 1.300.000,00 1.300.000,00

JUMLAH HARGA III 1.300.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 8.402.011,66
E. OVERHEAD DAN PROFIT 1.260.301,74
F. TOTAL DENGAN OVERHEAD (D+E) 9.662.313,40
G. PPN 11% (F X 11%) 1.062.854,47
H. HARGA SATUAN PEKERJAAN (F+G) 10.725.167,87

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
20
JENIS PEKERJAAN : Saluran U-ditch Ukuran 2500 x 2500 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 1.550.000,00 1.550.000,00

JUMLAH HARGA I 1.550.000,00

B. BAHAN
1 U-ditch 2500 x 2500 m' 1,0000 8.250.000,00 8.250.000,00
2 Lantai Kerja (BO) m3 0,1300 968.000,00 125.840,00
3 Pasir Urug m3 0,1300 310.000,00 40.300,00
4 Urugan m3 1,1130 11.000,00 12.243,00

JUMLAH HARGA II 8.428.383,00

C. PERALATAN ls 1,0000 1.500.000,00 1.500.000,00

JUMLAH HARGA III 1.500.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 11.478.383,00
E. OVERHEAD DAN PROFIT 1.721.757,45
F. TOTAL DENGAN OVERHEAD (D+E) 13.200.140,45
G. PPN 11% (F X 11%) 1.452.015,44
H. HARGA SATUAN PEKERJAAN (F+G) 14.652.155,89

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
21
JENIS PEKERJAAN : Saluran U-ditch Ukuran 3000 x 3000 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 2.000.000,00 2.000.000,00

JUMLAH HARGA I 2.000.000,00

B. BAHAN
1 U-ditch 3000 x 3000 m' 1,0000 15.750.000,00 15.750.000,00
2 Lantai Kerja (BO) m3 0,1550 968.000,00 150.040,00
3 Pasir Urug m3 0,1550 310.000,00 48.050,00
4 Urugan m3 1,4155 11.000,00 15.570,50

JUMLAH HARGA II 15.963.660,50

C. PERALATAN ls 1,0000 1.800.000,00 1.800.000,00

JUMLAH HARGA III 1.800.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 19.763.660,50
E. OVERHEAD DAN PROFIT 2.964.549,07
F. TOTAL DENGAN OVERHEAD (D+E) 22.728.209,57
G. PPN 11% (F X 11%) 2.500.103,05
H. HARGA SATUAN PEKERJAAN (F+G) 25.228.312,62

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN

22
JENIS PEKERJAAN : Tutup saluran U-ditch HD Ukuran 300 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 29.304,98 29.304,98

JUMLAH HARGA I 29.304,98

B. BAHAN m' 1,0000 300.000,00 300.000,00


1 Ukuran 300 mm
2 Mutu Beton fc' = 30 Mpa (K350)
3 Pembesian

JUMLAH HARGA II 300.000,00

C. PERALATAN Ls 1,0000 13.213,33 13.213,33

JUMLAH HARGA III 13.213,33


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 342.518,31
E. OVERHEAD DAN PROFIT 51.377,74
F. TOTAL DENGAN OVERHEAD (D+E) 393.896,05
G. PPN 11% (F X 11%) 43.328,56
H. HARGA SATUAN PEKERJAAN (F+G) 437.224,61

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
23
JENIS PEKERJAAN : Tutup saluran U-ditch HD Ukuran 400 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 30.225,49 30.225,49

JUMLAH HARGA I 30.225,49

B. BAHAN m' 1,0000 384.000,00 384.000,00


1 Ukuran 400 mm
2 Mutu Beton fc' = 30 Mpa (K350)
3 Pembesian

JUMLAH HARGA II 384.000,00

C. PERALATAN Ls 1,0000 21.500,00 21.500,00

JUMLAH HARGA III 21.500,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 435.725,49
E. OVERHEAD DAN PROFIT 65.358,82
F. TOTAL DENGAN OVERHEAD (D+E) 501.084,31
G. PPN 11% (F X 11%) 55.119,27
H. HARGA SATUAN PEKERJAAN (F+G) 556.203,58

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
24
JENIS PEKERJAAN : Tutup saluran U-ditch HD Ukuran 500 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 39.059,29 39.059,29

JUMLAH HARGA I 39.059,29

B. BAHAN m' 1,0000 405.000,00 405.000,00


1 Ukuran 500 mm
2 Mutu Beton fc' = 30 Mpa (K350)
3 Pembesian

JUMLAH HARGA II 405.000,00

C. PERALATAN ls 1,0000 59.700,00 59.700,00

JUMLAH HARGA III 59.700,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 503.759,29
E. OVERHEAD DAN PROFIT 75.563,89
F. TOTAL DENGAN OVERHEAD (D+E) 579.323,18
G. PPN 11% (F X 11%) 63.725,54
H. HARGA SATUAN PEKERJAAN (F+G) 643.048,72

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
25
JENIS PEKERJAAN : Tutup saluran U-ditch HD Ukuran 600 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 39.059,29 39.059,29

JUMLAH HARGA I 39.059,29

B. BAHAN m' 1,0000 566.666,67 566.666,66


1 Ukuran 600 mm
2 Mutu Beton fc' = 30 Mpa (K350)
3 Pembesian

JUMLAH HARGA II 566.666,66

C. PERALATAN ls 1,0000 59.700,00 59.700,00

JUMLAH HARGA III 59.700,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 665.425,95
E. OVERHEAD DAN PROFIT 99.813,89
F. TOTAL DENGAN OVERHEAD (D+E) 765.239,84
G. PPN 11% (F X 11%) 84.176,38
H. HARGA SATUAN PEKERJAAN (F+G) 849.416,22

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
26
JENIS PEKERJAAN : Tutup saluran U-ditch HD Ukuran 800 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 88.601,12 88.601,12

JUMLAH HARGA I 88.601,12

B. BAHAN m' 1,0000 800.000,00 800.000,00


1 Ukuran 800 mm
2 Mutu Beton fc' = 30 Mpa (K350)
3 Pembesian

JUMLAH HARGA II 800.000,00

C. PERALATAN ls 1,0000 55.500,00 55.500,00

JUMLAH HARGA III 55.500,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 944.101,12
E. OVERHEAD DAN PROFIT 141.615,16
F. TOTAL DENGAN OVERHEAD (D+E) 1.085.716,28
G. PPN 11% (F X 11%) 119.428,79
H. HARGA SATUAN PEKERJAAN (F+G) 1.205.145,07

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
27
JENIS PEKERJAAN : Tutup saluran U-ditch HD Ukuran 1000 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 108.392,19 108.392,19

JUMLAH HARGA I 108.392,19

B. BAHAN m' 1,0000 1.183.333,33 1.183.333,33


1 Ukuran 1000 mm
2 Mutu Beton fc' = 30 Mpa (K350)
3 Pembesian

JUMLAH HARGA II 1.183.333,33

C. PERALATAN ls 1,0000 61.700,00 61.700,00

JUMLAH HARGA III 61.700,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.353.425,52
E. OVERHEAD DAN PROFIT 203.013,82
F. TOTAL DENGAN OVERHEAD (D+E) 1.556.439,34
G. PPN 11% (F X 11%) 171.208,32
H. HARGA SATUAN PEKERJAAN (F+G) 1.727.647,66

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
28
JENIS PEKERJAAN : Tutup saluran U-ditch HD Ukuran 1200 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 129.416,74 129.416,74

JUMLAH HARGA I 129.416,74

B. BAHAN m' 1,0000 1.375.000,00 1.375.000,00


1 Ukuran 1200 mm
2 Mutu Beton fc' = 30 Mpa (K350)
3 Pembesian

JUMLAH HARGA II 1.375.000,00

C. PERALATAN ls 1,0000 73.788,00 73.788,00

JUMLAH HARGA III 73.788,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.578.204,74
E. OVERHEAD DAN PROFIT 236.730,71
F. TOTAL DENGAN OVERHEAD (D+E) 1.814.935,45
G. PPN 11% (F X 11%) 199.642,89
H. HARGA SATUAN PEKERJAAN (F+G) 2.014.578,34

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
29
JENIS PEKERJAAN : Tutup saluran U-ditch HD Ukuran 1400 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 151.674,78 151.674,78

JUMLAH HARGA I 151.674,78

B. BAHAN m' 1,0000 1.900.000,00 1.900.000,00


1 Ukuran 1400 mm
2 Mutu Beton fc' = 30 Mpa (K350)
3 Pembesian

JUMLAH HARGA II 1.900.000,00

C. PERALATAN ls 1,0000 97.226,67 97.226,67

JUMLAH HARGA III 97.226,67


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.148.901,45
E. OVERHEAD DAN PROFIT 322.335,21
F. TOTAL DENGAN OVERHEAD (D+E) 2.471.236,66
G. PPN 11% (F X 11%) 271.836,03
H. HARGA SATUAN PEKERJAAN (F+G) 2.743.072,69

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
30
JENIS PEKERJAAN : Tutup saluran U-ditch HD Ukuran 1500 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 201.674,78 201.674,78

JUMLAH HARGA I 201.674,78

B. BAHAN m' 1,0000 2.066.666,67 2.066.666,66


1 Ukuran 1500 mm
2 Mutu Beton fc' = 30 Mpa (K350)
3 Pembesian

JUMLAH HARGA II 2.066.666,66

C. PERALATAN ls 1,0000 97.733,67 97.733,67

JUMLAH HARGA III 97.733,67


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.366.075,11
E. OVERHEAD DAN PROFIT 354.911,26
F. TOTAL DENGAN OVERHEAD (D+E) 2.720.986,37
G. PPN 11% (F X 11%) 299.308,50
H. HARGA SATUAN PEKERJAAN (F+G) 3.020.294,87

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
31
JENIS PEKERJAAN : Tutup saluran U-ditch HD Ukuran 2000 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 251.674,78 251.674,78

JUMLAH HARGA I 251.674,78

B. BAHAN m' 1,0000 3.400.000,00 3.400.000,00


1 Ukuran 2000 mm
2 Mutu Beton fc' = 30 Mpa (K350)
3 Pembesian

JUMLAH HARGA II 3.400.000,00

C. PERALATAN ls 1,0000 124.650,33 124.650,33

JUMLAH HARGA III 124.650,33


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 3.776.325,11
E. OVERHEAD DAN PROFIT 566.448,76
F. TOTAL DENGAN OVERHEAD (D+E) 4.342.773,87
G. PPN 11% (F X 11%) 477.705,12
H. HARGA SATUAN PEKERJAAN (F+G) 4.820.478,99

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
32
JENIS PEKERJAAN : Tutup saluran U-ditch HD Ukuran 2500 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 301.674,78 301.674,78

JUMLAH HARGA I 301.674,78

B. BAHAN m' 1,0000 4.583.333,33 4.583.333,33


1 Ukuran 2500 mm
2 Mutu Beton fc' = 30 Mpa (K350)
3 Pembesian

JUMLAH HARGA II 4.583.333,33

C. PERALATAN ls 1,0000 139.566,67 139.566,67

JUMLAH HARGA III 139.566,67


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 5.024.574,78
E. OVERHEAD DAN PROFIT 753.686,21
F. TOTAL DENGAN OVERHEAD (D+E) 5.778.260,99
G. PPN 11% (F X 11%) 635.608,70
H. HARGA SATUAN PEKERJAAN (F+G) 6.413.869,69

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
33
JENIS PEKERJAAN : Tutup saluran U-ditch HD Ukuran 3000 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 351.674,78 351.674,78

JUMLAH HARGA I 351.674,78

B. BAHAN m' 1,0000 6.333.333,33 6.333.333,33


1 Ukuran 3000 mm
2 Mutu Beton fc' = 30 Mpa (K350)
3 Pembesian

JUMLAH HARGA II 6.333.333,33

C. PERALATAN ls 1,0000 179.535,67 179.535,67

JUMLAH HARGA III 179.535,67


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 6.864.543,78
E. OVERHEAD DAN PROFIT 1.029.681,56
F. TOTAL DENGAN OVERHEAD (D+E) 7.894.225,34
G. PPN 11% (F X 11%) 868.364,78
H. HARGA SATUAN PEKERJAAN (F+G) 8.762.590,12

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
34
JENIS PEKERJAAN : Saluran Box Culvert Ukuran 300 x 300 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 168.539,35 168.539,35

JUMLAH HARGA I 168.539,35

B. BAHAN
1 Saluran Box Culvert Ukuran 300 x 300 mm terpasang m' 1,00 741.666,67 741.666,66
2 Lantai Kerja (BO) m3 0,0150 361.650,53 5.424,75
3 Pasir Urug m3 0,0150 10.379,89 155,69

JUMLAH HARGA II 747.247,10

C. PERALATAN ls 1,0000 39.333,33 39.333,33

JUMLAH HARGA III 39.333,33


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 955.119,78
E. OVERHEAD DAN PROFIT 143.267,96
F. TOTAL DENGAN OVERHEAD (D+E) 1.098.387,74
G. PPN 11% (F X 11%) 120.822,65
H. HARGA SATUAN PEKERJAAN (F+G) 1.219.210,39

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
35
JENIS PEKERJAAN : Saluran Box Culvert Ukuran 600 x 600 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 200.000,00 200.000,00

JUMLAH HARGA I 200.000,00

B. BAHAN
1 Saluran Box Culvert Ukuran 600 x 600 mm m' 1,00 1.750.000,00 1.750.000,00
2 Lantai Kerja (BO) m3 0,0350 710.000,00 24.850,00
3 Pasir Urug m3 0,0350 300.000,00 10.500,00

JUMLAH HARGA II 1.785.350,00

C. PERALATAN ls 1,0000 450.000,00 450.000,00

JUMLAH HARGA III 450.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.435.350,00
E. OVERHEAD DAN PROFIT 365.302,50
F. TOTAL DENGAN OVERHEAD (D+E) 2.800.652,50
G. PPN 11% (F X 11%) 308.071,77
H. HARGA SATUAN PEKERJAAN (F+G) 3.108.724,27

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
36
JENIS PEKERJAAN : Saluran Box Culvert Ukuran 800 x 800 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 320.000,00 320.000,00

JUMLAH HARGA I 320.000,00

B. BAHAN
1 Saluran Box Culvert Ukuran 800 x 800 mm m' 1,00 2.416.666,67 2.416.666,66
2 Lantai Kerja (BO) m3 0,0450 710.000,00 31.950,00
3 Pasir Urug m3 0,0450 300.000,00 13.500,00

JUMLAH HARGA II 2.462.116,66

C. PERALATAN ls 1,0000 470.000,00 470.000,00

JUMLAH HARGA III 470.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 3.252.116,66
E. OVERHEAD DAN PROFIT 487.817,49
F. TOTAL DENGAN OVERHEAD (D+E) 3.739.934,15
G. PPN 11% (F X 11%) 411.392,75
H. HARGA SATUAN PEKERJAAN (F+G) 4.151.326,90

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
37
JENIS PEKERJAAN : Saluran Box Culvert Ukuran 1000 x 1000 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 820.000,00 820.000,00

JUMLAH HARGA I 820.000,00

B. BAHAN
1 Saluran Box Culvert Ukuran 1000 x 1000 mm m' 1,00 2.916.666,67 2.916.666,66
2 Lantai Kerja (BO) m3 0,0550 710.000,00 39.050,00
3 Pasir Urug m3 0,0550 300.000,00 16.500,00

JUMLAH HARGA II 2.972.216,66

C. PERALATAN ls 1,0000 970.000,00 970.000,00

JUMLAH HARGA III 970.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 4.762.216,66
E. OVERHEAD DAN PROFIT 714.332,49
F. TOTAL DENGAN OVERHEAD (D+E) 5.476.549,15
G. PPN 11% (F X 11%) 602.420,40
H. HARGA SATUAN PEKERJAAN (F+G) 6.078.969,55

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
38
JENIS PEKERJAAN : Saluran Box Culvert Ukuran 1200 x 1200 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 1.320.000,00 1.320.000,00

JUMLAH HARGA I 1.320.000,00

B. BAHAN
1 Saluran Box Culvert Ukuran 1200 x 1200 mm m' 1,00 5.416.666,67 5.416.666,66
2 Lantai Kerja (BO) m3 0,0650 710.000,00 46.150,00
3 Pasir Urug m3 0,0650 300.000,00 19.500,00

JUMLAH HARGA II 5.482.316,66

C. PERALATAN ls 1,0000 1.170.000,00 1.170.000,00

JUMLAH HARGA III 1.170.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 7.972.316,66
E. OVERHEAD DAN PROFIT 1.195.847,49
F. TOTAL DENGAN OVERHEAD (D+E) 9.168.164,15
G. PPN 11% (F X 11%) 1.008.498,05
H. HARGA SATUAN PEKERJAAN (F+G) 10.176.662,20

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
39
JENIS PEKERJAAN : Saluran Box Culvert Ukuran 1500 x 1500 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 1.520.000,00 1.520.000,00

JUMLAH HARGA I 1.520.000,00

B. BAHAN
1 Saluran Box Culvert Ukuran 1500 x 1500 mm m' 1,00 8.333.333,33 8.333.333,33
2 Lantai Kerja (BO) m3 0,0800 710.000,00 56.800,00
3 Pasir Urug m3 0,0800 300.000,00 24.000,00

JUMLAH HARGA II 8.414.133,33

C. PERALATAN ls 1,0000 1.370.000,00 1.370.000,00

JUMLAH HARGA III 1.370.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 11.304.133,33
E. OVERHEAD DAN PROFIT 1.695.619,99
F. TOTAL DENGAN OVERHEAD (D+E) 12.999.753,32
G. PPN 11% (F X 11%) 1.429.972,86
H. HARGA SATUAN PEKERJAAN (F+G) 14.429.726,18

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
40
JENIS PEKERJAAN : Saluran Box Culvert Ukuran 2000 x 2000 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 2.020.000,00 2.020.000,00

JUMLAH HARGA I 2.020.000,00

B. BAHAN
1 Saluran Box Culvert Ukuran 2000 x 2000 mm m' 1,00 10.000.000,00 10.000.000,00
2 Lantai Kerja (BO) m3 0,1050 710.000,00 74.550,00
3 Pasir Urug m3 0,1050 300.000,00 31.500,00

JUMLAH HARGA II 10.106.050,00

C. PERALATAN ls 1,00 1.870.000,00 1.870.000,00

JUMLAH HARGA III 1.870.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 13.996.050,00
E. OVERHEAD DAN PROFIT 2.099.407,50
F. TOTAL DENGAN OVERHEAD (D+E) 16.095.457,50
G. PPN 11% (F X 11%) 1.770.500,32
H. HARGA SATUAN PEKERJAAN (F+G) 17.865.957,82

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
41
JENIS PEKERJAAN : Saluran Box Culvert Ukuran 2500 x 2500 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 2.520.000,00 2.520.000,00

JUMLAH HARGA I 2.520.000,00

B. BAHAN
1 Saluran Box Culvert Ukuran 2500 x 2500 mm m' 1,00 17.500.000,00 17.500.000,00
2 Lantai Kerja (BO) m3 0,1300 710.000,00 92.300,00
3 Pasir Urug m3 0,1300 300.000,00 39.000,00

JUMLAH HARGA II 17.631.300,00

C. PERALATAN ls 1,0000 2.370.000,00 2.370.000,00

JUMLAH HARGA III 2.370.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 22.521.300,00
E. OVERHEAD DAN PROFIT 3.378.195,00
F. TOTAL DENGAN OVERHEAD (D+E) 25.899.495,00
G. PPN 11% (F X 11%) 2.848.944,45
H. HARGA SATUAN PEKERJAAN (F+G) 28.748.439,45

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
42
JENIS PEKERJAAN : Saluran Box Culvert Ukuran 3000 x 3000 mm terpasang
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA ls 1,0000 3.020.000,00 3.020.000,00

JUMLAH HARGA I 3.020.000,00

B. BAHAN
1 Saluran Box Culvert Ukuran 3000 x 3000 mm m' 1,00 20.000.000,00 20.000.000,00
2 Lantai Kerja (BO) m3 0,1550 710.000,00 110.050,00
3 Pasir Urug m3 0,1550 300.000,00 46.500,00

JUMLAH HARGA II 20.156.550,00

C. PERALATAN ls 1,0000 2.870.000,00 2.870.000,00

JUMLAH HARGA III 2.870.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 26.046.550,00
E. OVERHEAD DAN PROFIT 3.906.982,50
F. TOTAL DENGAN OVERHEAD (D+E) 29.953.532,50
G. PPN 11% (F X 11%) 3.294.888,57
H. HARGA SATUAN PEKERJAAN (F+G) 33.248.421,07

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN

JENIS PEKERJAAN : Pekerjaan Manhole Utilitas 2000 x 2000 x 3000


SATUAN : Unit

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 3.650.000,00 3.650.000,00

JUMLAH HARGA I 3.650.000,00

B. BAHAN
1 Manhole Utilitas 2000 x 2000 x 3000 (Mutu Beton K-350 dan Unit 1,0000 14.500.000,00 14.500.000,00
pembesian)

2 Lapisan Sirtu m3 0,7535 275.000,00 207.212,50


3 Lean Concrete m3 0,2152 750.000,00 161.400,00
4 Timbunan Pasir Makadam Padat m3 12,6000 310.000,00 3.906.000,00
5 Anyaman bambu/bilik m2 4,0000 75.000,00 300.000,00

JUMLAH HARGA II 19.074.612,50

C. PERALATAN Ls 1,0000 4.550.000,00 4.550.000,00

JUMLAH HARGA III 4.550.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 27.274.612,50
E. OVERHEAD DAN PROFIT 4.091.191,87
F. TOTAL DENGAN OVERHEAD (D+E) 31.365.804,37
G. PPN 11% (F X 11%) 3.450.238,48
H. HARGA SATUAN PEKERJAAN (F+G) 34.816.042,85

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN

JENIS PEKERJAAN : Pekerjaan Manhole Utilitas 2000 x 2000 x 3000 (simpang)


SATUAN : Unit

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 3.591.020,00 3.591.020,00

JUMLAH HARGA I 3.591.020,00

B. BAHAN
1 Manhole Utilitas 2000 x 2000 x 3000 Simpang (Mutu Beton K- Unit 1,0000 14.073.313,80 14.073.313,80
350 dan pembesian)
2 Lapisan Sirtu m3 0,7535 275.000,00 207.212,50
3 Lean Concrete m3 0,2152 750.000,00 161.400,00
4 Timbunan Pasir Makadam Padat m3 12,6000 310.000,00 3.906.000,00
5 Anyaman bambu/bilik m2 4,0000 75.000,00 300.000,00

JUMLAH HARGA II 18.647.926,30

C. PERALATAN Ls 1,0000 4.555.000,00 4.555.000,00

JUMLAH HARGA III 4.555.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 26.793.946,30
E. OVERHEAD DAN PROFIT 4.019.091,94
F. TOTAL DENGAN OVERHEAD (D+E) 30.813.038,24
G. PPN 11% (F X 11%) 3.389.434,20
H. HARGA SATUAN PEKERJAAN (F+G) 34.202.472,44

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN

JENIS PEKERJAAN : Pekerjaan Manhole Utilitas 1000 x 1200 x 2300


SATUAN : Unit

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 5.055.000,00 5.055.000,00

JUMLAH HARGA I 5.055.000,00

B. BAHAN
Manhole Utilitas 1000 x 1200 x 2300 (Mutu Beton K-350 dan Unit 1,0000 8.804.145,70 8.804.145,70
1 pembesian)

2 Lapisan Sirtu m3 0,2808 275.000,00 77.220,00


3 Lean Concrete m3 0,0802 750.000,00 60.150,00
4 Timbunan Pasir Makadam Padat m3 2,9400 310.000,00 911.400,00
5 Anyaman bambu/bilik m2 1,2000 75.000,00 90.000,00

JUMLAH HARGA II 9.942.915,70

C. PERALATAN Ls 1,0000 3.065.000,00 3.065.000,00

JUMLAH HARGA III 3.065.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 18.062.915,70
E. OVERHEAD DAN PROFIT 2.709.437,35
F. TOTAL DENGAN OVERHEAD (D+E) 20.772.353,05
G. PPN 11% (F X 11%) 2.284.958,83
H. HARGA SATUAN PEKERJAAN (F+G) 23.057.311,88

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN

JENIS PEKERJAAN : Pekerjaan Manhole Utilitas 1200 x 1200 x 2300


SATUAN : Unit

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 4.055.000,00 4.055.000,00

JUMLAH HARGA I 4.055.000,00

B. BAHAN
1 Manhole Utilitas 1200 x 1200 x 2300 (Mutu Beton K-350 dan Unit 1,0000 9.984.534,60 9.984.534,60
pembesian)

2 Lapisan Sirtu m3 0,3234 275.000,00 88.935,00


3 Lean Concrete m3 0,0924 750.000,00 69.300,00
4 Timbunan Pasir Makadam Padat m3 3,5280 310.000,00 1.093.680,00
5 Anyaman bambu/bilik m2 1,4400 75.000,00 108.000,00

JUMLAH HARGA II 11.344.449,60

C. PERALATAN Ls 1,0000 3.065.000,00 3.065.000,00

JUMLAH HARGA III 3.065.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 18.464.449,60
E. OVERHEAD DAN PROFIT 2.769.667,44
F. TOTAL DENGAN OVERHEAD (D+E) 21.234.117,04
G. PPN 11% (F X 11%) 2.335.752,87
H. HARGA SATUAN PEKERJAAN (F+G) 23.569.869,91

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN

JENIS PEKERJAAN : Pekerjaan Manhole Utilitas 1800 x 1200 x 2300


SATUAN : Unit

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 4.555.000,00 4.555.000,00

JUMLAH HARGA I 4.555.000,00

B. BAHAN
1 Manhole Utilitas 1800 x 1200 x 2300 (Mutu Beton K-350 dan Unit 1,0000 11.185.573,30 11.185.573,30
pembesian)

2 Lapisan Sirtu m3 0,4511 275.000,00 124.052,50


3 Lean Concrete m3 0,1288 750.000,00 96.600,00
4 Timbunan Pasir Makadam Padat m3 5,2920 310.000,00 1.640.520,00
5 Anyaman bambu/bilik m2 2,1600 75.000,00 162.000,00

JUMLAH HARGA II 13.208.745,80

C. PERALATAN Ls 1,0000 3.065.000,00 3.065.000,00

JUMLAH HARGA III 3.065.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 20.828.745,80
E. OVERHEAD DAN PROFIT 3.124.311,87
F. TOTAL DENGAN OVERHEAD (D+E) 23.953.057,67
G. PPN 11% (F X 11%) 2.634.836,34
H. HARGA SATUAN PEKERJAAN (F+G) 26.587.894,01

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN

JENIS PEKERJAAN : Pekerjaan Manhole Utilitas 1000 x 1200 x 2300 (Simpang)


SATUAN : Unit

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 5.055.000,00 5.055.000,00

JUMLAH HARGA I 5.055.000,00

B. BAHAN
1 Manhole Utilitas 1000 x 1200 x 2300 Simpang (Mutu Beton K- Unit 1,0000 8.082.435,60 8.082.435,60
350 dan pembesian)

2 Lapisan Sirtu m3 0,2808 275.000,00 77.220,00


3 Lean Concrete m3 0,0802 750.000,00 60.150,00
4 Timbunan Pasir Makadam Padat m3 2,9400 310.000,00 911.400,00
5 Anyaman bambu/bilik m2 1,2000 75.000,00 90.000,00

JUMLAH HARGA II 9.221.205,60

C. PERALATAN Ls 1,0000 3.065.000,00 3.065.000,00

JUMLAH HARGA III 3.065.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 17.341.205,60
E. OVERHEAD DAN PROFIT 2.601.180,84
F. TOTAL DENGAN OVERHEAD (D+E) 19.942.386,44
G. PPN 11% (F X 11%) 2.193.662,50
H. HARGA SATUAN PEKERJAAN (F+G) 22.136.048,94

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN

JENIS PEKERJAAN : Pekerjaan Manhole Utilitas 1200 x 1200 x 2300 (Simpang)


SATUAN : Unit

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 5.055.000,00 5.055.000,00

JUMLAH HARGA I 5.055.000,00

B. BAHAN
1 Manhole Utilitas 1200 x 1200 x 2300 Simpang (Mutu Beton K- Unit 1,0000 8.584.887,40 8.584.887,40
350 dan pembesian)
2 Lapisan Sirtu m3 0,3234 275.000,00 88.935,00
3 Lean Concrete m3 0,0924 750.000,00 69.300,00
4 Timbunan Pasir Makadam Padat m3 3,5280 310.000,00 1.093.680,00
5 Anyaman bambu/bilik m2 1,4400 75.000,00 108.000,00

JUMLAH HARGA II 9.944.802,40

C. PERALATAN Ls 1,0000 3.065.000,00 3.065.000,00

JUMLAH HARGA III 3.065.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 18.064.802,40
E. OVERHEAD DAN PROFIT 2.709.720,36
F. TOTAL DENGAN OVERHEAD (D+E) 20.774.522,76
G. PPN 11% (F X 11%) 2.285.197,50
H. HARGA SATUAN PEKERJAAN (F+G) 23.059.720,26

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN

JENIS PEKERJAAN : Pekerjaan Manhole Utilitas 1800 x 1200 x 2300 (simpang)


SATUAN : Unit

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 5.055.000,00 5.055.000,00

JUMLAH HARGA I 5.055.000,00

B. BAHAN
1 Manhole Utilitas 1800 x 1200 x 2300 Simpang (Mutu Beton K- Unit 1,0000 9.886.573,20 9.886.573,20
350 dan pembesian)
2 Lapisan Sirtu m3 0,4511 275.000,00 124.052,50
3 Lean Concrete m3 0,1288 750.000,00 96.600,00
4 Timbunan Pasir Makadam Padat m3 5,2920 310.000,00 1.640.520,00
5 Anyaman bambu/bilik m2 2,1600 75.000,00 162.000,00

JUMLAH HARGA II 11.909.745,70

C. PERALATAN Ls 1,0000 3.065.000,00 3.065.000,00

JUMLAH HARGA III 3.065.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 20.029.745,70
E. OVERHEAD DAN PROFIT 3.004.461,85
F. TOTAL DENGAN OVERHEAD (D+E) 23.034.207,55
G. PPN 11% (F X 11%) 2.533.762,83
H. HARGA SATUAN PEKERJAAN (F+G) 25.567.970,38

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
51
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W325 A Menggunakan Vibro Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 325 A m1 1,0000 660.000,00 660.000,00

JUMLAH HARGA II 660.000,00

C. PERALATAN Ls 1,0000 500.000,00 500.000,00

JUMLAH HARGA III 500.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.375.000,00
E. OVERHEAD DAN PROFIT 206.250,00
F. TOTAL DENGAN OVERHEAD (D+E) 1.581.250,00
G. PPN 11% (F X 11%) 173.937,50
H. HARGA SATUAN PEKERJAAN (F+G) 1.755.187,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
52
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W325 B Menggunakan Vibro Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 325 B m1 1,0000 690.000,00 690.000,00

JUMLAH HARGA II 690.000,00

C. PERALATAN Ls 1,0000 500.000,00 500.000,00

JUMLAH HARGA III 500.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.405.000,00
E. OVERHEAD DAN PROFIT 210.750,00
F. TOTAL DENGAN OVERHEAD (D+E) 1.615.750,00
G. PPN 11% (F X 11%) 177.732,50
H. HARGA SATUAN PEKERJAAN (F+G) 1.793.482,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
53
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W350 A Menggunakan Vibro Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 350 A m1 1,0000 680.000,00 680.000,00

JUMLAH HARGA II 680.000,00

C. PERALATAN Ls 1,0000 500.000,00 500.000,00

JUMLAH HARGA III 500.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.395.000,00
E. OVERHEAD DAN PROFIT 209.250,00
F. TOTAL DENGAN OVERHEAD (D+E) 1.604.250,00
G. PPN 11% (F X 11%) 176.467,50
H. HARGA SATUAN PEKERJAAN (F+G) 1.780.717,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
54
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W350 B Menggunakan Vibro Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 350 B m1 1,0000 700.000,00 700.000,00

JUMLAH HARGA II 700.000,00

C. PERALATAN Ls 1,0000 500.000,00 500.000,00

JUMLAH HARGA III 500.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.415.000,00
E. OVERHEAD DAN PROFIT 212.250,00
F. TOTAL DENGAN OVERHEAD (D+E) 1.627.250,00
G. PPN 11% (F X 11%) 178.997,50
H. HARGA SATUAN PEKERJAAN (F+G) 1.806.247,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
55
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W400 A Menggunakan Vibro Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 400 A m1 1,0000 720.000,00 720.000,00

JUMLAH HARGA II 720.000,00

C. PERALATAN Ls 1,0000 500.000,00 500.000,00

JUMLAH HARGA III 500.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.435.000,00
E. OVERHEAD DAN PROFIT 215.250,00
F. TOTAL DENGAN OVERHEAD (D+E) 1.650.250,00
G. PPN 11% (F X 11%) 181.527,50
H. HARGA SATUAN PEKERJAAN (F+G) 1.831.777,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
56
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W400 B Menggunakan Vibro Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 400 B m1 1,0000 740.000,00 740.000,00

JUMLAH HARGA II 740.000,00

C. PERALATAN Ls 1,0000 500.000,00 500.000,00

JUMLAH HARGA III 500.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.455.000,00
E. OVERHEAD DAN PROFIT 218.250,00
F. TOTAL DENGAN OVERHEAD (D+E) 1.673.250,00
G. PPN 11% (F X 11%) 184.057,50
H. HARGA SATUAN PEKERJAAN (F+G) 1.857.307,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
57
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W450 A Menggunakan Vibro Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 450 A m1 1,0000 890.000,00 890.000,00

JUMLAH HARGA II 890.000,00

C. PERALATAN Ls 1,0000 500.000,00 500.000,00

JUMLAH HARGA III 500.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.605.000,00
E. OVERHEAD DAN PROFIT 240.750,00
F. TOTAL DENGAN OVERHEAD (D+E) 1.845.750,00
G. PPN 11% (F X 11%) 203.032,50
H. HARGA SATUAN PEKERJAAN (F+G) 2.048.782,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
58
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W450 B Menggunakan Vibro Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 450 B m1 1,0000 1.070.000,00 1.070.000,00

JUMLAH HARGA II 1.070.000,00

C. PERALATAN Ls 1,0000 500.000,00 500.000,00

JUMLAH HARGA III 500.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.785.000,00
E. OVERHEAD DAN PROFIT 267.750,00
F. TOTAL DENGAN OVERHEAD (D+E) 2.052.750,00
G. PPN 11% (F X 11%) 225.802,50
H. HARGA SATUAN PEKERJAAN (F+G) 2.278.552,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
59
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W500 A Menggunakan Vibro Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 500 A m1 1,0000 970.000,00 970.000,00

JUMLAH HARGA II 970.000,00

C. PERALATAN Ls 1,0000 500.000,00 500.000,00

JUMLAH HARGA III 500.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.685.000,00
E. OVERHEAD DAN PROFIT 252.750,00
F. TOTAL DENGAN OVERHEAD (D+E) 1.937.750,00
G. PPN 11% (F X 11%) 213.152,50
H. HARGA SATUAN PEKERJAAN (F+G) 2.150.902,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
60
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W500 B Menggunakan Vibro Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 500 B m1 1,0000 1.120.000,00 1.120.000,00

JUMLAH HARGA II 1.120.000,00

C. PERALATAN Ls 1,0000 500.000,00 500.000,00

JUMLAH HARGA III 500.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.835.000,00
E. OVERHEAD DAN PROFIT 275.250,00
F. TOTAL DENGAN OVERHEAD (D+E) 2.110.250,00
G. PPN 11% (F X 11%) 232.127,50
H. HARGA SATUAN PEKERJAAN (F+G) 2.342.377,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
61
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W600 A Menggunakan Vibro Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 600 A m1 1,0000 1.190.000,00 1.190.000,00

JUMLAH HARGA II 1.190.000,00

C. PERALATAN Ls 1,0000 500.000,00 500.000,00

JUMLAH HARGA III 500.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.905.000,00
E. OVERHEAD DAN PROFIT 285.750,00
F. TOTAL DENGAN OVERHEAD (D+E) 2.190.750,00
G. PPN 11% (F X 11%) 240.982,50
H. HARGA SATUAN PEKERJAAN (F+G) 2.431.732,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
62
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W600 B Menggunakan Vibro Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 600 B m1 1,0000 1.310.000,00 1.310.000,00

JUMLAH HARGA II 1.310.000,00

C. PERALATAN Ls 1,0000 500.000,00 500.000,00

JUMLAH HARGA III 500.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.025.000,00
E. OVERHEAD DAN PROFIT 303.750,00
F. TOTAL DENGAN OVERHEAD (D+E) 2.328.750,00
G. PPN 11% (F X 11%) 256.162,50
H. HARGA SATUAN PEKERJAAN (F+G) 2.584.912,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
63
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W325 A Menggunakan Diesel Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 325 A Diesel m1 1,0000 660.000,00 660.000,00

JUMLAH HARGA II 660.000,00

C. PERALATAN Ls 1,0000 600.000,00 600.000,00

JUMLAH HARGA III 600.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.475.000,00
E. OVERHEAD DAN PROFIT 221.250,00
F. TOTAL DENGAN OVERHEAD (D+E) 1.696.250,00
G. PPN 11% (F X 11%) 186.587,50
H. HARGA SATUAN PEKERJAAN (F+G) 1.882.837,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
64
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W325 B Menggunakan Diesel Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 325 B Diesel m1 1,0000 680.000,00 680.000,00

JUMLAH HARGA II 680.000,00

C. PERALATAN Ls 1,0000 600.000,00 600.000,00

JUMLAH HARGA III 600.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.495.000,00
E. OVERHEAD DAN PROFIT 224.250,00
F. TOTAL DENGAN OVERHEAD (D+E) 1.719.250,00
G. PPN 11% (F X 11%) 189.117,50
H. HARGA SATUAN PEKERJAAN (F+G) 1.908.367,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
65
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W350 A Menggunakan Diesel Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 350 A Diesel m1 1,0000 680.000,00 680.000,00

JUMLAH HARGA II 680.000,00

C. PERALATAN Ls 1,0000 600.000,00 600.000,00

JUMLAH HARGA III 600.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.495.000,00
E. OVERHEAD DAN PROFIT 224.250,00
F. TOTAL DENGAN OVERHEAD (D+E) 1.719.250,00
G. PPN 11% (F X 11%) 189.117,50
H. HARGA SATUAN PEKERJAAN (F+G) 1.908.367,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
66
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W350 B Menggunakan Diesel Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 350 B Diesel m1 1,0000 700.000,00 700.000,00

JUMLAH HARGA II 700.000,00

C. PERALATAN Ls 1,0000 600.000,00 600.000,00

JUMLAH HARGA III 600.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.515.000,00
E. OVERHEAD DAN PROFIT 227.250,00
F. TOTAL DENGAN OVERHEAD (D+E) 1.742.250,00
G. PPN 11% (F X 11%) 191.647,50
H. HARGA SATUAN PEKERJAAN (F+G) 1.933.897,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
67
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W400 A Menggunakan Diesel Hammer Termasuk Capping Beam
SATUAN : -

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 400 A Diesel - 1,0000 720.000,00 720.000,00

JUMLAH HARGA II 720.000,00

C. PERALATAN Ls 1,0000 600.000,00 600.000,00

JUMLAH HARGA III 600.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.535.000,00
E. OVERHEAD DAN PROFIT 230.250,00
F. TOTAL DENGAN OVERHEAD (D+E) 1.765.250,00
G. PPN 11% (F X 11%) 194.177,50
H. HARGA SATUAN PEKERJAAN (F+G) 1.959.427,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
68
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W400 B Menggunakan Diesel Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 400 B Diesel m1 1,0000 740.000,00 740.000,00

JUMLAH HARGA II 740.000,00

C. PERALATAN Ls 1,0000 600.000,00 600.000,00

JUMLAH HARGA III 600.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.555.000,00
E. OVERHEAD DAN PROFIT 233.250,00
F. TOTAL DENGAN OVERHEAD (D+E) 1.788.250,00
G. PPN 11% (F X 11%) 196.707,50
H. HARGA SATUAN PEKERJAAN (F+G) 1.984.957,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
69
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W450 A Menggunakan Diesel Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 450 A Diesel m1 1,0000 890.000,00 890.000,00

JUMLAH HARGA II 890.000,00

C. PERALATAN Ls 1,0000 600.000,00 600.000,00

JUMLAH HARGA III 600.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.705.000,00
E. OVERHEAD DAN PROFIT 255.750,00
F. TOTAL DENGAN OVERHEAD (D+E) 1.960.750,00
G. PPN 11% (F X 11%) 215.682,50
H. HARGA SATUAN PEKERJAAN (F+G) 2.176.432,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
70
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W450 B Menggunakan Diesel Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 450 B Diesel m1 1,0000 1.070.000,00 1.070.000,00

JUMLAH HARGA II 1.070.000,00

C. PERALATAN Ls 1,0000 600.000,00 600.000,00

JUMLAH HARGA III 600.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.885.000,00
E. OVERHEAD DAN PROFIT 282.750,00
F. TOTAL DENGAN OVERHEAD (D+E) 2.167.750,00
G. PPN 11% (F X 11%) 238.452,50
H. HARGA SATUAN PEKERJAAN (F+G) 2.406.202,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
71
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W500 A Menggunakan Diesel Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 500 A Diesel m1 1,0000 970.000,00 970.000,00

JUMLAH HARGA II 970.000,00

C. PERALATAN Ls 1,0000 600.000,00 600.000,00

JUMLAH HARGA III 600.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.785.000,00
E. OVERHEAD DAN PROFIT 267.750,00
F. TOTAL DENGAN OVERHEAD (D+E) 2.052.750,00
G. PPN 11% (F X 11%) 225.802,50
H. HARGA SATUAN PEKERJAAN (F+G) 2.278.552,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
72
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W500 B Menggunakan Diesel Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 500 B Diesel m1 1,0000 1.120.000,00 1.120.000,00

JUMLAH HARGA II 1.120.000,00

C. PERALATAN Ls 1,0000 600.000,00 600.000,00

JUMLAH HARGA III 600.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.935.000,00
E. OVERHEAD DAN PROFIT 290.250,00
F. TOTAL DENGAN OVERHEAD (D+E) 2.225.250,00
G. PPN 11% (F X 11%) 244.777,50
H. HARGA SATUAN PEKERJAAN (F+G) 2.470.027,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
73
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W600 A Menggunakan Diesel Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 600 A Diesel m1 1,0000 1.190.000,00 1.190.000,00

JUMLAH HARGA II 1.190.000,00

C. PERALATAN Ls 1,0000 600.000,00 600.000,00

JUMLAH HARGA III 600.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.005.000,00
E. OVERHEAD DAN PROFIT 300.750,00
F. TOTAL DENGAN OVERHEAD (D+E) 2.305.750,00
G. PPN 11% (F X 11%) 253.632,50
H. HARGA SATUAN PEKERJAAN (F+G) 2.559.382,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
74
JENIS PEKERJAAN : Pekerjaan Corrugated Concrete Sheet Pile W600 B Menggunakan Diesel Hammer Termasuk Capping Beam
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA I 215.000,00

B. BAHAN
1 Corrugated Concrete Sheet Pile W 600 B Diesel m1 1,0000 1.310.000,00 1.310.000,00

JUMLAH HARGA II 1.310.000,00

C. PERALATAN Ls 1,0000 600.000,00 600.000,00

JUMLAH HARGA III 600.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2.125.000,00
E. OVERHEAD DAN PROFIT 318.750,00
F. TOTAL DENGAN OVERHEAD (D+E) 2.443.750,00
G. PPN 11% (F X 11%) 268.812,50
H. HARGA SATUAN PEKERJAAN (F+G) 2.712.562,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
75
JENIS PEKERJAAN : Preboring Diameter 350 mm ( 2 Lubang /m )
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 45.000,00 45.000,00

JUMLAH HARGA I 45.000,00

B. BAHAN

JUMLAH HARGA II -

C. PERALATAN Ls 1,0000 150.000,00 150.000,00

JUMLAH HARGA III 150.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 195.000,00
E. OVERHEAD DAN PROFIT 29.250,00
F. TOTAL DENGAN OVERHEAD (D+E) 224.250,00
G. PPN 11% (F X 11%) 24.667,50
H. HARGA SATUAN PEKERJAAN (F+G) 248.917,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
76
JENIS PEKERJAAN : Preboring Diameter 350 mm ( 2 Lubang /m ) dengan ponton
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 45.000,00 45.000,00

JUMLAH HARGA I 45.000,00

B. BAHAN

JUMLAH HARGA II -

C. PERALATAN Ls 1,0000 200.000,00 200.000,00

JUMLAH HARGA III 200.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 245.000,00
E. OVERHEAD DAN PROFIT 36.750,00
F. TOTAL DENGAN OVERHEAD (D+E) 281.750,00
G. PPN 11% (F X 11%) 30.992,50
H. HARGA SATUAN PEKERJAAN (F+G) 312.742,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
77
JENIS PEKERJAAN : Preboring Diameter 400 mm ( 2 Lubang /m )
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 45.000,00 45.000,00

JUMLAH HARGA I 45.000,00

B. BAHAN

JUMLAH HARGA II -

C. PERALATAN Ls 1,0000 165.000,00 165.000,00

JUMLAH HARGA III 165.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 210.000,00
E. OVERHEAD DAN PROFIT 31.500,00
F. TOTAL DENGAN OVERHEAD (D+E) 241.500,00
G. PPN 11% (F X 11%) 26.565,00
H. HARGA SATUAN PEKERJAAN (F+G) 268.065,00

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
78
JENIS PEKERJAAN : Preboring Diameter 400 mm ( 2 Lubang /m ) dengan ponton
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 45.000,00 45.000,00

JUMLAH HARGA I 45.000,00

B. BAHAN

JUMLAH HARGA II -

C. PERALATAN Ls 1,0000 215.000,00 215.000,00

JUMLAH HARGA III 215.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 260.000,00
E. OVERHEAD DAN PROFIT 39.000,00
F. TOTAL DENGAN OVERHEAD (D+E) 299.000,00
G. PPN 11% (F X 11%) 32.890,00
H. HARGA SATUAN PEKERJAAN (F+G) 331.890,00

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
79
JENIS PEKERJAAN : Preboring Diameter 450 mm ( 2 Lubang /m )
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 45.000,00 45.000,00

JUMLAH HARGA I 45.000,00

B. BAHAN

JUMLAH HARGA II -

C. PERALATAN Ls 1,0000 175.000,00 175.000,00

JUMLAH HARGA III 175.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 220.000,00
E. OVERHEAD DAN PROFIT 33.000,00
F. TOTAL DENGAN OVERHEAD (D+E) 253.000,00
G. PPN 11% (F X 11%) 27.830,00
H. HARGA SATUAN PEKERJAAN (F+G) 280.830,00

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
80
JENIS PEKERJAAN : Preboring Diameter 450 mm ( 2 Lubang /m ) dengan ponton
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 45.000,00 45.000,00

JUMLAH HARGA I 45.000,00

B. BAHAN

JUMLAH HARGA II -

C. PERALATAN Ls 1,0000 235.000,00 235.000,00

JUMLAH HARGA III 235.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 280.000,00
E. OVERHEAD DAN PROFIT 42.000,00
F. TOTAL DENGAN OVERHEAD (D+E) 322.000,00
G. PPN 11% (F X 11%) 35.420,00
H. HARGA SATUAN PEKERJAAN (F+G) 357.420,00

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
81
JENIS PEKERJAAN : Langsir Material Corrugated Concrete Sheet Pile dengan Ponton
SATUAN : batang

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 10.000,00 10.000,00

JUMLAH HARGA I 10.000,00

B. BAHAN

JUMLAH HARGA II -

C. PERALATAN Ls 1,0000 220.000,00 220.000,00

JUMLAH HARGA III 220.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 230.000,00
E. OVERHEAD DAN PROFIT 34.500,00
F. TOTAL DENGAN OVERHEAD (D+E) 264.500,00
G. PPN 11% (F X 11%) 29.095,00
H. HARGA SATUAN PEKERJAAN (F+G) 293.595,00

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
82
JENIS PEKERJAAN : Hending Corrugated Concrete Sheet Pile dengan Ponton
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 1.000,00 1.000,00

JUMLAH HARGA I 1.000,00

B. BAHAN

JUMLAH HARGA II -

C. PERALATAN Ls 1,0000 20.000,00 20.000,00

JUMLAH HARGA III 20.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 21.000,00
E. OVERHEAD DAN PROFIT 3.150,00
F. TOTAL DENGAN OVERHEAD (D+E) 24.150,00
G. PPN 11% (F X 11%) 2.656,50
H. HARGA SATUAN PEKERJAAN (F+G) 26.806,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
83
JENIS PEKERJAAN : Pekerjaan Pemancang dengan Ponton
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 41.000,00 41.000,00

JUMLAH HARGA I 41.000,00

B. BAHAN

JUMLAH HARGA II -

C. PERALATAN Ls 1,0000 250.000,00 250.000,00

JUMLAH HARGA III 250.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 291.000,00
E. OVERHEAD DAN PROFIT 43.650,00
F. TOTAL DENGAN OVERHEAD (D+E) 334.650,00
G. PPN 11% (F X 11%) 36.811,50
H. HARGA SATUAN PEKERJAAN (F+G) 371.461,50

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
84
JENIS PEKERJAAN : Angkutan Material Jarak Tempuh 200 m
SATUAN : m3

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 500,00 500,00

JUMLAH HARGA I 500,00

B. BAHAN

JUMLAH HARGA II -

C. PERALATAN Ls 1,0000 20.000,00 20.000,00

JUMLAH HARGA III 20.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 20.500,00
E. OVERHEAD DAN PROFIT 3.075,00
F. TOTAL DENGAN OVERHEAD (D+E) 23.575,00
G. PPN 11% (F X 11%) 2.593,25
H. HARGA SATUAN PEKERJAAN (F+G) 26.168,25

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
85
JENIS PEKERJAAN : Angkutan Material Jarak Tempuh 300 m
SATUAN : m3

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 500,00 500,00

JUMLAH HARGA I 500,00

B. BAHAN

JUMLAH HARGA II -

C. PERALATAN Ls 1,0000 30.000,00 30.000,00

JUMLAH HARGA III 30.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 30.500,00
E. OVERHEAD DAN PROFIT 4.575,00
F. TOTAL DENGAN OVERHEAD (D+E) 35.075,00
G. PPN 11% (F X 11%) 3.858,25
H. HARGA SATUAN PEKERJAAN (F+G) 38.933,25

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
86
JENIS PEKERJAAN : Angkutan Material Jarak Tempuh 400 m
SATUAN : m3

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 500,00 500,00

JUMLAH HARGA I 500,00

B. BAHAN

JUMLAH HARGA II -

C. PERALATAN Ls 1,0000 40.000,00 40.000,00

JUMLAH HARGA III 40.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 40.500,00
E. OVERHEAD DAN PROFIT 6.075,00
F. TOTAL DENGAN OVERHEAD (D+E) 46.575,00
G. PPN 11% (F X 11%) 5.123,25
H. HARGA SATUAN PEKERJAAN (F+G) 51.698,25

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
87
JENIS PEKERJAAN : Angkutan Material Jarak Tempuh 500 m
SATUAN : m3

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 500,00 500,00

JUMLAH HARGA I 500,00

B. BAHAN

JUMLAH HARGA II -

C. PERALATAN Ls 1,0000 50.000,00 50.000,00

JUMLAH HARGA III 50.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 50.500,00
E. OVERHEAD DAN PROFIT 7.575,00
F. TOTAL DENGAN OVERHEAD (D+E) 58.075,00
G. PPN 11% (F X 11%) 6.388,25
H. HARGA SATUAN PEKERJAAN (F+G) 64.463,25

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
88
JENIS PEKERJAAN : Angkutan Material Jarak Tempuh 600 m
SATUAN : m3

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 500,00 500,00

JUMLAH HARGA I 500,00

B. BAHAN

JUMLAH HARGA II -

C. PERALATAN Ls 1,0000 60.000,00 60.000,00

JUMLAH HARGA III 60.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 60.500,00
E. OVERHEAD DAN PROFIT 9.075,00
F. TOTAL DENGAN OVERHEAD (D+E) 69.575,00
G. PPN 11% (F X 11%) 7.653,25
H. HARGA SATUAN PEKERJAAN (F+G) 77.228,25

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
ANALISA HARGA SATUAN
89
JENIS PEKERJAAN : Pasang dan Bongkar Kisdam tinggi 2 m
SATUAN : m1

No. Komponen Satuan Perkiraan Harga Satuan Jumlah Harga


Kuantitas (Rp.) (Rp.)

A. TENAGA Ls 1,0000 500,00 500,00

JUMLAH HARGA I 500,00

B. BAHAN

JUMLAH HARGA II -

C. PERALATAN Ls 1,0000 19.000,00 19.000,00

JUMLAH HARGA III 19.000,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 19.500,00
E. OVERHEAD DAN PROFIT 2.925,00
F. TOTAL DENGAN OVERHEAD (D+E) 22.425,00
G. PPN 11% (F X 11%) 2.466,75
H. HARGA SATUAN PEKERJAAN (F+G) 24.891,75

Jakarta, 22 Desember 2022


PT.INDIE DIMENSI INOVASI

LOBI INDIARTO
Direktur Utama
DAFTAR HARGA SATUAN DASAR BAHAN

Harga Satuan
No. Uraian *) Satuan Bahan (Harga Keterangan**)
Loco +
Angkutan)
(Rp)

1 Timbunan Porous M3 Rp 108.000,00


2 Material Pilihan M3 Rp 96.000,00
3 Agregat Kasar M3 Rp 245.000,00
4 Agregat Halus M3 Rp 245.000,00
5 Pasir Pasang M3 Rp 205.000,00
6 Pasir Beton M3 Rp 210.000,00
7 Filter Plastik M2 Rp 3.600,00
8 Pipa Porous M' Rp 90.000,00
9 Semen (PC) Kg Rp 1.750,00
10 Mortar M3 Rp 25.000,00
11 Filter Stripe, dll Ls Rp 60.000,00
12 Batu Kali M3 Rp 210.000,00
13 Box Culvert Ukuran 3m x 3m M1 Rp 40.200.000,00
14 Bahan Timbunan M3 Rp 114.000,00
15 Geotekstile stabilisator kelas 1 M2 Rp 60.000,00
16 Geotekstile Saparator Kelas 1 M2 Rp 60.000,00
17 Agregat Kelas C M3 Rp 205.000,00
18 Agregat Kelas A Kg Rp 215.000,00
19 Agregat Kelas B Kg Rp 210.000,00
20 Aspal Emulsi Kg Rp 13.500,00
21 Kayu Perancah/Bekisting M3 Rp 2.000.000,00
22 Paku Kg Rp 15.000,00
23 Baja Tulangan Sirip BjTP 280 Kg Rp 16.000,00
24 Baja Tulangan Sirip BjTS 420A Kg Rp 16.500,00
25 Baja Tulangan Sirip BjTS 420B Kg Rp 17.000,00
26 Baja Tulangan Kg Rp 16.000,00
27 Kawat Beton Kg Rp 16.000,00
28 Bahan pondasi cerucuk M1 Rp 30.000,00
29 Gebalan Rumput M2 Rp 60.000,00
30 Cat Marka Thermoplastic Kg Rp 117.000,00
31 Minyak Pencair (Thinner) Liter Rp 33.000,00
32 Glass Bead Kg Rp 58.000,00
33 Pelat Rambu Jadi (Engineering Grade) BH Rp 300.000,00
34 Pipa Galvanis Dia.1,6" Batang Rp 300.000,00
38 Cat, dan bahan lainnya Ls Rp 24.000,00
39 Rel Pengaman M' Rp 500.000,00
Harga Satuan
No. Uraian *) Satuan Bahan (Harga Keterangan**)
Loco +
Angkutan)
(Rp)
40 Baut, dan material lain Ls Rp 28.000,00
41 Unit Lampu Penerangan Jalan Lengan Ganda, Tipe LED Buah Rp 900.000,00
42 Pagar Pemisah Pedestrian Galvanised M1 Rp 30.000,00
43 Lolos screen1 ukuran ( 0 - 5) M3 Rp 275.000,00
44 Lolos screen2 ukuran ( 0 - 5) M3 Rp 275.000,00
45 Lolos screen2 ukuran ( 5 - 9,5) M3 Rp 275.000,00
46 Lolos screen2 ukuran ( 9.5 - 19,0) M3 Rp 275.000,00
47 Filler Kg Rp 16.500,00
48 Aspal kg Rp 15.500,00
49 Aspal Emulsi kg Rp 13.500,00
50 Latex kg Rp 35.000,00
51 Casing M2 Rp 750.000,00
52 Pelat Rambu Jadi (Engineering Grade) bh Rp 235.000,00
53 Pipa Galvanis Dia.1,6" m1 Rp 99.500,00
54 Cat Galvanis Kg Rp 62.500,00
55 Baut Unit Rp 5.800,00
56 Cat Pelapisan Utama (Primary Coat) Kg Rp 50.000,00
57 Cat Akhir/Finishing Kg Rp 52.000,00
58 Primary Coat Kg Rp 90.000,00
59 Polyurethane Alkyd Copolymer Kg Rp 52.000,00
60 Baut Baja Buah Rp 17.500,00
61 Pipa PVC 3 Inch m1 Rp 25.000,00
62 Klem PVC unit Rp 7.500,00
63 asphaltic m Rp 1.350.000,00
64 sealent Kg Rp 115.000,00
65 Tabung Penyuntik bh Rp 53.000,00
66 Bahan Pacthing Beton m3 Rp 875.000,00
67 Bahan Akselerator Ltr Rp 55.000,00
68 Primary Coat Kg Rp 102.000,00
69 Pipa PVC m1 Rp 75.000,00

Jakarta,22 Desember 2022


PT.INDIE DIMENSI INOVASI

Lobi Indiarto
Direktur Utama